KR100633013B1 - Pile for retaining wall having connector bolt, connection structure and method of retaining wall - Google Patents

Pile for retaining wall having connector bolt, connection structure and method of retaining wall Download PDF

Info

Publication number
KR100633013B1
KR100633013B1 KR1020050038028A KR20050038028A KR100633013B1 KR 100633013 B1 KR100633013 B1 KR 100633013B1 KR 1020050038028 A KR1020050038028 A KR 1020050038028A KR 20050038028 A KR20050038028 A KR 20050038028A KR 100633013 B1 KR100633013 B1 KR 100633013B1
Authority
KR
South Korea
Prior art keywords
wall
concrete
fixing member
thumb pile
pile
Prior art date
Application number
KR1020050038028A
Other languages
Korean (ko)
Inventor
홍성영
오성남
Original Assignee
주식회사 스마텍엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 스마텍엔지니어링 filed Critical 주식회사 스마텍엔지니어링
Priority to KR1020050038028A priority Critical patent/KR100633013B1/en
Application granted granted Critical
Publication of KR100633013B1 publication Critical patent/KR100633013B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

An H-pile for a connector bolt assembling retaining wall, a connection structure of the retaining wall and a concrete underground wall thereby and a connection construction method thereof are provided to cut down construction cost, and to reduce construction period by supporting a form and a post with the H-pile and easily assembling or disassembling the form and the post. An H-pile(10) is installed in soil cement or concrete(30) for constructing a retaining wall, and a fixing member(12) is mounted and fixed outside an excavation flange of the H-pile and combined with an end of a wall connecting member(20) inserted to a concrete underground wall(50) to integrate the retaining wall with the concrete underground wall. A protection cover is installed in an upper part of the fixing member to restrict an assembling portion of the fixing member from being blocked in mounting the H-pile in soil cement or concrete and to easily separate soil cement or concrete from the H-pile. An end of a form support part(41) is fastened and installed to support a form(40) for constructing the concrete underground wall by the fixing member.

Description

커넥터 볼트 조립식 흙막이 벽체용 엄지말뚝, 이를 이용한 흙막이 벽체와 콘크리트 지하 벽체의 연결구조 및 그 연결시공방법{Pile for Retaining Wall having Connector Bolt, Connection Structure and Method of Retaining Wall} Thumb pile for connector bolt prefabricated wall, connection structure and construction method of retaining wall and concrete underground wall using it {Pile for Retaining Wall having Connector Bolt, Connection Structure and Method of Retaining Wall}

도 1은 본 발명에 따른 주열식 흙막이 벽체용 H빔 엄지말뚝의 구성을 보여주는 개략적인 분해 사시도이다.  Figure 1 is a schematic exploded perspective view showing the configuration of the H-beam thumb pile for the heat-staining wall according to the present invention.

도 2는 지반에 천공된 하나의 구멍에 타설된 소일 시멘트 또는 콘크리트 속에 본 발명에 따른 H빔 엄지말뚝이 매립되어 있는 상태의 개략적인 평면도이다.2 is a schematic plan view of a state in which the H-beam thumb pile according to the present invention is embedded in soil cement or concrete placed in one hole perforated in the ground.

도 3은 도 2의 선A-A에 따른 개략적인 측단면도이다. 3 is a schematic side cross-sectional view taken along line A-A of FIG.

도 4는 도 2의 선A-A에 따른 측단면도로서, 굴착측으로 소일 시멘트 또는 콘크리트, 그리고 보호덮개가 제거되어 H빔 엄지말뚝의 굴착측 플랜지 외면에 벽체 연결부재가 결합된 상태의 측단면도이다. 4 is a side cross-sectional view taken along line A-A of FIG. 2, in which the soil cement or concrete and the protective cover are removed to the excavation side, and a side cross-sectional view of the wall connection member coupled to the excavation side flange of the H-beam thumb pile.

도 5는 도 2의 선A-A에 따른 측단면도로서, H빔 엄지말뚝의 굴착측 플랜지 외면에 벽체 연결부재가 결합된 상태의 측단면도이다. 5 is a side cross-sectional view taken along the line A-A of FIG. 2, which is a side cross-sectional view of the wall connection member coupled to the excavation side flange outer surface of the H-beam thumb pile.

도 6은 도 5에서 콘크리트 지하 벽체를 위한 콘크리트가 타설된 상태를 보여주는 개략적인 측단면도이다. FIG. 6 is a schematic side cross-sectional view illustrating a state in which concrete for the concrete underground wall is poured in FIG. 5.

도 7은 종래의 기술에 따른 주열식 흙막이 벽체 구조를 보여주는 개략적인 평면도 이다. Figure 7 is a schematic plan view showing the structure of the columnar retaining wall according to the prior art.

<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>

10 : 엄지말뚝 11 : 플랜지10: thumb pile 11: flange

12 : 고정부재 13 : 보호덮개12: fixing member 13: protective cover

20 : 벽체 연결부재20: wall connecting member

본 발명은 커넥터 볼트 조립식 흙막이 벽체용 엄지말뚝, 이를 이용한 흙막이 벽체와 콘크리트 지하 벽체의 연결구조 및 그 연결시공방법에 관한 것으로서, 구체적으로는 흙막이 벽체와 콘크리트 지하 벽체를 일체로 연결하는 벽체 연결부재를 조립식으로 설치할 수 있는 구성과, 콘크리트 지하 벽체 타설용 거푸집을 용이하게 설치할 수 있는 구성을 가지도록 함으로써, 편리하고 효율적인 방식으로 흙막이 벽체와 콘크리트 지하 벽체를 일체화시켜 콘크리트 지하 벽체의 강성을 증가시킴과 동시에 콘크리트 지하 벽체 시공을 위한 거푸집 설치에 소요되는 작업을 최소화시킬 수 있는 새로운 형태의 흙막이 벽체용 엄지말뚝, 이를 이용한 흙막이 벽체와 콘크리트 지하 벽체의 연결구조 및 그 연결시공방법에 관한 것이다. The present invention relates to a thumb bolt for a connector bolt-assembled mud wall, a connection structure of a mud wall and a concrete basement wall using the same, and a connection construction method thereof. Specifically, a wall connection member for integrally connecting a mud wall and a concrete basement wall is provided. It has a structure that can be installed in a prefabricated manner, and a structure that can easily install a formwork for placing concrete underground walls, thereby increasing the rigidity of the concrete underground wall by integrating the retaining wall and the concrete underground wall in a convenient and efficient manner. The present invention relates to a new type of piling wall thumb pile that can minimize the work required for the installation of formwork for the construction of concrete underground walls, the connection structure of the construction wall and the concrete underground wall using the same, and a method of constructing the same.

일반적으로 지하 공간의 활용을 위하여 터파기 공사(지하 굴착공사)를 하게 되는데, 공사 중 지반의 붕괴를 예방하기 위하여 흙막이 벽체와 지보공(H빔으로 이루어진 버팀대 또는 앵커)으로 이루어진 흙막이 가시설을 설치한다. 흙막이 벽체의 종류로는 주열식 벽체, 쉬트파일(강널말뚝), 엄지말뚝-토류판 벽체 등이 있다. 최근의 도심지 굴착 공사에서는 주열식 벽체가 흙막이 벽체의 주종을 이루고 있다. In general, the excavation work (underground excavation work) is carried out for the utilization of underground spaces, and in order to prevent the collapse of the ground during the construction, install the temporary wall construction consisting of the wall and the ground (bracing or anchor made of H beam). Kinds of wall walls include main-row walls, sheet piles, and thumb pile-earth plate walls. In recent urban excavation work, the main wall is the dominant wall.

주열식 흙막이 벽체(103)는, 도 7에 도시된 것처럼, 콘크리트 지하 벽체(100) 시공 위치 측면에서 지반을 굴착한 후 H빔 엄지말뚝(101)을 소정 간격으로 설치한 후 상기 H빔 엄지말뚝(101)의 주위에 소일 시멘트 또는 콘크리트(102)를 타설하여 주열식 흙막이 벽체(103)를 형성하는 구조를 가지고 있다. 이러한 주열식 흙막이 벽체에 있어서, 상기 H빔 엄지말뚝(101)은 소일 시멘트 또는 콘크리트(102) 내에 매립되어 있기 때문에 인발하여 재활용하는 것이 극히 어렵다. 이를 고려하여 H빔 엄지말뚝(101)을 콘크리트 지하 벽체(100)의 강성을 증가시키는 구조 부재로 활용하려는 시도가 있었으며, 그 방안으로서 커넥션 볼트(110)를 이용하는 기술이 제안되었다. 즉, 도 7에 도시된 것처럼 H빔 엄지말뚝(101)의 일측 플랜지 전면에 커넥션 볼트(110)를 미리 고정 설치해놓고, 상기 커넥션 볼트(110)가 콘크리트 지하 벽체(100) 속에 매립되도록 함으로써, H빔 엄지말뚝(101)과 콘크리트 지하 벽체(100)를 일체로 만드는 것이다. As shown in FIG. 7, the main heat-staining wall 103 is excavated from the side of the construction location side of the concrete underground wall 100, and then installs the H-beam thumb pile 101 at predetermined intervals, and then the H-beam thumb pile. It has a structure which casts soil cement or concrete 102 around 101, and forms the columnar wall 23. As shown in FIG. In such a columnar wall, the H-beam thumb pile 101 is extremely difficult to draw and recycle because it is embedded in soil cement or concrete 102. In consideration of this, an attempt has been made to utilize the H beam thumb pile 101 as a structural member to increase the rigidity of the concrete underground wall 100, and a technique using the connection bolt 110 has been proposed as a solution. That is, as shown in FIG. 7, the connection bolt 110 is fixed to the front surface of one flange of the H beam thumb pile 101 in advance, and the connection bolt 110 is embedded in the concrete underground wall 100. The beam thumb pile 101 and the concrete underground wall 100 will be made integral.

그런데 위와 같은 종래 기술의 경우, 터파기 공사가 완료되거나 또는 진행 중인 상태에서는 H빔 엄지말뚝(101)에 설치된 커넥션 볼트(110)를 노출시키는 것이 용이하지 않다는 문제점이 있다. 즉, H빔 엄지말뚝(101) 주변으로 소일 시멘트 ㄸ또는 콘크리트(102)가 타설되어 있으므로 커넥션 볼트(110)가 노출되도록 하기 위해서는 H빔 엄지말뚝(101) 주변의 소일 시멘트 또는 콘크리트(102)를 제거하여야 하는데, 이 때 커넥션 볼트(110)가 손상될 가능성이 매우 높으므로 소일 시멘트 또는 콘크리트(102)의 제거에 상당한 주의가 필요하다. 따라서 이러한 종래 기술에서는 작업성이 저하되는 문제가 생기게 되는 것이다. By the way, in the prior art as described above, there is a problem that it is not easy to expose the connection bolt 110 installed in the H-beam thumb pile 101 in the state of completion or ongoing drilling process. That is, since the soil cement or concrete 102 is poured around the H beam thumb pile 101, in order to expose the connection bolt 110, the soil cement or concrete 102 around the H beam thumb pile 101 is exposed. At this time, it is very likely that the connection bolt 110 is damaged, so great care must be taken to remove the soil cement or concrete 102. Therefore, in this prior art, there is a problem that the workability is deteriorated.

특히, 커넥션 볼트(110)를 미리 설치하게 되면 H빔 엄지말뚝(101)의 단면 직경도 증가하게 되어 주열식 흙막이 벽체(103)의 시공을 위한 지반 천공 직경도 함께 커지게 되며, 그에 따라 지반 천공 비용이 증가되는 문제점도 발생하게 된다. 굴착시 대지 경계선에 여유가 없는 경우에는 증가된 H빔 엄지말뚝(101)의 단면 직경만큼 지하시설물의 연면적을 잠식할 수밖에 없으므로, 그만큼 지하시설물의 연면적이 줄어들게 되는 심각한 문제도 야기하게 된다. In particular, when the connection bolt 110 is installed in advance, the cross-sectional diameter of the H-beam thumb pile 101 is also increased, so that the ground drilling diameter for the construction of the main heating wall 103 is also increased. There is also a problem of increased cost. If there is no room at the boundary of the excavation site, the ground floor area of the underground facility is inevitably encroached by the increased cross-sectional diameter of the H-beam thumb pile 101, which causes a serious problem of reducing the total floor area of the underground facility.

한편, 커넥션 볼트(110)를 나중에 H빔 엄지말뚝(101)의 플랜지에 용접하는 방법도 있으나, 이 경우에는 다음과 같은 문제점을 피할 수 없게 된다. H빔 엄지말뚝(101)은 소일 시멘트 또는 콘크리트(102)에 매립되어 있으므로, 커넥션 볼트(110)의 설치를 위해서는 터파기가 진행되면서 콘크리트 지하 벽체가 설치될 굴착측면으로 상기 H빔 엄지말뚝(101)의 플랜지를 노출시켜야 한다. 그런데 H빔 엄지말뚝(101) 주변으로 소일 시멘트 또는 콘크리트(102)가 타설되어 있으므로 상기 H빔 엄지말뚝(101)의 플랜지 노출 외면에서 콘크리트(102)를 제거하여 커넥션 볼트(110)를 설치할 수 있을 만큼 깨끗한 플랜지 면이 되도록 만들기 위해서는 상당한 작업이 소요되며, 그 작업은 매우 많은 시간과 노력이 소요되는 어려운 작업이 된다. 따라서, 그만큼 공사비가 증가되는 단점이 있게 되는 것이다. On the other hand, there is also a method of welding the connection bolt 110 to the flange of the H-beam thumb pile 101, in this case, the following problems can not be avoided. Since the H-beam thumb pile 101 is buried in soil cement or concrete 102, the H-beam thumb pile 101 is installed on the excavation side where the concrete underground wall is to be installed while the trench proceeds for the installation of the connection bolt 110. Should expose the flanges. However, since the cement or concrete 102 is poured around the H beam thumb pile 101, the connection bolt 110 may be installed by removing the concrete 102 from the flange exposed outer surface of the H beam thumb pile 101. It takes a lot of work to make the flange face as clean as possible, which is a very time-consuming and difficult task. Therefore, there is a disadvantage that the construction cost increases by that much.

콘크리트 지하 벽체(100)를 타설할 때, 양생 전 콘크리트의 측압을 지지하기 위하여 기초 슬래브 또는 지하층 슬래브를 이용하여 경사 방향으로 동바리를 설치하고, 콘크리트 지하 벽체(100)의 타설을 위한 거푸집을 설치하게 된다. 그런데 이와 같이 슬래브를 이용하여 동바리와 거푸집을 설치하는 경우에는, 동바리를 슬래브에 고정시켜야 하므로 그에 따른 공사비가 많이 소요될 뿐만 아니라, 설치 및 해체에도 상당한 작업이 필요하다. When placing the concrete basement wall 100, in order to support the lateral pressure of the concrete before curing, using the foundation slab or basement slab to install the copper bar in the inclined direction, to install the formwork for placing the concrete basement wall (100) do. By the way, in the case of installing the copper bar and formwork using the slab in this way, it is necessary to fix the copper bar to the slab, as well as a lot of construction cost accordingly, it is necessary to install and dismantle.

본 발명은 상기한 것처럼 주열식 흙막이 벽체의 엄지말뚝과 콘크리트 지하 벽체의 일체 결합을 위한 커넥션 볼트를 설치함에 있어서, 종래의 기술이 가지고 있는 여러 가지 문제점을 해결하는 것을 목적으로 한다. 즉, 본 발명은 간단하고 용이한 방법으로 주열식 흙막이 벽체의 엄지말뚝과 콘크리트 지하 벽체를 일체로 결합할 수 있도록 하는 구성을 가진 엄지말뚝과, 이를 이용한 콘크리트 지하 벽체와의 연결구조, 그리고 그 연결시공방법을 제공하는 것을 목적으로 한다. The present invention aims to solve various problems of the prior art in installing a connection bolt for integrally coupling the thumb pile of the main heating wall and the concrete underground wall as described above. That is, the present invention is a simple and easy way to connect the thumb pile and the concrete basement wall of the heat-stacking wall body integrally, the connection structure with the concrete basement wall using the same, and the connection The purpose is to provide a construction method.

한편, 본 발명은 엄지말뚝을 콘크리트 지하 벽체의 시공을 위한 거푸집 및 동바리를 지지하는데 엄지말뚝 자체의 구조를 활용함으로써, 거푸집 및 동바리를 조립 및 해체 작업을 용이하게 할 수 있도록 하여 공사비를 절감할 뿐만 아니라, 공사 기간도 절감할 수 있도록 하는 엄지말뚝과, 이를 이용한 콘크리트 지하 벽체와의 연결구조, 그리고 그 연결시공방법을 제공하는 것을 목적으로 한다. On the other hand, the present invention by using the structure of the thumb pile itself to support the formwork and copper bar for the construction of the concrete base wall thumb pile, so as to facilitate the assembly and dismantling of the formwork and copper bar to reduce the construction cost In addition, it is an object of the present invention to provide a thumb pile and a connection structure to the concrete underground wall using the same, and the connection construction method that can reduce the construction period.

상술한 본 발명의 목적은, 소일 시멘트 또는 콘크리트에 매립되어 흙막이 벽체를 이루는 엄지말뚝의 굴착측 플랜지 외면에는, 콘크리트 지하 벽체에 매립되어 흙막이 벽체와 콘크리트 지하 벽체가 일체를 이루도록 하는 벽체 연결부재의 일단부가 조립되는 고정부재가 미리 부착되어 고정 설치되어 있으며; 상기 고정부재 위에는, 상기 엄지말뚝은 소일 시멘트 또는 콘크리트에 매립될 때 상기 고정부재의 결합부가 막히는 것을 방지하고 상기 소일 시멘트 또는 콘크리트가 엄지말뚝으로부터 쉽고 깨끗하게 분리될 수 있도록 하는 상기 보호덮개가 설치되어 있는 것을 특징으로 하는 흙막이 벽체용 엄지말뚝에 의하여 달성된다. An object of the present invention described above, one end of the wall connecting member embedded in the concrete underground wall to be integrated into the concrete underground wall to be integral to the excavation side flange of the thumb pile embedded in the soil cement or concrete to form a wall A fixing member to be assembled is attached and fixed in advance; On the fixing member, the thumb pile is provided with a protective cover which prevents the coupling portion of the fixing member from being blocked when embedded in soil cement or concrete, and allows the soil cement or concrete to be easily and cleanly separated from the thumb pile. It is achieved by a thumbstack for the wall wall, characterized in that.

본 발명에서는 상기한 엄지말뚝의 일실시예로서, 상기 고정부재의 일부는, 콘크리트 지하 벽체의 시공을 위한 거푸집을 설치하고 지지하기 위한 거푸집지지부재의 일단부를 고정 설치하기 위한 고정부재인 것을 특징으로 하는 흙막이 벽체용 엄지말뚝이 제공된다. In the present invention, as an embodiment of the thumb pile, a part of the fixing member is a fixing member for fixing one end of the formwork supporting member for installing and supporting the formwork for the construction of the concrete underground wall Provided is a thumb pile for a retaining wall.

또한 본 발명에서는 소일 시멘트 또는 콘크리트에 엄지말뚝이 매립되어 있는 흙막이 벽체와, 그 굴착측에 접하여 시공되는 콘크리트 지하 벽체의 연결구조로서, 상기 엄지말뚝의 굴착측 플랜지 외면에는 고정부재가 미리 부착되어 고정 설치되어 있고; 상기 고정부재에는 벽체 연결부재의 일단부가 조립되어 있으며; 상기 벽체 연결부재의 타단부는 콘크리트 지하 벽체의 콘크리트 내에 매립되어 상기 흙막이 벽체와 콘크리트 지하 벽체가 일체로 결합되어 있는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체의 연결구조가 제공된다. In addition, in the present invention as a connection structure of the earth wall wall with the thumb pile embedded in the soil cement or concrete, and the concrete underground wall to be constructed in contact with the excavation side, the fixing member is attached to the excavation side flange of the thumb pile in advance fixed installation It is done; One end of the wall connecting member is assembled to the fixing member; The other end of the wall connecting member is embedded in the concrete of the concrete underground wall is provided with a connection structure of the earth wall and the concrete underground wall, characterized in that the earth wall and the concrete underground wall is integrally coupled.

또한 본 발명에서는 소일 시멘트 또는 콘크리트에 엄지말뚝이 매립되어 있는 흙막이 벽체와, 그 굴착측에 접하여 시공되는 콘크리트 지하 벽체의 연결시공방법으로서, 콘크리트 지하 벽체에 매립되어 흙막이 벽체와 콘크리트 지하 벽체가 일체를 이루도록 하는 벽체 연결부재의 일단부가 조립되는 고정부재를 상기 엄지말뚝의 굴착측 플랜지 외면에 미리 부착하여 고정 설치하는 단계; 상기 고정부재 위에는, 상기 엄지말뚝은 소일 시멘트 또는 콘크리트에 매립될 때 상기 고정부재의 결합부가 막히는 것을 방지하고 상기 소일 시멘트 또는 콘크리트가 엄지말뚝으로부터 쉽고 깨끗하게 분리될 수 있도록 하는 상기 보호덮개를 설치하는 단계; 지반을 천공하여 소일 시멘트 또는 콘크리트 내에, 상기 고정부재와 보호덮개가 구비된 엄지말뚝이 매립되도록 설치하여 흙막이 벽체를 시공하는 단계; 터파기를 하면서 상기 엄지말뚝의 고정부재를 노출시키는 단계; 상기 벽체 연결부재의 일단부를 상기 고정부재에 조립하는 단계; 및 상기 벽체 연결부재의 타단부가 매립되도록 콘크리트를 타설하여 콘크리트 지하 벽체를 시공하는 단계를 포함하는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체의 연결시공방법이 제공된다. In addition, in the present invention, as a connection method of the soil wall with the thumb pile embedded in the soil cement or concrete, and the concrete underground wall constructed in contact with the excavation side, embedded in the concrete underground wall so that the earth wall and the concrete underground wall are integrated. Attaching and fixing the fixing member, to which the one end of the wall connecting member is assembled, to the excavation side flange outer surface of the thumb pile in advance; On the fixing member, the thumb pile is installed in the protective cover to prevent the coupling portion of the fixing member is blocked when embedded in the soil cement or concrete and to allow the soil cement or concrete to be easily and cleanly separated from the thumb pile ; Perforating the ground and installing in the cement or concrete so that the thumb pile with the fixing member and the protective cover is embedded to construct an earth wall; Exposing the fixing member of the thumb pile while digging; Assembling one end of the wall connecting member to the fixing member; And constructing the concrete underground wall by pouring concrete so that the other end of the wall connection member is embedded, and there is provided a method of connecting the retaining wall and the concrete underground wall.

본 발명에서는 상기한 연결시공방법의 일 실시예로서, 상기 콘크리트 지하 벽체의 시공을 위한 거푸집을 설치하고 지지하기 위한 거푸집지지부재의 일단부를 상기 고정부재에 고정 설치하는 단계; 및 상기 거푸집지지부재의 타단부에 고정수단을 이용하여 상기 거푸집을 고정 설치하는 단계를 더 포함하는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체의 연결시공방법이 제공된다. In the present invention, as an embodiment of the connection construction method, the step of fixing the one end of the formwork supporting member for installing and supporting the formwork for the construction of the concrete underground wall fixed to the fixing member; And fixing the formwork to the other end of the formwork supporting member by using a fixing means. The construction method of connecting the retaining wall and the concrete underground wall is further provided.

이하, 첨부된 예시도면을 참조하여 본 발명에 따른 주열식 흙막이 벽체용 엄지말뚝의 구성 및 이를 이용한 주열식 흙막이 벽체와 콘크리트 지하 벽체 간의 연결구조와 그 연결시공방법에 대하여 설명한다. 아래의 설명에서 상기 엄지말뚝의 일예로서 "H빔 엄지말뚝"을 예시하고 있으나, 본 발명의 엄지말뚝은 "H빔" 형상에 한정되는 것은 아니다. Hereinafter, with reference to the accompanying drawings will be described the configuration of the main pile wall for piles according to the present invention, the connection structure between the main heating wall and the concrete underground wall using the same and the construction method of the connection. In the following description, but one example of the thumb pile "H beam thumb pile" is illustrated, but the thumb pile of the present invention is not limited to the "H beam" shape.

도 1에는 본 발명에 따른 주열식 흙막이 벽체용 H빔 엄지말뚝(10)의 구성을 보여주는 개략적인 분해 사시도가 도시되어 있다. Figure 1 is a schematic exploded perspective view showing the configuration of the H-beam thumb pile 10 for the columnar wall according to the present invention.

본 발명에서는, H빔 엄지말뚝(10)의 굴착측 플랜지(11) 외면에는, 후술하는 바와 같이 커넥터 볼트와 같은 벽체 연결부재(20)의 일단부가 조립되는 암나사부와 같은 고정부재(12)가 미리 부착되어 고정 설치된다. 도면에 도시된 것처럼 상기 고정부재(12)는 H빔 엄지말뚝(10)의 플랜지 전면에 길이 방향으로 소정 간격을 두고 설치된다. 상기 고정부재(12) 위에는 보호덮개(13)가 설치된다. 흙막이 벽체를 형성하기 위하여 H빔 엄지말뚝(10)은 지반에서 소정 간격으로 소일 시멘트 또는 콘크리트에 매립되는데, 이 때 콘크리트 등이 상기 고정부재(12)의 결합부를 막게 되는 것을 방지하고 추후 지반 굴착을 진행하면서 H빔 엄지말뚝(10)과 그 주변의 콘크리트 등이 쉽게 그리고 깨끗하게 분리되도록 하기 위하여 상기 보호덮개(13)를 설치하는 것이다. In the present invention, the fixing member 12, such as a female screw portion, on which one end of the wall connecting member 20, such as a connector bolt, is assembled, is formed on the outer surface of the excavation side flange 11 of the H beam thumb pile 10, as described later. It is attached in advance and fixedly installed. As shown in the figure, the fixing member 12 is installed at a predetermined interval in the longitudinal direction on the flange front surface of the H-beam thumb pile 10. The protective cover 13 is installed on the fixing member 12. The H-beam thumb pile 10 is embedded in soil cement or concrete at predetermined intervals in the ground to form an earth wall, and prevents the concrete from blocking the coupling part of the fixing member 12 and later excavation of the ground. The protective cover 13 is installed so that the H beam thumb pile 10 and the surrounding concrete can be easily and cleanly separated.

도 2 내지 도 6에는 상기한 본 발명의 H빔 엄지말뚝(10)을 이용하여 흙막이 벽체를 시공하여 콘크리트 지하 벽체와 연결하는 구조 및 각 방법단계를 설명하기 위한 도면이 도시되어 있는데, 도 2에는 지반에 천공된 하나의 구멍에 타설된 소일 시멘트 또는 콘크리트(30) 속에 H빔 엄지말뚝(10)이 매립되어 있는 상태의 개략적인 평면도이고, 도 3 내지 도 6은 각 시공단계에서 도 2의 선A-A에 따른 개략적인 측단면도이다. 2 to 6 is a view for explaining the structure and each method step for connecting the concrete underground wall by constructing the wall using the H-beam thumb pile 10 of the present invention, Figure 2 is shown in FIG. 3 is a schematic plan view of a state in which the H beam thumb pile 10 is embedded in soil cement or concrete 30 which is placed in one hole perforated in the ground, and FIGS. A schematic side cross-sectional view according to AA.

앞서 설명하였듯이, 본 발명에 있어서 H빔 엄지말뚝(10)은 굴착측 플랜지(11)의 외면에 고정부재(12)가 설치된 상태로 소일 시멘트 또는 콘크리트(30) 속에 삽입되어 매립된다(도 2 및 도 3). 이 때, H빔 엄지말뚝(10)의 굴착측 플랜지(11) 외면은 보호덮개(13)로 덮여 있으므로 H빔 엄지말뚝(10)이 소일 시멘트 또는 콘크리트(30) 속에 매립되더라도 고정부재(12)의 결합부로 소일 시멘트 또는 콘크리트(30)가 유입되어 막게 되는 것이 방지된다. As described above, in the present invention, the H-beam thumb pile 10 is embedded in the soil cement or concrete 30 with the fixing member 12 installed on the outer surface of the excavation-side flange 11 and embedded (FIG. 2 and 3). At this time, the outer surface of the excavation side flange 11 of the H-beam thumb pile 10 is covered with a protective cover 13, so that the H-beam thumb pile 10 is embedded in the soil cement or concrete 30, but the fixing member 12 Soil cement or concrete 30 is prevented from being blocked by the coupling portion of the.

H빔 엄지말뚝(10)의 상부로부터 아래로 점차로 터파기 공사가 진행됨에 따라 굴착측으로 상기 H빔 엄지말뚝(10)을 둘러싸고 있는 소일 시멘트 또는 콘크리트(30)를 벗겨낸다. H빔 엄지말뚝(10)의 굴착측을 보호덮개(13)가 덮고 있으므로, 노출된 부분의 보호덮개(13)를 제거하게 되면 소일 시멘트 또는 콘크리트(30)를 벗겨낸 후에도 H빔 엄지말뚝(10)의 굴착측 플랜지(11) 외면은 깨끗한 상태를 유지하게 되며 소일 시멘트 또는 콘크리트(30)를 벗겨내는 작업도 매우 용이하게 된다. As the trench construction proceeds gradually from the top of the H-beam thumb pile 10, the cement or concrete 30 surrounding the H-beam thumb pile 10 is peeled off to the excavation side. Since the protective cover 13 covers the excavation side of the H-beam thumb pile 10, when the protective cover 13 of the exposed portion is removed, the H-beam thumb pile 10 even after peeling off the cement or concrete 30 Excavation side flange (11) outer surface of the) is to maintain a clean state and the work to peel off the cement or concrete 30 is also very easy.

이와 같이 소일 시멘트 또는 콘크리트(30)를 벗겨내고 보호덮개(13)를 제거하여 고정부재(12)가 노출되면 상기 고정부재(12)에는 콘크리트 지하 벽체와의 일체 연결을 위한 벽체 연결부재(20)의 일단부가 조립된다(도 4). 상기 벽체 연결부재(20)의 일예로는 단부에 나사부가 형성되어 있는 커넥터 볼트가 있는데, 상기 고정부재(12)로서 이에 대응되는 암나사 부재를 이용하는 경우 간단한 나사 결합을 통하여 상기 커넥터 볼트를 H빔 엄지말뚝(10)의 플랜지(11)에 용이하게 설치할 수 있게 된다. As such, when the cement or concrete 30 is peeled off and the protective cover 13 is removed, and the fixing member 12 is exposed, the fixing member 12 has a wall connection member 20 for integral connection with the concrete underground wall. One end of is assembled (FIG. 4). An example of the wall connecting member 20 is a connector bolt having a screw portion formed at an end thereof. When using the female screw member corresponding thereto as the fixing member 12, the connector bolt is connected to the H beam thumb through simple screwing. The flange 11 of the pile 10 can be easily installed.

본 발명에서는 콘크리트 지하 벽체의 타설을 위한 거푸집 설치에도 H빔 엄지말뚝(10)을 매우 유용하게 사용하게 된다. 도 5에는 도 4에 도시된 H빔 엄지말뚝(10)의 상태에서 콘크리트 지하 벽체의 타설을 위한 거푸집이 추가로 설치된 형상이 개략적인 측단면도로 도시되어 있다. In the present invention, the H-beam thumb pile 10 is also very useful for installing formwork for placing concrete underground walls. FIG. 5 is a schematic side cross-sectional view showing a form in which formwork is additionally installed for placing concrete underground walls in the state of the H beam thumb pile 10 shown in FIG. 4.

도면에 도시된 것처럼, H빔 엄지말뚝(10)의 굴착측 플랜지(11) 외면에 설치된 고정부재(12) 중 일부에는, 거푸집(40)을 설치하고 지지하기 위한 거푸집지지부재(41)의 일단부가 고정 설치된다. 상기 거푸집지지부재(41)의 단부에 나사를 형성하여, 고정부재(12)에 간단한 나사 결합시키므로써 매우 용이하게 설치할 수 있게 된다. 상기 거푸집지지부재(41)의 타측 단부에는 거푸집(40)을 고정하기 위한 고정수단(42)을 설치하여 상기 거푸집(40)이 H빔 엄지말뚝(10)의 플랜지(11)로부터 소정 간격을 유지한 상태로 안정적으로 설치되도록 한다. 상기 거푸집(40)을 고정하기 위한 고정수단(42)은 다양한 형태로 구성할 수 있는데, 일예로서 두 개의 너트를 설치하고 그 사이에 거푸집(40)을 끼워두는 형태로 간단하게 만들 수 있다. 그러나 반드시 이에 한정되는 것은 아니며 다양하게 상기 거푸집(40) 고정용 고정수단(42)을 형성할 수 있다. As shown in the figure, one end of the formwork supporting member 41 for installing and supporting the formwork 40 is fixed to a part of the fixing member 12 provided on the excavation side flange 11 outer surface of the H-beam thumb pile 10. The additional fixture is installed. By forming a screw at the end of the formwork supporting member 41, it can be installed very easily by simply screwing to the fixing member 12. The other end of the form support member 41 is provided with a fixing means 42 for fixing the form 40 so that the form 40 maintains a predetermined distance from the flange 11 of the H beam thumb pile 10. Ensure stable installation in one state. Fixing means 42 for fixing the formwork 40 can be configured in various forms, for example, it can be made simply by installing two nuts and sandwiching the formwork 40 therebetween. However, the present invention is not necessarily limited thereto, and various means for fixing the formwork 40 may be formed.

위와 같은 구성으로 거푸집(40)을 설치한 후, 도 6에 도시된 것처럼 보강철근이 배근된 상태에서 콘크리트 지하 벽체(50)를 위한 콘크리트를 타설하게 되면, H빔 엄지말뚝(10)에 일단이 고정 설치된 벽체 연결부재(20)가 콘크리트 지하 벽체(50) 속 에 매립되어 상기 H빔 엄지말뚝(10)과 콘크리트 지하 벽체(50), 더 나아가서는 H빔 엄지말뚝(10)을 포함하여 설치되는 흙막이 벽체와 콘크리트 지하 벽체(50)가 일체를 이루게 된다. After installing the formwork 40 in the above configuration, when placing the concrete for the concrete underground wall 50 in the reinforcement is reinforced as shown in Figure 6, one end to the H-beam thumb pile 10 The fixed wall connection member 20 is embedded in the concrete underground wall 50 to be installed including the H beam thumb pile 10, the concrete underground wall 50, and furthermore, the H beam thumb pile 10. The retaining wall and the concrete basement wall 50 are integrated.

이상 살펴본 바와 같이, 커넥션 볼트를 H빔 엄지말뚝에 미리 부착시켜 놓는 형태의 종래 기술에서는 커넥션 볼트의 손상 가능성이 높지만, 본 발명에 따르면 고정부재(12)를 H빔 엄지말뚝(10)의 굴착측 플랜지(11) 외면에 미리 부착시켜 놓고 지반 굴착을 진행하면서 벽체 연결부재(20)를 결합하는 구조를 가지고 있으므로, 위와 같은 커넥션 볼트의 손상 가능성이 전혀 없다는 장점이 있다. As described above, in the prior art in which the connection bolt is pre-attached to the H beam thumb pile, there is a high possibility of damage to the connection bolt, but according to the present invention, the fixing member 12 is excavated on the H beam thumb pile 10. Since the flange 11 is attached to the outer surface in advance and has a structure for coupling the wall connecting member 20 while the ground is being excavated, there is an advantage that there is no possibility of damage to the connection bolt as described above.

특히, 상기한 종래 기술에서는 H빔 엄지말뚝 주위의 소일 시멘트 또는 콘크리트 제거에 상당한 주의가 필요하고 그에 따라 작업성이 저하되는 문제가 있으나, 본 발명에서는 소일 시멘트 또는 콘크리트 제거가 용이하여 작업성 저하 현상이 없다는 장점이 있으며, 특히 보호덮개(13)를 사용하게 되는 경우, H빔 엄지말뚝의 플랜지 외면을 매우 용이한 방법으로 깨끗한 상태로 만들 수 있다는 장점이 있다. In particular, in the above-described prior art, there is a problem that considerable attention is required to remove the soil cement or concrete around the H-beam pile and the workability is deteriorated accordingly. However, in the present invention, the soil cement or concrete is easily removed to reduce workability. There is no advantage, especially when using the protective cover 13, there is an advantage that the flange outer surface of the H-beam thumb pile can be made clean in a very easy way.

한편, 본 발명은, 커넥션 볼트를 미리 설치하는 종래 기술과 대비하여 볼 때, H빔 엄지말뚝의 단면이 증가되지 아니하므로, 주열식 흙막이 벽체의 시공을 위한 지반 천공 직경의 증가 현상이 없으며, 천공 직경 증가에 따른 공기 상승, 비용 증가 등을 예방할 수 있게 되는 장점이 있다. 특히, 본 발명은 대지 경계선에 여유가 없는 굴착의 경우에도 지하시설물의 연면적 잠식 없이 용이하게 터파기를 할 수 있다 는 장점을 발휘하게 된다. On the other hand, the present invention, compared with the prior art of installing the connection bolt in advance, because the cross section of the H-beam thumb pile does not increase, there is no increase in the diameter of the ground perforation for the construction of the columnar wall, There is an advantage that can prevent the increase in air, increase in cost, etc. according to the increase in diameter. In particular, the present invention exhibits an advantage that even in the case of excavation having no margin on the land boundary, it can be easily excavated without encroaching on the floor area of the underground facility.

또한, 본 발명에서는 고정부재를 이용하여 콘크리트 지하 벽체의 시공을 위한 거푸집을 용이하게 설치할 수 있으므로, 종래의 기술에서와 같은 거푸집 지지를 위한 별도의 동바리 설치 및 그에 소요되는 별도의 동바리/거푸집 고정장치가 필요하지 않게 되는 장점이 있다. 특히, 본 발명에서는 거푸집 설치/해체 작업을 용이하게 수행할 수 있으므로 그만큼 작업을 간소화할 수 있고, 공기 절감 및 공사비 절감의 효과를 얻을 수 있게 된다. In addition, since the present invention can easily install the formwork for the construction of the concrete underground wall using the fixing member, the installation of a separate group for supporting the formwork as in the prior art and a separate group for fixing the formwork / formwork There is an advantage that does not need. Particularly, in the present invention, since the formwork installation / dismantling work can be easily performed, the work can be simplified, and the effect of saving air and reducing construction cost can be obtained.

그 뿐만 아니라, 본 발명의 경우에는, 공기가 촉박한 상황에서 기둥이나 슬래브의 시공과 무관하게, 주열식 흙막이 벽체를 시공한 후에 콘크리트 지하 벽체를 신속하게 진행할 수 있는 장점이 있으며, 필요에 따라서는 콘크리트 지하 벽체를 역방향으로 타설하여 시공할 수도 있게 된다. In addition, in the case of the present invention, regardless of the construction of the column or slab in a tight air condition, there is an advantage that can proceed quickly to the concrete basement wall after the construction of the main column wall, if necessary Concrete underground walls can also be installed by reversing.

Claims (5)

소일 시멘트 또는 콘크리트(30)에 매립되어 흙막이 벽체를 이루는 엄지말뚝(10)으로서, As a thumb pile (10) embedded in soil cement or concrete (30) to form an earthen wall, 상기 엄지말뚝(10)의 굴착측 플랜지(11) 외면에는, 콘크리트 지하 벽체(20)에 매립되어 흙막이 벽체와 콘크리트 지하 벽체(50)가 일체를 이루도록 하는 벽체 연결부재(20)의 일단부가 조립되는 고정부재(12)가 미리 부착되어 고정 설치되어 있으며; One end of the wall connecting member 20 is embedded in the excavation side flange 11 of the thumb pile 10 so as to be embedded in the concrete underground wall 20 so that the earth wall and the concrete underground wall 50 are integrated. The fixing member 12 is attached and fixed in advance; 상기 고정부재(12) 위에는, 상기 엄지말뚝(10)은 소일 시멘트 또는 콘크리트에 매립될 때 상기 고정부재(12)의 결합부가 막히는 것을 방지하고 상기 소일 시멘트 또는 콘크리트가 엄지말뚝(10)으로부터 쉽고 깨끗하게 분리될 수 있도록 하는 상기 보호덮개(13)가 설치되어 있는 것을 특징으로 하는 흙막이 벽체용 엄지말뚝. On the fixing member 12, the thumb pile 10 prevents the coupling portion of the fixing member 12 from being blocked when embedded in the soil cement or concrete, and the soil cement or concrete is easily and cleanly removed from the thumb pile 10. Thumbtack for wall wall, characterized in that the protective cover 13 is installed to be separated. 제1항에 있어서, The method of claim 1, 상기 고정부재(12)의 일부는, 콘크리트 지하 벽체(50)의 시공을 위한 거푸집(40)을 설치하고 지지하기 위한 거푸집지지부재(41)의 일단부를 고정 설치하기 위한 고정부재인 것을 특징으로 하는 흙막이 벽체용 엄지말뚝. A part of the fixing member 12 is a fixing member for fixing one end of the formwork supporting member 41 for installing and supporting the formwork 40 for the construction of the concrete underground wall 50. Thumb piles for wall walls. 소일 시멘트 또는 콘크리트(30)에 엄지말뚝(10)이 매립되어 있는 흙막이 벽체와, 그 굴착측에 접하여 시공되는 콘크리트 지하 벽체(50)의 연결구조로서, As a connection structure of the earth wall, the thumb pile 10 is embedded in the soil cement or concrete 30, and the concrete underground wall 50 constructed in contact with the excavation side, 상기 엄지말뚝(10)의 굴착측 플랜지(11) 외면에는 고정부재(12)가 미리 부착되어 고정 설치되어 있고; A fixing member 12 is attached to and fixed to an outer surface of the excavation side flange 11 of the thumb pile 10; 상기 고정부재(12)에는 벽체 연결부재(20)의 일단부가 조립되어 있으며; One end of the wall connecting member 20 is assembled to the fixing member 12; 상기 벽체 연결부재(20)의 타단부는 콘크리트 지하 벽체(50)의 콘크리트 내에 매립되어 상기 흙막이 벽체와 콘크리트 지하 벽체(50)가 일체로 결합되어 있는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체의 연결구조. The other end of the wall connecting member 20 is embedded in the concrete of the concrete underground wall 50 is connected to the earth wall and the concrete underground wall, characterized in that the earth wall and the concrete underground wall 50 is integrally combined. rescue. 소일 시멘트 또는 콘크리트에 엄지말뚝(10)이 매립되어 있는 흙막이 벽체와, 그 굴착측에 접하여 시공되는 콘크리트 지하 벽체(50)의 연결시공방법으로서, As a connection construction method of the soil wall with the thumb pile 10 embedded in soil cement or concrete and the concrete underground wall 50 constructed in contact with the excavation side, 콘크리트 지하 벽체(20)에 매립되어 흙막이 벽체와 콘크리트 지하 벽체(50)가 일체를 이루도록 하는 벽체 연결부재(20)의 일단부가 조립되는 고정부재(12)를 상기 엄지말뚝(10)의 굴착측 플랜지(11) 외면에 미리 부착하여 고정 설치하는 단계; The excavation side flange of the thumb pile 10 has a fixing member 12 embedded in the concrete underground wall 20 to which one end of the wall connecting member 20 is assembled so that the earth wall and the concrete underground wall 50 are integrated. (11) pre-attached to the outer surface and fixed installation; 상기 고정부재(12) 위에는, 상기 엄지말뚝(10)은 소일 시멘트 또는 콘크리트(30)에 매립될 때 상기 고정부재(12)의 결합부가 막히는 것을 방지하고 상기 소일 시멘트 또는 콘크리트가 엄지말뚝(10)으로부터 쉽고 깨끗하게 분리될 수 있도록 하는 상기 보호덮개(13)를 설치하는 단계; On the fixing member 12, the thumb pile 10 prevents the coupling portion of the fixing member 12 from being blocked when the thumb pile 10 is embedded in the soil cement or concrete 30, and the soil cement or the concrete pile 10. Installing the protective cover 13 so as to be easily and cleanly separated from the cover; 지반을 천공하여 소일 시멘트 또는 콘크리트(30) 내에, 상기 고정부재(12)와 보호덮개(13)가 구비된 엄지말뚝(10)이 매립되도록 설치하여 흙막이 벽체를 시공하는 단계; Drilling the ground to install the thumb pile (10) provided with the fixing member (12) and the protective cover (13) in soil cement or concrete (30) to construct an earth wall; 터파기를 하면서 상기 엄지말뚝(10)의 고정부재(12)를 노출시키는 단계; Exposing the fixing member 12 of the thumb pile 10 while digging; 상기 벽체 연결부재(20)의 일단부를 상기 고정부재(12)에 조립하는 단계; 및Assembling one end of the wall connecting member (20) to the fixing member (12); And 상기 벽체 연결부재(20)의 타단부가 매립되도록 콘크리트를 타설하여 콘크리트 지하 벽체(50)를 시공하는 단계를 포함하는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체(50)의 연결시공방법. The construction method of connecting the earth wall and the concrete underground wall 50, comprising the step of constructing the concrete underground wall 50 by placing concrete so that the other end of the wall connecting member 20 is embedded. 제4항에 있어서, The method of claim 4, wherein 상기 콘크리트 지하 벽체(50)의 시공을 위한 거푸집(40)을 설치하고 지지하기 위한 거푸집지지부재(41)의 일단부를 상기 고정부재(12)에 고정 설치하는 단계; 및 Fixing one end of the formwork supporting member 41 to install and support the formwork 40 for the construction of the concrete underground wall 50 to the fixing member 12; And 상기 거푸집지지부재(41)의 타단부에 고정수단(42)을 이용하여 상기 거푸집(40)을 고정 설치하는 단계를 더 포함하는 것을 특징으로 하는 흙막이 벽체와 콘크리트 지하 벽체(50)의 연결시공방법. Method of connecting the retaining wall and the concrete basement wall 50 further comprising the step of fixing the formwork 40 to the other end of the formwork support member 41 using the fixing means 42. .
KR1020050038028A 2005-05-06 2005-05-06 Pile for retaining wall having connector bolt, connection structure and method of retaining wall KR100633013B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050038028A KR100633013B1 (en) 2005-05-06 2005-05-06 Pile for retaining wall having connector bolt, connection structure and method of retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050038028A KR100633013B1 (en) 2005-05-06 2005-05-06 Pile for retaining wall having connector bolt, connection structure and method of retaining wall

Publications (1)

Publication Number Publication Date
KR100633013B1 true KR100633013B1 (en) 2006-10-12

Family

ID=37626048

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050038028A KR100633013B1 (en) 2005-05-06 2005-05-06 Pile for retaining wall having connector bolt, connection structure and method of retaining wall

Country Status (1)

Country Link
KR (1) KR100633013B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101219451B1 (en) * 2010-09-28 2013-01-11 홍지기술산업주식회사 Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
CN103088829A (en) * 2013-01-30 2013-05-08 上海城建市政工程(集团)有限公司 Construction method of concrete support in foundation pit
CN103397661A (en) * 2013-08-09 2013-11-20 韦江萍 Construction technology of underground combined profile steel-concrete outer wall structure
CN103437366A (en) * 2013-08-19 2013-12-11 浙江博雷重型机床制造有限公司 Prestress loading device connecting part
KR101780370B1 (en) * 2017-03-17 2017-10-10 홍석희 Composite structure using shear connector made of anchor and socket shoe
CN110777847A (en) * 2019-11-01 2020-02-11 深圳市建安(集团)股份有限公司 Confined space basement exterior wall pouring and waterproof integrated structure and construction method
KR102509793B1 (en) 2021-09-17 2023-03-14 (주)하나 Side pressure secure outlet for the multi-wall construction

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101219451B1 (en) * 2010-09-28 2013-01-11 홍지기술산업주식회사 Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
CN103088829A (en) * 2013-01-30 2013-05-08 上海城建市政工程(集团)有限公司 Construction method of concrete support in foundation pit
CN103088829B (en) * 2013-01-30 2015-08-26 上海城建市政工程(集团)有限公司 The construction method that in a kind of foundation ditch, concrete supports
CN103397661A (en) * 2013-08-09 2013-11-20 韦江萍 Construction technology of underground combined profile steel-concrete outer wall structure
CN103397661B (en) * 2013-08-09 2016-01-27 韦江萍 The construction technology of combined exterior wall structure under shaped steel-concrete ground
CN103437366A (en) * 2013-08-19 2013-12-11 浙江博雷重型机床制造有限公司 Prestress loading device connecting part
CN103437366B (en) * 2013-08-19 2016-06-08 浙江博雷重型机床制造有限公司 The connection member of prestressing force charger
KR101780370B1 (en) * 2017-03-17 2017-10-10 홍석희 Composite structure using shear connector made of anchor and socket shoe
CN110777847A (en) * 2019-11-01 2020-02-11 深圳市建安(集团)股份有限公司 Confined space basement exterior wall pouring and waterproof integrated structure and construction method
CN110777847B (en) * 2019-11-01 2021-04-27 深圳市建安(集团)股份有限公司 Confined space basement exterior wall pouring and waterproof integrated structure and construction method
KR102509793B1 (en) 2021-09-17 2023-03-14 (주)하나 Side pressure secure outlet for the multi-wall construction

Similar Documents

Publication Publication Date Title
KR100633013B1 (en) Pile for retaining wall having connector bolt, connection structure and method of retaining wall
KR101640449B1 (en) Construction method for open cutting in tunnel portal area
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
US20060179730A1 (en) Wall structural member and method for constructing a wall structure
KR101655217B1 (en) Construction method for open cutting in tunnel portal area
JP4343080B2 (en) Continuous underground wall
KR20120089665A (en) Earth retaining wall and method of constructing same
KR20170035741A (en) Construction method of retaining wall
JP2005120663A (en) Structure of earth retaining wall
KR101597542B1 (en) Self-supported type earth retaining wall structure and construction method thereof
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
JP2012031678A (en) Foundation for structure and method for constructing the same
JP2741387B2 (en) Construction manhole construction method
KR102355446B1 (en) Vertical underground structure and method for constructing the same
KR100659728B1 (en) Earth of building land-side protection wall structure
KR20090078684A (en) Composite wall using angled channel and constructing method thereof
JP4201229B2 (en) Construction method of underground concrete wall using buried formwork
JP4146250B2 (en) Open caisson bottom plate construction method
KR100999410B1 (en) Assembled wale beam and construction method of underground structure using the same
KR100981148B1 (en) Method for establishing the wall of the well and curb shoe for it and the upper form
KR20050082811A (en) A construction method of a wall for supporting a soil
JP2005264500A5 (en)
JP6019689B2 (en) Tunnel widening method
JP2005264500A (en) Cofferdam structure and cofferdam closure method for underwater existing structure
JP3227141B2 (en) Earth retaining plate

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee