KR100981258B1 - The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid - Google Patents

The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid Download PDF

Info

Publication number
KR100981258B1
KR100981258B1 KR1020090114494A KR20090114494A KR100981258B1 KR 100981258 B1 KR100981258 B1 KR 100981258B1 KR 1020090114494 A KR1020090114494 A KR 1020090114494A KR 20090114494 A KR20090114494 A KR 20090114494A KR 100981258 B1 KR100981258 B1 KR 100981258B1
Authority
KR
South Korea
Prior art keywords
retaining wall
wall block
geogrid
slope
soil
Prior art date
Application number
KR1020090114494A
Other languages
Korean (ko)
Inventor
윤정배
Original Assignee
윤정배
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤정배 filed Critical 윤정배
Priority to KR1020090114494A priority Critical patent/KR100981258B1/en
Application granted granted Critical
Publication of KR100981258B1 publication Critical patent/KR100981258B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1692Shapes conical or convex
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0084Geogrids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0085Geotextiles
    • E02D2300/0089Geotextiles non-woven

Abstract

PURPOSE: A retaining wall block for retaining wall construction and a construction method of a retaining wall using a retaining wall block and a retaining wall block and a geogrid are provided to prevent the inflow of water using water sealing mat and by reinforcing a foundation using a geogrid. CONSTITUTION: A retaining wall block for retaining wall construction is as follows. A foundation(100) is formed along a construction area floor. A retaining wall block(10) is stacked on the foundation. A drainage guide pipe(200) is filled with rubble and soil and established in the retaining wall block back side. A support stand(22) is inserted into each hook of a geogrid(20). The support stand is fitted in a hanging groove(13) of the retaining wall block. The retaining wall block is stacked on the top of the retaining wall block. The back side of the retaining wall block is filled with rubble and soil. A cutoff mat(600) is installed to the retaining wall block and construction area. The soil is installed to the top of the cutoff mat. A side ditch(700) is formed on the stepped soil.

Description

옹벽 시공을 위한 옹벽블록과 이 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법{the retaining wall block and the construction method of retaining wall with retaining wall block and geogrid }Retaining wall block and the construction method of retaining wall with retaining wall block and geogrid}

본 발명은 옹벽 시공을 위한 옹벽블록과 이 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법에 관한 것으로, 전면 상부에 좌·우 폭을 따라 걸림홈을 형성하는 육면체 형상의 옹벽블록과, 일측 가장자리를 따라 다수개의 고리를 일체로 구성한 지오그리드가 구비되어; 정리된 시공지 바닥에 기초를 형성하며; 형성한 기초를 따라 옹벽블록을 조적하고; 상기 조적된 옹벽블록 후면에는 배수유도관과 잡석이 부직포에 의해 싸이도록 설치하고, 부직포와 사면 사이에는 흙을 채우며; 구비된 지오그리드의 고리에 지지대를 끼워, 지지대를 옹벽블록의 걸림홈에 설치하여 지오그리드를 포설하며; 상기 설치된 옹벽블록 상부로 옹벽블록을 조적하고; 조적된 옹벽블록 후면에는 잡석을 감싼 부직포와 흙이 다져지도록 채우며; 이렇게 지오그리드의 설치, 옹벽블록의 조적, 그리고 옹벽블록과 사면 사이에 부직포에 싸인 잡석과 흙을 채우는 과정을 설계된 높이까지 진행한 다음; 옹벽블록과 채움된 흙 상부에, 차수매트와 흙을 순차로 포설하고; 측구의 형성으로 옹벽의 시공 방법을 완료하여; 지오그리드에 의해 지반을 보강하고, 차수매트에 의해 물의 유입을 1차로 방지하며, 옹벽블록 후면의 부직포에 쌓인 잡석을 따라, 물이 하부로 흘러내려 배수유도관을 따라 배수되므로, 시공된 옹벽의 배수를 용이하게 하고, 흙의 유실을 방지하여, 시공된 옹벽의 붕괴를 방지할 수 있는 것이다.The present invention relates to a retaining wall block for retaining wall construction, and a method of constructing a retaining wall using the retaining wall block and a geogrid. A geogrid comprising a plurality of rings integrally is provided; Form a base on the arranged construction floor; Depositing the retaining wall block along the formed base; A rear surface of the retained retaining wall block is installed so that the drainage induction pipe and the rubble are wrapped by the nonwoven fabric, and fills the soil between the nonwoven fabric and the slope; Inserting the support into the ring of the provided geogrid, install the support in the locking groove of the retaining wall block to install the geogrid; Assemble a retaining wall block above the installed retaining wall block; The retained wall block back is filled with non-woven fabric and rubble to cover the rubble; The process of installing the geogrid, masonry of the retaining wall block, and filling the rubble and soil wrapped in the nonwoven between the retaining wall block and the slope to the designed height; Placing the order mat and the soil in order on the retaining wall block and the filled soil; To complete the method of construction of the retaining wall by the formation of side openings; Geogrid reinforces the ground, prevents the inflow of water primarily by the order mat, and the rubble accumulated on the non-woven fabric at the back of the retaining wall block, and the water flows down and drains along the drainage induction pipe, so the drainage of the constructed retaining wall To facilitate, and to prevent the loss of soil, it is possible to prevent the collapse of the retaining wall constructed.

통상 옹벽은 토압에 저항하는 가장 일반적인 구조물로써, 도로, 철도, 항만, 방조제, 교대, 재개발 아파트 등 용지의 제한에 따른 토지의 최적 이용을 목적으로 사용하며, 주위에서 자주 볼 수 있는 옹벽 구조물로는 도로와 경계를 이루는 주택부지, 산기슭 등의 경사면에 설치되어, 토압 및 우수 등의 자연조건에 의해 이들이 붕괴를 막는 기능을 담당한다.Generally, the retaining wall is the most common structure that resists earth pressure. It is used for the optimal use of land due to the limitation of the land such as roads, railways, harbors, embankments, shifts, and redevelopment apartments. It is installed on the slopes of residential sites and foothills bordering roads, and is responsible for preventing them from collapsing due to natural conditions such as earth pressure and storm water.

기존에는 옹벽 구조물의 경우, 설치 높이 만큼 거푸집을 설치하여, 철근을 배근하고, 콘크리트를 타설하는 시공법이 있었으나, 최근에는, 콘크리트로 미리 단위 크기로 제조한 옹벽블록을 이용한 조립식 옹벽 공법이 다양하게 개발되고 있다.Previously, in the case of retaining wall structure, there was a construction method in which formwork was installed as much as the installation height, reinforcing reinforcing bars, and concrete was poured, but recently, various prefabricated retaining wall methods using retaining wall blocks manufactured in unit sizes of concrete have been developed in recent years. It is becoming.

그리고 옹벽블록을 이용한 시공 예로는, 국내특허등록 제0648110호에는 보강토 블록과 지오그리드를 이용한 앵커바에 의하여 결속된 보강토 블록 및 이를 이용한 설치각도 조절이 가능한 보강토 블록 설치구조 및 방법에 대한 내용이 게시되어 있고, 국내특허등록 제0386406호에는 옹벽 축조용 옹벽과 지오그리드 및 연결쇠를 이용한 조적식 옹벽 축조용 블럭구조 및 이를 이용한 옹벽 축조방법에 대한 내용이 게시되어 있다.And as an example of construction using retaining wall blocks, Korean Patent Registration No. 0648110 discloses the reinforcement earth block bound by the anchor bar using the reinforcement earth block and geogrid, and the structure and method of installing the reinforcement earth block that can adjust the installation angle using the same. , Korean Patent Registration No. 0386406 discloses the structure of the retaining wall for the retaining wall construction, the masonry retaining wall structure using the geogrid and the hinge and the retaining wall construction method using the same.

한편, 앞서 옹벽 시공으로 예시한 국내특허등록 두 가지는, 옹벽 시공에 모두 지오그리드를 포함하고 있으며, 둘 다 전면측의 지오그리드가 구속되는 것은, 각각 앵커바 또는 연결쇠에 의해서 지오그리드의 메쉬 부분을 구속하고 있는데, 이러한 경우, 지오그리드의 전면측 부분에 집중적으로 하중이 집중되므로, 설치 후에 지오그리드의 파손이 우려되었다.Meanwhile, the two domestic patent registrations exemplified in the retaining wall construction above include both the geogrids in the retaining wall construction, and both of them are constrained by the front side of the geogrid, respectively, by restricting the mesh portion of the geogrid by anchor bars or hinges. In this case, since the load is concentrated on the front side portion of the geogrid, the geogrid is broken after installation.

아울러, 옹벽블록을 시공하면서, 옹벽블록 후면에는 흙 채움을 하게 되는데, 옹벽 시공 후에는 비나 눈이 내리면서, 시공된 옹벽 상부에서 옹벽블록 후면을 타고 물이 스며들면, 채움한 흙이 같이 소실되어, 시간이 지난 후에, 옹벽블록옹벽블록괴 우려가 큰 문제점이 있었다.In addition, while constructing the retaining wall block, the back of the retaining wall block is filled with soil.After the retaining wall construction, the rain or snow falls, and when water enters the back of the retaining wall block from the top of the retained wall, the filled soil is lost. After a while, there is a big problem of retaining wall blocks.

또한, 기존의 옹벽블록은, 옹벽블록 내부에 공간을 형성하고 있고, 옹벽블록의 좌·우 폭이 전면에서 후면으로 갈수록 좁아지도록 형성하여, 커브 구간(곡선 구간, 모서리 구간)에도 옹벽블록이 용이하게 조적되도록 하는데, 그러한 옹벽블록을 직선 구간에 적용하면, 조적된 옹벽블록의 후면에는, 각 옹벽블록 사이에 공간이 발생하므로, 옹벽블록 후면을 흐르는 물이나, 뒷채움된 흙이 옹벽블록 내부로 유입되어, 옹벽블록의 내구성을 저하하고, 옹벽블록의 손상 및 옹벽 붕괴의 우려가 큰 문제점이 있었다.In addition, the existing retaining wall block forms a space inside the retaining wall block, and the left and right widths of the retaining wall block are formed to become narrower from the front side to the rear side, so that the retaining wall block is easily formed in the curved section (curve section, corner section). When the retaining wall block is applied to a straight section, space is generated between the retaining wall blocks at the rear of the retained wall block, so that water flowing through the rear wall of the retaining wall block or backfilled soil flows into the retaining wall block. As a result, the durability of the retaining wall block is reduced, and there is a great problem of the damage of the retaining wall block and the collapse of the retaining wall.

따라서 본 발명은 상기의 문제점을 해결하고자, 전면 상부에 좌·우 폭을 따라 걸림홈을 형성하는 육면체 형상의 옹벽블록과, 일측 가장자리를 따라 다수개의 고리를 일체로 구성한 지오그리드가 구비되어; 정리된 시공지 바닥에 기초를 형성하며; 형성한 기초를 따라 옹벽블록을 조적하고; 상기 조적된 옹벽블록 후면에는 배수유도관과 잡석이 부직포에 의해 싸이도록 설치하고, 부직포와 사면 사이에는 흙을 채우며; 구비된 지오그리드의 고리에 지지대를 끼워, 지지대를 옹벽블록의 걸림홈에 설치하여 지오그리드를 포설하며; 상기 설치된 옹벽블록 상부로 옹벽블록을 조적하고; 조적된 옹벽블록 후면에는 잡석을 감싼 부직포와 흙이 다져지도록 채우며; 이렇게 지오그리드의 설치, 옹벽블록의 조적, 그리고 옹벽블록과 사면 사이에 부직포에 싸인 잡석과 흙을 채우는 과정을 설계된 높이까지 진행한 다음; 옹벽블록과 채움된 흙 상부에, 차수매트와 흙을 순차로 포설하고; 측구의 형성으로 옹벽의 시공 방법을 완료하여; 지오그리드로 지반을 보강하고, 차수매트에 의해 물의 유입을 1차로 방지하며, 옹벽블록 후면의 부직포에 쌓인 잡석을 따라, 물이 하부로 흘러내려 배수유도관을 따라 배수되므로, 시공된 옹벽의 배수를 용이하게 하고, 흙의 유실을 방지하여, 시공된 옹벽의 붕괴를 방지하도록 한다.Therefore, the present invention is to solve the above problems, is provided with a retaining wall block of the hexahedral shape to form a locking groove along the left and right width in the upper front, and a geogrid consisting of a plurality of rings integrally along one side edge; Form a base on the arranged construction floor; Depositing the retaining wall block along the formed base; A rear surface of the retained retaining wall block is installed so that the drainage induction pipe and the rubble are wrapped by the nonwoven fabric, and fills the soil between the nonwoven fabric and the slope; Inserting the support into the ring of the provided geogrid, install the support in the locking groove of the retaining wall block to install the geogrid; Assemble a retaining wall block above the installed retaining wall block; The retained wall block back is filled with non-woven fabric and rubble to cover the rubble; The process of installing the geogrid, masonry of the retaining wall block, and filling the rubble and soil wrapped in the nonwoven between the retaining wall block and the slope to the designed height; Placing the order mat and the soil in order on the retaining wall block and the filled soil; To complete the method of construction of the retaining wall by the formation of side openings; Geogrid reinforces the ground, prevents the inflow of water primarily by the order mat, and the rubble accumulated on the nonwoven fabric at the back of the retaining wall block, and the water flows down and drains along the drainage induction pipe. To prevent the loss of soil and to prevent the collapse of the retaining wall.

또한, 상기 옹벽블록 후면에는 돌출된 다수개의 배수돌기를 일체로 구성하고, 상기 배수돌기에는‘

Figure 112009072470238-pat00001
’의 구조를 가지는 배수대가 일체로 구성되어, 시공된 옹벽의 옹벽블록 후면을 따라 물이 흐르되, 물은 배수돌기와, 배수대를 따라 흐르면서 배수되어, 옹벽블록 내부로 물의 유입을 방지하여, 옹벽블록의 내구성을 높이도록 한다.In addition, the rear wall of the retaining wall block is formed with a plurality of protruding drainage protrusions integrally,
Figure 112009072470238-pat00001
'Drainage having a structure of' is integrally formed, the water flows along the back wall retaining wall block of the retaining wall, water is drained and flows along the drainage, preventing the inflow of water into the retaining wall block, Make the block more durable.

상기 옹벽블록은 전면에서 후면으로 갈수록 좌·우 폭이 좁아지는 단면을 형성하되, 상기 배수돌기를 형성한 옹벽블록의 후면은 좌·우로 돌출된 돌출부를 형성하여, 옹벽블록의 후면으로 흐르는 물이 옹벽블록의 내부로 유입하는 것을 방지하도록 한다.The retaining wall block has a cross-section in which the left and right widths become narrower from the front side to the rear side, and the rear surface of the retaining wall block forming the drainage protrusion forms a protrusion protruding left and right, so that water flowing to the rear of the retaining wall block Prevent entry into the retaining wall block.

그리고 상기 옹벽블록의 후면 저면은 내측으로 경사를 형성한 경사부를 형성하여, 옹벽블록이 단차를 형성하면서 조적할 경우, 옹벽블록의 후면이 경사부에 의해서 조적된 옹벽블록의 상·하를 따라 연결되게 구성되어, 옹벽블록 내부로 물이 유입되는 것을 방지하여, 옹벽블록의 내구성을 유지할 수 있도록 한다.And the bottom surface of the rear wall of the retaining wall block forms an inclined portion formed inclined inward, when the retaining wall block is formed while forming a step, the rear surface of the retaining wall block is connected along the top and bottom of the retaining wall block is formed by the inclined portion In order to prevent water from flowing into the retaining wall block, the durability of the retaining wall block can be maintained.

아울러, 상기 시공지 사면에는 네일을 박고, 상기 지오그리드는 마주하는 양측 가장자리를 따라 고리를 형성한 것으로 구비하며, 지오그리드의 각 고리에는 지지대를 끼워, 지오그리드의 일단은 옹벽블록의 걸림홈에 구속되도록 하고, 그 타단은 사면에 박은 네일과 연결수단으로 연결하여 구속함에 따라, 지오그리드의 양단 구속과 지오그리드를 통한 보강이 용이하게 이루어지도록 한다.In addition, the construction paper slope nailed, the geogrid is provided with a ring formed along the opposite edges facing each other, each of the rings of the geogrid is fitted with a support, so that one end of the geogrid is bound to the retaining groove of the retaining wall block , The other end is constrained by connecting nails and connecting means to the slope, so that both ends of the geogrid and the reinforcement through the geogrid is easily made.

이와 같이 본 발명은, 전면 상부에 좌·우 폭을 따라 걸림홈을 형성하는 육면체 형상의 옹벽블록과, 일측 가장자리를 따라 다수개의 고리를 일체로 구성한 지오그리드가 구비되어; 정리된 시공지 바닥에 기초를 형성하며; 형성한 기초를 따라 옹벽블록을 조적하고; 상기 조적된 옹벽블록 후면에는 배수유도관과 잡석이 부직포에 의해 싸이도록 설치하고, 부직포와 사면 사이에는 흙을 채우며; 구비된 지오그 리드의 고리에 지지대를 끼워, 지지대를 옹벽블록의 걸림홈에 설치하여 지오그리드를 포설하며; 상기 설치된 옹벽블록 상부로 옹벽블록을 조적하고; 조적된 옹벽블록 후면에는 잡석을 감싼 부직포와 흙이 다져지도록 채우며; 이렇게 지오그리드의 설치, 옹벽블록의 조적, 그리고 옹벽블록과 사면 사이에 부직포에 싸인 잡석과 흙을 채우는 과정을 설계된 높이까지 진행한 다음; 옹벽블록과 채움된 흙 상부에, 차수매트와 흙을 순차로 포설하고; 측구의 형성으로 옹벽의 시공 방법을 완료하여; 지오그리드로 지반을 보강하고, 차수매트에 의해 물의 유입을 1차로 방지하며, 옹벽블록 후면의 부직포에 쌓인 잡석을 따라, 물이 하부로 흘러내려 배수유도관을 따라 배수되므로, 시공된 옹벽의 배수를 용이하게 하고, 흙의 유실이 방지되어, 시공된 옹벽의 붕괴를 방지하는 효과가 있다.As described above, the present invention includes a retaining wall block having a hexahedron shape that forms a locking groove along the left and right widths of the front surface, and a geogrid including a plurality of rings integrally formed along one edge thereof; Form a base on the arranged construction floor; Depositing the retaining wall block along the formed base; A rear surface of the retained retaining wall block is installed so that the drainage induction pipe and the rubble are wrapped by the nonwoven fabric, and fills the soil between the nonwoven fabric and the slope; Inserting the support into the loop of the provided geogrid, and installing the support in the locking groove of the retaining wall block to install the geogrid; Assemble a retaining wall block above the installed retaining wall block; The retained wall block back is filled with non-woven fabric and rubble to cover the rubble; The process of installing the geogrid, masonry of the retaining wall block, and filling the rubble and soil wrapped in the nonwoven between the retaining wall block and the slope to the designed height; Placing the order mat and the soil in order on the retaining wall block and the filled soil; To complete the method of construction of the retaining wall by the formation of side openings; Geogrid reinforces the ground, prevents the inflow of water primarily by the order mat, and the rubble accumulated on the nonwoven fabric at the back of the retaining wall block, and the water flows down and drains along the drainage induction pipe. It is easy to prevent the loss of the soil, there is an effect of preventing the collapse of the retaining wall constructed.

또한, 상기 옹벽블록 후면에는 돌출된 다수개의 배수돌기를 일체로 구성하고, 상기 배수돌기에는‘

Figure 112009072470238-pat00002
’의 구조를 가지는 배수대가 일체로 구성되어, 시공된 옹벽의 옹벽블록 후면을 따라 물이 흐르되, 물은 배수돌기와, 배수대를 따라 흐르면서 배수되어, 옹벽블록 내부로 물의 유입을 방지하여, 옹벽블록의 내구성이 높은 효과가 있다.In addition, the rear wall of the retaining wall block is formed with a plurality of protruding drainage protrusions integrally,
Figure 112009072470238-pat00002
'Drainage having a structure of' is integrally formed, the water flows along the back wall retaining wall block of the retaining wall, water is drained and flows along the drainage, preventing the inflow of water into the retaining wall block, The block has a high durability.

상기 옹벽블록은 전면에서 후면으로 갈수록 좌·우 폭이 좁아지는 단면을 형성하되, 상기 배수돌기를 형성한 옹벽블록의 후면은 좌·우로 돌출된 돌출부를 형성하여, 옹벽블록의 후면으로 흐르는 물이 옹벽블록의 내부로 유입하는 것을 방지하는 효과가 있다.The retaining wall block has a cross-section in which the left and right widths become narrower from the front side to the rear side, and the rear surface of the retaining wall block forming the drainage protrusion forms a protrusion protruding left and right, so that water flowing to the rear of the retaining wall block It is effective to prevent the flow into the retaining wall block.

그리고 상기 옹벽블록의 후면 저면은 내측으로 경사를 형성한 경사부를 형성 하여, 옹벽블록이 단차를 형성하면서 조적할 경우, 옹벽블록의 후면이 경사부에 의해서 조적된 옹벽블록의 상·하를 따라 연결되게 구성되어, 옹벽블록 내부로 물이 유입되는 것을 방지하여, 옹벽블록의 내구성을 유지해 주는 효과가 있다.And the bottom surface of the rear wall of the retaining wall block forms an inclined portion formed inclined inward, when the retaining wall block is formed while forming a step, the rear wall of the retaining wall block is connected along the top and bottom of the retaining wall block formed by the inclined portion It is configured to prevent water from flowing into the retaining wall block, thereby maintaining the durability of the retaining wall block.

아울러, 상기 시공지 사면에는 네일을 박고, 상기 지오그리드는 마주하는 양측 가장자리를 따라 고리를 형성한 것으로 구비하며, 지오그리드의 각 고리에는 지지대를 끼워, 지오그리드의 일단은 옹벽블록의 걸림홈에 구속되도록 하고, 그 타단은 사면에 박은 네일과 연결수단으로 연결하여 구속함에 따라, 지오그리드의 양단 구속과 지오그리드를 통한 보강이 용이한 효과가 있다.In addition, the construction paper slope nailed, the geogrid is provided with a ring formed along the opposite edges facing each other, each of the rings of the geogrid is fitted with a support, so that one end of the geogrid is bound to the retaining groove of the retaining wall block , The other end is constrained by the nail nailed to the slope and connecting means, there is an easy effect of both ends of the geogrid and reinforcement through the geogrid.

본 발명은 옹벽 시공을 위한 옹벽블록과 이 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법에 관한 것으로, 전면 상부에 좌·우 폭을 따라 걸림홈을 형성하는 육면체 형상의 옹벽블록과, 일측 가장자리를 따라 다수개의 고리를 일체로 구성한 지오그리드가 구비되어; 정리된 시공지 바닥에 기초를 형성하며; 형성한 기초를 따라 옹벽블록을 조적하고; 상기 조적된 옹벽블록 후면에는 배수유도관과 잡석이 부직포에 의해 싸이도록 설치하고, 부직포와 사면 사이에는 흙을 채우며; 구비된 지오그리드의 고리에 지지대를 끼워, 지지대를 옹벽블록의 걸림홈에 설치하여 지오그리드를 포설하며; 상기 설치된 옹벽블록 상부로 옹벽블록을 조적하고; 조적된 옹벽블록 후면에는 잡석을 감싼 부직포와 흙이 다져지도록 채우며; 이렇게 지오그리드의 설치, 옹벽블록의 조적, 그리고 옹벽블록과 사면 사이에 부직포에 싸인 잡석과 흙을 채우는 과정을 설계된 높이까지 진행한 다음; 옹벽블록과 채움된 흙 상부에, 차수매트와 흙을 순차로 포설하고; 측구의 형성으로 옹벽의 시공 방법을 완료하여; 지오그리드에 의해 지반을 보강하고, 차수매트에 의해 물의 유입을 1차로 방지하며, 옹벽블록 후면의 부직포에 쌓인 잡석을 따라, 물이 하부로 흘러내려 배수유도관을 따라 배수되므로, 시공된 옹벽의 배수를 용이하게 하고, 흙의 유실을 방지하여, 시공된 옹벽의 붕괴를 방지할 수 있는 것이다.The present invention relates to a retaining wall block for retaining wall construction, and a method of constructing a retaining wall using the retaining wall block and a geogrid. A geogrid comprising a plurality of rings integrally is provided; Form a base on the arranged construction floor; Depositing the retaining wall block along the formed base; A rear surface of the retained retaining wall block is installed so that the drainage induction pipe and the rubble are wrapped by the nonwoven fabric, and fills the soil between the nonwoven fabric and the slope; Inserting the support into the ring of the provided geogrid, install the support in the locking groove of the retaining wall block to install the geogrid; Assemble a retaining wall block above the installed retaining wall block; The retained wall block back is filled with non-woven fabric and rubble to cover the rubble; The process of installing the geogrid, masonry of the retaining wall block, and filling the rubble and soil wrapped in the nonwoven between the retaining wall block and the slope to the designed height; Placing the order mat and the soil in order on the retaining wall block and the filled soil; To complete the method of construction of the retaining wall by the formation of side openings; Geogrid reinforces the ground, prevents the inflow of water primarily by the order mat, and the rubble accumulated on the non-woven fabric at the back of the retaining wall block, and the water flows down and drains along the drainage induction pipe, so the drainage of the constructed retaining wall To facilitate, and to prevent the loss of soil, it is possible to prevent the collapse of the retaining wall constructed.

본 발명에 따른 옹벽블록과 지오그리드의 구조를 순차로 설명하면 다음과 같다.The structure of the retaining wall block and the geogrid according to the present invention will be described as follows.

먼저, 옹벽블록(10)은, 도3에 도시한 바와 같이, 육면체의 형상으로 구성되며, 내부에 상·하로 트인 끼움부(11)를 형성하고 있으며, 또한, 전면에서 후면으로 갈수록 좌·우로 좁아지는 폭을 형성하여, 전면에서 후면으로 갈수록 좁은 단면을 형성한다.First, as shown in FIG. 3, the retaining wall block 10 is configured in the shape of a cube, and forms a fitting portion 11 which is opened up and down inside, and from left to right as it goes from front to back. By forming a narrower width, a narrower cross section is formed from the front side to the rear side.

추가로, 옹벽블록(10)의 후면에는 좌·우 방향으로 돌출된 돌출부(15)를 일체로 형성하며, 상기 돌출부(15)를 포함하는 후면 길이는 전면 길이를 넘지 않는 것이 바람직하며, 이러한 돌출부(15)는, 옹벽블록(10)의 후면을 따라 흐르는 물이 옹벽블록(10) 내부로 유입되는 것을 방지한다.In addition, the rear surface of the retaining wall block 10 is integrally formed with a protrusion 15 protruding in the left and right directions, the rear length including the protrusion 15 is preferably not exceed the front length, such a protrusion 15 prevents water flowing along the rear surface of the retaining wall block 10 from flowing into the retaining wall block 10.

그리고 옹벽블록(10)의 상부에는 상부로 돌출된 걸림턱(12)을 다수개 형성하는데, 걸림턱(12)의 위치는, 옹벽블록(10)을 상·하로 쌓되, 걸림턱(12)은 상부의 옹벽블록(10)과 서로 간섭이 되지 않는 위치에 형성하는 것이 바람직한데, 옹벽블록(10)을 조적하면서 끼움부(11)는, 걸림턱(12)이 끼움되는 공간을 형성하므로, 끼움부(11)는 관통되지 않고, 걸림턱(12)의 간섭을 받지 않는 홈으로 형성되어도 무방하다.In addition, a plurality of locking projections 12 protruding upwardly are formed at the upper portion of the retaining wall block 10, and the positions of the locking projections 12 are stacked on the retaining wall block 10 up and down, and the locking projections 12 are The retaining wall block 10 is preferably formed in a position where it does not interfere with each other. While the retaining wall block 10 is fitted, the fitting portion 11 forms a space in which the locking step 12 is fitted, The part 11 may not be penetrated and may be formed as a groove which does not receive the interference of the locking step 12.

아울러, 상기 옹벽블록(10)의 전면 상부에는 전면과 평행하게 일자 형태로 파인 걸림홈(13)을 형성하는데, 자세하게는, 상기 걸림홈(13)에는 옹벽블록(10)의 전면과 평행하게 지지대(22)(22′)가 삽입될 수 있는 구조이다.In addition, the front of the retaining wall block 10 to form a locking groove 13 in the form of a straight parallel to the front surface, in detail, the locking groove 13 is supported in parallel with the front of the retaining wall block 10 (22) (22 ') can be inserted.

참고로, 지지대(22)(22′)는 후설하는 지오그리드(20)의 고리(21)(21′)를 끼워, 상기 옹벽블록(10)에 걸림홈(13)에 끼움되는 것으로, 도2 및 도6에 도시한 바와 같이, 지지대(22)(22′)는 원형, 사각, 및 기타 다각형 등 다양한 단면으로 일정 길이를 가지도록 형성하되, 내구성과 강도, 굽힘강도 등이 우수한 것을 사용하는 것이 바람직한데, 예를 들어, 지지대(22)(22′)는 봉, 파이프, 사각봉 등으로 구성할 수 있으며, 그 길이는 지오그리드(20)의 걸림홈(13)의 길이와 같거나, 또는, 상기 걸림홈(13)을 따라 다수 개가 끼워지도록 단위 길이로 구성한다.For reference, the support (22) (22 ') is fitted into the hook groove (13) in the retaining wall block 10 by fitting the ring 21 (21') of the geogrid 20 to be rearranged, Figure 2 and As shown in Figure 6, the support 22 (22 ') is formed to have a predetermined length in a variety of cross-sections, such as circular, square, and other polygons, it is preferable to use those excellent in durability, strength, bending strength, etc. For example, the support (22) (22 ') may be composed of a rod, a pipe, a square rod, and the like, the length is the same as the length of the locking groove 13 of the geogrid 20, or, It consists of a unit length so that a plurality of dogs are fitted along the locking groove 13.

그리고 상기 옹벽블록(10)의 후면에는 돌출된 배수돌기(14)를 다수개 형성하는데, 각 배수돌기(14)는 좌·우로는 일정 간격으로 형성하되, 상·하로는 서로 교차되도록 형성하는 것이 바람직하다.In addition, a plurality of protruding drainage protrusions 14 are formed on the rear surface of the retaining wall block 10. Each of the drainage protrusions 14 is formed at regular intervals in left and right directions, but is formed to cross each other in an upper and a lower direction. desirable.

또한, 상기 배수돌기(14)는, 옹벽블록(10)을 제조하면서 일체로 형성하거나, 또는, 합성수지 등을 이용하여, 배수돌기(14)가 형성된 판을 별도로 제작하여 옹벽블록(10)에 부착하여 사용한다. In addition, the drainage protrusion 14 may be integrally formed while manufacturing the retaining wall block 10, or may be separately manufactured and attached to the retaining wall block 10 by using a synthetic resin to form a plate having the drainage protrusion 14. Use it.

아울러, 상기 배수돌기(14)에는 배수대(10′)가 일체로 더 구성되며, 배수대(10′)는 일정 폭을 가지고,‘

Figure 112009072470238-pat00003
’의 구조로 형성되어, 상기 배수돌기(14)에 조립되는데, 배수대(10′)의 상단은 옹벽블록(10)의 후면 상단에서 조금 아래 위치되도록 조립하고, 배수대(10′) 하단은 옹벽블록(10)의 하단과 일치하도록 한다.In addition, the drainage protrusion 14 further comprises a drainage basin 10 'integrally, and the drainage basin 10' has a predetermined width,
Figure 112009072470238-pat00003
'Is formed in the structure, is assembled to the drain projection 14, the upper end of the drain (10') is assembled to be located slightly below the top of the rear of the retaining wall block 10, the bottom of the drain (10 ') It is to match the bottom of the retaining wall block (10).

추가로, 도4에 도시한 바와 같이, 상기 옹벽블록(10) 후면 하단은 내측으로 경사를 형성하는 경사부(16)를 형성하며, 옹벽블록(10)에 경사부(16)를 형성할 경우, 적용하는 배수대(10′)는, 옹벽블록(10)의 경사부(16)의 경사에 맞추어 배수대(10′)의 하단도 굽어지는 형상으로 형성되어, 배수대(10′)가 옹벽블록(10)에 밀착되게 조립되도록 구성한다.In addition, as shown in Figure 4, the bottom of the rear wall of the retaining wall block 10 forms an inclined portion 16 to form a slope inward, when the inclined portion 16 is formed in the retaining wall block 10 The drainage basin 10 'to be applied is formed in a shape in which the lower end of the drainage basin 10' is also bent in accordance with the inclination of the inclined portion 16 of the retaining wall block 10, and the drainage basin 10 'is the retaining wall. It is configured to be assembled in close contact with the block 10.

참고로, 상기 옹벽블록(10)의 전면은 심미성을 고려하여 다양한 형태로 형성될 수 있으며, 아울러, 별도로 가공한 자연석, 별도로 가공한 인공석, 기타 외장재와 같은 전면장식부를 일체로 부착하여 심미성을 높인다.For reference, the front surface of the retaining wall block 10 may be formed in various shapes in consideration of the aesthetics, and also by attaching the front decorative parts such as natural stone processed separately, artificial stone processed separately, other exterior materials integrally and aesthetics Increase

또한, 상기 옹벽블록(10)의 전면 높이와 후면 높이는 같도록 형성하거나, 또는, 후면으로 갈수록 낮은 높이를 가지도록 형성하면, 옹벽블록(10)을 쌓았을 때, 전체적으로 옹벽블록(10)이 후면 쪽으로 기울어지게 되어, 조적한 옹벽블록(10)이 전면으로 쓰러지는 것을 방지하는데, 이러한 기울기는 3도를 넘지 않도록 형성하는 것이 바람직하다.In addition, if the front height and the rear height of the retaining wall block 10 is formed to be the same, or formed to have a lower height toward the rear, when the retaining wall block 10 is stacked, the retaining wall block 10 as a whole It is inclined toward the side to prevent the masonry retaining wall block 10 from falling to the front side, which is preferably formed so as not to exceed 3 degrees.

이렇게 옹벽블록(10)은 내부에 상·하로 트인 끼움부(11)를 형성하고, 상부에는 걸림턱(12)과 걸림홈(13)을 형성하며, 배면에는 배수돌기(14)를 형성한 육면체로 구성하고, 옹벽블록(10)은, 콘크리트에 의해 일체로 제작되며(옹벽블록 내부에는 강도 보강을 위해 철근이 배근될 수 있다), 배수대(10′)는 별도로 ‘

Figure 112009072470238-pat00004
’의 구조를 가지도록 제작되어 조립하거나, 또는, 옹벽블록(10)과 배수돌기(14)를 별도로 구성하여 부착할 경우, 배수돌기(14)가 형성된 판을 형성하면서 배수대(10′)를 일체로 형성할 수 있으며, 또는, 옹벽블록(10)을 구성하면서 배수돌기(14), 배수대(10′)를 모두 일체로 제작할 수 있다.Thus, the retaining wall block 10 forms up and down fitting portions 11 therein, a locking jaw 12 and a locking groove 13 are formed on the upper side, and a hexahedron having a drainage protrusion 14 formed on the rear surface thereof. The retaining wall block 10 is integrally manufactured by concrete (reinforcing bars can be reinforced inside the retaining wall block for strength reinforcement), and the drainage basin 10 'is separately'
Figure 112009072470238-pat00004
When fabricated and assembled to have a structure of ', or when the retaining wall block 10 and the drainage protrusion 14 are separately configured and attached, the drainage stand 10' is formed while forming a plate on which the drainage protrusion 14 is formed. The drainage protrusions 14 and the drainage stand 10 'may be integrally manufactured while the retaining wall block 10 is formed.

이어서, 지오그리드(20)를, 도5 내지 도7을 참고하여 설명하면, 지오그리드(20)는 통상의 메시 구조로 형성하되, 한 가장자리 또는 마주하는 양쪽 가장자리를 따라 고리(21)(21′)가 일체로 형성된 구조로 구성하는데, 그 고리(21)(21′)에는 지지대(22)(22′)가 끼움될 수 있는 구조이며, 고리(21)(21′)는 설명한 옹벽블록(10)의 걸림홈(13)을 따라 끼움될 수 있는 단면 크기를 가지며, 지오그리드(20)는, 통상적인 지오그리드(20)의 재질로 구성하며, 내구성과 강도가 우수한 것을 사용한다.Subsequently, the geogrid 20 will be described with reference to FIGS. 5 to 7, wherein the geogrid 20 is formed in a conventional mesh structure, and the ring 21, 21 ′ is formed along one edge or both opposing edges. It consists of a structure formed integrally, the support (22) (22 ') is a structure that can be fitted to the ring (21) (21'), the ring (21) (21 ') of the retaining wall block 10 described It has a cross-sectional size that can be fitted along the locking groove 13, the geogrid 20 is composed of a material of a conventional geogrid 20, and uses the excellent durability and strength.

아울러, 지오그리드(20)는 고리(21)(21′)가 형성된 위치에 따라 두 가지 종류를 가지는데, 설명의 편리상, 도5에 도시한 바와 같이, 한 가장자리를 따라 고리(21)를 형성한 지오그리드(20)를 일측고리지오그리드라 칭하고, 도7에 도시한 바와 같이, 마주하는 양쪽 가장자리를 고리(21)(21′)를 형성한 지오그리드(20)를 양측고리지오그리드라 칭하며, 일측고리지오그리드는 일측 가장자리를 따라 고리(21)를 형성하고, 그 길이는 다양하게 구성하며, 또한, 양측고리지오그리드는 그 길이를 일정하게 구성한다.In addition, the geogrid 20 has two types according to the position where the rings 21 and 21 'are formed. For convenience of description, as shown in FIG. 5, the rings 21 are formed along one edge. One geogrid 20 is referred to as one side ridge geogrid, and as shown in FIG. 7, the geogrid 20 formed by rings 21 and 21 'facing both edges is referred to as both side ridge geogrid and one side ridge geogrid. Form a ring 21 along one side edge, the length of which is configured in various ways, and both sides of the ridge grid constitutes a constant length.

이러한 구조의 옹벽블록(10)과 지오그리드(20)를 이용한 옹벽의 시공 방법은, 시공 방법에 따라서 성토법과 네일링법이 있으며, 구체적인 시공 방법은 도16의 공정도를 참고하여 순차로 설명하면 다음과 같다.The retaining wall construction method using the retaining wall block 10 and the geogrid 20 having such a structure includes a filling method and a nailing method according to the construction method, and the detailed construction method will be described in detail with reference to the process diagram of FIG. 16. .

먼저, 시공지 정리 공정(S1)은, 옹벽을 시공할 시공지(옹벽의 시공지는 사면, 절벽, 절개지 등 옹벽 시공이 필요한 곳이 시공지이며, 이하, 설명의 편리성을 위해 시공지는 사면과 사면에 접하는 바닥으로 적는다)를 정리할 것으로, 사면은 통상의 방법으로 정리하고, 이 사면과 접하는 바닥은 기초(100)를 형성하기 위해 일정 깊이로 부분 파내어 평평하게 정리한다.First, the construction site arrangement step (S1) is a construction site for constructing the retaining wall (the construction site of the retaining wall is a place where the retaining wall construction such as slopes, cliffs, and cutouts is required, and the construction site will be described below for convenience of explanation. The slopes are arranged in a conventional manner, and the bottoms in contact with the slopes are partially dug to a certain depth to form a foundation 100 to be flattened.

또한, 상기 시공지 정리 공정(S1)에서, 적용하는 옹벽의 시공 방법이 성토법의 경우에는, 도1에 도시한 바와 같이, 지오그리드(20)가 포설되는 위치 및 토압을 고려하여, 사면을 추가로 더 성토하여(사면을 파내어, 사면을 제거하여)하도록 한다.In addition, in the construction site rearranging step (S1), when the method of constructing the retaining wall to be applied is a fill method, the slope is added in consideration of the position and earth pressure where the geogrid 20 is installed, as shown in FIG. Use it to dig more (to dig out the slope and remove the slope).

그리고 기초 형성 공정(S2)은, 도1에 도시한 바와 같이, 시공된 옹벽(옹벽블록, 뒷채움된 블록, 흙)의 하중을 하부로 전달하기 위해서 시공지 바닥을 따라 기초(100)를 형성하는 공정으로, 시공하는 옹벽의 규모를 고려하여 통상적인 방법으로 기초(100)를 형성하는데, 잡석(300)을 채워 기초(100)를 형성하는 방법, 또는, 철근을 배근하지 않고 콘크리트를 타설·경화하는 방법, 또는, 철근을 배근한 뒤에 콘크리트를 타설·경화하는 방법 등이 있는데, 기초(100)는 통상적인 방법이 적용되므로 더 구체적인 시공 방법은 생략한다.And base forming step (S2), as shown in Figure 1, to form a base 100 along the construction site floor to transfer the load of the retaining wall (retaining wall block, backfilled block, soil) to the bottom In the process, the foundation 100 is formed by a conventional method in consideration of the scale of the retaining wall to be constructed, and the method of filling the rubble 300 to form the foundation 100, or placing and hardening concrete without reinforcing the rebar. There is a method, or a method of placing and hardening concrete after reinforcing the reinforcing bar, and since the conventional method is applied to the foundation 100, a more specific construction method is omitted.

또, 옹벽블록 조적 공정(S3)은, 도1 및 도12 및 도13에 도시한 바와 같이, 상기 구성된 기초(100)에 구비된 옹벽블록(10)을 조적하는 공정으로, 옹벽블록(10)은 배수돌기(14)가 사면 쪽을 향하도록 설치하며, 옹벽블록(10)의 크기에 따라 한 층으로 배열하거나, 또는, 두 층 이상으로 조적하되, 옹벽블록(10)은 지오그리드(20)를 설치할 높이만큼 조적한다.(한 번에 조적하는 옹벽블록 높이가 지오그리드가 포설되는 위치가 된다.)In addition, as shown in FIGS. 1, 12, and 13, the retaining wall block stacking step S3 is a step of stacking the retaining wall block 10 provided in the foundation 100 configured as described above. The silver drainage protrusion 14 is installed facing the slope, and arranged in one layer according to the size of the retaining wall block 10, or assemble in two or more layers, the retaining wall block 10 is a geogrid 20 Install as much as the height to be installed. (The height of retaining wall block to install at one time will be the location where the geogrid is installed.

아울러, 옹벽블록(10)을 두 층 이상으로 쌓게 되는 경우에는, 도13 내지 도15에 도시한 바와 같이, 상·하의 옹벽블록(10)은 반폭씩 오프셋되도록 조적하며(상·하의 옹벽블록의 위치가 반폭씩 교차되도록 조적하는 것이 바람직하고, 완전히 반폭씩은 아니더라도, 조적된 옹벽블록의 상·하 위치가 완전 일치하지 않도록 한다), 하부 옹벽블록(10)의 걸림턱(12)이 상부의 옹벽블록(10)의 끼움부(11)에 속하도록 하며, 배수대(10′)가 별도로 구성된 경우에는, 설치된 옹 벽블록(10)의 각 배수돌기(14)에 배수대(10′)를 설치한다.In addition, when the retaining wall block 10 is stacked in two or more layers, as shown in FIGS. 13 to 15, the upper and lower retaining wall blocks 10 are stacked so as to be offset by half width (upper and lower retaining wall blocks). It is preferable to arrange the positions so that they cross each other by half width, and even if they are not completely half-width apart, the upper and lower positions of the retained retaining wall blocks do not coincide perfectly.) If it belongs to the fitting portion 11 of the block 10, and the drainage basin 10 'is configured separately, a drainage basin 10' is installed in each drain projection 14 of the retaining wall block 10 installed. do.

참고로, 옹벽블록(10)은 전면에서 후면으로 갈수록 그 좌·우 폭이 좁아지는 단면을 형성하고 있기 때문에, 옹벽블록(10)을 조적하는 구간이 굽어있더라도 용이하게 조적할 수 있으며, 또한, 옹벽블록(10)이 전면에서 후면으로 갈수록 그 높이가 낮아지는 단면을 형성하면, 옹벽블록(10)을 쌓으면서 옹벽블록(10)을 쌓았을 때, 전체적으로 옹벽블록(10)이 사면측으로 기울어지는 각도를 가지므로, 옹벽블록(10)이 전면으로 넘어지는 것을 방지하는 효과가 있으며, 또한, 각 상·하로 반폭씩 교차되는 위치로 조적되는 옹벽블록(10)은 하중을 균일하게 하부로 전달하면서, 걸림턱(12)에 의해서, 측면의 외력에 의해서도 옹벽블록(10)의 붕괴를 방지하는 효과가 있다.For reference, since the retaining wall block 10 forms a cross section in which the left and right widths thereof become narrower from the front side to the rear side, the retaining wall block 10 can be easily stacked even if the section for aligning the retaining wall block 10 is bent. When the retaining wall block 10 forms a cross section whose height decreases from the front to the rear, when the retaining wall block 10 is stacked while the retaining wall block 10 is stacked, the retaining wall block 10 is inclined toward the slope as a whole. Since the retaining wall block 10 has an effect of preventing the falling of the retaining wall block 10 to the front side, and the retaining wall block 10 is assembled to a position where the width of the retaining wall block crosses each half, the load is uniformly transmitted downward. By the locking step 12, even if the external force of the side has an effect of preventing the collapse of the retaining wall block 10.

아울러, 옹벽블록(10)을 쌓는 방법은 여러 가지가 있는데, 도1 및 도8에 도시한 바와 같이, 조적하는 옹벽블록(10)의 상·하의 전면 위치가 일치되도록 하여, 조적된 옹벽블록(10)의 전면이 평면을 형성하는 구조로 쌓는 방법이 있고, 또는, 도11에 도시한 바와 같이, 옹벽블록(10)을 쌓으면서, 옹벽블록(10)의 상·하가 단차가 생기도록 쌓으면, 조적된 옹벽블록(10)의 전면이 경사를 형성하는 구조로 쌓는 방법이 있는데, 이러한 옹벽블록(10)의 조적 구조는, 시공지의 구조, 설계자 및 시공자의 의견의 고려하여 결정한다.In addition, there are various ways to stack the retaining wall block 10. As shown in FIGS. 1 and 8, the retaining wall block (10) is formed so that the front and lower front positions of the retaining wall block 10 to be aligned coincide with each other. There is a method of stacking the front surface of 10) in a plane-forming structure, or as shown in Fig. 11, when the retaining wall blocks 10 are stacked, the retaining wall blocks 10 are stacked so that a step is formed. There is a method of stacking the retained wall block 10 in a structure in which the front surface of the assembled retaining wall block 10 forms an inclination.

참고로, 도11 및 도12에 도시한 바와 같이, 옹벽블록(10)의 상·하의 전면 위치가 단차를 두어 쌓는 경우에는, 옹벽블록(10) 후면 하단에 경사부(16)가 형성 된 것을 사용하면, 조적한 옹벽블록(10) 후면의 상·하를 따라 연결이 연속적으로 이루어지는 특징이 있다.For reference, as shown in FIGS. 11 and 12, when the front and bottom front positions of the retaining wall block 10 are stacked with a step, the inclined portion 16 is formed at the lower rear side of the retaining wall block 10. When used, there is a characteristic that the connection is continuously made along the top and bottom of the retaining wall block 10 rear surface.

그리고 기초(100)에 옹벽블록(10)을 쌓은 경우, 조적된 옹벽블록(10) 전면은 실제 지면보다 낮은 상태이므로, 조적된 옹벽블록(10)의 전면과 후면에는 흙(500)(501)을 일정 높이로 포설하고 다짐하도록 한다.And when the retaining wall block 10 is stacked on the foundation 100, since the front surface of the retained retaining wall block 10 is lower than the actual ground, soil 500 and 501 are formed on the front and rear surfaces of the retained retaining wall block 10. Install at a certain height and make a commitment.

이어지는, 뒷채움 공정(S4)은, 도1, 도2, 도10, 도11 및 도15에 도시한 바와 같이, 상기 설치된 옹벽블록(10) 후면으로 잡석(300)과 흙(500)으로 뒷채움하되, 잡석(300) 하부는 배수유도관(200)을 설치하고, 배수유도관(200)과 잡석(300)은 부직포(400)에 의해 싸여, 잡석(300)과 흙(500)은 부직포(400)에 의해 분리되도록 옹벽블록(10)과 사면 사이를 채우는 공정이다.Subsequently, the back filling process (S4), as shown in Figures 1, 2, 10, 11 and 15, backfilled with rubble 300 and soil 500 to the rear of the retaining wall block 10 installed, , Rubble 300 is installed in the drainage induction pipe 200, the drainage induction pipe 200 and rubble 300 is wrapped by a nonwoven fabric 400, rubble 300 and soil 500 is a nonwoven fabric 400 It is a process of filling between the retaining wall block 10 and the slope to be separated by).

그리고 뒷채움 공정(S4)에 의해서, 잡석(300)과 흙(500)이 부직포(400)에 의해 분리되는 시공 구조를 위해서, 잡석(300)을 먼저 채우고, 흙(500)을 나중에 채우는 방법, 흙(500)을 먼저 채우고, 잡석(300)을 나중에 채우는 방법, 잡석(300)과 흙(500)을 조금씩 높이를 맞추며 채워 가는 방법 등이 있다.And by the back-filling process (S4), for the construction structure in which rubble 300 and soil 500 are separated by nonwoven fabric 400, the rubble 300 is filled first, the soil 500 is filled later, the method of soil Fill the 500 first, the method of filling the rubble 300 later, there is a method of filling the rubble 300 and the soil 500 by adjusting the height little by little.

우선, 잡석(300)을 먼저 채우고, 흙(500)을 나중에 채우는 방법을 상세히 설명하면, 상기 옹벽블록 조적 공정(S3) 다음으로, 조적된 옹벽블록(10) 후면에, 부직포(400)를 바닥에 일정 폭을 가지도록 깔되, 부직포(400)의 양단이 조적된 옹벽블록(10) 상부까지 돌출되도록 옹벽블록(10)의 길이 방향을 따라 포설하도록 하며, 상기 부직포(400) 내부에 옹벽블록(10)의 후면을 따라 배수유도관(200)을 설치한다.First, the method of filling the rubble 300 first, followed by filling the soil 500 will be described in detail. Next, the retaining wall block masonry process (S3) is followed by the nonwoven fabric 400 on the rear of the retained retaining wall block 10. Is laid so as to have a predetermined width, so that both ends of the nonwoven fabric 400 to be installed along the longitudinal direction of the retaining wall block 10 so as to project up to the top of the retained retaining wall block 10, the retaining wall block (inside the nonwoven fabric 400) Install drainage induction pipe 200 along the back of the 10).

참고로, 상기 배수유도관(200)은, 일종의 파이프로, 표면을 따라 물이 흘러들어가고, 빠져나갈 수 있는 구조로, 일반 파이프에 외주연을 따라 관통된 구멍을 다수개 형성한 유공관을 사용하거나, 또는, 통상의 집속다발관, 집속배수판, 집속배수관 등을 사용하도록 한다.For reference, the drainage induction pipe 200 is a kind of pipe, a structure in which water flows along the surface, and can exit, using a perforated pipe having a plurality of perforated holes formed along an outer circumference of a general pipe. Or, use a conventional bundle bundle tube, focusing drainage plate, focusing drainage pipe and the like.

그리고, 부직포(400) 내부에 설치된 배수유도관(200) 상부로 잡석(300)(잡석은 부직포 내부에서 공극을 형성하기 위한 것으로, 잡석외에도, 잡석을 대체할 수 있는 기타 골재나 기타 자재를 이용하여도 무방하다.)을 채워 부직포(400)로 싸고(채워진 잡석 상부까지 부직포를 덮어도 무방하다), 부직포(400)와 사면 사이는 흙(500)을 조적된 옹벽블록(10) 높이까지 채우면서 단단히 다지도록 하는데, 흙(500)의 다짐기계나 다짐도구를 이용하여 충분히 다지는 것이 바람직하다.And, the rubble 300 to the top of the drain induction pipe 200 installed in the nonwoven fabric 400 (the rubble is to form a void in the nonwoven fabric, in addition to the rubble, using other aggregates or other materials that can replace the rubble It is wrapped with a nonwoven fabric 400 (or may cover the nonwoven fabric to the top of the filled rubble), and fills the soil 500 between the nonwoven fabric 400 and the slope up to the height of the retained retaining wall block 10. While firmly chopped, it is preferable to chop sufficiently using a compaction machine or compaction tool of the soil (500).

그외에도, 뒷채움 공정(S4)에서, 잡석(300)을 먼저 채우고, 흙(500)을 나중에 채우는 방법은, 흙(500)을 사면 쪽으로 조적된 옹벽블록(10) 높이까지 채워 다짐한 뒤에, 옹벽블록(10) 후면에 부직포(400)를 깔아, 배수유도관(200)을 설치하고, 잡석(300)을 채우는 방법이다. In addition, in the back filling process (S4), the method of filling the rubble 300 first, and later filling the soil 500, after the soil 500 is fixed to the height of the retaining wall block (10) is assembled to the slope, the retaining wall block (10) The non-woven fabric 400 is laid on the back, the drainage induction pipe 200 is installed, the rubble 300 is a method of filling.

그리고, 뒷채움 공정(S4)에서, 잡석(300)과 흙(500)을 조금씩 높이를 맞추며 채워 가는 방법은, 부직포(400)와 배수유도관(200)을 설치하고, 잡석(300)을 일정 높이로 채운 뒤에, 사면 측에는 일정 높이로 흙(500)을 채우며(사면 측에 흙을 먼저 채우고, 부직포와 배수유도관을 설치하여도 무방하다), 다시 부직포(400)의 잡 석(300) 채우기와 사면 측에 흙을 채우는 과정을 반복하여, 조적된 옹벽블록(10) 높이 만큼 뒷채움을 실시한다.And, in the back filling step (S4), the method of filling the rubble 300 and the soil 500 by gradually raising the height, the non-woven fabric 400 and the drainage induction pipe 200 is installed, the rubble 300 is a certain height After filling with, fill the soil 500 to a certain height on the slope side (fill the soil on the slope side first, and may be installed non-woven fabric and drainage induction pipe), and again filling the rubble (300) of the non-woven fabric 400 and By repeating the process of filling the soil on the slope side, the filling is carried out by the height of the retained retaining wall block 10.

한편, 뒷채움 공정(S4) 과정에서, 잡석(300)과 흙(500)을 채우면서, 무게로 인한, 쓰러짐을 방지하기 위해서, 채움되는 잡석(300)과 흙(500)의 공간을 분리할 수 있는 분리막을 사용하고, 뒷채움이 완료된 뒤에 분리막은 제거하도록 한다.On the other hand, in the back filling process (S4), while filling the rubble 300 and the soil 500, due to the weight, in order to prevent the fall, the space of the rubble 300 and the soil 500 to be filled can be separated Use a separate membrane and remove the membrane after backfill is complete.

그리고 지오그리드 설치 공정(S5)은, 도2, 도12 및 도13에 도시한 바와 같이, 구비한 지오그리드(20)의 각 고리(21)에 지지대(22)를 끼워 설치하고, 지오그리드(20)가 결합한 지지대(22)를 옹벽블록(10) 각 상부의 걸림홈(13)에 끼워 설치하는 공정이며, 지오그리드(20)의 설치는 성토법과 네일링법에 따라 차이가 있다.In the geogrid installation step S5, as shown in FIGS. 2, 12, and 13, the support 22 is fitted to each ring 21 of the provided geogrid 20, and the geogrid 20 is installed. The combined support 22 is inserted into the locking groove 13 at each upper portion of the retaining wall block 10, and the installation of the geogrid 20 is different depending on the filling method and the nailing method.

먼저, 성토법은, 도1, 도2 및 도11에 도시한 바와 같이, 지오그리드(20)는 일측고리지오그리드를 적용하는데, 먼저, 시공지 정리 공정(S1)에서 지오그리드(20)에 미치는 토압을 고려하여 사면을 성토한 상태이고, 일측고리지오그리드를 설계된 위치까지 포설하며, 이 과정으로, 일측지오그리드의 일단은 옹벽블록(10)의 걸림홈(13)에서 구속되고, 그 타측은, 토압에 의해 구속되는 구조이다.First, the fill method, as shown in Figures 1, 2 and 11, the geogrid 20 is applied to one side of the geogrid grid, first, the earth pressure applied to the geogrid 20 in the construction site arrangement step (S1) The slope is in consideration, and one side of the geogrid is installed to the designed position. In this process, one end of the one side geogrid is constrained in the locking groove 13 of the retaining wall block 10, and the other side thereof is caused by earth pressure. It is a constrained structure.

또, 네일링법은 지오그리드(20)는 양측고리지오그리드를 적용하며, 또한, 지오그리드의 설치 구조에 대해서 두 가지 실시예를 가진다.In addition, the nailing method of the geogrid 20 is applied to both sides of the geogrid grid, and also has two embodiments with respect to the installation structure of the geogrid.

먼저, 네일링법의 제 1실시예에 따른 지오그리드(20)의 설치 방법을 살펴보면, 도8 및 도9에 도시한 바와 같이, 사면을 따라 네일(800)을 박아 넣고, 양측고 리지오그리드의 고리(21)(21′)에는 각각 지지대(22)(22′)를 끼우며, 지오그리드(20)의 일측 지지대(22)는 옹벽블록(10)의 걸림홈(13)에 설치하여 구속되고, 그 타측의 지지대(22′) 및 고리(21′)는 사면에 설치된 네일(800)의 끝단과 연결수단(801)으로 연결한다.First, referring to the installation method of the geogrid 20 according to the first embodiment of the nailing method, as shown in Figs. 8 and 9, the nail 800 is driven along the slope, and the ring of the two high ridge geogrid ( 21 and 21 'are respectively fitted with supports 22 and 22', and one support 22 of the geogrid 20 is constrained by being installed in the locking groove 13 of the retaining wall block 10 and the other side thereof. The support 22 'and the ring 21' are connected to the end of the nail 800 installed on the slope and the connecting means 801.

다음으로, 네일링법의 제 2실시예에 따른 지오그리드의 설치를 도15의 시공 측단면도 및 도17의 공정도를 참고하여 살펴보면, 사면을 따라 네일(800)을 박아 넣고, 양측고리지오그리드의 일측 고리(21)에는 지지대(22)를 끼우며, 지오그리드(20)의 일측 지지대(22)는 옹벽블록(10)의 걸림홈(13)에 설치하여 구속하고, 그 타측은 사면쪽으로 어느 정도 펼친 다음, 상부로 꺾고, 그 꺾인 부분(모서리)을 따라 지오그리드(20)는 사면에 설치된 네일(800)의 끝단과 연결수단(801)으로 연결한다.Next, referring to the installation of the geogrid according to the second embodiment of the nailing method with reference to the construction side cross-sectional view of Figure 15 and the process diagram of Figure 17, injecting nail 800 along the slope, one side of the ring of both sides ( 21, the support 22 is fitted, one side support 22 of the geogrid 20 is installed in the locking groove 13 of the retaining wall block 10, restrained, the other side to some extent toward the slope, and then the top The geogrid 20 is connected to the end of the nail 800 installed on the slope and the connecting means 801 along the bent portion (edge).

참고로, 네일(800)의 구조와 시공 방법은, 통상적인 네일 구조 및 네일링 공법을 적용하므로, 그 구조 및 시공 방법에 대한 구체적인 설명은 생략하며, 네일(800)과 지오그리드(20)의 연결에 이용되는 연결수단(801)은, 와이어, 로프, 철근, 띠형 지오그리드 등을 이용하도록 한다.For reference, since the structure and construction method of the nail 800 is applied to the conventional nail structure and nailing method, a detailed description of the structure and construction method is omitted, connection of the nail 800 and the geogrid 20 Connection means 801 to be used, such as wire, rope, reinforcing bar, strip geogrid.

이어서, 옹벽블록 조적 공정(S6)은, 도1, 도8, 도10, 도11 내지 도15에 도시한 바와 같이, 상기 설치된 옹벽블록(10) 상부로 옹벽블록(10)을 조적하는 공정으로, 옹벽블록(10)은 배수돌기(14)가 사면 측을 향하도록 설치하며, 옹벽블록(10)의 크기에 따라, 옹벽블록(10)은 다음 지오그리드(20)를 설치할 높이만큼 조적하며, 배수대(10′)가 별도로 구성된 경우에는, 설치된 옹벽블록(10)의 각 배수돌기(14)에 배수대(10′)를 설치하는데, 옹벽블록(10)을 설치하는 방법 및 구조에 대한 설명은, 상기 옹벽블록 조적 공정(S3)에 구체적으로 설명되어 있으므로 생략한다.Subsequently, as shown in FIGS. 1, 8, 10, and 11 to 15, the retaining wall block forming step S6 is a step of depositing the retaining wall block 10 on the installed retaining wall block 10. , The retaining wall block 10 is installed so that the drainage protrusion 14 faces the slope side, and according to the size of the retaining wall block 10, the retaining wall block 10 is assembled by a height to install the next geogrid 20, drainage When the base 10 'is configured separately, a drainage stand 10' is installed in each of the drainage protrusions 14 of the retaining wall block 10, and the description of the method and structure for installing the retaining wall block 10 will be described. Since the retaining wall block forming step S3 is described in detail, the description will be omitted.

다음으로, 뒷채움 공정(S7)은, 도1, 도8, 도10에 도시한 바와 같이, 상기 설치된 옹벽블록(10) 후면으로 잡석(300)과 흙(500)으로 뒷채움하되, 잡석(300)은 부직포(400)에 의해 싸여, 잡석(300)과 흙(500)은 부직포(400)에 의해 분리되는 구조로 옹벽블록(10)과 사면 사이를 채우는 공정으로, 이 뒷채움 공정(S7)은 앞선 뒷채움 공정(S4)과 달리 배수유도관(200)을 설치하지 않는 것 외에는 그 시공 방법이 대동소이하므로 구체적인 시공 방법에 대한 설명을 생략한다.Next, the back filling step (S7), as shown in Figures 1, 8, 10, backfilling the rubble 300 and the soil 500 to the rear of the retaining wall block 10 installed, but the rubble 300 Silver is wrapped by a non-woven fabric 400, rubble 300 and soil 500 is a process of filling between the retaining wall block 10 and the slope in a structure that is separated by a nonwoven fabric 400, this back filling process (S7) Unlike the backfill process (S4), except that the drainage induction pipe 200 is not installed, the construction method is substantially the same, so a description of the specific construction method is omitted.

그래서 이렇게 뒷채움 공정(S7)으로 설계된 높이가 되지 않으면, 성토법과 제 1실시예에 따른 네일링법의 경우, 도1의 단면도 및 도16의 공정도와 같이, 앞선 지오그리드 설치 공정(S5) 내지 뒷채움 공정(S7)을 설계된 높이가 될 때까지 반복한다.Thus, if the height is not designed in the backfilling process (S7), in the case of the fill method and the nailing method according to the first embodiment, as shown in the cross-sectional view of Figure 1 and the process of Figure 16, the geogrid installation process (S5) to the backfilling process ( Repeat S7) until the designed height is reached.

반면, 제 2실시예에 따른 네일링법의 경우에는, 뒷채움 공정(S7) 이후에는, 지오그리드(20)의 끝단이 상부로 돌출된 상태로 유지하며, 도10의 시공 단면도 및 도17의 공정도에서와 같이, 뒷채움 공정(S7) 다음에는, 지오그리드 설치 공정(S5 ′)이 추가된다.On the other hand, in the case of the nailing method according to the second embodiment, after the back filling process (S7), the end of the geogrid 20 is maintained in a state protruding upwards, and in the construction sectional view of FIG. Similarly, after the backfilling step S7, a geogrid mounting step S5 'is added.

그래서 지오그리드 설치 공정(S5′)은 상부를 향하는 지오그리드(20)를 다시 전면으로 꺾어서(꺾는 위치는 뒷채움된 높이, 즉, 조적된 옹벽블록 높이와 일치하는 높이에서 꺾는다.다시 말하면, 드러난 부분 그대로 옹벽블록 방향으로 꺾는다), 그 끝단의 고리(21′)에 지지대(22′)를 끼워, 그 지지대(22′)를 옹벽블록(10)의 걸림홈(13)에 걸리도록 끼워 넣으며, 상부에서 꺾인 부분(모서리)을 따라 지오그리드(20)는 상기 네일(800)의 끝단과 연결수단(801)에 연결하는 공정으로, 이렇게 지오그리드(20)의 설치가, 네일링법의 제 2실시예에 따라 지오그리드(20)를 설치하는 경우에는, 시공된 지오그리드(20)의 측단면은, 지오그리드(20)의 중간부분이 사면 쪽에 수직 방향으로 매설되어, 시공된 측면에서 보았을 때, 지오그리드(20)가 대략‘

Figure 112009072470238-pat00005
’ 의 형태로 매입되는 구조이다.Thus, the geogrid installation process (S5 ′) folds the geogrid 20 facing upwards to the front again (the bending position is at a height that corresponds to the backfilled height, ie, the height of the retained retaining wall block). The support 22 'is inserted into the ring 21' at the end thereof, and the support 22 'is fitted to the locking groove 13 of the retaining wall block 10. Geogrid 20 is a process of connecting the end of the nail 800 and the connecting means 801 along the bent portion (corner) in this way, the installation of the geogrid 20 according to the second embodiment of the nailing method When the geogrid 20 is installed, the side cross section of the constructed geogrid 20 is buried in the direction perpendicular to the slope of the middle portion of the geogrid 20, and the geogrid 20 is approximately viewed from the constructed side. '
Figure 112009072470238-pat00005
It is a structure that is purchased in the form of '.

다음으로, 앞서 설명한 옹벽블록 조적 공정(S6)과 뒷채움 공정(S7)을 실시하고, 이때에도, 설계된 높이가 되지 않으면, 지오그리드 설치 공정(S5), 옹벽블록 조적 공정(S6), 뒷채움 공정(S7), 지오그리드 설치 공정(S5′), 옹벽블록 조적 공정(S6)과 뒷채움 공정(S7)을 반복하여 설계된 높이까지 공정을 반복한다.Next, if the retaining wall block forming step (S6) and the backfilling step (S7) described above are performed, and at this time, the height is not designed, the geogrid installation step (S5), the retaining wall block forming step (S6), and the backfilling step (S7) are performed. ), Geogrid installation process (S5 '), retaining wall block masonry process (S6) and backfill process (S7) is repeated to repeat the process to the designed height.

참고로, 옹벽블록(10)을 조적하고, 뒷채움을 하면서, 조적한 옹벽블록(10)의 끼움부(11)에 일반 흙을 투입하고, 끼움부(11)의 흙에 씨나, 식물, 나무 등을 심으면, 시공된 옹벽 전면에 식생을 용이하게 할 수 있다.For reference, while retaining the retaining wall block 10, and backfilling, the general soil is put into the fitting portion 11 of the retaining wall block 10, the seed, plants, trees, etc. into the soil of the fitting portion 11 Planting can facilitate the vegetation on the entire retaining wall.

이렇게 성토법, 또는, 네일링법에 의한 뒷채움 공정(S7)으로 원하는 높이가 되지 않았을 경우에는, 앞선 지오그리드 설치 공정(S5)(또는, 지오그리드 설치 공정(S5´)) 내지 뒷채움 공정(S7)을 원하는 높이가 될 때까지 반복하며, 설계된 높이가 되면, 다음으로는, 차수매트 포설 공정(S8)을 실시한다.When the desired height is not achieved by the backfilling process (S7) by the filling method or the nailing method, the desired geogrid installation process (S5) (or the geogrid installation process (S5 ')) or the backfilling process (S7) is desired. It repeats until it reaches height, and when it becomes a designed height, next, the order mat installation process (S8) is performed.

상기 차수매트 포설 공정(S8)은, 도1, 도8, 도11에 도시한 바와 같이, 옹벽블록(10)과 시공지, 즉, 사면까지 차수매트(600)를 포설하는 공정으로, 차수매트(600)는 방수가 되는 시트로, 통상의 방수지 및 방수시트를 사용하는 것이 바람직하다.The order mat laying step S8 is a process of laying the order mat 600 up to the retaining wall block 10 and the construction site, that is, the slope, as shown in FIGS. 1, 8, and 11. 600 is a waterproof sheet, it is preferable to use ordinary waterproof paper and waterproof sheet.

다음으로, 지반 포설 및 다짐 공정(S9)은, 상기 설치된 차수매트(600) 상부로 흙(500)을 포설하고 다짐기계나 다짐도구로 다지는 공정이다.Next, the ground laying and compacting step (S9) is a process of laying the soil 500 on the installed order mat 600 and compacting with a compaction machine or compaction tool.

추가로, 측구 형성 공정(S10)은, 도1, 도8, 도11에 도시한 바와 같이, 상기 다짐된 흙(500)에 측구(700)를 형성하는 것으로, 측구(700)는, 시공된 옹벽 최상단의 옹벽블록(10) 상단 바로 후면을 따라 형성하거나, 또는 원지반 쪽을 따라 형성하는데(두 곳 모두 형성해도 무방하다), 측구(700)는 빗물 등이 흘러 배수하기 위한 것으로, 측구(700)가 형성된 방향으로 경사를 형성하면 배수가 더욱 용이한 특성이 있다.In addition, the side opening forming step (S10), as shown in Figs. 1, 8, and 11, by forming the side opening 700 in the compacted soil 500, the side opening 700 is constructed To form along the rear of the retaining wall block 10 at the top of the retaining wall immediately above, or along the base side (may be formed in both places), the side opening 700 is for draining rainwater and flow, side opening 700 When the inclination is formed in the direction in which) is formed, there is a characteristic that drainage is easier.

이러한 옹벽의 시공 과정으로, 사면 전면에는 옹벽블록(10)이 조적되고, 옹벽블록(10) 후면에는 잡석(300)을 싼 부직포(400)를 구성하고, 그 잡석 가장 하부 에는 배수유도관(200)을 구성하며, 상기 잡석(300)을 싼 부직포(400)와 원지반 사이에는 흙(500)으로 채워 다짐된 상태이며, 일정 높이를 따라 지오그리드(20)가 포설·매설되되, 지오그리드(20)의 전면은 옹벽블록(10)의 걸림홈(13)에 구속되고, 지오그리드(20)의 후면은 네일(800)이나 흙(500)의 토압에 의해 구속되는 구조로 시공된다.In the construction of the retaining wall, the retaining wall block 10 is formed on the front surface of the slope, and the rear wall of the retaining wall block 10 constitutes a nonwoven fabric 400 wrapped with the rubble 300, and the bottom of the rubble is a drainage induction pipe 200. And a state in which the rubble 300 is wrapped between the nonwoven fabric 400 and the ground, which is filled with soil 500, and the geogrid 20 is laid and buried along a predetermined height, but the geogrid 20 is The front surface is constrained by the locking groove 13 of the retaining wall block 10, the rear surface of the geogrid 20 is constructed in a structure that is constrained by the earth pressure of the nail (800) or soil (500).

따라서, 본 발명에 따라 옹벽의 시공 방법에 의해 매설된 지오그리드(20)는, 흙(500) 사이의 마찰저항력과 수동저항력의 상호작용력으로 토압에 저항하는 역할을 하여, 옹벽블록(10)과 사면 사이에 채움된 흙(500) 내부의 인장력을 높이고, 연약 지반을 보강하며, 지오그리드(20)의 전면과 후면은 모두 구속되는 구조로, 시공된 옹벽 구조의 지반을 보강한다.Therefore, the geogrid 20 buried by the method of constructing the retaining wall according to the present invention serves to resist the earth pressure by the interaction force between the frictional resistance and the passive resistance between the soil 500, the retaining wall block 10 and the slope Increasing the tensile force inside the soil (500) filled in between, reinforcing the soft ground, both the front and rear of the geogrid 20 is constrained structure, reinforcing the ground of the construction of the retaining wall structure.

또한, 옹벽의 시공 방법에 의한 옹벽 구조에서, 빗물은 차수매트(600)에 의해 일차적인 침투를 방지하고, 빗물이나 사면에서 발생한 물은 잡석(300)을 포함하는 부직포(400) 내부로 유입되어 하부로 흐르며, 또한, 옹벽블록(10) 후면의 물은 배수돌기(14)를 따라 흘러내리되, 물이 배수대(10′)를 따라 흘러내리고, 옹벽블록(10)의 후면은 좌·우로 돌출된 돌출부(15)를 형성하므로, 옹벽블록(10)이 상·하로 반폭씩 교차되게 조적되어도, 옹벽블록(10) 내부로 물이나 흙이 투입되는 것을 방지하며, 옹벽블록(10) 후면을 따라 물이 빠지므로, 옹벽블록(10)의 내구성이 떨어지는 것을 방지한다.In addition, in the retaining wall structure by the method of constructing the retaining wall, rainwater prevents primary penetration by the order mat 600, and the water generated from the rainwater or the slope is introduced into the nonwoven fabric 400 including the rubble 300. Flowing downward, the water in the rear of the retaining wall block 10 flows down along the drainage protrusion 14, the water flows along the drainage 10 ', the rear of the retaining wall block 10 to the left and right Since the protruding protrusion 15 is formed, even if the retaining wall block 10 is assembled to cross each other in a half width, it prevents water or soil from being introduced into the retaining wall block 10, and the rear surface of the retaining wall block 10 is prevented. As water is drained, the durability of the retaining wall block 10 is prevented from falling.

추가로, 옹벽블록(10)의 후면 하단에 경사부(16)를 형성한 경우에는, 옹벽블 록(10)을 조적하면서 전면에 상·하로 단차를 형성하면서 조적하는 경우에, 조적된 옹벽블록(10)의 후면의 연결이 연속되게 이어지므로, 잡석(300)에 쌓인 부직포(400)와 옹벽블록(10) 후면의 밀착을 용이하게 하고, 옹벽블록(10) 후면(배수돌기 및 배수대)을 따라 물의 배수가 이루어지므로, 옹벽블록(10) 내부로 물이 유입되는 것을 방지하는 특징이 있다.In addition, in the case where the inclined portion 16 is formed at the lower rear side of the retaining wall block 10, the retaining wall block 10 is formed while the retaining wall block 10 is formed while the upper and lower steps are formed on the front surface. Since the connection of the rear of the (10) is continuously connected to facilitate the close contact of the nonwoven fabric 400 and the retaining wall block 10 rear accumulated in the rubble (300), the retaining wall block 10 rear (drainage projection and drain) Since the drainage of the water is made along, there is a feature that prevents water from flowing into the retaining wall block (10).

또한, 부직포(400)의 잡석(300) 및 옹벽블록(10)의 후면을 따라 빠지는 물은 배수유도관(200)으로 유입되어 외부로 물이 빠지는 구조에 의해, 시공된 옹벽 구조 내부의 물의 배수가 용이한 특징이 있다.In addition, the water falling along the rear surface of the rubble 300 and the retaining wall block 10 of the nonwoven fabric 400 is introduced into the drainage induction pipe 200 to drain the water to the outside, the drainage of the water inside the constructed retaining wall structure There is an easy feature.

그리고 옹벽블록(10) 후면의 잡석(300)은 그 공극으로 인해서 배수가 용이하게 이루어지도록 하는데, 잡석(300)은 부직포(400)로 싸여 있으므로, 잡석(300)의 흩어짐(이동)을 방지하고, 잡석(300)과 사면 사이에 뒷채움된 흙(500)의 유실을 방지하여, 시공된 옹벽의 붕괴를 방지할 수 있는 것이다.And the rubble 300 at the rear of the retaining wall block 10 to facilitate the drainage due to the voids, because the rubble 300 is wrapped in a non-woven fabric 400, to prevent the scattering (movement) of the rubble 300 To prevent the loss of the backfilled soil 500 between the rubble 300 and the slope, it is possible to prevent the collapse of the constructed retaining wall.

도 1은 본 발명의 성토법에 따라 시공된 옹벽을 보여주는 단면도.1 is a cross-sectional view showing a retaining wall constructed in accordance with the fill method of the present invention.

도 2는 도 1의 A부분 확대도.FIG. 2 is an enlarged view of portion A of FIG. 1; FIG.

도 3은 본 발명에 따른 옹벽블록의 사시도.3 is a perspective view of a retaining wall block according to the present invention;

도 4는 본 발명에 따른 옹벽블록의 다른 예시도.4 is another exemplary view of the retaining wall block according to the present invention;

도 5는 본 발명에 따른 지오그리드의 사시도.5 is a perspective view of a geogrid according to the present invention.

도 6은 도 5의 B부분 확대도.6 is an enlarged view of a portion B of FIG. 5;

도 7은 본 발명에 따른 지오그리드의 다른 예시도.Figure 7 is another illustration of a geogrid according to the present invention.

도 8은 본 발명에 따른 네일링법의 제 1실시예에 의해 시공된 옹벽을 보여주는 측단면도.Figure 8 is a side cross-sectional view showing a retaining wall constructed by a first embodiment of the nailing method according to the present invention.

도 9는 본 발명에 따른 네일링법의 제 1실시예에 의해 시공된 옹벽을 보여주는 평단면도.9 is a plan sectional view showing a retaining wall constructed by the first embodiment of the nailing method according to the present invention.

도 10은 본 발명에 따른 네일링법의 제 2실시예에 의해 시공된 옹벽을 보여주는 측단면도.Figure 10 is a side cross-sectional view showing a retaining wall constructed by a second embodiment of the nailing method according to the present invention.

도 11은 본 발명에 따라 옹벽블록을 단차로 조적하며 시공된 옹벽을 보여주는 측단면도.Figure 11 is a side cross-sectional view showing a retaining wall constructed by stepping the retaining wall block in step according to the present invention.

도 12는 도 11의 C부분 확대도.FIG. 12 is an enlarged view of a portion C of FIG. 11; FIG.

도 13은 본 발명의 시공 과정을 보여주는 사시도.13 is a perspective view showing a construction process of the present invention.

도 14는 본 발명의 시공 과정을 보여주는 또 다른 사시도.14 is another perspective view showing a construction process of the present invention.

도 15는 본 발명에 따라 시공되어 조적된 옹벽블록을 보여주는 배면도.Figure 15 is a rear view showing a retaining wall block constructed and constructed in accordance with the present invention.

도 16은 본 발명의 시공 방법에 따른 공정도.16 is a process chart according to the construction method of the present invention.

도 17은 본 발명에 따른 네일링법의 제 2실시예에 따른 공정도.17 is a process chart according to a second embodiment of the nailing method according to the present invention.

[ 도면의 주요 부분에 대한 부호의 설명 ][Description of Code for Major Parts of Drawing]

10 : 옹벽블록 13 : 걸림홈10: retaining wall block 13: hanging groove

14 : 배수돌기 20 : 지오그리드14: drainage protrusion 20: geogrid

200 : 배수유도관 600 : 차수매트200: drainage induction pipe 600: order mat

Claims (10)

삭제delete 삭제delete 통상의 공지된 옹벽블록에 있어서,In a conventional known retaining wall block, 옹벽블록(10)은 내부가 상·하로 트인 끼움부(11)를 형성하고, 상부면에는 상부로 돌출된 걸림턱(12)을 형성하되 전면 상부의 좌·우 폭을 따라서는 걸림홈(13)을 일체로 형성하며,The retaining wall block 10 forms a fitting portion 11 having an upper and lower inside, and a locking jaw 12 protruding upward from an upper surface thereof, but a locking groove 13 along the left and right widths of the front upper portion. ) Integrally, 이 옹벽블록(10)의 좌·우 폭이 전면에서 후면으로 갈수록 점차 작아지는 구조를 가지도록 형성하되 옹벽블록(10)의 후면은 좌·우로 돌출된 돌출부(15)를 더 형성하도록 하며, The left and right widths of the retaining wall block 10 are formed to have a structure that gradually decreases from the front side to the rear side, but the rear side of the retaining wall block 10 forms a protrusion 15 protruding left and right. 좌·우로 돌출된 돌출부(15)를 더 형성한 옹벽블록(10) 후면에는 돌출된 다수개의 배수돌기(14)를 일체로 형성하되, 이들 배수돌기(14) 사이에는‘
Figure 112010044888300-pat00024
'의 구조를 지닌 배수대(10')가 일체로 구비된 옹벽블록으로 구성됨으로써,
On the rear surface of the retaining wall block 10 further formed with a protrusion 15 protruding to the left and right, a plurality of protruding drainage protrusions 14 are integrally formed between the drainage protrusions 14.
Figure 112010044888300-pat00024
By consisting of the retaining wall block is integrally provided with a drain (10 ') having a structure of,
옹벽블록의 후면을 따라 흘러내리는 물은 이들 배수돌기와 배수대를 따라 유도되어 흐르면서 배수되어, 옹벽블록 내부로 물의 유입을 방지하고 옹벽블록의 내구성을 높이도록 함을 특징으로 하는 옹벽 시공을 위한 옹벽블록.Water flowing along the rear surface of the retaining wall block is guided and flows along these drainage protrusions and drains to prevent the inflow of water into the retaining wall block and the retaining wall block for building the retaining wall, characterized in that to increase the durability of the retaining wall block. .
제 3항에 있어서,The method of claim 3, wherein 옹벽블록(10)의 후면 하단은 내측으로 경사를 형성한 경사부(16)를 더 형성하여, 상,하 옹벽블록(10)을 단차를 형성하면서 조적 할 경우, 이 경사부(16)에 의하여 조적 된 상. 하 옹벽블록(10)의 후면은 서로 연속적으로 연결된 후면을 이루도록 함으로써,The bottom of the rear surface of the retaining wall block 10 further forms an inclined portion 16 inclined inwardly, and when the upper and lower retaining wall blocks 10 are formed while forming a step, the inclined portion 16 Masonry statue. By rear surface of the retaining wall block 10 to form a rear surface connected to each other continuously, 옹벽블록의 후면을 따라 흘러내리는 물은 이들 배수돌기와 배수대를 따라 유도되어 흐르면서 배수되어, 인접하는 옹벽블록 사이의 공간 내부로 물의 유입을 방지하고 옹벽블록의 내구성을 높이도록 함을 특징으로 하는 옹벽 시공을 위한 옹벽블록.Retaining wall characterized in that the water flowing along the rear of the retaining wall block is guided and flows along these drainage projections and drains to prevent the inflow of water into the space between adjacent retaining wall blocks and to increase the durability of the retaining wall block. Retaining wall block for construction. 삭제delete 삭제delete 삭제delete 시공지의 바닥과 사면을 파내고 정리하는 시공지 정리 공정(S1);Construction site cleaning process (S1) to dig and clean the bottom and slope of the construction site; 상기 정리된 바닥에 기초를 형성하는 기초 형성 공정(S2);A foundation forming step (S2) of forming a foundation on the arranged bottom; 상기 기초 형성 공정(S2)에 따라 형성된 기초 상부를 따라 준비된 청구항 3 또는 청구항 4의 옹벽블록 중 어느 하나를 선택하여 배열·조적하는 옹벽블록 조적 공정(S3);A retaining wall block forming step (S3) of selecting and arranging and aligning any one of the retaining wall blocks of claim 3 or 4 prepared along the upper part of the foundation formed according to the forming step (S2); 상기 조적된 옹벽블록 후면에는 배수유도관이 설치되고, 배수유도관 상부에는 잡석이 채워지되, 배수유도관과 잡석은 부직포에 의해 싸이고, 부직포와 사면 사이에는 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S4);A drainage induction pipe is installed at the rear of the retained retaining wall block, and rubble is filled at the upper part of the drainage induction pipe, but the drainage induction pipe and the rubble are wrapped by a nonwoven fabric, and the retaining wall block and the slope are filled with soil between the nonwoven fabric and the slope. Backfilling step (S4) filling the gap; 상기 뒷채움 공정(S4)을 완료한 후, 가장자리를 따라 다수개의 고리를 일체로 형성한 통상의 지오그리드를 준비한 다음, 이 지오그리드의 고리에 지지대를 끼워, 그 지지대를 조적된 최상부 옹벽블록의 걸림홈에 끼우고, 지오그리드를 포설하는 지오그리드 설치 공정(S5);After completing the back filling step (S4), after preparing a conventional geogrid with a plurality of loops integrally formed along the edges, and then put a support in the ring of the geogrid, the support in the locking groove of the top retaining wall block A geogrid installation step (S5) of sandwiching and laying the geogrid; 상기 옹벽블록 조적 공정(S3)에 따라 조적된 옹벽블록의 상부에 다음 단계의 옹벽블록을 배열·조적하는 옹벽블록 조적 공정(S6);A retaining wall block forming step (S6) of arranging and arranging a retaining wall block of a next step on top of the retaining wall block assembled according to the retaining wall block forming step (S3); 상기 설치된 옹벽블록 후면에, 잡석을 부직포에 의해 싸이도록 옹벽블록 높이까지 채우고, 잡석을 싼 부직포와 사면 사이에 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S7)을 실행하되,On the rear of the retaining wall block, the rubble is filled up to the height of the retaining wall block so as to be wrapped by the nonwoven fabric, and the backfilling process (S7) is performed to fill the gap between the retaining wall block and the slope with a chopped structure by filling the rubble between the nonwoven fabric and the slope. 이렇게 상기 지오그리드 설치 공정(S5) 내지 뒷채움 공정(S7)을 설계된 높이가 되도록 반복한 뒤에;After repeating the geogrid installation process (S5) to backfill process (S7) to the designed height; 마지막에 설치된 옹벽블록, 잡석을 감싼 부직포, 채움·다짐된 흙 상부로, 차수매트를 포설하는 차수매트 포설 공정(S8);An order mat laying step (S8) for laying the order mat with a retaining wall block installed at the end, a nonwoven fabric wrapped with rubble, and a filled and compacted soil; 상기 포설된 차수매트 상부로 흙을 포설하여 다짐하는 지반 포설 및 다짐 공정(S9);A ground laying and compacting process (S9) for laying soil by placing soil on the placed order mat; 상기 다짐된 최상부 흙에 측구를 형성하는 측구 형성 공정(S10);A side opening forming step of forming a side opening in the top soil compacted (S10); 으로 단계별 시공이 완료됨을 특징으로 하는 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법.Retaining wall construction method using a retaining wall block and geogrid, characterized in that the step-by-step construction is completed. 시공지의 바닥과 사면을 정리하는 시공지 정리 공정(S1);Construction site cleaning process for cleaning the floor and the slope of the construction site (S1); 상기 정리된 바닥에 기초를 형성하는 기초 형성 공정(S2);A foundation forming step (S2) of forming a foundation on the arranged bottom; 상기 기초 형성 공정(S2)에 따라 형성된 기초 상부를 따라 준비된 청구항 3 또는 청구항 4의 옹벽블록 중 어느 하나를 선택하여 배열·조적하는 옹벽블록 조적 공정(S3);A retaining wall block forming step (S3) of selecting and arranging and aligning any one of the retaining wall blocks of claim 3 or 4 prepared along the upper part of the foundation formed according to the forming step (S2); 상기 조적된 옹벽블록 후면에는 배수유도관이 설치되고, 배수유도관 상부에는 잡석이 채워지되, 배수유도관과 잡석은 부직포에 의해 싸이고, 부직포와 사면 사이에는 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S4);A drainage induction pipe is installed at the rear of the retained retaining wall block, and rubble is filled at the upper part of the drainage induction pipe, but the drainage induction pipe and the rubble are wrapped by a nonwoven fabric, and the retaining wall block and the slope are filled with soil between the nonwoven fabric and the slope. Backfilling step (S4) filling the gap; 상기 뒷채움 공정(S4)을 완료한 후 원지반 사면을 따라 네일을 박아 설치한 다음, 서로 마주하는 양측 가장자리를 따라 다수개의 고리를 일체로 형성한 통상의 지오그리드를 준비한 다음, 이 지오그리드의 양쪽 고리에 지지대를 각각 끼워, 일측의 지지대는 조적 된 최상부 옹벽블록의 걸림홈에 끼워 설치하고, 그 타측의 지지대는 연결수단으로 원지반 사면을 따라 박은 네일과 연결하는 방법으로 지오그리드를 포설하는 지오그리드 설치 공정(S5);After completing the backfilling process (S4), nails are installed along the disc slope, and then, after preparing a conventional geogrid in which a plurality of rings are integrally formed along both edges facing each other, a support is formed on both rings of the geogrid. And the support of one side is installed in the engaging groove of the top retaining wall block, and the support of the other side is a geogrid installation process of laying the geogrid by connecting nails along the base slope as a connecting means (S5). ; 상기 옹벽블록 조적 공정(S3)에 따라 조적된 옹벽블록의 상부에 다음 단계의 옹벽블록을 배열·조적하는 옹벽블록 조적 공정(S6);A retaining wall block forming step (S6) of arranging and arranging a retaining wall block of a next step on top of the retaining wall block assembled according to the retaining wall block forming step (S3); 상기 설치된 옹벽블록 후면에, 잡석을 부직포에 의해 싸이도록 옹벽블록 높이까지 채우고, 잡석을 싼 부직포와 사면 사이에 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S7)을 실행하되, 이렇게 지오그리드 설치 공정(S5) 내지 뒷채움 공정(S7)을 설계된 높이가 되도록 반복한 뒤에;On the rear of the retaining wall block, the rubble is filled up to the height of the retaining wall block so as to be wrapped by the nonwoven fabric, and the backfilling process (S7) is performed to fill the gap between the retaining wall block and the slope with a chopped structure by filling the rubble between the nonwoven fabric and the slope. After repeating the geogrid installation process (S5) to backfill process (S7) to the designed height; 마지막에 설치된 옹벽블록, 잡석을 감싼 부직포, 채움·다짐된 흙 상부로, 차수매트를 포설하는 차수매트 포설 공정(S8);An order mat laying step (S8) for laying the order mat with a retaining wall block installed at the end, a nonwoven fabric wrapped with rubble, and a filled and compacted soil; 상기 포설된 차수매트 상부로 흙을 포설하여 다짐하는 지반 포설 및 다짐 공정(S9);A ground laying and compacting process (S9) for laying soil by placing soil on the placed order mat; 상기 다짐된 최상부 흙에 측구를 형성하는 측구 형성 공정(S10);A side opening forming step of forming a side opening in the top soil compacted (S10); 으로 단계별 시공이 완료됨을 특징으로 하는 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법.Retaining wall construction method using a retaining wall block and geogrid, characterized in that the step-by-step construction is completed. 시공지의 바닥과 사면을 정리하는 시공지 정리 공정(S1);Construction site cleaning process for cleaning the floor and the slope of the construction site (S1); 상기 정리된 바닥에 기초를 형성하는 기초 형성 공정(S2);A foundation forming step (S2) of forming a foundation on the arranged bottom; 상기 기초 형성 공정(S2)에 따라 형성된 기초 상부를 따라 준비된 청구항 3 또는 청구항 4의 옹벽블록 중 어느 하나를 선택하여 배열·조적하는 옹벽블록 조적 공정(S3);A retaining wall block forming step (S3) of selecting and arranging and aligning any one of the retaining wall blocks of claim 3 or 4 prepared along the upper part of the foundation formed according to the forming step (S2); 상기 조적된 옹벽블록 후면에는 배수유도관이 설치되고, 배수유도관 상부에는 잡석이 채워지되, 배수유도관과 잡석은 부직포에 의해 싸이고, 부직포와 사면 사이에는 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S4);A drainage induction pipe is installed at the rear of the retained retaining wall block, and rubble is filled at the upper part of the drainage induction pipe, but the drainage induction pipe and the rubble are wrapped by a nonwoven fabric, and the retaining wall block and the slope are filled with soil between the nonwoven fabric and the slope. Backfilling step (S4) filling the gap; 상기 뒷채움 공정(S4)을 완료한 후, 원지반 사면을 따라 네일을 박아 설치한 다음, 양측 가장자리를 따라 다수개의 고리를 일체로 형성한 통상의 지오그리드를 준비한 다음, 이 지오그리드의 일측 고리에 지지대를 끼워 조적된 옹벽블록의 걸림홈에 끼워 설치하고, 지오그리드의 타측은 원지반인 사면 전면 부근까지 깔고, 나머지는 상부로 꺾고, 꺾인 부분은 연결수단으로 원지반 사면을 따라 박은 네일과 연결하는 방법으로 지오그리드를 포설하는 지오그리드 설치 공정(S5);After completing the backfilling process (S4), nails are installed along the base surface slope, and then, after preparing a conventional geogrid in which a plurality of rings are integrally formed along both edges, a support is fitted to one ring of the geogrid. Install the geogrid by inserting it into the hanging groove of the retained wall block, laying the other side of the geogrid to near the front surface of the slope, and bending the rest to the top, and connecting the bent portion with nail nailed along the base slope as a connecting means. Geogrid installation process (S5); 상기 옹벽블록 조적 공정(S3)에 따라 조적된 옹벽블록의 상부에 다음 단계의 옹벽블록을 배열·조적 하는 옹벽블록 조적 공정(S6);A retaining wall block forming step (S6) of arranging and arranging a retaining wall block of a next step on top of the retaining wall block assembled according to the retaining wall block forming step (S3); 상기 설치된 옹벽블록 후면에, 잡석을 부직포에 의해 싸이도록 옹벽블록 높이까지 채우고, 잡석을 싼 부직포와 사면 사이에 흙을 채워 다진 구조로 옹벽블록과 사면 사이를 채우는 뒷채움 공정(S7);A back filling step of filling the retaining wall block to the height of the retaining wall block so that the rubble is surrounded by the nonwoven fabric, and filling the rubble between the retaining wall block and the slope with a compacted structure to fill the soil between the nonwoven fabric and the slope; 상기 뒷채움 공정(S7)을 완료한 후, 상기 지오그리드 설치 공정(S5)에 따라 상부로 꺽인 상태로 설치되어 상부로 돌출된 지오그리드 끝단 고리에 지지대를 끼워, 옹벽블록 조적 공정(S6)에 따라 조적된 최상부 옹벽블록의 걸림홈에 상기 지지대를 끼워 설치하며, 지오그리드의 꺽인 부분에서 연결수단을 이용 사면에 박힌 네일과 연결하는 방식으로 시공하여, 시공된 지오그리드가 측면에서 보아 ‘
Figure 112010044888300-pat00025
’ 의 형태로 매입되는 구조를 지니도록 설치하는 지오그리드 설치 공정(S5´)을 실행하되,
After completing the backfill process (S7), the support is fitted in the geogrid end ring is installed in a state bent to the top according to the geogrid installation process (S5) protruding to the upper, and retained wall block masonry step (S6) The support is inserted into the locking groove of the upper retaining wall block, and the construction is performed by connecting the nail to the slope using the connecting means at the bent portion of the geogrid, and the constructed geogrid is viewed from the side '
Figure 112010044888300-pat00025
Perform the geogrid installation process (S5´), which is installed to have a structure that is embedded in the form of ',
상기, 지오그리드 설치 공정(S5), 옹벽블록 조적 공정(S6), 뒷채움 공정(S7), 지오그리드 설치 공정(S5´), 옹벽블록 조적 공정(S6), 뒷채움 공정(S7)을 설계된 높이가 되도록 반복한 뒤에; The geogrid installation process (S5), retaining wall block masonry process (S6), backfilling process (S7), geogrid installation process (S5 '), retaining wall block masonry process (S6), backfilling process (S7) is repeated to the designed height After one; 마지막에 설치된 옹벽블록, 잡석을 감싼 부직포, 채움·다짐 된 흙 상부로 차수 매트를 포설하는 차수 매트 포설 공정(S8);An order mat laying step (S8) of laying the order mat on top of the retaining wall block, the rubble-wrapped nonwoven fabric, and the filled and compacted soil; 상기 포설된 차수 매트 상부로 흙을 포설하여 다짐하는 지반 포설 및 다짐 공정(S9);A ground laying and compacting process (S9) for laying soil on the installed order mats and compacting the soil; 상기 다짐 된 최상부 흙에 측구를 형성하는 측구 형성 공정(S10);A side opening forming step of forming a side opening in the compacted top soil (S10); 으로 단계별 시공이 완료됨을 특징으로 하는 옹벽블록과 지오그리드를 이용한 옹벽의 시공 방법.Retaining wall construction method using a retaining wall block and geogrid, characterized in that the step-by-step construction is completed.
KR1020090114494A 2009-11-25 2009-11-25 The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid KR100981258B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090114494A KR100981258B1 (en) 2009-11-25 2009-11-25 The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090114494A KR100981258B1 (en) 2009-11-25 2009-11-25 The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid

Publications (1)

Publication Number Publication Date
KR100981258B1 true KR100981258B1 (en) 2010-09-10

Family

ID=43009931

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090114494A KR100981258B1 (en) 2009-11-25 2009-11-25 The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid

Country Status (1)

Country Link
KR (1) KR100981258B1 (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101057168B1 (en) 2011-03-04 2011-08-17 주식회사 삼안 Method for reinforceing abutment back zone forbridge
ES2396781A1 (en) * 2011-01-27 2013-02-26 Ingenieros Y Asociados Cvii, S.L. Piece for the formation of land containment walls. (Machine-translation by Google Translate, not legally binding)
KR101267234B1 (en) * 2013-01-09 2013-05-27 서재호 Retaining wall of grassing a plant
KR101371092B1 (en) * 2011-11-10 2014-03-10 (주)에스오씨산업 Length control for Coupler using Reinforced earth Retaining wall a method of construction
KR101757116B1 (en) * 2016-05-31 2017-07-26 동의대학교 산학협력단 Reinforced Earth Retaining Wall Equipped with Water Inflow Prevention and Draining Water Function
KR101787366B1 (en) * 2017-02-22 2017-10-18 우경기술주식회사 A Retaining wall using Precast pile and Construction method thereof
KR101870086B1 (en) * 2017-09-25 2018-06-21 주식회사 지오셀코리아 slope construction method using geo cell
CN109024665A (en) * 2018-09-11 2018-12-18 四川睿铁科技有限责任公司 A kind of building-brick type reinforced earth bulkhead and its construction method
CN109653241A (en) * 2019-01-16 2019-04-19 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement counterfort wall structure and construction method
KR102191879B1 (en) * 2019-09-06 2020-12-16 김재봉 Segmental retaining wall and method of contructing segmental retaining wall
KR102235064B1 (en) * 2020-11-30 2021-04-02 (유)이안지오텍 Construction Method for Vegetable Soil Bag Wall using Earth Anchors and Grids
WO2021179095A1 (en) * 2020-03-13 2021-09-16 International Precast Shoring Systems Inc. Prefabricated shoring panel
CN114411687A (en) * 2022-02-11 2022-04-29 西安公路研究院有限公司 Renewable resource slope shallow drainage device for road reconstruction and extension and building method
CN114606973A (en) * 2022-01-26 2022-06-10 新疆交通规划勘察设计研究院有限公司 Earth work check room retaining wall structure
CN115126282A (en) * 2022-07-25 2022-09-30 中国十九冶集团有限公司 Post-reinforcement method for permanent support of adjacent important building structures
CN115142465A (en) * 2022-06-18 2022-10-04 中国水利水电第十六工程局有限公司 Construction method of inclined gravity retaining wall
KR20220140930A (en) * 2021-04-09 2022-10-19 이장원 Reinforced earth walls and construction method thereof
CN116180802A (en) * 2022-12-07 2023-05-30 国网福建省电力有限公司经济技术研究院 Modular fort construction method for blocking waste soil in power transmission and transformation engineering tower foundation construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002206240A (en) * 2001-01-10 2002-07-26 Geo System Co Ltd Reinforced earth structure and construction method therefor
KR100458901B1 (en) * 2002-09-05 2004-12-08 김학준 Breast wall constructing block
KR100621678B1 (en) * 2004-03-09 2006-09-13 필드터프승목(주) Method for installing drainage block
KR200429718Y1 (en) * 2006-08-17 2006-10-27 박석림 Block for breast wall construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002206240A (en) * 2001-01-10 2002-07-26 Geo System Co Ltd Reinforced earth structure and construction method therefor
KR100458901B1 (en) * 2002-09-05 2004-12-08 김학준 Breast wall constructing block
KR100621678B1 (en) * 2004-03-09 2006-09-13 필드터프승목(주) Method for installing drainage block
KR200429718Y1 (en) * 2006-08-17 2006-10-27 박석림 Block for breast wall construction

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2396781A1 (en) * 2011-01-27 2013-02-26 Ingenieros Y Asociados Cvii, S.L. Piece for the formation of land containment walls. (Machine-translation by Google Translate, not legally binding)
KR101057168B1 (en) 2011-03-04 2011-08-17 주식회사 삼안 Method for reinforceing abutment back zone forbridge
KR101371092B1 (en) * 2011-11-10 2014-03-10 (주)에스오씨산업 Length control for Coupler using Reinforced earth Retaining wall a method of construction
KR101267234B1 (en) * 2013-01-09 2013-05-27 서재호 Retaining wall of grassing a plant
KR101757116B1 (en) * 2016-05-31 2017-07-26 동의대학교 산학협력단 Reinforced Earth Retaining Wall Equipped with Water Inflow Prevention and Draining Water Function
KR101787366B1 (en) * 2017-02-22 2017-10-18 우경기술주식회사 A Retaining wall using Precast pile and Construction method thereof
KR101870086B1 (en) * 2017-09-25 2018-06-21 주식회사 지오셀코리아 slope construction method using geo cell
CN109024665A (en) * 2018-09-11 2018-12-18 四川睿铁科技有限责任公司 A kind of building-brick type reinforced earth bulkhead and its construction method
CN109653241A (en) * 2019-01-16 2019-04-19 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement counterfort wall structure and construction method
KR102191879B1 (en) * 2019-09-06 2020-12-16 김재봉 Segmental retaining wall and method of contructing segmental retaining wall
WO2021179095A1 (en) * 2020-03-13 2021-09-16 International Precast Shoring Systems Inc. Prefabricated shoring panel
KR102235064B1 (en) * 2020-11-30 2021-04-02 (유)이안지오텍 Construction Method for Vegetable Soil Bag Wall using Earth Anchors and Grids
KR20220140930A (en) * 2021-04-09 2022-10-19 이장원 Reinforced earth walls and construction method thereof
KR102576395B1 (en) * 2021-04-09 2023-09-11 이장원 Reinforced earth walls
CN114606973A (en) * 2022-01-26 2022-06-10 新疆交通规划勘察设计研究院有限公司 Earth work check room retaining wall structure
CN114411687A (en) * 2022-02-11 2022-04-29 西安公路研究院有限公司 Renewable resource slope shallow drainage device for road reconstruction and extension and building method
CN115142465A (en) * 2022-06-18 2022-10-04 中国水利水电第十六工程局有限公司 Construction method of inclined gravity retaining wall
CN115126282A (en) * 2022-07-25 2022-09-30 中国十九冶集团有限公司 Post-reinforcement method for permanent support of adjacent important building structures
CN116180802A (en) * 2022-12-07 2023-05-30 国网福建省电力有限公司经济技术研究院 Modular fort construction method for blocking waste soil in power transmission and transformation engineering tower foundation construction

Similar Documents

Publication Publication Date Title
KR100981258B1 (en) The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid
KR101105092B1 (en) A precast retaining panel and construction method of the same with half pc type backfill
KR100741528B1 (en) Environment green wall
CA2561785A1 (en) A reinforced soil retaining wall system and method of construction
KR100641815B1 (en) Reinforced geotextile mat and reinforcement of earth slopes and embankments using the same
CN109972638A (en) The construction method of prefabricated assembled thin-wall mould-shell lattice girder ecological slope protection
KR100874961B1 (en) Reinforced earth retaining wall wire mesh
KR100654936B1 (en) Method for constructing retaining wall
KR101383624B1 (en) Retaining Wall Having Natural Rock And Construction Method Thereof
KR101963362B1 (en) Reinforced gabion retaining wall capable of completely drainage and construction method thereof
KR101235826B1 (en) The method of constructing block for wall
KR100889257B1 (en) Precast concrete facing panel using greening of retaining panel's front
KR20080108879A (en) Reinforcing method of bearing power for soft ground and reinforcing apparatus used in the same method
KR100748607B1 (en) The construction method of basement drainage having double drainage canals and the system
CN212316949U (en) Supporting construction of side slope
US5551798A (en) Culvert end wall retainer system
KR100647071B1 (en) The method of constructing bloclk for wall
KR101501733B1 (en) The eco-friendly precast l type retaining wall fixed with an anchor
KR20090073330A (en) Revetment structure using natural stones
KR100451429B1 (en) Combination system of block type reinforced retaining wall used waste concrete and waste limestone and constructing method thereof
KR101012653B1 (en) Retaining wall structure and construnction method of the retaining wall structure
KR100794669B1 (en) Wire net for reinforced earth retaining wall and method of constructing the reinforced earth retaining wall utilizing the wire net
CN110939141A (en) Supporting construction of side slope
JP2750364B2 (en) Steep embankment
KR200433390Y1 (en) The construction system of basement drainage having double drainage canals

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130930

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140827

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150902

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee