KR100656413B1 - The construction method of basement drainage having double drainage canals and the system - Google Patents

The construction method of basement drainage having double drainage canals and the system Download PDF

Info

Publication number
KR100656413B1
KR100656413B1 KR1020050112879A KR20050112879A KR100656413B1 KR 100656413 B1 KR100656413 B1 KR 100656413B1 KR 1020050112879 A KR1020050112879 A KR 1020050112879A KR 20050112879 A KR20050112879 A KR 20050112879A KR 100656413 B1 KR100656413 B1 KR 100656413B1
Authority
KR
South Korea
Prior art keywords
drainage
drain
groundwater
building
concrete layer
Prior art date
Application number
KR1020050112879A
Other languages
Korean (ko)
Inventor
박옥교
Original Assignee
박옥교
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박옥교 filed Critical 박옥교
Priority to KR1020050112879A priority Critical patent/KR100656413B1/en
Application granted granted Critical
Publication of KR100656413B1 publication Critical patent/KR100656413B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0085Geotextiles
    • E02D2300/0089Geotextiles non-woven

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A method of constructing a ground water drainage for reducing upward water pressure of a construction and a system thereof are provided to ease the width of the discharge volume change due to the rise of the upward water pressure according to the height difference of the drain boards. In a construction method of forming a drainage for discharging the ground water through a sump pit(50), a method of constructing a ground water drainage for reducing upward water pressure of a construction comprises a first process of stopped to be on a level with an excavated finishing surface(20); a second process of installing drain boards(3,300) working as a drainage; a third process of forming a first discarding concrete layer by pouring a mortar up to a predetermined height; a fourth process of forming a second discarding concrete layer by pouring the mortar at the excavated finishing surface with a predetermined height; and a fifth process of placing the drain boards on the upper surface of the second discarding concrete layer.

Description

건축물의 상향수압 감소를 위한 지하수 배수로 시공방법 및 그 시스템 {The construction method of basement drainage having double drainage canals and the system}The construction method of basement drainage having double drainage canals and the system}

도 1은 종래 지하층 바닥 배수로 시공방법을 나타내는 단면도이다.1 is a cross-sectional view showing a method for constructing a conventional basement floor drain.

도 2는 종래 지하층 바닥 배수로의 다른 시공방법을 나타내는 단면도이다.Figure 2 is a cross-sectional view showing another construction method of the conventional basement floor drain.

도 3은 본 발명의 방법에 따라 시공된 제 1 실시례의 단면도이다.3 is a cross-sectional view of the first embodiment constructed in accordance with the method of the present invention.

도 4는 본 발명의 방법에 따라 시공된 제 2 실시례의 단면도이다.4 is a cross-sectional view of a second embodiment constructed in accordance with the method of the present invention.

도 5a 내지 5f는 본 발명의 방법에 따라 시공되는 순서를 나타낸 단면도이다.5a to 5f are cross-sectional views illustrating the sequence of construction according to the method of the present invention.

도 6a 내지 6g는 본 발명의 다른 방법에 따라 시공되는 순서를 나타낸 단면도이다.6a to 6g are cross-sectional views showing the sequence of construction according to another method of the present invention.

도 7은 본 발명의 방법에 따라 시공된 제 3 실시례의 단면도이다.7 is a sectional view of a third embodiment constructed in accordance with the method of the present invention.

도 8은 본 발명의 방법에 따라 시공된 제 4 실시례의 단면도이다.8 is a sectional view of a fourth embodiment constructed in accordance with the method of the present invention.

도 9는 본 발명의 방법에 적용된 커넥터의 사시도이다.9 is a perspective view of a connector applied to the method of the present invention.

도 10은 도 9의 커넥터의 단면도이다.10 is a cross-sectional view of the connector of FIG. 9.

도 11은 도 9의 커넥터를 적용하여 시공된 제 5 실시례의 단면도이다.FIG. 11 is a sectional view of a fifth embodiment constructed by applying the connector of FIG. 9. FIG.

도 12는 도 11의 실시례의 단면도이다.12 is a cross-sectional view of the embodiment of FIG. 11.

도 13a는 본 발명의 방법에 따라 "∩"형 굴곡을 갖는 제2배수재를 적용한 제 6 실시례의 단면도이고, 도 13b는 이를 약간 변형한 실시례의 단면도이다.FIG. 13A is a cross-sectional view of a sixth embodiment employing a second drainage material having “∩” shaped bends in accordance with the method of the present invention, and FIG. 13B is a cross-sectional view of an embodiment with a slight modification thereof.

도 14는 도 9의 커넥터와 "∩"형 굴곡을 갖는 제2배수재를 적용한 제 7 실시례의 단면도이다.FIG. 14 is a cross-sectional view of the seventh embodiment to which the connector of FIG. 9 and the second drainage material having the "curve" type bend are applied.

< 도면의 주요 부분에 대한 부호에 대한 설명 ><Description of the symbols for the main parts of the drawings>

1 : 지하층 3, 3a, 3b, 3c : (제1)배수재1: basement floor 3, 3a, 3b, 3c: (1) drainage

11 : 콘크리트벽 12 : 바닥콘크리트11: concrete wall 12: floor concrete

13 : 지하수 20 : 굴토마감면13: groundwater 20: gulto finish

30 : 자갈층 40 : 배수관30: gravel layer 40: drain pipe

41 : 관통홀 50 : 집수정41: through hole 50: water collecting well

60, 60' : 토목섬유(부직포) 70 : 합성수지비닐(필름) 60, 60 ': Geotextile (non-woven fabric) 70: Synthetic resin vinyl (film)

100 : 버림콘크리트(층) 110 : 상부케이스 100: discarded concrete (floor) 110: upper case

120 : 하부케이스 140 : 개구부 120: lower case 140: opening

200 : (바닥)구체콘크리트(층) 300 : 제2배수재 200: (bottom) concrete concrete (layer) 300: second drain

400 : 연결부재 1000 : 커넥터400: connecting member 1000: connector

본 발명은 지하수 배수로 시공방법 및 그 시스템에 관한 것으로서, 구체적으로는 두 개 이상의 면에 걸쳐 형성된 배수재의 시공방법과 그 시스템에 관한 것이다.The present invention relates to a groundwater drainage construction method and system thereof, and more particularly, to a construction method and a system of drainage material formed over two or more surfaces.

대형건물 및 지하구조물 중 특히, 깊은 굴착을 요하는 지하공사는 필연적으로 지하수의 상향수압(Uplift Pressure)에 대한 문제에 직면하게 된다. 현장의 지질과 시공조건을 고려하여 안전하고 경제성 있는 상향수압 처리 방안을 마련하는 것은 상당히 중요한 문제이다. Among large buildings and underground structures, especially underground constructions that require deep excavation inevitably face the problem of uplift pressure of groundwater. Considering the geology and construction conditions of the site, it is very important to prepare a safe and economical upstream hydraulic pressure treatment plan.

일반적으로 건물의 기초 바닥에 작용하는 상향수압 처리를 위해서 사하중과 영구(부력)앙카를 통한 공법이 많이 사용되나, 이는 건물의 내구성 및 안전성과 관련하여 부력앙카의 인장력에 대한 지속적인 신뢰성이 보장되지 않는다는 한계가 있다.In general, a process using dead weight and permanent (buoyancy) anchors is often used for the upward hydraulic pressure treatment on the foundation floor of a building, which does not guarantee the continuous reliability of the buoyancy anchor's tensile force in relation to the durability and safety of the building. There is a limit.

이를 개선한 방법이 기초바닥 아래에 인위적인 집수정과 배수층을 형성하여 부지 내로 유입되는 지하수가 배수로를 따라 집수정으로 모이면 정기적으로 이를 펌핑하여 배출시킴으로써 기초바닥 콘크리트에 양압(Uplifting Water Pressure)이 작용하지 않도록 하는 기초바닥 영구 배수시스템(Permanent Underdrainage System)방법이다. 이는 종래의 방법에 비해 높은 지하수위와 비례하여 작용하는 상향수압 문제를 보다 안정적이고, 영구적으로 해결하게 하는 장점이 있다.An improved method is to create an artificial catchment and drainage layer under the foundation floor, and when the groundwater flowing into the site is collected into the sump along the drainage, it is pumped and discharged regularly so that the uplifting water pressure acts on the foundation floor concrete. Permanent Underdrainage System. This has the advantage of more stable and permanently solve the problem of up-water pressure in proportion to the high groundwater level compared to the conventional method.

이러한 영구 배수시스템을 첨부된 도면을 참조하여 상세하게 설명하도록 한다. 도 1을 참조하면, 지하층 바닥 배수 시공에 있어서 지하층(1)이 시공될 때 콘 크리트벽(11)과 바닥콘크리트(12)가 타설되어 일정면적의 지하층(1)이 만들어지고, 상기 바닥콘크리트(12)의 하부측 자갈층(30)에는 굴토마감면(20)의 수두차에 의한 높은 상향수압이 바닥 콘크리트(12)로 발생될 때 균열 및 누수현상을 최소화시키도록 둘레에 일정 간격을 두고 다수의 관통홀(41)이 형성된 배수관이 매설되어 있다. This permanent drainage system will be described in detail with reference to the accompanying drawings. Referring to FIG. 1, when the basement layer 1 is constructed in the basement floor drainage construction, the concrete wall 11 and the floor concrete 12 are poured to form a basement layer 1 having a predetermined area, and the floor concrete ( The lower side gravel layer 30 of 12) has a plurality of spaced apart at a predetermined interval so as to minimize cracks and water leakage when high upwater pressure caused by the water head difference of the oyster finish surface 20 is generated in the bottom concrete 12 A drain pipe in which the through hole 41 is formed is embedded.

또한, 상기 바닥콘크리트(12)의 일측에는 바닥콘크리트보다 낮게 일정면적의 집수정(50)이 시공되고, 이 집수정(50)에는 상기 자갈층(30)에 매설된 배수관(40)의 출구측이 연결되도록 시공되어 있으며, 이 집수정(50)에 집수된 지하수는 펌프(미도시)에 의해 외부로 펌핑되도록 구성되어 있다. 또한, 상기 배수관(40)의 외주면에 형성된 다수의 관통홀(41)에 자갈층(30)의 자갈 및 모래 등이 침투하거나, 관통홀(41)을 막는 것을 방지하기 위하여 부직포(60')가 감겨져 있다.In addition, one side of the bottom concrete 12 is constructed with a water collecting well 50 of a predetermined area lower than the bottom concrete, and the water collecting well 50 has an outlet side of the drain pipe 40 embedded in the gravel layer 30. It is constructed to be connected, and the groundwater collected in the sump 50 is configured to be pumped out by a pump (not shown). In addition, the nonwoven fabric 60 'is wound around the plurality of through holes 41 formed on the outer circumferential surface of the drain pipe 40 to prevent the gravel and sand of the gravel layer 30 from penetrating or blocking the through holes 41. have.

그러나, 상기 종래의 방법은 시공방법이 까다롭고 바닥콘크리트(12)와 배수관(40) 사이의 상압수압에 의해 바닥콘크리트(12) 밑으로 직접 발생하는 지하수만이 아니라 바닥콘크리트(12)와 배수관(40)과의 사이에서 상압수압에 의해 바닥 콘크리트 밑으로 직접 발생하는 지하수가 배수관(40)의 관통홀(41)을 통해 제대로 배수되지 못하게 되어 전반적으로 배수작용이 원활하지 못하는 문제점이 있고, 발생되는 상압수압에 의해 배수관이 파괴되어 지하수의 배수가 불가능한 문제점이 있었다.However, the conventional method is difficult to construct and the ground concrete 12 and the drain pipe (as well as the groundwater generated directly below the bottom concrete 12 by atmospheric pressure between the bottom concrete 12 and the drain pipe 40). There is a problem that the groundwater generated directly below the bottom concrete by the atmospheric pressure between the 40) is not properly drained through the through-hole 41 of the drain pipe 40, the overall drainage action is not smooth, There was a problem that the drainage of the groundwater is impossible because the drainage pipe is destroyed by the atmospheric pressure.

이러한 종래의 문제점을 개선한 지하층 바닥 배수로 시공방법이 개발되어 한국특허 제383665호로 등록되었다. 이 시공방법의 주요 내용은 도 2에 도시되어 있다. 도 2를 참조하면, 굴토마감면(20) 위에 소정 높이를 갖는 배수재(또는 거푸집 )(3)을 가로 및 세로로 서로 소정의 간격을 이루면서 수평되게 연결하여 배치하되 상기 암반층의 굴토마감면(20)과 상기 배수재(3) 사이에 부직포(60)를 위치시키면서 일측으로 모여진 배수재(3)의 출구(31)가 상기 집수정(50)과 연결되도록 설치하고 그 위에 몰탈을 소정 높이로 타설하여 바닥콘크리트(12)를 형성하는 방식이다.The basement floor drainage construction method was developed to improve the conventional problems and registered as Korean Patent No. 383665. The main contents of this construction method are shown in FIG. Referring to FIG. 2, the drainage material (or formwork) 3 having a predetermined height is horizontally and vertically connected to each other horizontally and vertically at a predetermined interval on the gulting finish surface 20, but the gulting finish surface 20 of the rock layer is disposed. ) And the outlet 31 of the drainage material 3 gathered to one side while placing the nonwoven fabric 60 between the drainage material 3 and the drainage material 3 is connected to the water collecting well 50, and the mortar is poured to a predetermined height on the bottom thereof. The concrete 12 is formed.

이러한 개선된 구성은, 배수로(4)가 굴토마감면(20)에 접하여 바닥 콘크리트(12)의 저면에 일체로 구성되었기 때문에 종래와 같이 배수로를 구성하기 위한 자갈층이나 자갈층을 확보하기 위한 굴착공사 및 별도의 배수관이 필요 없게 된다. 따라서 공사기간을 단축시키고 자재비 및 공사비를 절감시킬 수 있게 되며, 지하수로부터 발생되는 수압이 바닥 콘크리트(12)의 저면으로 작용되기 전에 일체로 형성된 배수로(4)를 따라 유도되어 집수정(50)으로 빠지게 되는 장점이 있다.This improved configuration, since the drainage passage 4 is integrally formed on the bottom surface of the bottom concrete 12 in contact with the gulting finish surface 20 and excavation work to secure the gravel layer or gravel layer for constituting the drainage as in the prior art and There is no need for a separate drain pipe. Therefore, it is possible to shorten the construction period and reduce the material cost and construction cost, and the hydraulic pressure generated from the groundwater is guided along the drainage channel 4 formed integrally before acting as the bottom of the bottom concrete 12 to the sump well 50. There is an advantage of being missing.

상기 특허 기술에서는 굴토마감면 상에 가로 또는 세로로 설치된 배수재(또는 거푸집)들은 일 평면 상에서 직접적으로 집수정으로 연결되는 배수재와 연결되어 지하수를 배수정으로 보내도록 되어 있으나, 실제 건설 현장에서는 공사기간의 단축 또는 구체콘크리트의 이음시공과 배수재의 파손 등의 여러 원인에 의하여 배수재 중 일부는 집수정으로 연결된 타 배수재와 직접 연결되지 못한 상태에서 버림콘크리트가 타설되고 배수로 설치 공정이 불완전하게 마무리되고 다음 공정으로 이어지는 경우가 종종 있어 왔다. 또한 배수재의 설치 높이가 변동되거나, 또는 양압에 대한 완충작용을 위해 의도적으로 배수재의 설치 높이를 다양하게 해야 하는 필요도 있게 된다.In the patented technology, drainage (or formwork) installed horizontally or vertically on the gulting finish surface is connected to drainage directly connected to a collecting well on one plane to send groundwater to the drainage well. Due to various reasons such as shortening or splice construction of concrete and damage of drainage materials, some of the drainage materials are not directly connected to other drainage materials connected to the sump, and the discarded concrete is laid and the drainage installation process is incompletely finished. It has often been followed. It is also necessary to vary the installation height of the drain, or to intentionally vary the installation height of the drain for buffering against positive pressure.

이러한 실제 건설 현장에서의 요구에 대해 종래의 특허 기술만으로는 명확한 해결책이 제시되지 않고 있으므로 새로운 시공방법과 시스템에 대한 필요성이 증대되고 있는 상황이다.Since there is no clear solution with the conventional patented technology, the need for a new construction method and system is increasing.

본 발명은 상기에서 기술한 문제점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은 굴토마감면 위의 배수재가 다양한 높이와 층에 위치될 수 있는 시공방법을 제공하여, 배수재 시공의 공간적 제약을 개선하고 원활한 배수가 가능하도록 하며, 상향 수압에 대한 완충효과를 갖는 배수시스템을 갖도록 하는 것을 목적으로 한다.The present invention has been made to solve the above-described problems, an object of the present invention to provide a construction method in which the drainage on the gulto finish surface can be located at various heights and layers, improving the spatial constraints of the construction of drainage The purpose of the present invention is to provide a drainage system having a cushioning effect against upward hydraulic pressure, and to enable smooth drainage.

상기한 목적을 달성하기 위한 본 발명의 시공방법 및 구성은, 지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로를 형성시키는 시공방법에 있어서, 굴토 후의 상면 자체 또는 잔토층, 자갈층. 버럭 등을 이용하여 굴토마감면이 수평을 이루도록 정지하는 1 공정, 상기 굴토마감면 위에, 지하수가 유입되어 모아져 흐르도록 하기 위한 배수로 기능을 하는 배수재를 설치하는 2 공정, 상기 배수재가 설치된 일부 영역 및 상기 굴토마감면의 일부 영역에 상기 배수재를 덮도록 소정 높이로 몰탈을 타설하여 제1버림콘크리트층을 형성하는 3 공정, 상기 3 공정에서 상기 제1버림콘크리트층이 형성되지 않은 타 영역 에 위치하는 상기 배수재를 상기 굴토마감면으로부터 이격시킨 후, 상기 타 영역의 굴토마감면에 소정 높이로 몰탈을 타설하여 제2버림콘크리트층을 형성하는 4 공정, 및 이격시킨 타 영역의 상기 배수재를 상기 제2버림콘크리트층의 상면에 위치시키는 5 공정을 포함하여 구성되는 것을 특징으로 한다.The construction method and configuration of the present invention for achieving the above object, the drainage for draining the groundwater to the sump formed on one side while preventing the high upward pressure caused by the water head difference of the groundwater generated in the bottom concrete floor of the underground building structure In the construction method for forming a, the upper surface itself after the excavation or the after-layer layer, gravel layer. One step of stopping the oyster finish surface horizontally by using a bag, etc., two steps of installing a drainage function as a drainage to allow groundwater to flow in and collect thereon, and a partial region in which the drainage material is installed; A third process of forming mortar at a predetermined height to cover the drainage material in a portion of the gulting finish surface to form a first discarded concrete layer; and in the third process, located in another region where the first discarded concrete layer is not formed After the drainage material is spaced apart from the gulting finish surface, pouring mortar at a predetermined height into the gulting finish surface of the other region to form a second discarded concrete layer; It characterized in that it comprises a five step of placing on the upper surface of the discarded concrete layer.

또한 상기 배수재를 상기 집수정과 연결시켜 상기 배수재 내의 지하수를 상기 집수정으로 흐르도록 하는 공정을 더 포함하여 구성되는 것을 일 특징으로 한다.In addition, it characterized in that it further comprises the step of connecting the drainage material to the sump well to flow the groundwater in the drainage to the sump.

또한 상기 배수재, 상기 제1버림콘크리트층 및 상기 제2버림콘크리트층의 위에 소정의 몰탈을 타설하여 바닥콘크리트층을 형성하는 공정을 더 포함하여 구성되는 것을 일 특징으로 한다.The method may further include forming a bottom concrete layer by pouring a predetermined mortar on the drainage material, the first cast concrete layer and the second cast concrete layer.

또한 상기 4 공정에서, 상기 제2버림콘크리트층 내에 별도의 배수재를 추가하여 구비하는 것을 일 특징으로 한다.In addition, in the step 4, it is characterized in that the additional drain material is provided in the second cast concrete layer.

또한 지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로를 형성시키는 시공방법에 있어서, 굴토 후의 상면 자체 또는 잔토층, 자갈층, 버럭 등을 이용하여 굴토마감면이 수평을 이루도록 정지하는 1 공정, 상기 굴토마감면 위에, 지하수가 유입되어 모아져 흐르도록 하기 위한 배수로 기능을 하는 제1배수재를 설치하는 2 공정, 상기 배수재가 설치된 영역 및 상기 굴토마감면에 상기 제1배수재를 덮도록 소정 높이로 몰탈을 타설하여 버림콘크리트층을 형성하는 3 공정, 상기 3 공정 후 상기 버림콘크리트층의 상측에 제2배수재를 설치하는 4 공정, 및 상기 제1배수재와 상기 제2배수재가 서로 연통되도록 연결시키는 5 공정을 포함하여 구성되는 것을 일 특징으로 한다.In addition, in the construction method of forming a drainage path for draining the groundwater to the sump well formed on one side while preventing the high up-water pressure caused by the water head difference of the ground concrete generated in the lower concrete floor of the underground building structure, the upper surface itself after the excavation or after the earth soil layer , 1 step of stopping the oyster finish surface horizontally by using a gravel layer, a block, etc., 2 process of installing a first drainage that functions as a drainage for the groundwater flows into the collected flow through the gulto finish surface, the drainage 4 to form the discarded concrete layer by pouring mortar to a predetermined height so as to cover the first drainage material in the region where the pit is finished and the gulting finish surface, and after the step 3, to install a second drainage material on the upper side of the discarded concrete layer. And five steps of connecting the first drain and the second drain to communicate with each other. And the work being configured.

또한 상기 제1배수재 또는 상기 제2배수재를 상기 집수정과 연결시켜 상기 제1배수재 또는 상기 제2배수재 내의 지하수를 상기 집수정으로 흐르도록 하는 공정을 더 포함하여 구성되는 것을 일 특징으로 한다.In addition, it characterized in that it further comprises a step of connecting the first drain or the second drain to the sump and the ground water in the first drain or the second drain to flow to the sump.

또한 상기 제2배수재 및 상기 버림콘크리트층의 위에 소정의 몰탈을 타설하여 바닥콘크리트층을 형성하는 공정을 더 포함하여 구성되는 것을 일 특징으로 한다.The method may further include forming a bottom concrete layer by pouring a predetermined mortar on the second drainage material and the discarded concrete layer.

또한 상기 제1배수재와 상기 제2배수재는 연결부재에 의해 상호 연결되는 것을 일 특징으로 한다.In addition, the first drain and the second drain is characterized in that interconnected by a connecting member.

또한 상기 연결부재는 상기 3 공정시에 매립하여 설치하는 것을 일 특징으로 한다.In addition, the connecting member is characterized in that the installation is embedded in the three process.

또한 상기 연결부재는 상기 버림콘크리트층의 소정 위치를 소정 형상으로 개방시켜 삽입하는 것을 일 특징으로 한다.In addition, the connecting member is characterized in that the inserting the predetermined position of the discarded concrete layer by opening in a predetermined shape.

또한 상기 3 공정에서 상기 버림콘크리트층 내에 별도의 배수재를 추가하는 것을 일 특징으로 한다.In addition, in the step 3, it is characterized in that a separate drainage material is added to the discarded concrete layer.

또한 지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로 시스템에 있어서, 굴토 후의 상면 자체 또는 잔토층, 자갈층, 버럭 등을 이용하여 형성된 굴토마감면 위에 위치되는 제1배수재, 상기 제1배수재 와 상기 굴토마감면의 상측에 소정 높이로 몰탈이 타설되어 형성되는 버림콘크리트층, 상기 버림콘크리트층의 상측에 위치되는 제2배수재, 및 상기 제1배수재 또는 상기 제2배수재 내로 유입된 지하수가 흘러 저장되도록 연결되어 있는 집수정을 포함하여 구성되는 것을 특징으로 한다.In addition, in the drainage system for draining the groundwater to the sump well formed on one side while preventing the high upwater pressure caused by the water head difference of the ground concrete generated in the lower concrete floor of the underground building structure, the top surface itself after the excavation, or the soil layer, the gravel layer, the burglary A first drain disposed on the gulting finish surface formed by using the same, a cast concrete layer formed by pouring mortar at a predetermined height on the upper side of the first drain and the gulting finish surface; It characterized in that it comprises a drainage, and the sump is connected to the ground water flowing into the first drainage or the second drainage to be stored.

또한 상기 제1배수재와 상기 제2배수재는 일체로 형성되어 연결되어 있는 것을 일 특징으로 한다.In addition, the first drain and the second drain is characterized in that formed integrally connected.

또한 상기 제1배수재와 상기 제2배수재는 상호 분리되어 있으며, 상기 제1배수재와 상기 제2배수재는 분리된 단부가 상호 연결되는 것을 일 특징으로 한다.In addition, the first drain and the second drain is separated from each other, the first drain and the second drain is characterized in that the separated end is interconnected.

또한 상기 제1배수재와 상기 제2배수재는 상호 분리되어 있으며, 상기 제1배수재와 상기 제2배수재는 연결부재에 의해 상호 연결되는 것을 일 특징으로 한다.In addition, the first drain and the second drain is separated from each other, the first drain and the second drain is characterized in that the interconnection by a connecting member.

또한 상기 배수재는 드레인매트, 배수판, 다발관, 중공관, 호스, 플라스틱관, 유공관, 무공관, 목재, 합성수지, 비닐, 부직포 또는 콘크리트블록 중 어느 하나를 사용하여 배수로가 형성되도록 하는 것을 일 특징으로 한다.In addition, the drainage is characterized in that the drainage is formed using any one of the drain mat, drainage plate, bundle tube, hollow tube, hose, plastic tube, perforated tube, non-perforated tube, wood, synthetic resin, vinyl, non-woven fabric or concrete block. do.

또한 상기 버림콘크리트층 내에는 상기 집수정과 연결되는 제3배수재가 더 구비되는 것을 일 특징으로 한다.In addition, the discarded concrete layer is characterized in that the third drainage is further provided to be connected to the sump.

상기와 같은 본 발명의 구성을, 첨부된 도면에 도시된 각 실시례를 참조하여 보다 상세하게 설명하도록 한다.The configuration of the present invention as described above will be described in more detail with reference to each embodiment shown in the accompanying drawings.

도 3은 본 발명의 일 실시례이다. 본 발명의 배수재 시공방법은 굴토마감면 (20) 위에 제1배수재(3)를 가로 및 세로의 격자형태로 연결시키며, 이러한 연결은 커넥터를 이용하여 격자를 이루게 하거나, 커넥터 없이 직접적으로 배수재와 배수재를 연결할 수 있다. 이러한 제1배수재 중 일부는 주배수로가 되어 여러 부배수재를 통해 집수 이송된 지하수를 최종적으로 집수정(50)으로 처리하게 된다.3 is an embodiment of the present invention. The drainage construction method of the present invention connects the first drainage material 3 to the horizontal and vertical lattice shape on the gulto finish surface 20, such a connection to form a grid using a connector, or directly drainage and drainage material without a connector Can be connected. Some of the first drains become the main drainage, and finally, the groundwater transferred to the sump through the various drainages is finally treated as the sump 50.

전술한 바와 같이 여러 제1배수로(3) 중 특정 작업 조건에 의하여 집수정(50)으로 직접 연결되지 못하는 경우 또는 배수로의 높이를 다르게 해야 하는 경우에는, 굴토마감면(20) 위의 제1배수재(3)를 연결시키고, 버림콘크리트(100)를 타설한 후, 버림콘크리트(100)층 위에 집수정(50)과 직접적으로 연결되는 제2배수재(300)와 상호 연결하여, 제1배수재(3) 내의 지하수를 제2배수재(300)를 통하여 집수정(50)까지 흐르도록 유도한다. As described above, when the first drainage channel 3 is not directly connected to the sump 50 by a specific working condition, or when the height of the drainage channel needs to be different, the first drainage material on the gulting finish surface 20 (3) is connected, and after casting the cast concrete 100, interconnected with the second drain 300 is directly connected to the sump 50 on the cast concrete 100, the first drain (3) ) Guides the groundwater in the flow through the second drain 300 to the sump (50).

제1배수재(3)와 제2배수재(300)의 형태는 드레인매트, 배수판, 다발관, 중공관, 호스, 플라스틱관, 유공관 또는 무공관 등 다양하게 구성될 수 있으며, 특히, 다발관의 경우 S형 다발관이나 판형 다발관을 사용할 수 있다. 또한, 제1배수재(3)와 제2배수재(300)는 그 재질이 목재, 합성수지, 토목섬유(직물, 편물 및 부직포를 포함하는 의미임), 콘크리트 블록 또는 스티로폼 등 다양하게 선택할 수 있다. 즉, 버림콘크리트(100) 층 내에서 지하수가 흐르는 일정 공간을 확보하기 위한 거푸집 기능을 하는 구성이라면 특별한 제한이 없다.The shape of the first drainage material 3 and the second drainage material 300 may be variously configured such as a drain mat, a drainage plate, a bundle pipe, a hollow pipe, a hose, a plastic pipe, a hole pipe, or a non-pipe pipe, and in particular, a bundle pipe S-shaped bundle tubes or plate-shaped bundle tubes may be used. In addition, the first drainage material 3 and the second drainage material 300 may be variously selected from materials such as wood, synthetic resin, geotextiles (meaning fabric, knitted fabric and nonwoven fabric), concrete block, or styrofoam. That is, there is no particular limitation as long as it has a formwork function for securing a predetermined space in which groundwater flows within the discarded concrete 100 layer.

이 때, 제1배수재(3)와 제1배수재(300)는 일체형이거나, 직접적으로 연결시킬 수도 있으며, 연결의 편의를 위하여 슬리브 또는 커넥터와 같은 연결부재(400)를 중간에 구비할 수도 있다. 이러한 커넥터의 형태는 PVC관, 중공관, 유공관, 사 각박스형으로 구성하는 것이 가능하며, 슬리브는 스틸관, P.E관 등을 사용하는 것이 가능하다.At this time, the first drainage material 3 and the first drainage material 300 may be integrated or directly connected, or may be provided with a connecting member 400 such as a sleeve or a connector in the middle for convenience of connection. Such a connector can be configured as a PVC tube, a hollow tube, a perforated tube, a square box type, and the sleeve may use a steel tube, a P.E tube, or the like.

상기 연결부재(400)는 제1배수재(3)에 미리 커넥터 또는 슬리브를 연결한 후 버림콘크리트를 타설하여 제2배수재(300)와의 연결을 위한 포인트를 제공하거나, 타설된 버림콘크리트를 천공하여 개방부를 형성시켜 커넥터 또는 슬리브를 장착 후 제1배수재(3)와 제2배수재(300)을 연결할 수 있다. 아울러 전술한 바와 같이, 이러한 연결부재(400)의 사용 없이 직접적으로 제1배수재(3)와 제2배수재(300)를 연결할 수도있으며, 처음부터 일체의 배수재를 사용하여 여러 높이로 시공하는 방법도 가능하다. 이에 대해서는 후술하도록 한다.The connecting member 400 connects the connector or the sleeve to the first drainage material 3 in advance, and then casts the discarded concrete to provide a point for connection with the second drainage 300, or opens the drilled discarded concrete. By forming a part, the first drain 3 and the second drain 300 may be connected after the connector or the sleeve is mounted. In addition, as described above, the first drainage material 3 and the second drainage material 300 may be directly connected to each other without the use of the connecting member 400. Also, a method of constructing at various heights using a single drainage material from the beginning may also be used. It is possible. This will be described later.

본 발명의 시공방법에서도 통상의 지하층 시공방법과 같이 굴토마감면(20) 위 및/또는 제1배수재(3) 위에 토목섬유(편직, 직물, 부직포, 웹, 매트, 네트·그리드 및 플라스틱시트 등 포함)(60)를 깔거나, 제1배수재(3)만 토목섬유를 감싸서 사용할 수 있다. 또한, 제1배수재(3) 위에는 방수를 위하여 합성수지비닐(70)을 덮은 후 버림콘크리트를 타설할 수 있으며, 필요에 따라 굴토마감면(20) 위에도 합성수지비닐(70)을 덮은 후 제1배수재(3)를 설치할 수 있다. 즉, 합성수지비닐(70)과 토목섬유(60)는 다양한 위치에서 필요에 따라 적용하여 사용할 수 있으며 사용에 제한이 없다. 이하 도면에서는 편의상 토목섬유(60)와 합성수지비닐(70)의 도시를 생략하기도 하였다.Also in the construction method of the present invention, geotextiles (knitting, woven fabric, nonwoven fabric, web, mat, net grid and plastic sheet, etc.) on the gulting finish surface 20 and / or on the first drainage material 3 as in the conventional underground construction method. Including) 60, or only the first drain (3) can be used to wrap the geotextile. In addition, after the synthetic resin vinyl 70 is covered on the first drainage material 3 for waterproofing, the discarded concrete may be poured, and if necessary, the first drainage material may also be covered with the synthetic resin vinyl 70 on the gulto finish surface 20. 3) can be installed. In other words, the synthetic resin vinyl 70 and the geosynthetic fiber 60 can be used as needed in various locations and there is no limit to the use. In the following drawings, the geotextile 60 and the synthetic resin vinyl 70 are omitted for convenience.

도 4는 또 다른 실시례로서, 주배수로의 역할을 하던 제1배수로(3)가 집수정 (50)까지 도달하지 못한 경우에 제1배수재(3)와 제1배수재(300)의 연결방식을 보여주고 있다. 도 4를 참조하면, 양 배수재(3, 300)의 연결을 위하여 중간에 연결부재(400)가 구비되며, 연결부재(400)는 전술한 바와 같이 버림콘크리트 타설 전 미리 제1배수재(3) 또는 제2배수재(300)에 연결 시킬 수 있으나, 버림콘크리트 타설 후 천공을 하여 연결부재(400)를 제1배수재(3)에 연결한 후 다시 제2배수재(300)를 연결할 수도 있다.4 is another embodiment, in which the first drainage 3 and the first drainage 300 is connected when the first drainage 3 serving as the main drainage does not reach the catchment 50. Is showing. 4, the connection member 400 is provided in the middle for the connection of both drains (3, 300), the connection member 400 is the first drain (3) or in advance before casting concrete as described above Although it may be connected to the second drainage 300, it may be connected to the second drainage 300 again after connecting the connecting member 400 to the first drainage (3) by drilling after casting discarded concrete.

도 5a 내지 5f는 본 발명의 방법에 따라 시공되는 순서를 나타낸 단면도이다. 도 5a 내지 5f를 참조하면, 일체의 배수재를 별도의 연결부재 없이 시공하는 방법을 나타낸다. 도 5a는 지하층을 파낸 후에 굴토마감면(20)을 형성하는 단계이고, 도 5b는 굴토마감면(20)의 상측에, 배수재(3)를 배치하는 단계이다.5a to 5f are cross-sectional views illustrating the sequence of construction according to the method of the present invention. 5A to 5F, a method of constructing an integral drainage without a separate connecting member is shown. FIG. 5A illustrates a step of forming a gulting finish surface 20 after digging a basement layer, and FIG. 5B is a step of arranging a drain 3 on an upper side of the gulting finish surface 20.

배수재(3)를 배치하고, 토목섬유, 합성수지 비닐 등을 배수재 또는 그 주위에 깔거나, 감은 후에는 콘크리트 몰탈을 타설하여 소정 높이의 제1버림콘크리트층(101)을 형성한다. 이 때 제1버림콘크리트층(101)은 도 5c에서와 같이 전체 굴토마감면(20) 중 일부의 면적, 또는 일부의 위치에만 형성하도록 한다. 따라서 제1버림콘크리트층(101)을 형성하고 난 후 배수재(3)의 일부분은 제1버림콘크리트층(101)에 의해 매몰되나, 다른 부분은 외부로 개방된 상태에 놓이게 된다.After the drainage material 3 is disposed and geotextiles, synthetic resin vinyl, and the like are laid or wrapped around the drainage material or wrapped around it, concrete mortar is poured to form the first cast concrete layer 101 having a predetermined height. At this time, as shown in FIG. 5C, the first discarded concrete layer 101 may be formed only at an area of a part of the entire gulting finish surface 20 or at a part of the location. Therefore, after the first cast concrete layer 101 is formed, a part of the drain material 3 is buried by the first cast concrete layer 101, but the other part is placed in an open state to the outside.

이 후 도 5d와 같이 제1버림콘크리트층(101)에 의해 매몰되지 않은 부분의 배수재(3)를 굴토마감면(20)으로부터 들어 올리거나, 일측으로 감아 이격시킨 후, [5]와 같이 타설되지 않은 부분에 대하여 콘크리트 몰탈을 타설하여 제2버림콘크리 트층(102)을 형성한다. 제2버림콘크리트층(102)은 제1버림콘크리트층(101)과 나란히 형성할 수도 있고, 서로 높이를 달리하여 구성할 수도 있다. 또한 제1버림콘크리트층(101)이 완전히 양생된 후에 제2버림콘크리트층(101)을 형성할 수도 있고, 제1버림콘크리트층(101)이 타설된 후 바로 배수재(3)를 이격시켜 제2버림콘크리트층(102)을 타설할 수도 있다.Thereafter, as shown in FIG. 5D, the drainage material 3 of the portion not buried by the first cast concrete layer 101 is lifted from the gulting finish surface 20, or rolled to one side, and then placed as shown in [5]. The second mortar concrete layer 102 is formed by pouring concrete mortar for the portion that is not. The second discarded concrete layer 102 may be formed in parallel with the first discarded concrete layer 101, or may be configured to have different heights from each other. In addition, after the first cast concrete layer 101 is completely cured, the second cast concrete layer 101 may be formed, or after the first cast concrete layer 101 is poured, the drainage material 3 may be spaced apart from the second cast material. The discarded concrete layer 102 may be poured.

도 6a 내지 6g는 본 발명의 다른 방법에 따라 시공되는 순서를 나타낸 단면도이다. 도 6a 내지 6g를 참조하면, 두 개 이상의 배수재를 연결하여 시공하는 방법을 나타낸다. 도 6a 와 같이 형성된 굴토마감면(20) 상의 소정 위치에 도 6b와 같이 제1배수재(3)를 위치시키고, 그 상측에 도 6c와 같이 콘크리트 몰탈을 타설하여 버림콘크리트층(100)을 형성한다. 6a to 6g are cross-sectional views showing the sequence of construction according to another method of the present invention. 6A to 6G, a method of connecting two or more drainage materials is shown. The first drainage material 3 is positioned as shown in FIG. 6B at a predetermined position on the gulting finish surface 20 formed as shown in FIG. 6A, and concrete mortar is poured on the upper side thereof to form the discarded concrete layer 100. .

버림콘크리트층(100)에는 도 6d와 같이 천공작업을 통하거나, 별도의 거푸집, 커넥터, 슬리브 등을 이용하여 개방부(103)를 형성하도록 한다. 도 6e 내지 6g는 다양한 방식의 연결부재(401, 402, 403) 제1배수재(3)와 제2배수재(300)를 연결한 방식을 나타낸다. 도 6e와 같이 연결부재(401)가 버림콘크리트층(100)을 관통할 수도 있으며, 도 6f와 같이 연결부재(402)가 버림콘크리트층(100) 내에 위치하거나, 도 6g와 같이 연결부재(403)이 버림콘크리트층(100) 상층에 위치할 수도 있다.The discarded concrete layer 100 may be formed through the drilling operation as shown in FIG. 6D or by using an additional formwork, a connector, a sleeve, or the like, to form the opening 103. 6E to 6G illustrate a method in which the first draining material 3 and the second draining material 300 are connected to the connection members 401, 402, and 403 of various methods. As shown in FIG. 6E, the connecting member 401 may penetrate the discarded concrete layer 100, and as illustrated in FIG. 6F, the connecting member 402 may be located in the discarded concrete layer 100 or as illustrated in FIG. 6G. ) May be located above the discarded concrete layer 100.

경우에 따라서는 버림콘크리트(100)를 타설하기 이전에 제1배수재(3)와 제2배수재(300)를 연결시킨 후, 버림콘크리트(100)를 타설해 가면서 제1배수재(3)는 굴토마감면(20)에 접촉되도록, 제2배수재(300)는 일정 높이 위에 위치하도록 구성 할 수도 있다. 아울러 제1배수재(3)와 제2배수재(300)가 상호 높이차를 갖도록 하는 공정은, 2회 이상 반복되어 다단의 형상을 이루는 것도 가능하다.In some cases, the first drainage material 3 is connected to the first drainage material 3 and the second drainage material 300 before the casting concrete 100 is poured. To be in contact with the reduction surface 20, the second drain 300 may be configured to be positioned above a certain height. In addition, the process of making the 1st drainage material 3 and the 2nd drainage material 300 have a mutual height difference can also be repeated 2 or more times, and can form a multistage shape.

도 7은 또 다른 실시례로서, 여러 개의 제1배수재(3)를 하나의 제2배수재(300)에 연결한 모습을 보여주고 있다. 도 5와 같이 본 발명에서는 제1배수재(3)와 제2배수재(300) 사이의 연결 형태, 구성에 특별히 제한을 두지 않으며, 제1배수재(3)와 제2배수재(300)의 연결을 통하여 실제 시공 현장에서 바닥콘크리트(200)의 이음시공, 제1배수재(3)의 파손 등에 의하여 제1배수재(3)가 집수정(50)까지 연결되지 못하는 경우 본 발명의 방법을 사용함으로써 단락된 제1배수재(3)를 제2배수재(300)를 통하여 집수정까지 통하게 할 수 있다.FIG. 7 shows another embodiment in which several first drainers 3 are connected to one second drainer 300. In the present invention, as shown in FIG. 5, no particular limitation is imposed on the configuration and configuration of the connection between the first drain 3 and the second drain 300, and through the connection of the first drain 3 and the second drain 300. When the first drainage material 3 is not connected to the sump well 50 due to the joint construction of the floor concrete 200 at the actual construction site, the breakage of the first drainage material 3, etc. The first drain 3 may be led to the sump through the second drain 300.

도 8은 또 다른 실시례로서, 제2배수재(300)와 연결되어 있는 제1배수재(3a)와 버림콘크리트층(100)에서 집수정까지 연결된 배수재(3c)에 의해 연결되어 있는 배수재(3b)를 보여주고 있다. 이처럼 본 발명에서는 모든 배수재가 제2배수재(300)와 연결되어 집수정까지 통하게 되어야 함을 의미하는 것이 아니며, 필요에 따라 선택적으로 제1배수재(3)를 제2배수재(300)와 연결시켜 사용할 수 있음을 특징으로 하는 것임을 알 수 있다.8 is another embodiment, the drainage material 3b connected by the first drainage material 3a connected to the second drainage material 300 and the drainage material 3c connected from the discarded concrete layer 100 to the sump well. Is showing. As described above, the present invention does not mean that all drainage materials are connected to the second drainage material 300 so that the water collecting wells may be passed through. Optionally, the first drainage material 3 may be selectively connected to the second drainage material 300 when necessary. It can be seen that it is characterized by.

도 9의 사시도와 도 10의 단면도는 종래 고안기술인 실용신안등록 제314875호의 커넥터를 본 발명의 공법에 적용할 수 있도록 개량한 커넥터(1000)로서, 종래 와는 달리 상부케이스(110)의 적당한 위치에 개구부(140)를 설치하여 이 부분을 통하여 제2배수재(300)와 연결을 할 수 있다.9 is a perspective view of Figure 10 and the cross-sectional view of Figure 10 is a connector 1000 improved to be applicable to the method of the present invention Utility Model Registration No. 314875, which is a conventional design technology, unlike the prior art in the proper position of the upper case 110 The opening 140 may be installed to connect with the second drain 300 through this portion.

도 11은 커넥터(1000)을 이용하여 제1배수재(3a, 3b)를 제2배수재(300)와 연결시킨 모습을 나타낸다. 도 11에서는 각 배수재들의 연결 상태를 이해하기 위하여 버림콘크리트(100)와 바닥콘크리트(200)를 도시하지 않았다. 제1배수재(3) 중 집수 역할을 하는 배수재(3a)가 커넥터(1000)에 연결되어 있으며, 주배수로 역할을 하는 배수재(3b)의 경우 집수정(50)까지 연결되지 못한 상태로 커넥터(1000)와 연결되어 있다. 따라서, 도 11과 같이 커넥터(1000)의 상부 개구부(140)을 통하여 제2배수재(300)와 연결되어 최종적으로 집수정(50)까지 연통하게 된다.11 illustrates a state in which the first drains 3a and 3b are connected to the second drains 300 using the connector 1000. In FIG. 11, the discarded concrete 100 and the bottom concrete 200 are not illustrated in order to understand the connection state of the respective drainage materials. The drainage material 3a, which serves as a catchment of the first drainage material 3, is connected to the connector 1000. In the case of the drainage material 3b, which serves as the main drainage, the connector 1000 may not be connected to the water collecting well 50. ) Therefore, as shown in FIG. 11, the second drain member 300 is connected through the upper opening 140 of the connector 1000 to finally communicate with the collecting well 50.

도 12은 도 11의 단면도로서, 본 발명의 커넥터(1000)을 사용하여 제1배수재(3a, 3b)를 격자형태로 연결한 후 개구부(140)를 통하여 제2배수재(300)와 연결된 모습을 보여주고 있다. 일반적으로 커넥터(1000)를 사용하는 경우 주배수로로 다발관 형태의 배수재(3b)를 사용하고 집수를 위한 배수재로는 드레인매트(3a)를 사용하는 것이 바람직하다.FIG. 12 is a cross-sectional view of FIG. 11 and illustrates a state in which the first drainers 3a and 3b are connected to the second drainer 300 through the opening 140 after the first drainers 3a and 3b are connected in a lattice form using the connector 1000 of the present invention. Is showing. In general, when the connector 1000 is used, it is preferable to use a drain pipe 3b in the form of a bundle pipe as a main drain and to use a drain mat 3a as a drain for drainage.

도 13a는 본 발명에 있어서, 제2배수재(300)의 형태가 단순히 일자형이 아닌 다양한 변화를 가질 수 있음을 보여주기 위하여 도시한 것으로서, 특히 도 13과 같이 중간에 "∩"형을 형성하게 할 수 있다. 상기 "∩"형의 제2배수재(300)는 제1배 수재(3)의 일측에 연결부재(400)로서 설치된 슬리브를 연장하거나 바닥콘크리트(200)에 매설되는 철근 또는 철망에 최상 굴곡부를 결속하여 설치할 수 있다. 제2배수재(300)의 일부에 "∩"형을 가짐으로써, 지하수의 수두차에 의하여 집수정(50)으로 유입되는 지하수의 양을 완충, 조절할 수 있는 수압조절이 가능한 배수로의 효과를 갖게 된다. 경우에 따라서는 도 13b와 같이 제2배수재(300)의 단부를 수평하게 형성할 수도 있다.FIG. 13A is a view illustrating that the shape of the second drainage material 300 may have various changes, not just a straight line, in the present invention. In particular, as shown in FIG. Can be. The second drainage material 300 of the “∩” type extends the sleeve installed as the connecting member 400 on one side of the first drainage material 3 or binds the uppermost bent portion to the reinforcing steel or the wire mesh embedded in the bottom concrete 200. Can be installed. By having a "∩" type in a part of the second drain 300, it has the effect of a hydraulic pressure control can be adjusted to buffer, regulate the amount of groundwater flowing into the sump 50 by the groundwater head difference. . In some cases, the end of the second drain 300 may be horizontally formed as shown in FIG. 13B.

도 14는 도 13과 같은 "∩"형을 갖는 제2배수재(300)와 본 발명의 커넥터(1000)을 함께 사용한 경우의 실시례이다. 도 12와는 기본적인 구조를 같이하며, 다만 제2배수재(300)이 "∩"형으로 만곡되어 있음을 알 수 있다.FIG. 14 illustrates an embodiment in which the second draining material 300 having a “∩” shape as shown in FIG. 13 is used together with the connector 1000 of the present invention. 12 is the same as the basic structure, it can be seen that the second drain 300 is curved in a "∩" type.

지금까지 설명한 바와 같이, 본 발명에서 제1배수재(3)와 제2배수재(300) 사이의 연결방식에는 제한이 없으며, 현장 상황에 따라 다양하게 변화시키면서 연결시킬 수 있으며, 제2배수재(300)의 형태도 단순한 일자형이 아닌 굴곡을 가질 수 있음을 알 수 있다. As described so far, there is no limitation in the connection method between the first drain 3 and the second drain 300 in the present invention, it can be connected in a variety of changes depending on the site situation, the second drain 300 It can be seen that the shape of may have a curve rather than a simple straight line.

이와 같이 연통되는 배수재의 높낮이가 달라지면서 시공할 수 있도록 하는 방법에 의해 시공된 배수재는, 배수재 간에 서로 차이가 있는 높이 만큼의 압력을 완충시키는 효과가 있다. 즉, 상향 수압이 증가하는 경우에, 제1배수재로부터 제2배수재까지의 높이차로 인한 압력보다 작은 경우에는, 배수재 내부에서 그 압력이 흡수되어 완충 작용을 하는 효과를 갖게 된다.The drainage material constructed by the method of allowing the construction of the drainage material communicated with each other in such a manner has the effect of buffering the pressure as much as the difference between the drainage materials. That is, when the upward hydraulic pressure is increased, if the pressure is smaller than the pressure due to the difference in height from the first drain to the second drain, the pressure is absorbed inside the drain and has a buffering effect.

이러한 본 발명은 구성과 효과는 상기 실시례들로 인하여 한정되지 아니하며, 특허청구범위에 기재된 범위 내에서 당업자가 자유롭게 변형 실시할 수 있는 범위를 포함한다.The present invention is not limited to the configuration and effects due to the above embodiments, and includes a range that can be freely modified by those skilled in the art within the scope of the claims.

본 발명에 의한 지하층 바닥 콘크리트를 이용한 배수로 시공방법은 배수로 공사에 있어서 종래의 방법에 비하여 작업 환경에 따른 유연성을 가질 수 있다는 효과를 갖는다.Drainage construction method using the basement floor concrete according to the present invention has the effect that can have flexibility according to the working environment in the drainage construction compared to the conventional method.

또한 본 발명은 연결이 끊어지거나 일체로 연결이 어려운 배수재 시공을 가능하게 할 수 있는 효과를 갖는다.In addition, the present invention has the effect that it is possible to enable the construction of the drainage difficult to disconnect or integrally connected.

또한 본 발명은 다양한 높낮이를 갖는 배수재를 상호 연결시키는 방법을 제공함에 따라, 연결이 끊어지거나, 일체로 연결이 어려운 배수재 시공을 가능하게 하는 효과를 갖는다.In addition, the present invention provides a method for interconnecting the drainage having a variety of heights, has the effect of enabling the construction of the drainage is difficult to disconnect or integrally connected.

또한 본 발명은 배수재 내에 높이차를 갖도록 하여, 상향수압의 증가에 따른 배수량 변화의 폭을 완화시키는 효과를 갖는다.In addition, the present invention is to have a height difference in the drain, it has the effect of mitigating the width of the change in displacement with the increase in the upstream pressure.

Claims (19)

지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로를 형성시키는 시공방법에 있어서,In the construction method to form a drainage path for draining the groundwater to the sump well formed on one side while preventing the high upward water pressure caused by the water head difference of the groundwater generated in the lower concrete floor of the underground building structure, 굴토 후의 상면 자체 또는 잔토층, 자갈층. 버럭 등을 이용하여 굴토마감면이 수평을 이루도록 정지하는 1 공정;The upper surface itself or the after-layer after gravel, gravel layer. 1 step of stopping so that the oyster finish surface is horizontal using a barrel or the like; 상기 굴토마감면 위에, 지하수가 유입되어 모아져 흐르도록 하기 위한 배수로 기능을 하는 배수재를 설치하는 2 공정;Two steps of installing a drain on the gulto finish surface functioning as a drain for allowing the ground water to flow in; 상기 배수재가 설치된 일부 영역 및 상기 굴토마감면의 일부 영역에 상기 배수재를 덮도록 소정 높이로 몰탈을 타설하여 제1버림콘크리트층을 형성하는 3 공정;Three steps of forming a first discarded concrete layer by pouring mortar to a predetermined height to cover the drainage material in the partial region in which the drainage material is installed and in the partial region of the gulting finish surface; 상기 3 공정에서 상기 제1버림콘크리트층이 형성되지 않은 타 영역에 위치하는 상기 배수재를 상기 굴토마감면으로부터 이격시킨 후, 상기 타 영역의 굴토마감면에 소정 높이로 몰탈을 타설하여 제2버림콘크리트층을 형성하는 4 공정; 및In the step 3, the drainage material located in the other region where the first cast concrete layer is not formed is spaced apart from the gulting finish surface, and then mortar is poured into the gulting finish surface of the other region to make the second casting concrete. 4 process of forming a layer; And 이격시킨 타 영역의 상기 배수재를 상기 제2버림콘크리트층의 상면에 위치시키는 5 공정;을 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.5. The method of constructing a groundwater drainage channel for reducing the up-water pressure of the building, characterized in that it comprises a; 5 step of placing the drainage material in the other area spaced apart on the upper surface of the second cast concrete layer. 제 1 항에 있어서,The method of claim 1, 상기 배수재를 상기 집수정과 연결시켜 상기 배수재 내의 지하수를 상기 집수정으로 흐르도록 하는 공정을 더 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.And connecting the drainage material with the sump to allow the groundwater in the drainage to flow to the sump. 제 1 항에 있어서, The method of claim 1, 상기 배수재, 상기 제1버림콘크리트층 및 상기 제2버림콘크리트층의 위에 소정의 몰탈을 타설하여 바닥콘크리트층을 형성하는 공정을 더 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Groundwater drainage for reducing the up-water pressure of the building, characterized in that it further comprises the step of forming a floor concrete layer by placing a predetermined mortar on the drainage material, the first cast concrete layer and the second cast concrete layer. Construction method. 지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로를 형성시키는 시공방법에 있어서,In the construction method to form a drainage path for draining the groundwater to the sump well formed on one side while preventing the high upward water pressure caused by the water head difference of the groundwater generated in the lower concrete floor of the underground building structure, 굴토 후의 상면 자체 또는 잔토층, 자갈층, 버럭 등을 이용하여 굴토마감면이 수평을 이루도록 정지하는 1 공정;A first step of stopping the gulto finish surface horizontally by using the upper surface itself after the gulting, or the remnant layer, the gravel layer, and the burl; 상기 굴토마감면 위에, 지하수가 유입되어 모아져 흐르도록 하기 위한 배수로 기능을 하는 제1배수재를 설치하는 2 공정;A second step of installing a first drainage material that functions as a drainage to allow the groundwater to flow in and collect on the gulto finish surface; 상기 배수재가 설치된 영역 및 상기 굴토마감면에 상기 제1배수재를 덮도록 소정 높이로 몰탈을 타설하여 버림콘크리트층을 형성하는 3 공정;3 to form a cast concrete layer by pouring mortar to a predetermined height so as to cover the first drainage material in a region where the drainage material is installed and the gulting finish surface; 상기 3 공정 후 상기 버림콘크리트층의 상측에 제2배수재를 설치하는 4 공정; 및Four steps of installing a second drainage material on the discarded concrete layer after the three steps; And 상기 제1배수재와 상기 제2배수재가 서로 연통되도록 연결시키는 5 공정;을 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.And a fifth process of connecting the first drain and the second drain to communicate with each other. 3. 제 4 항에 있어서,The method of claim 4, wherein 상기 제1배수재 또는 상기 제2배수재를 상기 집수정과 연결시켜 상기 제1배수재 또는 상기 제2배수재 내의 지하수를 상기 집수정으로 흐르도록 하는 공정을 더 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Connecting the first drain or the second drain to the sump to flow groundwater in the first or second drain to the sump; Groundwater drainage method for reduction. 제 4 항에 있어서, The method of claim 4, wherein 상기 제2배수재 및 상기 버림콘크리트층의 위에 소정의 몰탈을 타설하여 바닥콘크리트층을 형성하는 공정을 더 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.And forming a bottom concrete layer by pouring a predetermined mortar on the second drainage material and the discarded concrete layer. 제 4 항에 있어서, The method of claim 4, wherein 상기 제1배수재와 상기 제2배수재는 연결부재에 의해 상호 연결되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Groundwater drainage construction method for reducing the up-water pressure of the building, characterized in that the first drain and the second drain is interconnected by a connecting member. 제 7 항에 있어서,The method of claim 7, wherein 상기 연결부재는 상기 3 공정시에 매립하여 설치하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.The connecting member is a groundwater drainage construction method for reducing the up-water pressure of the building, characterized in that the installation is buried in the three process. 제 7 항에 있어서,The method of claim 7, wherein 상기 연결부재는 상기 버림콘크리트층의 소정 위치를 소정 형상으로 개방시켜 삽입하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.The connecting member is a groundwater drainage construction method for reducing the up-water pressure of the building, characterized in that for inserting by opening a predetermined position of the discarded concrete layer in a predetermined shape. 지하 건축 구조물의 바닥콘크리트 하부층에서 발생되는 지하수의 수두차에 의한 높은 상향수압을 방지시키면서 지하수를 일측에 형성된 집수정으로 배수시키기 위한 배수로 시스템에 있어서,In the drainage system for draining the groundwater to the sump well formed on one side while preventing the high upwater pressure caused by the water head difference of the groundwater generated in the lower concrete floor of the underground building structure, 굴토 후의 상면 자체 또는 잔토층, 자갈층, 버럭 등을 이용하여 형성된 굴토마감면 위에 위치되는 제1배수재;A first drainage material positioned on the top surface itself after the gulting or on the gulting finish surface formed by using a residual soil layer, a gravel layer, a burl, or the like; 상기 제1배수재와 상기 굴토마감면의 상측에 소정 높이로 몰탈이 타설되어 형성되는 버림콘크리트층;A discarded concrete layer formed by pouring mortar to a predetermined height above the first drainage material and the gulting finish surface; 상기 버림콘크리트층의 상측에 위치되는 제2배수재; 및A second drainage material disposed above the discarded concrete layer; And 상기 제1배수재 또는 상기 제2배수재 내로 유입된 지하수가 흘러 저장되도록 연결되어 있는 집수정;을 포함하여 구성되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.Groundwater drainage system for reducing the up-water pressure of the building, characterized in that it comprises a; a water collecting well connected to the ground water flows into the first drain or the second drain. 제 10 항에 있어서,The method of claim 10, 상기 제1배수재와 상기 제2배수재는 일체로 형성되어 연결되어 있는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.The ground drainage system for reducing the up-water pressure of the building, characterized in that the first drain and the second drain is formed integrally connected. 제 10 항에 있어서,The method of claim 10, 상기 제1배수재와 상기 제2배수재는 상호 분리되어 있으며,The first drain and the second drain is separated from each other, 상기 제1배수재와 상기 제2배수재는 분리된 단부가 상호 연결되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.Groundwater drainage system for reducing the up-water pressure of the building, characterized in that the first drain and the second drain is separated end is interconnected. 제 10 항에 있어서,The method of claim 10, 상기 제1배수재와 상기 제2배수재는 상호 분리되어 있으며,The first drain and the second drain is separated from each other, 상기 제1배수재와 상기 제2배수재는 연결부재에 의해 상호 연결되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.Groundwater drainage system for reducing the up-water pressure of the building, characterized in that the first drain and the second drain is interconnected by a connecting member. 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 배수재는:The drainage device of claim 1, wherein the drainage material is: 드레인매트, 배수판, 다발관, 중공관, 호스, 플라스틱관, 유공관, 무공관, 목재, 합성수지, 비닐, 부직포 또는 콘크리트블록 중 어느 하나를 사용하여 배수로가 형성되도록 하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Upward pressure of the building, characterized in that the drainage channel is formed by using any one of the drain mat, drain plate, bundle pipe, hollow pipe, hose, plastic pipe, oil pipe, non-pipe, wood, synthetic resin, vinyl, non-woven fabric or concrete block Groundwater drainage method for reduction. 제 4 항 내지 제 9 항 중 어느 한 항에 있어서, 상기 제1배수재 및 상기 제2배수재는:The method of claim 4, wherein the first drain and the second drain are: 드레인매트, 배수판, 다발관, 중공관, 호스, 플라스틱관, 유공관, 무공관, 목재, 합성수지, 비닐, 부직포 또는 콘크리트블록 중 어느 하나를 사용하여 배수로가 형성되도록 하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Upward pressure of the building, characterized in that the drainage channel is formed by using any one of the drain mat, drain plate, bundle pipe, hollow pipe, hose, plastic pipe, oil pipe, non-pipe, wood, synthetic resin, vinyl, non-woven fabric or concrete block Groundwater drainage method for reduction. 제 10 항 내지 제 13 항 중 어느 한 항에 있어서, 상기 제1배수재 및 상기 제2배수재는:The method of claim 10, wherein the first drain and the second drain are: 드레인매트, 배수판, 다발관, 중공관, 호스, 플라스틱관, 유공관, 무공관, 목재, 합성수지, 비닐, 부직포 또는 콘크리트블록 중 어느 하나를 사용하여 배수로가 형성되도록 하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.Upward pressure of the building, characterized in that the drainage channel is formed by using any one of the drain mat, drain plate, bundle pipe, hollow pipe, hose, plastic pipe, oil pipe, non-pipe, wood, synthetic resin, vinyl, non-woven fabric or concrete block Groundwater drainage system for reduction. 제 1 항에 있어서,The method of claim 1, 상기 4 공정에서,In the above 4 steps, 상기 제2버림콘크리트층 내에 별도의 배수재를 추가하여 구비하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Groundwater drainage construction method for reducing the up-water pressure of the building, characterized in that provided by adding a separate drain in the second cast concrete layer. 제 4 항에 있어서,The method of claim 4, wherein 상기 3 공정에서,In the above 3 steps, 상기 버림콘크리트층 내에 별도의 배수재를 추가하는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시공방법.Groundwater drainage construction method for reducing the up-water pressure of the building, characterized in that to add a separate drain in the discarded concrete layer. 제 10 항에 있어서,The method of claim 10, 상기 버림콘크리트층 내에는 상기 집수정과 연결되는 제3배수재가 더 구비되는 것을 특징으로 하는 건축물의 상향수압 감소를 위한 지하수 배수로 시스템.The groundwater drainage system for reducing the up-water pressure of the building, characterized in that the discarded concrete layer further comprises a third drainage connected to the sump.
KR1020050112879A 2005-11-24 2005-11-24 The construction method of basement drainage having double drainage canals and the system KR100656413B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050112879A KR100656413B1 (en) 2005-11-24 2005-11-24 The construction method of basement drainage having double drainage canals and the system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050112879A KR100656413B1 (en) 2005-11-24 2005-11-24 The construction method of basement drainage having double drainage canals and the system

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020050033246U Division KR200408863Y1 (en) 2005-11-24 2005-11-24 The construction system of basement drainage having double drainage canals

Publications (1)

Publication Number Publication Date
KR100656413B1 true KR100656413B1 (en) 2006-12-13

Family

ID=37732933

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050112879A KR100656413B1 (en) 2005-11-24 2005-11-24 The construction method of basement drainage having double drainage canals and the system

Country Status (1)

Country Link
KR (1) KR100656413B1 (en)

Similar Documents

Publication Publication Date Title
KR100981258B1 (en) The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid
KR20030026055A (en) a under drainage method for building using perforated drain pipes
KR100616123B1 (en) Device for drain underground water and method for construction the same
KR100753556B1 (en) De-pressure drainage method and the system
KR100665984B1 (en) The construction method of basement self drainage
KR100939311B1 (en) Prestressed quay wall and construction method thereof
KR100748607B1 (en) The construction method of basement drainage having double drainage canals and the system
KR200396485Y1 (en) Device for drain underground water for construction the same
KR100655384B1 (en) Method of drain construction for basement
KR200408863Y1 (en) The construction system of basement drainage having double drainage canals
KR100926694B1 (en) Groundwater collection and drainage system of the substructure under the underground structure
KR200433390Y1 (en) The construction system of basement drainage having double drainage canals
KR100655383B1 (en) Method of drain construction for basement
KR100656413B1 (en) The construction method of basement drainage having double drainage canals and the system
KR100665985B1 (en) The construction method of basement self drainage
KR100326868B1 (en) Drain Board and Drainage method using the same
KR200434601Y1 (en) Drain Board System Of Basement Floor Construction
KR100666102B1 (en) Vertical type basement drainage system
KR100666103B1 (en) Convertible de-pressure drainage method and the system
KR100383656B1 (en) Drainage construction method for concrete bottom of the underground floor
KR200431569Y1 (en) Hole Drain Board
KR200413305Y1 (en) Convertible de-pressure drainage system
KR100905661B1 (en) Connector and system for apparatus draining
KR20020013168A (en) A drainage construction method of ground floor
KR200446848Y1 (en) Vertical type basement drainage system

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee