KR100617950B1 - Under Water Dry Structure Construction Method and Functional Working Ship - Google Patents
Under Water Dry Structure Construction Method and Functional Working Ship Download PDFInfo
- Publication number
- KR100617950B1 KR100617950B1 KR1020040097038A KR20040097038A KR100617950B1 KR 100617950 B1 KR100617950 B1 KR 100617950B1 KR 1020040097038 A KR1020040097038 A KR 1020040097038A KR 20040097038 A KR20040097038 A KR 20040097038A KR 100617950 B1 KR100617950 B1 KR 100617950B1
- Authority
- KR
- South Korea
- Prior art keywords
- caisson
- hydraulic jack
- work
- pile
- work line
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/04—Flat foundations in water or on quicksand
- E02D27/06—Floating caisson foundations
Abstract
본 발명은 수중에 케이슨을 설치하는 기능성 작업선을 수면으로부터 일정 높이만큼 상승시킨 상태에서 케이슨 설치 작업을 안전하게 작업하고, 이 작업선의 일측을 중심으로 벌려 구조물로부터 편리하게 이탈시키는 수중 건식 구조물 시공방법 및 그 기능성 작업선을 개시한다.The present invention provides a method for constructing underwater dry structures that safely work the caisson installation work in a state in which the functional work line for installing the caisson in the water is raised by a certain height from the water surface, and conveniently separated from the structure by spreading the work line around one side of the work line. The functional work line is started.
이를 위하여 본 발명은 원형, 각형 등에 따라 그 중앙에 케이슨 통공을 형성하고, 지지파일의 측면에서 지지파일을 지지하는 제1유압잭과, 그 상면에 지지파일을 승하강시키는 제2유압잭이 설치된 작업선을 작업현장으로 이동하는 단계와, 제2유압잭의 작동으로 토사층(암석층)에 지지파일을 고정하는 단계와, 제2유압잭의 작동으로 고정된 지지파일을 따라 작업선을 수면으로부터 일정 높이만큼 상승시키는 단계와, 작업선의 상면에서 케이슨을 조립하여 케이슨 통공으로 케이슨을 침설시켜 제1유압잭으로 지지하는 단계와, 케이슨 내부에 교각 등의 구조물을 시공한 다음 제2유압잭으로 케이슨을 인양시킨 후 분리하는 단계와, 제2유압잭을 작동시켜 지지파일로부터 작업선을 수면으로 하강시키는 단계와, 이후 토사층(암석층)에 고정된 지지파일을 제2유압잭의 작동으로 부상시키는 단계와 작업선의 결합부를 분리시킨 후 힌지부를 중심으로 좌우 분리시켜 구조물로부터 작업선을 이탈시키는 단계로 이루어진다.To this end, the present invention forms a caisson through hole in the center of the circular, square, etc., the first hydraulic jack for supporting the support pile on the side of the support pile, and the second hydraulic jack for lifting up and down the support pile on its upper surface Moving the work site to the work site, fixing the support pile to the soil layer (rock layer) by the operation of the second hydraulic jack, and raising the work line from the surface along the support pile fixed by the operation of the second hydraulic jack. And assembling the caissons from the upper surface of the working ship, submerging the caissons through the caisson through holes to support them with the first hydraulic jack, and constructing a pier or the like inside the caissons, and then lifting the caissons with the second hydraulic jacks and separating them. And operating the second hydraulic jack to lower the working line from the support pile to the surface, and then removing the support pile fixed to the soil layer (rock layer). It is composed of the step of floating by the operation of the hydraulic jack and separating the coupling of the work line and then separated from the left and right around the hinge portion to separate the work line from the structure.
이와 같은 본 발명은 작업선에서 직접 케이슨을 침설함으로써 별도의 작업선 없이 간편하게 케이슨을 침설할 수 있고, 작업선을 수면으로부터 일정 높이까지 상 승시킴으로써 파랑(波浪), 풍향 등에 관계없이 작업을 할 수 있으며, 작업선이 분리/결합되어 구조물로부터 용이하게 이탈되는 효과를 가지게 되는 것이다.In the present invention, by immersing the caisson directly from the working ship, it is possible to immerse the caisson easily without a separate working ship, and can work regardless of the wave or wind direction by raising the working ship to a certain height from the surface. And, the work line is separated / combined to have an effect that is easily separated from the structure.
수중 건식 구조물, 작업선, 말뚝기초, 작업기초Underwater dry structures, work ships, pile foundations, work foundations
Description
도1은 본 발명의 기능성 작업선을 나탸낸 평면도.1 is a plan view showing a functional working line of the present invention.
도2는 본 발명 기능성 작업선의 다른 실시예를 나타낸 평면도.Figure 2 is a plan view showing another embodiment of the functional working line of the present invention.
도3은 본 발명 기능성 작업선의 요부를 나타낸 분해사시도.Figure 3 is an exploded perspective view showing the main portion of the functional working line of the present invention.
도4는 본 발명 수중 건식 구조물 시공방법의 흐름도.4 is a flowchart of the method for constructing a dry structure underwater in the present invention.
도5는 본 발명 수중 건식 구조물 시공방법의 다른 실시예를 나타낸 흐름도.Figure 5 is a flow chart showing another embodiment of the underwater dry structure construction method of the present invention.
도6a는 본 발명 제2유압잭으로 지지파일을 하강시키기 위해 고정된 상태를 나타낸 단면도.Figure 6a is a cross-sectional view showing a fixed state for lowering the support pile with the second hydraulic jack of the present invention.
도6b는 본발명 제2유압잭으로 지지파일을 하강시키는 상태를 나타낸 단면도.Figure 6b is a cross-sectional view showing a state of lowering the support pile with the second hydraulic jack of the present invention.
도6c는 본 발명 제2유압잭으로 지지파일을 하강시킨 상태를 나타낸 단면도.Figure 6c is a cross-sectional view showing a state in which the support pile is lowered by the second hydraulic jack of the present invention.
도7a는 본 발명 케이슨을 제1유압잭으로 고정하기 전 상태를 나타낸 단면도.Figure 7a is a sectional view showing a state before fixing the caisson of the present invention with the first hydraulic jack.
도7b는 본 발명 제1유압잭 작동으로 케이슨을 고정시킨 상태를 나타낸 단면도.Figure 7b is a sectional view showing a state in which the caisson is fixed by the first hydraulic jack operation of the present invention.
도8a는 본 발명의 말뚝기초를 이용한 수중 건식 구조물시공방법을 나타낸 것으로써, 작업선이 작업현장으로 이동한 상태를 나타낸 단면도.Figure 8a is a cross-sectional view showing a state in which the work line moved to the work site showing the construction method of underwater dry structure using the pile foundation of the present invention.
도8b는 제2유압잭으로 지지파일의 시공 및 작업선을 상승시켜 말뚝기초를 시 공하는단면도.Figure 8b is a cross-sectional view of constructing the pile foundation by raising the construction and work line of the support pile with a second hydraulic jack.
도8c는 케이슨을 조립하여 침설하는 단면도.Figure 8c is a cross-sectional view of the caisson assembled.
도8d는 케이슨을 지지하고 토사층의 제거와 평탄작업 후 레벨링 콘크리트를 타설, 양생한 단면도.Fig. 8D is a cross-sectional view of the caisson, which pours leveling concrete after removing and leveling the soil layer;
도8e는 케이슨 하부에 팽창튜브를 설치하여 외수의 유입을 차단하고 배수시킨 후 말뚝 두부를 정리한 단면도.Figure 8e is a cross-sectional view of the pile head after installing the expansion tube in the lower caisson to block the inflow and drainage of external water.
도8f는 교각 구조물을 시공한 단면도.Figure 8f is a cross-sectional view of the construction of the bridge structure.
도8g는 팽창튜브의 철거하고 외수를 유입시킨 후 케이슨을 인양한 단면도.Figure 8g is a cross-sectional view of lifting the caisson after the removal of the expansion tube and the inflow of external water.
도8h는 제2유압잭을 작동시켜 작업선을 하강시킨 단면도.Fig. 8H is a sectional view of lowering the work line by operating the second hydraulic jack.
도8i는 지지파일 해체하고 작업선을 분리 이탈시킨 단면도.Figure 8i is a cross-sectional view of dismantling the support pile and separating the work line.
도9는 본 발명의 직접기초를 이용한 수중 건식 구조물시공방법을 나타낸 것으로써, 작업선이 작업현장으로 이동한 상태를 나타낸 단면도.Figure 9 is a cross-sectional view showing a state in which the working ship moved to the work site showing the construction method of underwater dry structure using the direct foundation of the present invention.
도9b는 지지층에 지지파일을 시공하고, 작업선을 상승시켜 하상 토사층을 준설한 단면도.Fig. 9B is a sectional view in which a support pile is installed on a support layer, and a working soil is raised to dredge a bottom soil layer.
도9c는 암석층의 굴착, 평탄 작업 후 레벨링 콘크리트를 타설, 양생한 단면도.Fig. 9C is a cross-sectional view of pouring and leveling concrete after excavation and flattening of a rock layer.
도9d는 케이슨 조립 후 바라스트 탱크에 물 주입하여 침설한 단면도.Figure 9d is a cross-sectional view of the ballast tank after the caisson assembly by injecting water.
도9e는 지지층에 수밀재를 압착시켜 외수를 차단하고, 케이슨 내부를 배수한 단면도.Fig. 9E is a cross-sectional view of the watertight material pressed against the support layer to block external water and draining the interior of the caisson.
도9f는 암석층 굴착 및 평탄하게 고른 단면도.9F illustrates rock layer excavation and flattened cross-sectional view.
도9g는 구조물을 시공한 단면도.Figure 9g is a cross-sectional view of the construction of the structure.
도9h는 바라스트 탱크의 물을 배수하고 케이슨을 인양 및 해체한 단면도.Fig. 9H is a cross-sectional view of draining water of the barast tank and lifting and disassembling the caisson.
도9i는 유압잭으로 작업선을 하강시킨 후 지지파일을 해체하여 작업선을 분리, 이탈시킨 단면도.Figure 9i is a cross-sectional view of separating and leaving the work line by dismantling the support pile after lowering the work line with a hydraulic jack.
도10a는 작업선으로 구조물을 시공하는 상태의 평면도.Figure 10a is a plan view of a state of constructing a structure with a working line.
도10b는 작업선을 분리시킨 상태의 평면도.Fig. 10B is a plan view of a state in which the work line is separated.
도10c는 작업선을 이탈시킨 상태의 평면도.Fig. 10C is a plan view of the state where the work line is separated.
*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *
10: 작업선 11: 케이슨 삽입공10: Workline 11: caisson insertion hole
12: 제1유압잭 13: 받침대12: 1st hydraulic jack 13: pedestal
14: 붐 15: 지지파일14: Boom 15: Support pile
16: 고정대 17: 고정핀16: holder 17: fixing pin
18: 통공 20: 지지대18: through air 20: support
21: 제2유압잭 22: 붐21: 2nd Hydraulic Jack 22: Boom
23: 연결대 24: 연결핀23: connecting rod 24: connecting pin
25: 통공 30: 힌지부25: through hole 30: hinge part
31: 고정프레임 32: 결합부31: fixed frame 32: coupling portion
40; 지지판 41: 말뚝기초 시공장비40; Support plate 41: pile foundation construction equipment
42: 레벨링 콘크리트 43: 팽창튜브42: leveling concrete 43: expansion tube
44: 바라스트 탱크44: Barast Tank
본 발명은 수중 건식 구조물 시공방법 및 그 기능성 작업선에 관한 것으로, 특히 수중에 케이슨을 침설하는 기능성 작업선을 수면으로부터 일정 높이만큼 상승시켜 케이슨 침설 작업을 안전하게 진행하고, 이 작업선의 일측을 중심으로 벌려 구조물로부터 편리하게 이탈시키는 수중 건식 구조물 시공방법 및 그 기능성 작업선에 관한 것이다.The present invention relates to a method for constructing an underwater dry structure and a functional working line thereof, and in particular, a functional working line for submerging the caisson in water is raised by a certain height from the surface to safely proceed with the caisson subsidence work, and focuses on one side of the working line. The present invention relates to a method for constructing an underwater dry structure which is easily separated from an open structure, and a functional work line thereof.
주지하는 바와 같이 수중에 교각을 설치하거나 대형 구조물을 시공하기 위해서는 육상에서 케이슨을 제작하여 이를 예인선으로 옮겨 싣고서 케이슨을 설치하고자 하는 장소로 이동하게 된다.As is well known, in order to install a pier or construct a large structure underwater, a caisson is manufactured on land, and it is moved to a tugboat and moved to a place where the caisson is to be installed.
이러한 케이슨을 수중에 설치하기 위해서는 케이슨을 잡아주는 예인선과 함께 수중에 침설되는 케이슨이 수직 상태를 유지되도록 그 주변에 다수의 작업선을 배치시켜 이러한 작업선으로부터 케이슨에 연결된 로프 등으로 잡아주어 케이슨이 움직이지 않고, 수직상태를 계속 유지되게 한다.In order to install these caissons underwater, a number of working ships are arranged around them so that the caissons submerged in the water along with the tugboat holding the caissons are held vertically, and the caissons are held by ropes connected to the caissons. It doesn't move and keeps upright.
이와 같이 케이슨의 설치 또는 구조물 시공시에 작업현장에 별도의 작업선을 투입하여 작업을 진행하여야 하는 불편함이 있고, 지지층에 세워진 케이슨의 규격이 작아 전도되거나 부등침하가 발생하는 경우 별도의 지지 시설을 설치하여야 하는 불편함이 있었으며, 이로 인하여 안전사고가 발생하는 문제점이 있고, 케이슨 설치 작업 및 구조물 시공시에 파랑(波浪)에 의해 작업이 지연되는 어려움이 있었 다.As such, there is inconvenience of having to put a separate work line into the work site when installing caissons or constructing a structure, and if the caissons set on the support floor are small and fall down or have an uneven settlement, a separate supporting facility There was an inconvenience to install the, there is a problem that a safety accident occurs, there was a difficulty in delaying the work due to the wave (wave) during the caisson installation work and construction of the structure.
상기와 같은 문제점을 해결하기 위하여 본 발명은 수중에 설치되는 케이슨의 견고한 설치가 가능하며, 별도의 작업선이 불필요하고, 파랑에 의한 작업 지연을 최소화하는 수중 건식 구조물 시공방법 및 그 기능성 작업선을 제공하는 데 있다.In order to solve the above problems, the present invention can be installed firmly in the caisson to be installed in the water, there is no need for a separate work line, the construction method of underwater dry structure and its functional work line to minimize the work delay caused by blue To provide.
상기와 같은 목적을 달성하기 위하여 본 발명은 원형, 각형 등의 형상에 따라 그 중앙에 케이슨 삽입공을 형성하고, 지지파일의 측면에서 지지파일을 지지하는 제1유압잭과, 그 상면에 지지파일을 상승,하강시키는 제2유압잭이 설치된 작업선을 예인선으로 작업현장에 이동시키는 단계와, 제2유압잭의 작동으로 토사층(암석층)에 지지파일을 견고하게 고정시키는 단계와, 또한 제2유압잭의 작동으로 고정된 지지파일을 따라 작업선을 수면으로부터 일정 높이만큼 상승시키는 단계와, 작업선에서 케이슨을 조립하여 상기 케이슨 삽입공으로 케이슨을 침설시켜 제1유압잭으로 이를 견고하게 지지하는 단계와, 케이슨 내부에 교각 등의 구조물을 시공한 다음 제2유압잭으로 케이슨을 부상시켜 이를 분리하는 단계와, 제2유압잭을 작동시켜 지지파일로부터 작업선을 수면으로 하강시키는 단계와, 이후 토사층(암석층)에 고정된 지지파일을 제2유압잭의 작동으로 인양시키는 단계와, 작업선의 결합부를 분리시킨 후 힌지부를 중심으로 좌우 분리시켜 구조물로부터 작업선을 이탈시키는 단계로 이루어지는 것을 수중 건식 구조물 시공방법을 제안한다.In order to achieve the above object, the present invention is to form a caisson insertion hole in the center according to the shape of the circular, square, etc., the first hydraulic jack for supporting the support pile from the side of the support pile, and the support pile on the upper surface Moving the work line provided with the second hydraulic jack to ascend and descend to the work site by a towboat; and firmly fixing the support pile to the soil layer (rock layer) by the operation of the second hydraulic jack, and also by the operation of the second hydraulic jack. Raising the work line along the fixed support pile from the surface by a certain height, Assembling the caisson from the work line to immerse the caisson with the caisson insertion hole to firmly support it with the first hydraulic jack, and pier inside the caisson After constructing the back structure, lifting the caisson with the second hydraulic jack and separating it, and operating the second hydraulic jack to remove the support pile from the supporting pile. Lowering the upline to the surface, then lifting the supporting pile fixed to the soil layer (rock layer) by the operation of the second hydraulic jack, separating the coupling part of the work line, and separating the work line from the structure by separating the work line from the structure. It proposes the construction method of underwater dry structure consisting of the step of leaving.
또한, 케이슨의 조립 및 분리가 가능한 작업공간을 가지는 크기로 이루어지 고 그 중앙에 케이슨의 형상에 따라 형성된 케이슨 통공과, 그 길이방향을 따라 분리/결합되고 일측에는 회전 가능하게 설치된 힌지부와, 타측에는 볼트와 너트로 분리/결합되게 형성된 결합부와, 그 상면에 케이슨의 침설 후 케이슨을 지지하도록 설치된 제1유압잭과, 지지파일을 하상에 고정시킨 후 지지파일을 따라 수면으러부터 일정 높이만큼 승하강되게 설치된 제2유압잭을 설치한 기능성 작업선을 제안한다.In addition, the caisson through hole is formed in the size having a work space that can be assembled and detached, according to the shape of the caisson in the center, the hinge portion separated / coupled along the longitudinal direction and rotatably installed on one side, On the other side, the coupling part formed to be separated / coupled by bolts and nuts, the first hydraulic jack installed to support the caisson after the caisson subsidence on the upper surface, and the support pile fixed to the lower side and then along the support pile to a certain height from the water surface We propose a functional work boat on which a second hydraulic jack is installed.
이와 같은 본 발명은 별도의 작업선 없이 작업선에서 케이슨을 설치함으로써 케이슨을 간편하게 설치하고, 작업선이 수상에 견고하게 위치한 상태에서 작업이 이루어짐으로써 파랑(波浪)에 의해 작업의 지연 없이 케이슨 설치 작업을 신속하게 작업할 수 있게 되는 것이다.In the present invention, the caisson is installed easily by installing the caisson from the working ship without a separate working ship, the work is carried out in a state where the working ship is firmly positioned in the water, the installation of the caisson without delay by the blue wave (wave) Will be able to work quickly.
이하, 본 발명의 실시예를 도면을 참조하여 설명한다.Hereinafter, embodiments of the present invention will be described with reference to the drawings.
도시된 바와 같이, 케이슨(1)의 형태에 따라 건조(建造)된 기능성 작업선(10)을 예인선으로 작업현장에 이동하는 단계와, 작업선(10) 상면에 설치된 유압잭(21)을 작동시켜 지지층(2)에 지지파일(15)을 항타하여 이를 견고하게 고정하는 단계와, 이 지지파일(15)에 결합된 유압잭(21)으로 작업선(10)을 수면으로부터 일정 높이까지 끌어올려 고정하는 단계와, 시공하고자 하는 구조물에 적합한 크기의 케이슨(1)을 조립하여 이를 지지층(2)에 견고하게 침설시키는 단계와, 이러한 케이슨(1) 내부에 시공하고자 하는 구조물을 시공한 후 상기 케이슨(1)을 인양시켜 이를 해체하는 단계와, 작업선(10)이 수면에 닿도록 유압잭(21)으로 작업선(10)을 하강시키는 단계와, 작업선(10)으로부터 지지파일(15)을 뽑아 올린 후 작업선(10)의 결 합부를 해제하여 구조물로부터 작업선(10)을 이탈하는 단계로 이루어진다.As shown in the figure, the step of moving the functional working
또한, 작업선(10)은 일측에 돌출된 고정프레임(31)에 회전 가능한 힌지부(30)를 결합하고, 타측에 돌출되어 볼트,너트로 체결되는 결합부(32)를 형성하여 작업선(10)이 힌지부(30)를 중심으로 회전시켜 분리/결합되어진다.In addition, the
도시된 바와 같이 본 발명의 기능성 작업선(10)은 일정 두께를 가지는 평탄한 면을 가지고, 도 1 내지 도3에 도시된 바와 같이 그 중앙에 원형 또는 각형 등 삽입되는 케이슨(1)의 크기 보다 큰 크기로 이루어지는 케이슨 삽입공(11)을 형성하고, 그 외측에 침설되는 케이슨(1)을 잡아주는 유압잭(12)을 설치한다.As shown, the functional working
이러한 유압잭(12)은 작업선(10)의 상면에 받침대(13)를 견고하게 고정시키고, 그 상면에 붐(14)이 설치된 유압잭(12)을 고정하며, 상기 붐(14)은 유압잭(12)의 작동에 따라 수평 이동되어 케이슨(1)의 외경에 밀착되어 케이슨(1)을 견고하게 지지하도록 설치된다.The
이와 함께 작업선(10)에는 지지층(2)에 지지파일(15)을 고정하는 다수개 고정대(16)를 설치하고, 상기 지지파일(15)에는 일정한 간격으로 고정핀(17)과 연결핀(24)이 삽입되는 통공(15a)을 형성하며, 이 고정대(16)는 작업선(10)의 상면에 고정핀(17)이 삽입되는 통공(18)을 형성한다.Along with this, the
또한, 고정대(16)와 함께 작업선(10)의 상면에 지지대(20)를 다수개 고정하고, 이의 상면에 유압잭(21)의 작동에 따라 수직 이동하는 붐(22)을 설치하며, 그 상부에 연결대(23)를 설치하고, 그 연결대(23)에는 연결핀(24)이 삽입되는 통공(25)을 형성한다.In addition, a plurality of
이러한 고정대(16)와 지지대(20)는 작업선(10)을 고정하는 지지파일(15)을 설치하는 다수개의 개소에 설치된다.Such a
이와 같은 작업선(10)은 그 길이방향의 중심으로 구조물의 시공 후 이를 양측으로 벌려 구조물로부터의 이탈되게 이등분 분할되고, 작업선(10)의 일측에는 고정프레임(31)을 돌출시켜 힌지부(30)를 결합하고, 타측에는 볼트, 너트로 체결되는 결합부(32)를 형성시켜 힌지부(30)를 중심으로 회전되어 분리/결합된다.The
아울러, 도4, 도5에 도시된 바와 같이 본 발명의 수중 건식 구조물 시공방법을 말뚝기초를 이용한 시공방법과 직접기초를 이용한 시공방법에 따라 설명하기로 한다.In addition, as shown in Figures 4 and 5 will be described according to the construction method using the pile foundation and the construction method using the foundation of the underwater dry structure of the present invention.
먼저, 말뚝기초를 이용한 수중 건식 구조물 시공방법은 건조된 작업선(10)을 예인하여 도8a에서와 같이 구조물을 시공하고자 하는 작업현장으로 이동하고, 이러한 작업선(10)에는 케이슨(1)을 지지하는 유압잭(12)과, 지지파일(15)을 상승, 하강시키는 유압잭(21)이 설치된다(S100).First, the method for constructing an underwater dry structure using a pile foundation is towed the dried working
작업현장에 도착한 작업선(10)은 유압잭(21)을 이용하여 일정 길이를 가지는 지지파일(15)을 토사층(2)에 항타하여 이를 견고하게 고정시키고, 상기 지지파일(15)의 하부에는 지지파일(15)이 토사층(2)에 박은 상태에서 지지파일(15)과 토사층(2)이 밀착된 상태를 유지하기 위한 지지판(40)이 구비된다(S101).Working
이후 도6에 도시된 바와 같이 작업선(10)에 설치된 유압잭(21)의 연결대(23)를 하강시킨 상태에서 지지파일(15)의 통공(15a)에 고정핀(17)을 끼우고 또한, 연결대(23)에 연결핀(24)을 끼워 고정시키며, 지지파일(15) 하강되게 고정핀(17)을 고정대(16)로부터 이탈시킨다.6 and then the fixing
이 상태에서 붐(22)을 하강시켜 지지파일(15)을 하강시키고, 다시 고정핀(17)으로 지지파일(15)을 고정시킨 후 붐(22)을 상승시켜 연결핀(24)을 고정시켜 붐(22)을 하강시키면서 반복적으로 지지파일(15)을 하강시켜 토사층(2)에 고정시킨다.In this state, the
이렇게 토사층(2)에 지지파일(15)의 고정이 완료되면 도8b와 같이 유압잭(21)은 상기의 과정과 반대로 지지파일(15)로부터 작업선(10)을 수면으로부터 일정 높이 상승시킨다(S102).When the fixing of the
이후 작업선(10)의 상부에 말뚝기초(3)를 시공하는 말뚝기초 시공장비(41)를 설치하여 암석층(4)에 말뚝기초(3)를 다수개 박게 된다(S103).After installing the pile
아울러 작업선(10)의 상면에서 케이슨(1)을 조립하여(S104) 도8c 및 도10에서와 같이 케이슨(1)을 침하시키게 되고, 케이슨(1)의 침하가 완료되면 작업선(10)의 상면에 설치된 유압잭(12)을 작동시켜 케이슨(1)이 움직이지 않도록 붐(14)으로 케이슨(1)을 지지한다(S105).In addition, assembling the
또한, 케이슨(1) 내부의 바닥면이 고르도록 토사층(2)의 굴곡면을 제거하여 평탄하게 하고(S106), 이후 도8d에서와 같이 구조물 시공의 기초가 되는 레벨링 콘크리트(42)를 일정 두께로 타설하여 양생한다(S107).In addition, the curved surface of the
이러한 케이슨(1) 하부에 도8e에서와 같이 팽창튜브(43)을 설치하고(S108), 상기의 팽창튜브(43)을 팽창시켜 케이슨(1)의 외부로부터 물이 유입되는 것을 차단하고, 이와 더불어 케이슨(1) 내부의 물을 빼는 배수작업을 하게 된다(S109).An
이렇게 케이슨(1) 내부는 건식상태로 되고, 말뚝기초(3)의 상부를 정리하며(S110), 도8f에서와 같이 그 상부에 교각(5) 또는 구조물을 시공하게 된다(S111).Thus, the interior of the
구조물의 시공이 완료되면 도8g에서와 같이 케이슨(1)으로부터 팽창튜브(43)를 철거하여 외수를 유입되게 하고(S112), 유압잭(12)을 작동시켜 케이슨(1)의 지지를 해제하여 케이슨(1)을 인양한 후 이를 해제하게 된다(S113).When the construction of the structure is completed, remove the
이후 도8h에서와 같이 유압잭(21)을 작동시켜 지지파일(15)로부터 작업선(10)을 하강하게 되고(S114), 도8i에서와 같이 유압잭(21)을 작동시켜 토사층(2)에 고정된 지지파일(15)을 뽑아 올리며(S115), 작업선(10)의 결합부(32)를 해제시켜 구조물로부터 작업선(10)을 이탈시키게 된다(S116).Thereafter, as shown in FIG. 8H, the
또한, 직접기초 시공방법에 의한 수중 건식 구조물 시공방법은 도9a에서와 같이 건조된 작업선(10)을 예인하여 작업현장으로 이동시키고(S200), 도9b에서와 같이 유압잭(21)을 이용하여 일정 길이를 가지는 지지파일(15)을 암석층(4)에 항타하여 이를 견고하게 고정시키고(S201), 이러한 지지파일(15)의 시공은 상기 말뚝기초를 이용한 시공방법과 동일하다.In addition, the method of construction of underwater dry structure by the direct foundation construction method is towed to the working site to dry the working
이후 도9b에서와 같이 유압잭(21)을 작동시켜 작업선(10)을 수면으로부터 일정 높이까지 상승시키고(S202), 지지파일(15)이 시공된 하상 토사층을 준설하고(S203), 다시 암석층(4)을 굴착기로 굴착하여 구조물이 설치되는 작업면을 평탄하게 한다(S204).Thereafter, as shown in FIG. 9B, the
이러한 암석층(4)에 도9c에서와 같이 구조물 시공의 기초가 되는 레벨링 콘크리트(42)를 타설하여 이를 양생하고(S205), 이후 도9d에서와 같이 작업선(10)의 상면에서 케이슨(1)을 조립하고, 바라스트 탱크(44) 내부에 물을 주입시켜 케이슨(1)을 침설시킨다(S206). The
아울러 암석층(4)에 수밀재를 압착시켜 외수의 유입을 차단하고(S207), 도9e에서와 같이 모터 펌프(6)를 설치하여 케이슨(1) 내부의 물을 배수시키며(S208), 도9f에서와 같이 굴착기로 암석층(4)을 굴착하여 구조물이 시공되는 지면을 평탄하게 한다(S209).In addition, the watertight material is pressed to the
이 상태에서 도9g에서와 같이 교각(5) 등의 구조물을 시공하여 양생이 완료되면(S210), 도9h에서와 같이 바라스트 탱크(44)로부터 물을 배수시키게 된다(S211).In this state, as shown in FIG. 9G, when the construction of the structure such as the
이후 도9i에서와 같이 케이슨(1)을 인양하여 작업선(10)에서 해체하고(S212), 유압잭(21)을 작동시켜 지지파일(15)로부터 작업선(10)을 하강하게 되고(S213), 유압잭(21)을 작동시켜 암석층(4)에 고정된 지지파일(15)을 뽑아 올리며(S214), 도10에서와 같이 작업선(10)의 결합부(32)를 해제시켜 구조물로부터 작업선(10)을 이탈시키게 된다(S215).Then, as shown in FIG. 9i, the
상기한 바와 같이 본 발명은 작업선에서 케이슨을 침설하면서 이를 유압잭으로 견고하게 지지시킴으로써 별도의 작업선 없이 간편하게 케이슨을 침설할 수 있고, 작업선에 설치된 유압잭으로 지지파일을 시공하여 유압잭으로 작업선을 수면으로부터 일정 높이까지 상승시킴으로써 파랑(波浪), 풍향 등에 관계없이 작업을 할 수 있으며, 작업선이 분리/결합되어 구조물로부터 용이하게 이탈되는 효과를 가지 게 되는 것이다.
As described above, the present invention can immerse the caisson easily without a separate working ship by steadily supporting the caisson in the working ship with a hydraulic jack, and by installing the support pile with the hydraulic jack installed on the working ship, the working ship with the hydraulic jack. By raising to a certain height from the surface of the water can work regardless of the wave (wave), wind direction, etc., the work line is separated / combined to have the effect of easily separated from the structure.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040097038A KR100617950B1 (en) | 2004-11-24 | 2004-11-24 | Under Water Dry Structure Construction Method and Functional Working Ship |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040097038A KR100617950B1 (en) | 2004-11-24 | 2004-11-24 | Under Water Dry Structure Construction Method and Functional Working Ship |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20-2004-0033609U Division KR200382622Y1 (en) | 2004-11-26 | 2004-11-26 | Functional Working Ship for Under Water Dry Structure |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20060057851A KR20060057851A (en) | 2006-05-29 |
KR100617950B1 true KR100617950B1 (en) | 2006-08-29 |
Family
ID=37153113
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020040097038A KR100617950B1 (en) | 2004-11-24 | 2004-11-24 | Under Water Dry Structure Construction Method and Functional Working Ship |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100617950B1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100916749B1 (en) * | 2007-08-31 | 2009-09-14 | (주)힘틀 | Lifter |
KR100973090B1 (en) * | 2009-11-26 | 2010-07-30 | (주) 선암기술연구소 | Construction method and bridge safeguard for vessel guidance apparatus |
KR101247754B1 (en) | 2010-08-31 | 2013-03-25 | 삼성중공업 주식회사 | Elevating system for leg and wind turbine installation vessel with the same |
KR101540519B1 (en) * | 2013-11-06 | 2015-07-30 | 현대건설주식회사 | Maintenance apparatus for underwater tidal current generator |
KR101576504B1 (en) * | 2015-10-26 | 2015-12-21 | 에스앤에스이앤지 주식회사 | Barge having jackup device |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101247753B1 (en) * | 2010-08-31 | 2013-03-25 | 삼성중공업 주식회사 | Elevating system for leg and wind turbine installation vessel with the same |
KR101050824B1 (en) * | 2011-01-31 | 2011-07-20 | 혜림엔지니어링(주) | Pier constructing method for expanding using oscillator on brideg expanding of upper part over water |
BE1024096B1 (en) * | 2013-10-29 | 2017-11-14 | Baggerwerken Decloedt En Zoon N.V. | DEVICE AND METHOD FOR APPLYING TO A UNDERWATER FLOOR OF A LOW MATERIAL WITH PRIOR DETERMINED LEVEL LEVEL |
CN104787706A (en) * | 2015-04-09 | 2015-07-22 | 江苏华夏重工有限公司 | Positioning pile lifting system |
CN113562140A (en) * | 2021-07-23 | 2021-10-29 | 舟山长宏国际船舶修造有限公司 | Wood pier pressing tool |
-
2004
- 2004-11-24 KR KR1020040097038A patent/KR100617950B1/en not_active IP Right Cessation
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100916749B1 (en) * | 2007-08-31 | 2009-09-14 | (주)힘틀 | Lifter |
KR100973090B1 (en) * | 2009-11-26 | 2010-07-30 | (주) 선암기술연구소 | Construction method and bridge safeguard for vessel guidance apparatus |
KR101247754B1 (en) | 2010-08-31 | 2013-03-25 | 삼성중공업 주식회사 | Elevating system for leg and wind turbine installation vessel with the same |
KR101540519B1 (en) * | 2013-11-06 | 2015-07-30 | 현대건설주식회사 | Maintenance apparatus for underwater tidal current generator |
KR101576504B1 (en) * | 2015-10-26 | 2015-12-21 | 에스앤에스이앤지 주식회사 | Barge having jackup device |
Also Published As
Publication number | Publication date |
---|---|
KR20060057851A (en) | 2006-05-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5057223B2 (en) | Temporary wall construction method using steel segments | |
KR100617950B1 (en) | Under Water Dry Structure Construction Method and Functional Working Ship | |
US4063426A (en) | Three column tower | |
KR100714179B1 (en) | Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof | |
CN100535264C (en) | Steel boxed cofferdam and recovery method thereof | |
KR100383409B1 (en) | Construction Method of Direct Foundation for using Caisson | |
KR20140058951A (en) | Caisson tube water-tight structure and under water structure construction method for soft ground | |
KR200382622Y1 (en) | Functional Working Ship for Under Water Dry Structure | |
KR100733082B1 (en) | Device of Bridge Pier Mould Construction and methed thereof | |
JPS58143023A (en) | Caisson for pile supporting type breakwater | |
JP4260448B2 (en) | Connection method and structure of submerged shaft and horizontal shaft | |
JP2001348888A (en) | Method and device for constructing underwater foundation structure | |
KR200404677Y1 (en) | Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof | |
KR100556302B1 (en) | Caisson Installed Support Means and Construction Method of Underwater Structure Using It | |
KR100621410B1 (en) | Dry Construction Method of Underwater Structure Using Watertight Caisson | |
JP2004190374A (en) | Soft ground improving method and soft ground improving unit | |
KR101154623B1 (en) | Device for constructing pier in the water and pier constructing method using the same | |
JPS6143493B2 (en) | ||
KR20020081530A (en) | Well form for the base operation of pier and it's operation method | |
KR101158035B1 (en) | caisson and construction method of underwater structure using it | |
JP2001317060A (en) | Construction method for underwater foundation | |
KR100581403B1 (en) | Method for constructing for a soft-ground breakwater | |
KR20080065207A (en) | A direct base construction method of underwater concrete using a hollow cylindrical steel mold having a buoyancy | |
CN113605465B (en) | Prestress tensioning structure and method for anti-floating construction | |
CN216007009U (en) | A auxiliary device for foundation ditch precipitation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20110822 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20120823 Year of fee payment: 7 |
|
LAPS | Lapse due to unpaid annual fee |