KR100647071B1 - The method of constructing bloclk for wall - Google Patents

The method of constructing bloclk for wall Download PDF

Info

Publication number
KR100647071B1
KR100647071B1 KR1020060020855A KR20060020855A KR100647071B1 KR 100647071 B1 KR100647071 B1 KR 100647071B1 KR 1020060020855 A KR1020060020855 A KR 1020060020855A KR 20060020855 A KR20060020855 A KR 20060020855A KR 100647071 B1 KR100647071 B1 KR 100647071B1
Authority
KR
South Korea
Prior art keywords
block
retaining wall
cement
gravel
blocks
Prior art date
Application number
KR1020060020855A
Other languages
Korean (ko)
Inventor
권병무
Original Assignee
대명콘텍 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대명콘텍 주식회사 filed Critical 대명콘텍 주식회사
Priority to KR1020060020855A priority Critical patent/KR100647071B1/en
Application granted granted Critical
Publication of KR100647071B1 publication Critical patent/KR100647071B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion

Abstract

A construction method of a block for a retaining wall is provided to increase bearing force against horizontal earth pressure, and to prevent collapse of the retaining wall by alternately arranging the blocks, vertically connecting a cement rod, fixing a meshed grid between the blocks and draining water. The position of a retaining wall is set, and a foundation or a slope is formed by horizontally compacting the ground. Fitting projections are removed from the foundation, and gravel(13) is charged between the blocks and a gravel charge hole(8) by integrating block corners(2a,2b). Cement charge holes(9a,9b) are filled with cement, and a grid mesh(14) is mounted from an upper part(6) of the block to the slope by laying and compacting gravel and soil in a rear wall(5) and the slope. A second block is constructed by integrating the corners of the blocks with each other and charging gravel, cement and soil. The final block is constructed, and cement mortar is poured and cured. The grid is formed by forming a band with bonding plural thermoplastic resin coated cords including chemical fiber assemblies by heat and horizontally and vertically arranging the bands.

Description

옹벽용 블록 시공방법{THE METHOD OF CONSTRUCTING BLOCLK FOR WALL}Block construction method for retaining wall {THE METHOD OF CONSTRUCTING BLOCLK FOR WALL}

도 1은 본 발명의 옹벽용 블록 시공방법에 사용되는 옹벽블록의 정면 사시도1 is a front perspective view of a retaining wall block used in the retaining wall block construction method of the present invention;

도 2는 본 발명의 옹벽용 블록 시공방법에 사용되는 옹벽블록의 배면 사시도Figure 2 is a rear perspective view of the retaining wall block used in the retaining wall block construction method of the present invention

도 3은 본 발명의 옹벽용 블록 시공방법의 시공진행중인 상태를 나타낸 사시도Figure 3 is a perspective view showing the construction in progress of the retaining wall block construction method of the present invention

도 4는 본 발명의 옹벽용 블록 시공방법의 수직 적층된 상태의 측면도Figure 4 is a side view of a vertically stacked state of the retaining wall block construction method of the present invention

도 5는 본 발명의 옹벽용 블록 시공방법의 경사 옹벽시공 진행중인 상태의 사시도Figure 5 is a perspective view of the inclined retaining wall construction in progress of the retaining wall block construction method of the present invention

도 6은 본 발명의 옹벽용 블록 시공방법의 경사 적층된 상태의 측면도Figure 6 is a side view of the laminated stack state of the retaining wall block construction method of the present invention

도 7은 본 발명의 옹벽용 블록 시공방법에 사용되는 격자 망을 나타낸 사시도7 is a perspective view showing a grid net used in the retaining wall block construction method of the present invention

본 발명은 옹벽용 블록의 시공방법에 관한 것으로 구체적으로는 옹벽용 블록에는 수평 및 수직으로 강력하게 연결고정되는 수단이 형성되어 있으며 또 블록 전 면 폭보다 후면 폭을 짧게 하고 블록 전후면 사이에 잘룩부가 형성되어 채움재를 충진케 할 수 있게 함으로써 상하ㆍ좌우 블록간의 이완을 방지하며 블록 몸체 내측에 수직으로 형성된 자갈 충진공과 블록 후면에 자갈을 충진하므로서 배수가 용이하고 하층단과 상층단의 블록을 엇갈리게 축성하여 입체감과 조형미를 갖게 하며 단과 단 사이에는 격자(grid)를 삽입하여 내측 토양에 수평으로 매몰시킴으로써 옹벽의 붕괴를 방지할 수 있도록 한 옹벽용 블록의 축성방법에 관한 것이다.The present invention relates to a method for constructing a retaining wall block. Specifically, the retaining wall block is provided with a means for strongly and horizontally fixing the retaining wall block. By forming an additional part to fill the filling material, it prevents loosening between the upper, lower, left and right blocks, and makes the drainage easy by filling the gravel filling hole formed vertically inside the block body and the gravel at the rear of the block, and making the lower and upper blocks alternate. This invention relates to a method of building retaining wall blocks to prevent the collapse of the retaining wall by inserting a grid between the ends and the ends to bury them horizontally in the inner soil.

종래 옹벽의 시공방법으로 등록특허공보(등록번호 10-0527293호)에 기재된 내용과 같이 경사면에 시공되는 옹벽 시공방법에 있어서, 지면의 상측에 등 간격으로 수직포스트(10)가 설치되는 수직포스트 설치단계와 상기 설치된 수직포스트(10)와 수직포스트(10) 사이에 수평부재(20)가 설치되는 수평부재 설치단계와 상기 수평부재(20)의 후면으로 스트립(30)이 설치되는 스트립 설치단계와 상기 수직포스트(10)와 수지포스트(10)의 전면으로 경사지게 제 1 스크린 홈부(41)가 형성된 한 쌍의 프론트포스트(40)가 이음부재(50)에 의하여 연결설치되는 프론트포스트 설치단계와 상기 한 쌍의 프로트포스트(40)와 또 다른 한 쌍의 프로트포스트(40') 사이의 제 1 스크린 홈부(41)에 제 1 스크린(60)이 슬라이드 결합하고 프론트포스트(40)의 후면에 제 2 스크린(70)이 볼트 결합되어지는 스크린 결합단계와 상기 결합된 제 1 스크린(60)과 제2 스크린(70) 사이에 식생부가 조성되는 식생부 조성단계와 수직포스트(10)와 프론트포스트(40) 및 이음부재(50) 사이에 돌채웁작업이 순차적으로 제공되어 옹벽(A)이 시공되는 옹벽시공방법에 관한 것으로 우선 옹벽용 구조물이 프레임들로 구성되어 있고 각각의 수직 포스트와 수평부재들이 끼움과 볼트결합 등 복잡한 조립으로 형성됨으로써 시공방법이 복잡하고 구조물이 중량감이 없어 내측의 토압을 견디기 힘들며 친환경적인 조형미를 현출시킬 수 없고 특히 스트립(띠 강판), 볼트 등과 같은 구조물의 부품 등은 산화부식으로 오래가지 않아 손상이 오므로 옹벽의 붕괴를 초래케 하는 옹벽용 구조물이라 할 수 있으며 또 종래 관련기술로서 국내공개특허공보(공개번호: 10-2005-0110603호)가 소개되고 있다. In the retaining wall construction method, which is constructed on an inclined surface as described in the prior art retaining wall construction method (Registration No. 10-0527293), a vertical post is installed in which the vertical posts 10 are installed at equal intervals above the ground. And a horizontal member installation step of installing a horizontal member 20 between the installed vertical post 10 and the vertical post 10, and a strip installation step of installing a strip 30 to the rear surface of the horizontal member 20; The front post installation step of connecting the front post 40, the first post groove portion 41 is formed to be inclined toward the front of the vertical post 10 and the resin post 10 is connected by the joint member 50 and the A first screen 60 slides into a first screen groove 41 between a pair of front posts 40 and another pair of front posts 40 'and a second rear surface of the front post 40. Screen 70 is bolted A vegetation part forming step in which a vegetation part is formed between the screen coupling step and the combined first screen 60 and the second screen 70, and between the vertical post 10, the front post 40, and the joint member 50. The retaining wall construction method in which the retaining wall (A) is constructed by sequentially providing the stone filling work on the retaining wall is first constructed. The retaining wall structure is composed of frames, and each vertical post and horizontal members are formed by complex assembly such as fitting and bolting. Therefore, the construction method is complicated, and the structure is not heavy, so it is difficult to endure earth pressure inside, and it is impossible to express eco-friendly molding beauty. Especially, parts of the structure such as strip (steel plate), bolts, etc. are damaged due to oxidation corrosion for a long time. It can be called a retaining wall structure that causes the retaining wall to collapse. In addition, as a related art, Korean Patent Publication No. 10-2005-0110603 It is opening.

이는 조립체(11)가 중량감이 없으며 조립체간의 상하ㆍ좌우 결합이 약하고 불안정하여 수평 토압을 견디기 어려움으로써 전체적인 수직 벽 축성은 거의 불가능하므로 계단 벽 축성으로 한정됨으로써 전체적으로는 경사지게 시공할 수밖에 없는 결함이 있을 뿐만 아니라 어스앵커(20)의 머리부의 방청을 위한 안착홈(14)의 형성, 안착홈(14)에 덮개(30) 삽입, 스토퍼홈(33)에 스토퍼(40)의 삽입체결, 덮개(30)의 측면에 형성된 몰탈투입홈(32)을 통한 몰탈주입과 조립체와 조립체의 상하 연결에 있어서 핀홀에 핀의 삽입 등 시공작업이 극히 까다롭고 많은 시간이 소요되며 핀, 스토퍼, 어스앵커 등 금속재질로 구성됨으로써 쉽게 부식될 수 있고 특히 어스앵커 삽입시 토양내에 돌이나 견고한 물질이 매몰되어 있을 경우는 밀어 넣을 수 없고 어스앵커가 봉상으로 되어 있어 사면의 토양내에서 쉽게 빠질 수 있다.This is because the assembly 11 has no weight, and the up, down, left and right coupling between the assemblies is weak and unstable, so that it is difficult to endure the horizontal earth pressure. Formation of the seating groove 14 for rust prevention of the head of the earth anchor 20, inserting the cover 30 in the seating groove 14, fastening of the stopper 40 in the stopper groove 33, cover 30 Mortar injection through the mortar injection groove 32 formed on the side of the assembly and the construction work such as the insertion of the pin into the pinhole in the vertical connection of the assembly and the assembly is extremely demanding and takes a lot of time, such as metal materials such as pins, stoppers, earth anchors, etc. It can be easily corroded and cannot be pushed, especially if there is a stone or solid material buried in the soil when the earth anchor is inserted. Uh it can be easily dislodged from the surface of the soil.

또 다른 종래기술로서 국내공개특허공보(공개번호 10-2005-00787)에는 생태블록 및 생태블록의 시공방법이 소개되고 있다.As another conventional technology, the Korean public patent publication (Publication No. 10-2005-00787) introduces an ecological block and a construction method of the ecological block.

여기서는 기초부(75)에 뚫어진 구멍에 철근을 꽂고 철근에 식생블록(20)에 수직방향으로 뚫어진 2개의 관통구(62)를 삽입하여 축성하는 시공방법으로 철근의 상단에 식생블록(20)의 구멍(62)에 하나씩 끼워 하측으로 내려오게 하는 작업은 극 히 까다롭고 또한 인접한 블록의 수직 열을 축성할 시는 인접부의 결합 조립부분이 돌부(25)와 오목부(27)로 구성되어 있어 기초부(75)에 철근이 끼워져 있는 상태에서는 축성이 불가능하다고밖에 볼 수 없으며 아니면 높이 축성한 다음에 철근을 구멍으로 기워 넣는다면 생태블록(20) 각각의 관통구(62) 그리고 기초부(75)에 뚫어진 구멍이 정확하게 일치되지 않으면 철근을 관통시키는 것이 불가능한 문제점이 있고 만일 축성되었다 하더라도 기초부(75)의 사면 방향에 따라 식생블록이 축성되므로 이로 인해 식생블록(20)의 바닥면이 내측으로 경사지게 축성될 수밖에 없다. 이는 우천시 빗 불이 전부 내측으로 흘러들어 지반을 취약하게 하므로 붕괴요인이 발생하게 된다.Here, insert the reinforcing bar into the hole drilled in the base portion 75 and insert the two through-holes 62 drilled in the vertical direction to the vegetation block 20 in the reinforcement by the construction method of the vegetation block 20 on the top of the rebar It is extremely difficult to insert one by one into the hole 62 and to lower it. Also, when building vertical rows of adjacent blocks, the joining assembly of the adjacent parts is composed of the protrusions 25 and the concave parts 27. If the reinforcement is inserted into the reinforcing portion (75) can only be seen that the layering is impossible, or if the reinforcing reinforcing the reinforcing reinforcing the reinforcing reinforcing the reinforcing reinforcing bars in each of the ecological block 20 and the base portion 75 There is a problem that it is impossible to penetrate the reinforcing bar if the holes are not exactly matched, and even if it is built up because the vegetation block is built up along the slope direction of the base 75, because of this vegetation block 20 This can only be consecrated inclined inner bottom surface. This is because rain rains all flow inward to make the ground vulnerable, causing decay.

그 밖에도 잘 알려진 철근 구조물의 옹벽 구조물이 있다. 이는 구조학적으로 견실하긴 하나 기초부에 수평 토압을 견딜 수 있는 구조적인 설계가 뒤따라 한다. 예를 들어 바닥 판부를 크게 형성해야 하고 내측으로 바닥부와 수직벽부를 고정연결시키는 지지수단이 형성되어야 하고 기초작업을 위해 땅을 깊이 파야하며 거푸집의 제작, 철근의 삽입, 몰탈의 양생 등 인건비, 재료비, 시공기간 등에서 크게 불리하다 하겠다.There is also a well-known retaining wall structure of reinforcing steel structures. This is structurally robust but is followed by a structural design that can withstand horizontal earth pressure on the foundation. For example, the bottom plate should be large, support means for fixing the bottom and the vertical wall inwards should be formed, and the ground should be dug deep for foundation work, labor costs such as the production of formwork, the insertion of rebar, the curing of mortar, It is very disadvantageous in material cost and construction period.

본 발명은 시멘트 블록에 의한 옹벽 시공방법으로서 종래 금속 또는 프라스틱재의 지지체, 프레임, 연결수단 등으로 연결 조립되는 옹벽 구조물이나 통상의 시멘트 블록과는 달리 세석 또는 자갈을 충진하는 자갈 충진공 구비되어 중량감을 갖는 옹벽용 블록으로 자체 중량에 의해서 수평으로 작용하는 토압에 대한 지지력 을 확보함과 동시에 축성시 단과 단 사이에 격자(grid)를 삽입하여 자갈과 매립토로 매몰시킴으로써 수평토압에 대한 지지력을 극대화할 수 있고 우천시 약해진 토양의 유동과 이동을 저지하여 붕괴를 방지할 수 있으며 옹벽 전면이 돌출부와 오목부로 형성되게 함으로써 입체감에 의한 조형미를 현출시킬 수 있고 고정수단으로 블록과 블록간에 이완이 방지되며 옹벽 내측에서 외측으로 배수가 용이한 옹벽블록의 시공방법을 제공함에 있다.The present invention is a retaining wall construction method using a cement block, unlike a retaining wall structure or a conventional cement block, which is connected and assembled by a support, a frame, a connecting means, etc. of a conventional metal or plastic material, a gravel filling hole filled with fine stone or gravel is provided. It is a retaining wall block with its own weight, which secures the bearing capacity against the earth pressure acting horizontally by its own weight, and at the same time, it inserts a grid between the stage and the stage and burys it with gravel and landfill to maximize the bearing capacity for the horizontal soil pressure. It can prevent the collapse by preventing the flow and movement of the soil weakened in rainy weather. The front surface of the retaining wall is formed by the protrusions and the concave parts, so that the molding beauty can be expressed by the three-dimensional effect. Provides construction method of retaining wall block that is easy to drain to outside It is.

본 발명은 종래 옹벽블록 시공방법의 문제점을 개선한 옹벽블록 시공방법으로 시공에 사용되는 옹벽블록은 도 1, 도 2에 나타난 바와 같이 앞측에는 전면벽(1)의 양측에 내측으로 꺾어진 전면벽(1a,1b)이 대칭으로 형성되어 있고 전면벽(1a,1b)의 외측 모서리(2a,2b)에서 좌ㆍ우로 측벽(3a,3b)이 형성되는데 블록 내측으로 수렴되어 대칭되게 형성됨과 동시에 각각 잘룩부(4a,4b)가 형성되어 있으며 후측에는 전체 전면폭 보다 짧은 후면 벽(5)이 형성되어 있고 상면(6)에는 자갈충진공(8) 및 주변에 내측으로 턱(9a',9b')이 형성된 시멘트 충진공(9a,9b)이 형성되어 있으며 저면(10)에는 전면에서부터 좌우측에 걸림돌기(7a,7b), 시멘트 충진공(9a,9b)의 주변에 내측으로 턱(9a',9b')이 형성되어 있는 옹벽블록(A)이라 할 수 있으며 이와 같은 블록으로 옹벽을 시공하는 방법은 다음과 같다.According to the present invention, the retaining wall block used in the construction of the retaining wall block construction method improves the problems of the conventional retaining wall block construction method. As shown in FIGS. 1 and 2, the front wall is inwardly curved on both sides of the front wall 1 ( 1a and 1b are formed symmetrically and sidewalls 3a and 3b are formed at the left and right side edges 2a and 2b of the front walls 1a and 1b. Part 4a and 4b are formed, and rear side wall 5 is formed on the rear side, which is shorter than the entire front width, and on the upper side 6, gravel filling hole 8 and around the jaw 9a ', 9b' inward. The formed cement filling holes 9a and 9b are formed, and the bottom surface 10 has the jaws 9a 'and 9b inward around the locking projections 7a and 7b and the cement filling holes 9a and 9b from the front and left sides. It can be called a retaining wall block (A) in which ') is formed. And the like.

이를 단계별로 설명하면Explain this step by step

1. 사면 및 기초면 형성단계1. Formation of slope and foundation surface

옹벽이 축성될 위치를 설계(선정)한 다음 이 위치 내측으로 흙을 파내고 사 면(12)을 형성한 다음 옹벽이 축성될 위치의 지면을 수평으로 다지거나 시멘트 몰탈 또는 고화토를 타설하여 수평면을 형성하여 축성 기초면(11)을 형성한다.After designing (selecting) the location where the retaining wall is to be built, excavate the soil inside the location and form slopes 12, then level the ground where the retaining wall is to be built, or cast cement mortar or solidified soil Is formed to form the layering base surface 11.

2. 블록 1단 축성단계2. Block 1st Step

기초면(11) 위에 걸림돌기(7a, 7b)를 제거하고 블록 상면(6)은 위로, 전면벽(1)은 전방으로 향하도록 하나의 블록모서리(2b)와 인접하는 블록모서리(2a)를 일치시키고 인접한 모서리(2a)와 또 다른 블록모서리(2b)를 일치시키는 방법으로 일단을 축성한 다음 블록과 블록사이에 발생하는 공간 및 자갈충진공(7)에 자갈(13)을 채우고 시멘트충진공(9a, 9b)에는 시멘트를 충진시키며 후면벽(5)에는 자갈, 사면(12)측으로는 매립토(14)를 블록의 높이 수준으로 매립하고 다짐한 다음 그 위에 블록의 상면에서 경사면까지 망사체로 된 격자(grid)(14)로 포장한다.Remove the block projections 7a and 7b on the base surface 11, and move the block edge 2a adjacent to one block edge 2b so that the block top surface 6 faces upward and the front wall 1 faces forward. One end is built up by matching and matching the adjacent edges 2a and another block edge 2b, and then the gravel 13 is filled in the space and gravel filling hole 7 between the blocks and the block Cement is filled in (9a, 9b), gravel on the rear wall (5), landfill soil (14) on the slope 12 is buried and compacted to the height level of the block, and then a grid of mesh from the top surface to the slope of the block thereon. It is packed with a grid 14.

3. 블록 2단 축성단계3. Block two-stage building stage

상기 1단 축성이 된 블록 상면에 1단 블록과 블록사이에 정확하게 놓이도록 축성하되 인접한 블록과 블록사이에 모서리를 일치시켜 2단을 축성하고 1단에서와 같이 블록과 블록사이 및 자갈충진공에는 자갈을 충진하고 시멘트충진공에는 시멘트 몰탈을 충진시킨 다음 후면벽(5)에는 자갈(쇄석), 사면(12)측으로는 매립토(15)를 2단 블록의 상면 수준으로 충진 매립하고 다짐한 다음 2단 블록 상면에서 경사면까지 격자(grid)의 망상체(14)로 포장한다.Lay the first stage block on the upper surface of the block to be precisely laid between the first stage block and the block, but the edge between the adjacent block and the block to build the second stage, and as in the first stage between the block and blocks and gravel filling vacuum Fill the gravel and fill the cement filling hole with cement mortar, fill the back wall (5) with gravel (crushed stone), landfill soil (15) on the slope (12) side to the upper level of the two-stage block, and then Wrapped in a grid of nets 14 from the top of the block to the slope.

4. 나머지 단 축성단계(마감단계)4. The other shortening stage (finishing stage)

블록 2단 축성 방법으로 되풀이하여 축성하여 최종단까지 축성한 다음 역시 자갈충진 및 시멘트충진, 그리고 흙을 매립한 다음 다짐하고 시멘트 몰탈로 타설하 여 일정두께로 마감한다.Repeat with the two-stage layering method and build up to the final stage. Also, gravel filling, cement filling, and soil are reclaimed, then compacted and poured with cement mortar to finish to a certain thickness.

이상의 옹벽 시공방법은 옹벽을 수직으로 축성하는 시공방법이며 옹벽을 경사지게도 축성할 수 있다.The retaining wall construction method described above is a construction method in which the retaining wall is vertically accumulated, and the retaining wall can also be inclined.

옹벽을 경사지게 시공하는 방법은 도 5 내지도 6에서와 같이 블록 1단 축성 시공방법은 수직옹벽 1단 축성 방법과 동일하고 블록 2단 축성은 1단 축성이 된 블록 상면에 2단 블록을 1단 블록과 블록사이에 엇갈리게 적층하되 1단 블록보다 약간 후측(내측)으로 놓이게 하는 차이밖에 없다.As for the method of constructing the retaining wall in an inclined manner, as in FIG. 5 to FIG. 6, the one-step block construction method is the same as that of the vertical retaining wall one-step layering method, and the two-step block layer has one step of two-stage blocks on the upper surface of the block. The only difference is that the blocks are stacked alternately between blocks, but slightly behind the first block.

여기에서는 블록하면의 돌기 위치가 수직옹벽 시공방법보다 자갈충진공의 뒷쪽으로 위치하여 삽입되며 옹벽의 경사도는 상단의 블록위치가 하단의 블록위치보다 얼마만큼 내측으로 위치하는가에 따라 결정되나 자갈충진공의 전후폭에 따라 제한 된다.In this case, the projection position on the lower surface of the block is inserted behind the gravel filling hole than the vertical retaining wall construction method, and the inclination of the retaining wall is determined by how much the block position at the top is located inward from the block position at the bottom. Limited by front and rear width.

수직옹벽과 또 다른 차이점은 수직옹벽에서는 시멘트 충진공이 일치하여 충진공에 의해 하단에서부터 상단까지 직선상의 봉상체가 형성되지만 경사옹벽에서는 시멘트 충진공이 전후로 엇갈리게 연결되어도 6에서와 같이 측단면에서 볼 때 단에서 약간씩 꺽여진 상태로 연결되며 자갈충진공 역시 수직옹벽에서는 하단에서 최종단까지 횡방향으로 엇갈리면서 연결되나 경사옹벽에서는 횡방향 및 전후방향에서 엇갈리면서 하단에서 최종단까지 연결된다. 그밖에 동일단의 인접한 블록과 블록의 공간에 자갈체움, 블록내측의 자갈체움, 경사면측의 흙의 매립 등은 같은 시공법으로 행해진다.Another difference from the vertical retaining wall is that the cement filling hole coincides with the vertical retaining wall to form a straight rod from the bottom to the upper end by the filling hole. However, in the gradient retaining wall, the cement filling hole is staggered back and forth. In the vertical retaining wall, the gravel filling is also connected in a transverse direction from the bottom to the final end in the vertical retaining wall, but in the inclined retaining wall, the gravel filling is connected from the lower end to the final end. In addition, in the adjacent block of the same stage and the space of the block, the gravel box, the gravel box inside the block, the landfill of the soil on the inclined surface, etc. are performed by the same construction method.

이상의 시공방법으로 축성하면 상단층의 블록하면 돌기(7a, 7b)가 하단층에 접하고 있는 양측 블록 자갈충진공(8)에 삽입되어 결착되고 상단층의 블록은 그 위 단의 블록돌기(7a, 7b)에 의하여 블록의 자갈충진공(8)에 삽입되면서 결착되므로 블록간의 상호 이완을 방지함과 동시에 강력하게 고정되며 시멘트 충진공 또한 상측단의 블록 시멘트충진공(9a, 9b)이 하단층에 인접한 양블록 충진공(9b,9a)과 수직으로 일치되어 충진되는 시멘트에 의하여 수직으로 시멘트의 봉상체(16)가 연속적으로 형성되므로서 이 역시 블록간의 이완을 방지함과 동시에 수평 및 수직으로 블록을 강력하게 고정시킨다. When the above-described construction method is established, the lower surface block projections 7a and 7b of the upper layer are inserted into and bound to both block gravel filling holes 8 in contact with the lower layer, and the block of the upper layer blocks the upper projections 7a and 7b. 7b) is inserted into the gravel filling hole (8) of the block, thereby binding and preventing the mutual relaxation between the blocks at the same time strongly fixed and cement filling hole also the block cement filling holes (9a, 9b) of the upper end in the lower layer Since the rod-shaped body 16 of cement is continuously formed vertically by cement filled vertically coinciding with adjacent two-block filling holes 9b and 9a, this also prevents relaxation between blocks and blocks blocks horizontally and vertically. Strongly fix it.

또한, 격자망(grid)(14)은 블록의 단과 단사이에서 시멘트 봉상체에 결착됨과 동시에 돌기에 눌려 결착되고 내측으로는 자갈 및 매립토에 매몰됨으로써 옹벽은 강력한 수평토압을 견딜 수 있어 붕괴될 염려가 없다.In addition, the grid 14 binds to the cement rod between the ends of the block and at the same time is pressed by the protrusions and buried in the gravel and the landfill inward so that the retaining wall can withstand a strong horizontal earth pressure and collapse. There is no.

여기에서 격자(grid)(14)는 도 7에서와 같이 인장강도가 뛰어난 폴리에스텔 파이버 또는 나이론 파이버사 된 합성섬유 집속체(14a)를 폴리에티렌, PVC 등과 같은 열가소성 수지로 압출 코팅한 코드(14b)를 여러 가닥(strand)으로 인접시켜 열 융착한 밴드(14c)로 가로 및 세로로 일정간격으로 열 융착시켜서 된 격자(gird)이다.Here, the grid 14 is a cord obtained by extrusion coating a polyester fiber or nylon fiber-made synthetic fiber bundle 14a having excellent tensile strength with a thermoplastic resin such as polystyrene, PVC, etc. It is a gird | lattice which was heat-welded by the band 14c by 14b) adjacent to several strands, and was heat-fused at predetermined intervals horizontally and vertically.

상기 코드의 직경은 1㎜~1.5㎜이고 인장강도는 50㎏ f/1.5㎜ 가닥 정도로서 밴드의 인장강도는 더욱 크고 밴드간의 간격은 3㎝~4㎝로서 1m의 폭일 경우 5~6톤까지 버틸 수 있다.The diameter of the cord is 1mm ~ 1.5mm and the tensile strength is about 50kg f / 1.5mm strands, the band's tensile strength is bigger and the spacing between bands is 3cm ~ 4cm. have.

이와 같은 격자 망상체는 종래 금속재로된 스트립, 봉상체의 앵커와는 수분 및 공기에 의한 부식손상이 발생하지 않고 우천시 물이 침투해 약해진 지반의 유동 이나 이동을 저지함으로써 쉽게 세굴이 발생하지 않으므로 옹벽의 붕괴 방지기능이 탁월하다 할 수 있다.Such lattice reticular body does not cause corrosion damage due to moisture and air with strips and rods made of conventional metals, and does not easily scour due to water infiltration during rainy weather and prevents weak ground from moving or moving. Excellent anti-collapsing function.

본 발명에 의한 옹벽블록 시공방법은 불록 전면에 각이 형성되어 있고 블록을 횡으로 엇갈리게 축성함으로써 입체적인 조형비를 현출시키며 자갈충진공에 의한 돌기의 맞물림 그리고 시멘트 충진공에 의하여 시멘트 봉상체가 수직으로 연결되어 있어 상하는 물론 좌우로 강력하게 고정되어 있으며 옹벽의 블록단과 단 사이에 망상체로 된 격자가 결착고정되어 수평으로 경사면까지 연결 매몰되어 있어 수평 토압에 대한 지지력을 극대화할 수 있고 우수나 누수에 의하여 약해진 지반의 유동이나 이동을 저지하여 붕괴의 위험을 방지할 수 있으며 블록의 자갈충진공 및 블록간의 공간에 채워진 자갈과 옹벽 충진된 자갈층으로 우수한 배수기능을 갖는 견고하고 안전한 옹벽블록의 시공방법이라 할 수 있다.In the retaining wall block construction method according to the present invention, an angle is formed on the front surface of the block and the block is transversely accumulated to exhibit a three-dimensional modeling ratio, and the cement rod is vertically formed by the engagement of the projections by the gravel filling process and the cement filling hole. As it is connected, it is strongly fixed to the upper and lower sides, and to the left and right, and the grid of mesh is fixed between the block end and the end of the retaining wall, and it is connected and buried horizontally to the inclined surface to maximize the bearing capacity for horizontal earth pressure. It can prevent the risk of collapse by preventing the flow or movement of weak ground, and it is a method of constructing a solid and safe retaining wall block that has excellent drainage function by the gravel filling of blocks and the gravel and retaining wall filled gravel layer. Can be.

Claims (2)

전면벽(1)의 양측 내측으로 꺽어진 전면벽(1a, 1b)이 대칭으로 형성되어 있고 전면벽(1a, 1b)의 외측모서리(2a, 2b)에서 좌ㆍ우로 측벽(3a, 3b)이 형성되데 블록 내측으로 수렴되어 대칭되게 형성됨과 동시에 각각 잘룩부(4a, 4b)가 형성되어 있으며 후측에는 후면벽(5)이 형성되어 있고 상면(6)에는 자갈충진공(8), 턱(9a', 9b')이 형성된 시멘트충진공(9a, 9b)이 형성되어 있으며 저면(10)에는 좌ㆍ우측에 걸림돌기(7a, 7b), 턱(9a', 9b')이 형성된 시멘트충진공(9a, 9b)이 있는 옹벽블록(A)으로 옹벽을 시공함에 있어 The front walls 1a and 1b, which are bent to both inner sides of the front wall 1, are formed symmetrically, and the side walls 3a and 3b to the left and right sides of the outer edges 2a and 2b of the front walls 1a and 1b are symmetrically formed. Converging to the inside of the block is formed symmetrically, and at the same time the cutouts (4a, 4b) are formed, respectively, the rear wall (5) is formed on the rear side and the gravel filling hole (8), jaw (9a) on the upper surface (6) Cement filling holes (9a, 9b) having a ', 9b') is formed and the cement filling hole (7a, 7b, jaw (9a ', 9b') is formed on the bottom and left side (10) In retaining wall construction with retaining wall block (A) with 9a, 9b) 옹벽이 축성될 위치를 설정하고 이 위치에 지면을 수평으로 다지거나 기초면(11)을 옹벽 축성 위치 내측으로 사면(12)을 형성하는 기초면 및 사면 형성단계와;A base surface and a slope forming step of setting a position at which the retaining wall is to be built and leveling the ground at this position or forming the slope 12 into the retaining wall layering position; 기초면(11) 위에 걸림돌기(7a, 7b)를 제거하고 블록모서리(2b)와 인접하는 블록모서리(2a) 일치시켜 횡으로 일단을 축성한 다음 불록과 블록사이에 발생하는 공간 및 자갈충진공(8)에 자갈(13)을 채우고 시멘트충진공(9a, 9b)에는 시멘트를 충진시키며 후면벽(5)에는 자갈을, 사면(12)측으로는 매립토(15)을 블록높이 수준으로 매립하고 다짐한 다음 그 위에 블록상면(6)에서 사면(12)까지 격자망(14)으로 포장하는 블록 1단 축성단계와;After removing the locking projections 7a and 7b on the base surface 11 and matching the block edges 2b to the adjacent block edges 2a, the ends are horizontally formed and space and gravel filling spaces generated between the blocks and the blocks are formed. (8) to fill the gravel (13), the cement filling holes (9a, 9b) to fill the cement, the rear wall (5) to the gravel (12) to the landfill soil (15) to the level of the block and reclaimed Next, the first stage of block forming step of paving the lattice network 14 from the block top surface 6 to the slope 12; 상기 1단 축성이 된 블록 상면에 1단 블록과 블록사이에 놓이도록 축성하되 인접한 블록과 블록사이에 모서리(2b) 및 (2a)를 일치시켜 횡으로 축성하고 1단 축성과 동일한 방법으로 자갈, 시멘트, 메립토를 충진 및 매립한 다음 1단 축성방법 으로 격자를 포장하는 블록 2단 축성단계와;Lay the first stage block to be placed between the first stage block and the block to be laid between the blocks and the adjacent block and the edges (2b) and (2a) coincide in the horizontal layer and in the same way as the first stage layering gravel, A two-stage layering step of paving the lattice in one-stage layering method after filling and embedding cement and landfill; 블록 2단 축성 방법을 되풀이하여 최종단까지 축성 시공한 다음 시멘트 몰탈로 타설하는 마감단계를 포함하는 옹벽용 블록 시공방법Retaining wall block construction method including finishing step of repeating block two-stage layering method and finishing finishing to final stage and then placing with cement mortar 청구항 1항에 있어서 격자(grid)(14)는 화학섬유 집속체(14a)를 열가소성 수지 압출 코팅된 코드(14b)를 여러 가닥으로 인접시켜 열융착시킨 밴드(14c)로 가로 및 세로로 일정간격으로 열융착시켜서 된 격자임을 특징으로 하는 옹벽용 블록 시공방법The grid (14) according to claim 1, wherein the grid (14) is horizontally and vertically spaced in a band (14c) by heat-sealing the chemical fiber bundle (14a) by adjoining the thermoplastic resin extrusion coated cord (14b) into several strands. Retaining wall block construction method characterized in that the grid is heat-sealed
KR1020060020855A 2006-03-06 2006-03-06 The method of constructing bloclk for wall KR100647071B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060020855A KR100647071B1 (en) 2006-03-06 2006-03-06 The method of constructing bloclk for wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060020855A KR100647071B1 (en) 2006-03-06 2006-03-06 The method of constructing bloclk for wall

Publications (1)

Publication Number Publication Date
KR100647071B1 true KR100647071B1 (en) 2006-11-23

Family

ID=37712775

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060020855A KR100647071B1 (en) 2006-03-06 2006-03-06 The method of constructing bloclk for wall

Country Status (1)

Country Link
KR (1) KR100647071B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100815837B1 (en) 2006-08-10 2008-03-21 김주현 Method for constructing environmental affinity reinforcement soil retaining wall using environmental affinity block with lower open portion and side plate rear portion
KR100821946B1 (en) * 2007-05-08 2008-04-15 주식회사 오륙개발 Reinforcement block
CN110678609A (en) * 2017-03-21 2020-01-10 生态顶级株式会社 Assembled type earthquake-proof retaining wall building block system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100815837B1 (en) 2006-08-10 2008-03-21 김주현 Method for constructing environmental affinity reinforcement soil retaining wall using environmental affinity block with lower open portion and side plate rear portion
KR100821946B1 (en) * 2007-05-08 2008-04-15 주식회사 오륙개발 Reinforcement block
CN110678609A (en) * 2017-03-21 2020-01-10 生态顶级株式会社 Assembled type earthquake-proof retaining wall building block system

Similar Documents

Publication Publication Date Title
US6089792A (en) Reinforced retaining wall
KR100981258B1 (en) The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid
KR100495782B1 (en) A Facing panel for reinforced earth wall and its construction method
KR101088158B1 (en) Method for underground roadway using slurry wall method
KR101105092B1 (en) A precast retaining panel and construction method of the same with half pc type backfill
WO2000020695A1 (en) Concrete masonry unit for reinforced retaining wall
CN111005403A (en) Assembled three-dimensional reinforced earth retaining wall and construction method thereof
CN109972638B (en) Construction method of prefabricated thin-wall formwork lattice beam ecological slope protection
KR100583294B1 (en) A Facing panel for reinforced earth wall and its construction method
KR100647071B1 (en) The method of constructing bloclk for wall
KR101254145B1 (en) Gravity type concrete precast modular retaining wall utilizing shear key and connected steel bar and constructing method thereof
KR100750703B1 (en) A vegetation block and a method for constructing the cut ground using
KR101963362B1 (en) Reinforced gabion retaining wall capable of completely drainage and construction method thereof
KR101111655B1 (en) method for reinforced of soft ground by using top pile
KR100815837B1 (en) Method for constructing environmental affinity reinforcement soil retaining wall using environmental affinity block with lower open portion and side plate rear portion
KR102178399B1 (en) A reinforced earth wall block with supporting structure of reinforced earth for excellent seismic performance and the contruction method thereof
KR101271290B1 (en) Underground reclamation type water storage tank having a assembling structure
KR200263961Y1 (en) Sectional block for retaining wall building
KR20090020082A (en) Tension soil nail for slope stability and construction method of precast concrete block using the same
CN211547805U (en) Reinforced retaining wall capable of improving seepage-proofing and drainage performance
JP2003268771A (en) Dry block, its molding form, its molding method and reinforcing earth structure using the dry block
KR100885909B1 (en) Self-supporting temporary establishment breast using public works' fiber mesh and constructing method thereof
KR100451429B1 (en) Combination system of block type reinforced retaining wall used waste concrete and waste limestone and constructing method thereof
KR100750702B1 (en) A vegetation block and a method for constructing the building area using
CN211547806U (en) Assembled ecological reinforced earth retaining wall and retaining wall panel thereof

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20111219

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20130107

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141028

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151026

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161101

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20171101

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20181105

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20191106

Year of fee payment: 14