KR100617950B1 - Under Water Dry Structure Construction Method and Functional Working Ship - Google Patents

Under Water Dry Structure Construction Method and Functional Working Ship Download PDF

Info

Publication number
KR100617950B1
KR100617950B1 KR1020040097038A KR20040097038A KR100617950B1 KR 100617950 B1 KR100617950 B1 KR 100617950B1 KR 1020040097038 A KR1020040097038 A KR 1020040097038A KR 20040097038 A KR20040097038 A KR 20040097038A KR 100617950 B1 KR100617950 B1 KR 100617950B1
Authority
KR
South Korea
Prior art keywords
caisson
hydraulic jack
work
pile
work line
Prior art date
Application number
KR1020040097038A
Other languages
Korean (ko)
Other versions
KR20060057851A (en
Inventor
배석동
Original Assignee
(주) 선암기술연구소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 선암기술연구소 filed Critical (주) 선암기술연구소
Priority to KR1020040097038A priority Critical patent/KR100617950B1/en
Publication of KR20060057851A publication Critical patent/KR20060057851A/en
Application granted granted Critical
Publication of KR100617950B1 publication Critical patent/KR100617950B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/04Flat foundations in water or on quicksand
    • E02D27/06Floating caisson foundations

Abstract

본 발명은 수중에 케이슨을 설치하는 기능성 작업선을 수면으로부터 일정 높이만큼 상승시킨 상태에서 케이슨 설치 작업을 안전하게 작업하고, 이 작업선의 일측을 중심으로 벌려 구조물로부터 편리하게 이탈시키는 수중 건식 구조물 시공방법 및 그 기능성 작업선을 개시한다.The present invention provides a method for constructing underwater dry structures that safely work the caisson installation work in a state in which the functional work line for installing the caisson in the water is raised by a certain height from the water surface, and conveniently separated from the structure by spreading the work line around one side of the work line. The functional work line is started.

이를 위하여 본 발명은 원형, 각형 등에 따라 그 중앙에 케이슨 통공을 형성하고, 지지파일의 측면에서 지지파일을 지지하는 제1유압잭과, 그 상면에 지지파일을 승하강시키는 제2유압잭이 설치된 작업선을 작업현장으로 이동하는 단계와, 제2유압잭의 작동으로 토사층(암석층)에 지지파일을 고정하는 단계와, 제2유압잭의 작동으로 고정된 지지파일을 따라 작업선을 수면으로부터 일정 높이만큼 상승시키는 단계와, 작업선의 상면에서 케이슨을 조립하여 케이슨 통공으로 케이슨을 침설시켜 제1유압잭으로 지지하는 단계와, 케이슨 내부에 교각 등의 구조물을 시공한 다음 제2유압잭으로 케이슨을 인양시킨 후 분리하는 단계와, 제2유압잭을 작동시켜 지지파일로부터 작업선을 수면으로 하강시키는 단계와, 이후 토사층(암석층)에 고정된 지지파일을 제2유압잭의 작동으로 부상시키는 단계와 작업선의 결합부를 분리시킨 후 힌지부를 중심으로 좌우 분리시켜 구조물로부터 작업선을 이탈시키는 단계로 이루어진다.To this end, the present invention forms a caisson through hole in the center of the circular, square, etc., the first hydraulic jack for supporting the support pile on the side of the support pile, and the second hydraulic jack for lifting up and down the support pile on its upper surface Moving the work site to the work site, fixing the support pile to the soil layer (rock layer) by the operation of the second hydraulic jack, and raising the work line from the surface along the support pile fixed by the operation of the second hydraulic jack. And assembling the caissons from the upper surface of the working ship, submerging the caissons through the caisson through holes to support them with the first hydraulic jack, and constructing a pier or the like inside the caissons, and then lifting the caissons with the second hydraulic jacks and separating them. And operating the second hydraulic jack to lower the working line from the support pile to the surface, and then removing the support pile fixed to the soil layer (rock layer). It is composed of the step of floating by the operation of the hydraulic jack and separating the coupling of the work line and then separated from the left and right around the hinge portion to separate the work line from the structure.

이와 같은 본 발명은 작업선에서 직접 케이슨을 침설함으로써 별도의 작업선 없이 간편하게 케이슨을 침설할 수 있고, 작업선을 수면으로부터 일정 높이까지 상 승시킴으로써 파랑(波浪), 풍향 등에 관계없이 작업을 할 수 있으며, 작업선이 분리/결합되어 구조물로부터 용이하게 이탈되는 효과를 가지게 되는 것이다.In the present invention, by immersing the caisson directly from the working ship, it is possible to immerse the caisson easily without a separate working ship, and can work regardless of the wave or wind direction by raising the working ship to a certain height from the surface. And, the work line is separated / combined to have an effect that is easily separated from the structure.

수중 건식 구조물, 작업선, 말뚝기초, 작업기초Underwater dry structures, work ships, pile foundations, work foundations

Description

수중 건식 구조물 시공방법 및 그 기능성 작업선{Under Water Dry Structure Construction Method and Functional Working Ship}Underwater Dry Structure Construction Method and Functional Working Ship

도1은 본 발명의 기능성 작업선을 나탸낸 평면도.1 is a plan view showing a functional working line of the present invention.

도2는 본 발명 기능성 작업선의 다른 실시예를 나타낸 평면도.Figure 2 is a plan view showing another embodiment of the functional working line of the present invention.

도3은 본 발명 기능성 작업선의 요부를 나타낸 분해사시도.Figure 3 is an exploded perspective view showing the main portion of the functional working line of the present invention.

도4는 본 발명 수중 건식 구조물 시공방법의 흐름도.4 is a flowchart of the method for constructing a dry structure underwater in the present invention.

도5는 본 발명 수중 건식 구조물 시공방법의 다른 실시예를 나타낸 흐름도.Figure 5 is a flow chart showing another embodiment of the underwater dry structure construction method of the present invention.

도6a는 본 발명 제2유압잭으로 지지파일을 하강시키기 위해 고정된 상태를 나타낸 단면도.Figure 6a is a cross-sectional view showing a fixed state for lowering the support pile with the second hydraulic jack of the present invention.

도6b는 본발명 제2유압잭으로 지지파일을 하강시키는 상태를 나타낸 단면도.Figure 6b is a cross-sectional view showing a state of lowering the support pile with the second hydraulic jack of the present invention.

도6c는 본 발명 제2유압잭으로 지지파일을 하강시킨 상태를 나타낸 단면도.Figure 6c is a cross-sectional view showing a state in which the support pile is lowered by the second hydraulic jack of the present invention.

도7a는 본 발명 케이슨을 제1유압잭으로 고정하기 전 상태를 나타낸 단면도.Figure 7a is a sectional view showing a state before fixing the caisson of the present invention with the first hydraulic jack.

도7b는 본 발명 제1유압잭 작동으로 케이슨을 고정시킨 상태를 나타낸 단면도.Figure 7b is a sectional view showing a state in which the caisson is fixed by the first hydraulic jack operation of the present invention.

도8a는 본 발명의 말뚝기초를 이용한 수중 건식 구조물시공방법을 나타낸 것으로써, 작업선이 작업현장으로 이동한 상태를 나타낸 단면도.Figure 8a is a cross-sectional view showing a state in which the work line moved to the work site showing the construction method of underwater dry structure using the pile foundation of the present invention.

도8b는 제2유압잭으로 지지파일의 시공 및 작업선을 상승시켜 말뚝기초를 시 공하는단면도.Figure 8b is a cross-sectional view of constructing the pile foundation by raising the construction and work line of the support pile with a second hydraulic jack.

도8c는 케이슨을 조립하여 침설하는 단면도.Figure 8c is a cross-sectional view of the caisson assembled.

도8d는 케이슨을 지지하고 토사층의 제거와 평탄작업 후 레벨링 콘크리트를 타설, 양생한 단면도.Fig. 8D is a cross-sectional view of the caisson, which pours leveling concrete after removing and leveling the soil layer;

도8e는 케이슨 하부에 팽창튜브를 설치하여 외수의 유입을 차단하고 배수시킨 후 말뚝 두부를 정리한 단면도.Figure 8e is a cross-sectional view of the pile head after installing the expansion tube in the lower caisson to block the inflow and drainage of external water.

도8f는 교각 구조물을 시공한 단면도.Figure 8f is a cross-sectional view of the construction of the bridge structure.

도8g는 팽창튜브의 철거하고 외수를 유입시킨 후 케이슨을 인양한 단면도.Figure 8g is a cross-sectional view of lifting the caisson after the removal of the expansion tube and the inflow of external water.

도8h는 제2유압잭을 작동시켜 작업선을 하강시킨 단면도.Fig. 8H is a sectional view of lowering the work line by operating the second hydraulic jack.

도8i는 지지파일 해체하고 작업선을 분리 이탈시킨 단면도.Figure 8i is a cross-sectional view of dismantling the support pile and separating the work line.

도9는 본 발명의 직접기초를 이용한 수중 건식 구조물시공방법을 나타낸 것으로써, 작업선이 작업현장으로 이동한 상태를 나타낸 단면도.Figure 9 is a cross-sectional view showing a state in which the working ship moved to the work site showing the construction method of underwater dry structure using the direct foundation of the present invention.

도9b는 지지층에 지지파일을 시공하고, 작업선을 상승시켜 하상 토사층을 준설한 단면도.Fig. 9B is a sectional view in which a support pile is installed on a support layer, and a working soil is raised to dredge a bottom soil layer.

도9c는 암석층의 굴착, 평탄 작업 후 레벨링 콘크리트를 타설, 양생한 단면도.Fig. 9C is a cross-sectional view of pouring and leveling concrete after excavation and flattening of a rock layer.

도9d는 케이슨 조립 후 바라스트 탱크에 물 주입하여 침설한 단면도.Figure 9d is a cross-sectional view of the ballast tank after the caisson assembly by injecting water.

도9e는 지지층에 수밀재를 압착시켜 외수를 차단하고, 케이슨 내부를 배수한 단면도.Fig. 9E is a cross-sectional view of the watertight material pressed against the support layer to block external water and draining the interior of the caisson.

도9f는 암석층 굴착 및 평탄하게 고른 단면도.9F illustrates rock layer excavation and flattened cross-sectional view.

도9g는 구조물을 시공한 단면도.Figure 9g is a cross-sectional view of the construction of the structure.

도9h는 바라스트 탱크의 물을 배수하고 케이슨을 인양 및 해체한 단면도.Fig. 9H is a cross-sectional view of draining water of the barast tank and lifting and disassembling the caisson.

도9i는 유압잭으로 작업선을 하강시킨 후 지지파일을 해체하여 작업선을 분리, 이탈시킨 단면도.Figure 9i is a cross-sectional view of separating and leaving the work line by dismantling the support pile after lowering the work line with a hydraulic jack.

도10a는 작업선으로 구조물을 시공하는 상태의 평면도.Figure 10a is a plan view of a state of constructing a structure with a working line.

도10b는 작업선을 분리시킨 상태의 평면도.Fig. 10B is a plan view of a state in which the work line is separated.

도10c는 작업선을 이탈시킨 상태의 평면도.Fig. 10C is a plan view of the state where the work line is separated.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10: 작업선 11: 케이슨 삽입공10: Workline 11: caisson insertion hole

12: 제1유압잭 13: 받침대12: 1st hydraulic jack 13: pedestal

14: 붐 15: 지지파일14: Boom 15: Support pile

16: 고정대 17: 고정핀16: holder 17: fixing pin

18: 통공 20: 지지대18: through air 20: support

21: 제2유압잭 22: 붐21: 2nd Hydraulic Jack 22: Boom

23: 연결대 24: 연결핀23: connecting rod 24: connecting pin

25: 통공 30: 힌지부25: through hole 30: hinge part

31: 고정프레임 32: 결합부31: fixed frame 32: coupling portion

40; 지지판 41: 말뚝기초 시공장비40; Support plate 41: pile foundation construction equipment

42: 레벨링 콘크리트 43: 팽창튜브42: leveling concrete 43: expansion tube

44: 바라스트 탱크44: Barast Tank

본 발명은 수중 건식 구조물 시공방법 및 그 기능성 작업선에 관한 것으로, 특히 수중에 케이슨을 침설하는 기능성 작업선을 수면으로부터 일정 높이만큼 상승시켜 케이슨 침설 작업을 안전하게 진행하고, 이 작업선의 일측을 중심으로 벌려 구조물로부터 편리하게 이탈시키는 수중 건식 구조물 시공방법 및 그 기능성 작업선에 관한 것이다.The present invention relates to a method for constructing an underwater dry structure and a functional working line thereof, and in particular, a functional working line for submerging the caisson in water is raised by a certain height from the surface to safely proceed with the caisson subsidence work, and focuses on one side of the working line. The present invention relates to a method for constructing an underwater dry structure which is easily separated from an open structure, and a functional work line thereof.

주지하는 바와 같이 수중에 교각을 설치하거나 대형 구조물을 시공하기 위해서는 육상에서 케이슨을 제작하여 이를 예인선으로 옮겨 싣고서 케이슨을 설치하고자 하는 장소로 이동하게 된다.As is well known, in order to install a pier or construct a large structure underwater, a caisson is manufactured on land, and it is moved to a tugboat and moved to a place where the caisson is to be installed.

이러한 케이슨을 수중에 설치하기 위해서는 케이슨을 잡아주는 예인선과 함께 수중에 침설되는 케이슨이 수직 상태를 유지되도록 그 주변에 다수의 작업선을 배치시켜 이러한 작업선으로부터 케이슨에 연결된 로프 등으로 잡아주어 케이슨이 움직이지 않고, 수직상태를 계속 유지되게 한다.In order to install these caissons underwater, a number of working ships are arranged around them so that the caissons submerged in the water along with the tugboat holding the caissons are held vertically, and the caissons are held by ropes connected to the caissons. It doesn't move and keeps upright.

이와 같이 케이슨의 설치 또는 구조물 시공시에 작업현장에 별도의 작업선을 투입하여 작업을 진행하여야 하는 불편함이 있고, 지지층에 세워진 케이슨의 규격이 작아 전도되거나 부등침하가 발생하는 경우 별도의 지지 시설을 설치하여야 하는 불편함이 있었으며, 이로 인하여 안전사고가 발생하는 문제점이 있고, 케이슨 설치 작업 및 구조물 시공시에 파랑(波浪)에 의해 작업이 지연되는 어려움이 있었 다.As such, there is inconvenience of having to put a separate work line into the work site when installing caissons or constructing a structure, and if the caissons set on the support floor are small and fall down or have an uneven settlement, a separate supporting facility There was an inconvenience to install the, there is a problem that a safety accident occurs, there was a difficulty in delaying the work due to the wave (wave) during the caisson installation work and construction of the structure.

상기와 같은 문제점을 해결하기 위하여 본 발명은 수중에 설치되는 케이슨의 견고한 설치가 가능하며, 별도의 작업선이 불필요하고, 파랑에 의한 작업 지연을 최소화하는 수중 건식 구조물 시공방법 및 그 기능성 작업선을 제공하는 데 있다.In order to solve the above problems, the present invention can be installed firmly in the caisson to be installed in the water, there is no need for a separate work line, the construction method of underwater dry structure and its functional work line to minimize the work delay caused by blue To provide.

상기와 같은 목적을 달성하기 위하여 본 발명은 원형, 각형 등의 형상에 따라 그 중앙에 케이슨 삽입공을 형성하고, 지지파일의 측면에서 지지파일을 지지하는 제1유압잭과, 그 상면에 지지파일을 상승,하강시키는 제2유압잭이 설치된 작업선을 예인선으로 작업현장에 이동시키는 단계와, 제2유압잭의 작동으로 토사층(암석층)에 지지파일을 견고하게 고정시키는 단계와, 또한 제2유압잭의 작동으로 고정된 지지파일을 따라 작업선을 수면으로부터 일정 높이만큼 상승시키는 단계와, 작업선에서 케이슨을 조립하여 상기 케이슨 삽입공으로 케이슨을 침설시켜 제1유압잭으로 이를 견고하게 지지하는 단계와, 케이슨 내부에 교각 등의 구조물을 시공한 다음 제2유압잭으로 케이슨을 부상시켜 이를 분리하는 단계와, 제2유압잭을 작동시켜 지지파일로부터 작업선을 수면으로 하강시키는 단계와, 이후 토사층(암석층)에 고정된 지지파일을 제2유압잭의 작동으로 인양시키는 단계와, 작업선의 결합부를 분리시킨 후 힌지부를 중심으로 좌우 분리시켜 구조물로부터 작업선을 이탈시키는 단계로 이루어지는 것을 수중 건식 구조물 시공방법을 제안한다.In order to achieve the above object, the present invention is to form a caisson insertion hole in the center according to the shape of the circular, square, etc., the first hydraulic jack for supporting the support pile from the side of the support pile, and the support pile on the upper surface Moving the work line provided with the second hydraulic jack to ascend and descend to the work site by a towboat; and firmly fixing the support pile to the soil layer (rock layer) by the operation of the second hydraulic jack, and also by the operation of the second hydraulic jack. Raising the work line along the fixed support pile from the surface by a certain height, Assembling the caisson from the work line to immerse the caisson with the caisson insertion hole to firmly support it with the first hydraulic jack, and pier inside the caisson After constructing the back structure, lifting the caisson with the second hydraulic jack and separating it, and operating the second hydraulic jack to remove the support pile from the supporting pile. Lowering the upline to the surface, then lifting the supporting pile fixed to the soil layer (rock layer) by the operation of the second hydraulic jack, separating the coupling part of the work line, and separating the work line from the structure by separating the work line from the structure. It proposes the construction method of underwater dry structure consisting of the step of leaving.

또한, 케이슨의 조립 및 분리가 가능한 작업공간을 가지는 크기로 이루어지 고 그 중앙에 케이슨의 형상에 따라 형성된 케이슨 통공과, 그 길이방향을 따라 분리/결합되고 일측에는 회전 가능하게 설치된 힌지부와, 타측에는 볼트와 너트로 분리/결합되게 형성된 결합부와, 그 상면에 케이슨의 침설 후 케이슨을 지지하도록 설치된 제1유압잭과, 지지파일을 하상에 고정시킨 후 지지파일을 따라 수면으러부터 일정 높이만큼 승하강되게 설치된 제2유압잭을 설치한 기능성 작업선을 제안한다.In addition, the caisson through hole is formed in the size having a work space that can be assembled and detached, according to the shape of the caisson in the center, the hinge portion separated / coupled along the longitudinal direction and rotatably installed on one side, On the other side, the coupling part formed to be separated / coupled by bolts and nuts, the first hydraulic jack installed to support the caisson after the caisson subsidence on the upper surface, and the support pile fixed to the lower side and then along the support pile to a certain height from the water surface We propose a functional work boat on which a second hydraulic jack is installed.

이와 같은 본 발명은 별도의 작업선 없이 작업선에서 케이슨을 설치함으로써 케이슨을 간편하게 설치하고, 작업선이 수상에 견고하게 위치한 상태에서 작업이 이루어짐으로써 파랑(波浪)에 의해 작업의 지연 없이 케이슨 설치 작업을 신속하게 작업할 수 있게 되는 것이다.In the present invention, the caisson is installed easily by installing the caisson from the working ship without a separate working ship, the work is carried out in a state where the working ship is firmly positioned in the water, the installation of the caisson without delay by the blue wave (wave) Will be able to work quickly.

이하, 본 발명의 실시예를 도면을 참조하여 설명한다.Hereinafter, embodiments of the present invention will be described with reference to the drawings.

도시된 바와 같이, 케이슨(1)의 형태에 따라 건조(建造)된 기능성 작업선(10)을 예인선으로 작업현장에 이동하는 단계와, 작업선(10) 상면에 설치된 유압잭(21)을 작동시켜 지지층(2)에 지지파일(15)을 항타하여 이를 견고하게 고정하는 단계와, 이 지지파일(15)에 결합된 유압잭(21)으로 작업선(10)을 수면으로부터 일정 높이까지 끌어올려 고정하는 단계와, 시공하고자 하는 구조물에 적합한 크기의 케이슨(1)을 조립하여 이를 지지층(2)에 견고하게 침설시키는 단계와, 이러한 케이슨(1) 내부에 시공하고자 하는 구조물을 시공한 후 상기 케이슨(1)을 인양시켜 이를 해체하는 단계와, 작업선(10)이 수면에 닿도록 유압잭(21)으로 작업선(10)을 하강시키는 단계와, 작업선(10)으로부터 지지파일(15)을 뽑아 올린 후 작업선(10)의 결 합부를 해제하여 구조물로부터 작업선(10)을 이탈하는 단계로 이루어진다.As shown in the figure, the step of moving the functional working ship 10 constructed in accordance with the shape of the caisson 1 to the work site with a tug, and by operating the hydraulic jack 21 installed on the upper surface of the work ship 10 Driving the support pile 15 to the support layer 2 and fixing the support pile 15 firmly, and pulling the work line 10 up to a predetermined height from the surface by a hydraulic jack 21 coupled to the support pile 15. And assembling a caisson 1 having a size suitable for the structure to be constructed and immersing it firmly in the support layer 2, and after constructing the structure to be constructed inside the caisson 1, the caisson (1). ) Lifting and dismantling it, lowering the working line 10 with the hydraulic jack 21 so that the working line 10 touches the water surface, and pulling up the support pile 15 from the working line 10. After the connection of the work line 10 is released to the work line (1) 0).

또한, 작업선(10)은 일측에 돌출된 고정프레임(31)에 회전 가능한 힌지부(30)를 결합하고, 타측에 돌출되어 볼트,너트로 체결되는 결합부(32)를 형성하여 작업선(10)이 힌지부(30)를 중심으로 회전시켜 분리/결합되어진다.In addition, the work line 10 is coupled to the rotatable hinge portion 30 to the fixed frame 31 protruding on one side, and to form a coupling portion 32 is protruded to the other side and fastened with bolts, nuts (work line ( 10) is rotated about the hinge portion 30 is separated / combined.

도시된 바와 같이 본 발명의 기능성 작업선(10)은 일정 두께를 가지는 평탄한 면을 가지고, 도 1 내지 도3에 도시된 바와 같이 그 중앙에 원형 또는 각형 등 삽입되는 케이슨(1)의 크기 보다 큰 크기로 이루어지는 케이슨 삽입공(11)을 형성하고, 그 외측에 침설되는 케이슨(1)을 잡아주는 유압잭(12)을 설치한다.As shown, the functional working line 10 of the present invention has a flat surface having a predetermined thickness, and larger than the size of the caisson 1 inserted into the center or the like, as shown in FIGS. 1 to 3. A caisson insertion hole 11 having a size is formed, and a hydraulic jack 12 for holding the caisson 1 submerged outside thereof is provided.

이러한 유압잭(12)은 작업선(10)의 상면에 받침대(13)를 견고하게 고정시키고, 그 상면에 붐(14)이 설치된 유압잭(12)을 고정하며, 상기 붐(14)은 유압잭(12)의 작동에 따라 수평 이동되어 케이슨(1)의 외경에 밀착되어 케이슨(1)을 견고하게 지지하도록 설치된다.The hydraulic jack 12 firmly secures the base 13 to the upper surface of the work line 10, and fixes the hydraulic jack 12 provided with the boom 14 on the upper surface thereof, and the boom 14 is the hydraulic jack 12. It moves horizontally in accordance with the operation of the) to be in close contact with the outer diameter of the caisson (1) is installed to firmly support the caisson (1).

이와 함께 작업선(10)에는 지지층(2)에 지지파일(15)을 고정하는 다수개 고정대(16)를 설치하고, 상기 지지파일(15)에는 일정한 간격으로 고정핀(17)과 연결핀(24)이 삽입되는 통공(15a)을 형성하며, 이 고정대(16)는 작업선(10)의 상면에 고정핀(17)이 삽입되는 통공(18)을 형성한다.Along with this, the work line 10 is provided with a plurality of holders 16 for fixing the support pile 15 to the support layer 2, the support pile 15 is fixed pin 17 and the connecting pin at regular intervals ( 24 is formed to form a through hole (15a), the fixing rod 16 forms a through hole 18 into which the fixing pin 17 is inserted into the upper surface of the working line (10).

또한, 고정대(16)와 함께 작업선(10)의 상면에 지지대(20)를 다수개 고정하고, 이의 상면에 유압잭(21)의 작동에 따라 수직 이동하는 붐(22)을 설치하며, 그 상부에 연결대(23)를 설치하고, 그 연결대(23)에는 연결핀(24)이 삽입되는 통공(25)을 형성한다.In addition, a plurality of supports 20 are fixed to the upper surface of the work line 10 together with the fixing table 16, and the upper surface thereof is provided with a boom 22 that vertically moves in accordance with the operation of the hydraulic jack 21, the upper portion thereof A connecting rod 23 is installed at the connecting rod 23, and the connecting pin 23 forms a through hole 25 into which the connecting pin 24 is inserted.

이러한 고정대(16)와 지지대(20)는 작업선(10)을 고정하는 지지파일(15)을 설치하는 다수개의 개소에 설치된다.Such a support 16 and the support 20 are installed in a plurality of places to install the support pile 15 for fixing the work line 10.

이와 같은 작업선(10)은 그 길이방향의 중심으로 구조물의 시공 후 이를 양측으로 벌려 구조물로부터의 이탈되게 이등분 분할되고, 작업선(10)의 일측에는 고정프레임(31)을 돌출시켜 힌지부(30)를 결합하고, 타측에는 볼트, 너트로 체결되는 결합부(32)를 형성시켜 힌지부(30)를 중심으로 회전되어 분리/결합된다.The work line 10 is divided into two parts to be separated from the structure by opening it to both sides after the construction of the structure to the center of the longitudinal direction, one side of the work line 10 protrudes the fixing frame 31 to the hinge portion ( 30) is coupled to the other side by forming a coupling portion 32 is fastened with a bolt, nut is rotated about the hinge portion 30 is separated / coupled.

아울러, 도4, 도5에 도시된 바와 같이 본 발명의 수중 건식 구조물 시공방법을 말뚝기초를 이용한 시공방법과 직접기초를 이용한 시공방법에 따라 설명하기로 한다.In addition, as shown in Figures 4 and 5 will be described according to the construction method using the pile foundation and the construction method using the foundation of the underwater dry structure of the present invention.

먼저, 말뚝기초를 이용한 수중 건식 구조물 시공방법은 건조된 작업선(10)을 예인하여 도8a에서와 같이 구조물을 시공하고자 하는 작업현장으로 이동하고, 이러한 작업선(10)에는 케이슨(1)을 지지하는 유압잭(12)과, 지지파일(15)을 상승, 하강시키는 유압잭(21)이 설치된다(S100).First, the method for constructing an underwater dry structure using a pile foundation is towed the dried working ship 10 to the work site to be constructed as shown in Figure 8a, the caisson (1) to the work ship 10 A hydraulic jack 12 for supporting and a hydraulic jack 21 for raising and lowering the support pile 15 are provided (S100).

작업현장에 도착한 작업선(10)은 유압잭(21)을 이용하여 일정 길이를 가지는 지지파일(15)을 토사층(2)에 항타하여 이를 견고하게 고정시키고, 상기 지지파일(15)의 하부에는 지지파일(15)이 토사층(2)에 박은 상태에서 지지파일(15)과 토사층(2)이 밀착된 상태를 유지하기 위한 지지판(40)이 구비된다(S101).Working line 10 arrived at the work site is driven by the hydraulic jack 21 to support the support pile 15 having a certain length to the soil layer (2) to firmly fix it, the lower support of the support pile 15 In the state in which the pile 15 is embedded in the soil layer 2, the support plate 40 for maintaining the state in which the support pile 15 and the soil layer 2 are in close contact is provided (S101).

이후 도6에 도시된 바와 같이 작업선(10)에 설치된 유압잭(21)의 연결대(23)를 하강시킨 상태에서 지지파일(15)의 통공(15a)에 고정핀(17)을 끼우고 또한, 연결대(23)에 연결핀(24)을 끼워 고정시키며, 지지파일(15) 하강되게 고정핀(17)을 고정대(16)로부터 이탈시킨다.6 and then the fixing pin 17 is inserted into the through hole 15a of the support pile 15 while the connecting table 23 of the hydraulic jack 21 installed on the work line 10 is lowered. The connecting pin 24 is fixed to the connecting table 23, and the fixing pin 17 is detached from the fixing table 16 so as to lower the support pile 15.

이 상태에서 붐(22)을 하강시켜 지지파일(15)을 하강시키고, 다시 고정핀(17)으로 지지파일(15)을 고정시킨 후 붐(22)을 상승시켜 연결핀(24)을 고정시켜 붐(22)을 하강시키면서 반복적으로 지지파일(15)을 하강시켜 토사층(2)에 고정시킨다.In this state, the support pile 15 is lowered by lowering the boom 22, and after fixing the support pile 15 with the fixing pin 17, the boom 22 is raised to fix the connecting pin 24. While lowering the boom 22, the support pile 15 is repeatedly lowered and fixed to the soil layer 2.

이렇게 토사층(2)에 지지파일(15)의 고정이 완료되면 도8b와 같이 유압잭(21)은 상기의 과정과 반대로 지지파일(15)로부터 작업선(10)을 수면으로부터 일정 높이 상승시킨다(S102).When the fixing of the support pile 15 to the soil layer 2 is completed as shown in FIG. 8B, the hydraulic jack 21 raises the work line 10 from the surface of the support pile 15 by a predetermined height as opposed to the above process (S102). ).

이후 작업선(10)의 상부에 말뚝기초(3)를 시공하는 말뚝기초 시공장비(41)를 설치하여 암석층(4)에 말뚝기초(3)를 다수개 박게 된다(S103).After installing the pile foundation construction equipment 41 for constructing the pile foundation (3) on the upper part of the work line (10) will be a plurality of pile foundation (3) in the rock layer (4) (S103).

아울러 작업선(10)의 상면에서 케이슨(1)을 조립하여(S104) 도8c 및 도10에서와 같이 케이슨(1)을 침하시키게 되고, 케이슨(1)의 침하가 완료되면 작업선(10)의 상면에 설치된 유압잭(12)을 작동시켜 케이슨(1)이 움직이지 않도록 붐(14)으로 케이슨(1)을 지지한다(S105).In addition, assembling the caisson 1 from the upper surface of the work line 10 (S104) to sink the caisson 1 as shown in Figures 8c and 10, and when the immersion of the caisson 1 is completed, the work line 10 By operating the hydraulic jack 12 installed on the upper surface of the caisson (1) to support the caisson (1) by the boom 14 (S105).

또한, 케이슨(1) 내부의 바닥면이 고르도록 토사층(2)의 굴곡면을 제거하여 평탄하게 하고(S106), 이후 도8d에서와 같이 구조물 시공의 기초가 되는 레벨링 콘크리트(42)를 일정 두께로 타설하여 양생한다(S107).In addition, the curved surface of the soil layer 2 is removed and flattened so that the bottom surface of the caisson 1 is even (S106), and then, as shown in FIG. After curing by curing (S107).

이러한 케이슨(1) 하부에 도8e에서와 같이 팽창튜브(43)을 설치하고(S108), 상기의 팽창튜브(43)을 팽창시켜 케이슨(1)의 외부로부터 물이 유입되는 것을 차단하고, 이와 더불어 케이슨(1) 내부의 물을 빼는 배수작업을 하게 된다(S109).An expansion tube 43 is installed in the lower part of the caisson 1 as shown in FIG. 8E (S108), and the expansion tube 43 is expanded to block water from flowing from the outside of the caisson 1, and In addition, the drainage work to drain the water inside the caisson (1) is to be performed (S109).

이렇게 케이슨(1) 내부는 건식상태로 되고, 말뚝기초(3)의 상부를 정리하며(S110), 도8f에서와 같이 그 상부에 교각(5) 또는 구조물을 시공하게 된다(S111).Thus, the interior of the caisson 1 is in a dry state, arranging the upper portion of the pile foundation (S110), and as shown in Figure 8f to the pier (5) or to construct a structure (S111).

구조물의 시공이 완료되면 도8g에서와 같이 케이슨(1)으로부터 팽창튜브(43)를 철거하여 외수를 유입되게 하고(S112), 유압잭(12)을 작동시켜 케이슨(1)의 지지를 해제하여 케이슨(1)을 인양한 후 이를 해제하게 된다(S113).When the construction of the structure is completed, remove the expansion tube 43 from the caisson (1) as shown in Figure 8g to allow the inflow of fresh water (S112), by operating the hydraulic jack 12 to release the support of the caisson (1) caisson After lifting (1) it is released (S113).

이후 도8h에서와 같이 유압잭(21)을 작동시켜 지지파일(15)로부터 작업선(10)을 하강하게 되고(S114), 도8i에서와 같이 유압잭(21)을 작동시켜 토사층(2)에 고정된 지지파일(15)을 뽑아 올리며(S115), 작업선(10)의 결합부(32)를 해제시켜 구조물로부터 작업선(10)을 이탈시키게 된다(S116).Thereafter, as shown in FIG. 8H, the hydraulic jack 21 is operated to lower the work line 10 from the support pile 15 (S114), and as shown in FIG. 8I, the hydraulic jack 21 is operated to be fixed to the soil layer 2. Pulling up the support pile 15 (S115), by releasing the engaging portion 32 of the working line 10 is to leave the working line 10 from the structure (S116).

또한, 직접기초 시공방법에 의한 수중 건식 구조물 시공방법은 도9a에서와 같이 건조된 작업선(10)을 예인하여 작업현장으로 이동시키고(S200), 도9b에서와 같이 유압잭(21)을 이용하여 일정 길이를 가지는 지지파일(15)을 암석층(4)에 항타하여 이를 견고하게 고정시키고(S201), 이러한 지지파일(15)의 시공은 상기 말뚝기초를 이용한 시공방법과 동일하다.In addition, the method of construction of underwater dry structure by the direct foundation construction method is towed to the working site to dry the working ship 10 as shown in Figure 9a (S200), using a hydraulic jack 21 as shown in Figure 9b The support pile 15 having a predetermined length is firmly fixed to the rock layer 4 (S201), and the construction of the support pile 15 is the same as the construction method using the pile foundation.

이후 도9b에서와 같이 유압잭(21)을 작동시켜 작업선(10)을 수면으로부터 일정 높이까지 상승시키고(S202), 지지파일(15)이 시공된 하상 토사층을 준설하고(S203), 다시 암석층(4)을 굴착기로 굴착하여 구조물이 설치되는 작업면을 평탄하게 한다(S204).Thereafter, as shown in FIG. 9B, the hydraulic jack 21 is operated to raise the work line 10 to a certain height from the surface (S202), and the dredging soil soil layer on which the support pile 15 is constructed is dredged (S203), and the rock layer ( Excavating 4) with an excavator to flatten the working surface on which the structure is installed (S204).

이러한 암석층(4)에 도9c에서와 같이 구조물 시공의 기초가 되는 레벨링 콘크리트(42)를 타설하여 이를 양생하고(S205), 이후 도9d에서와 같이 작업선(10)의 상면에서 케이슨(1)을 조립하고, 바라스트 탱크(44) 내부에 물을 주입시켜 케이슨(1)을 침설시킨다(S206). The rock layer 4 is poured with leveling concrete 42, which is the basis for the construction of the structure, as shown in FIG. 9C, and cured it (S205), and then the caisson 1 on the upper surface of the work line 10 as shown in FIG. 9D. Assembling, injecting water into the ballast tank 44 to immerse the caisson (S206).

아울러 암석층(4)에 수밀재를 압착시켜 외수의 유입을 차단하고(S207), 도9e에서와 같이 모터 펌프(6)를 설치하여 케이슨(1) 내부의 물을 배수시키며(S208), 도9f에서와 같이 굴착기로 암석층(4)을 굴착하여 구조물이 시공되는 지면을 평탄하게 한다(S209).In addition, the watertight material is pressed to the rock layer 4 to block the inflow of external water (S207), and as shown in FIG. 9E, a motor pump 6 is installed to drain the water inside the caisson 1 (S208) and FIG. 9F. As in the excavation of the rock layer 4 with an excavator to flatten the ground on which the structure is constructed (S209).

이 상태에서 도9g에서와 같이 교각(5) 등의 구조물을 시공하여 양생이 완료되면(S210), 도9h에서와 같이 바라스트 탱크(44)로부터 물을 배수시키게 된다(S211).In this state, as shown in FIG. 9G, when the construction of the structure such as the piers 5 is completed (S210), water is drained from the ballast tank 44 as shown in FIG. 9H (S211).

이후 도9i에서와 같이 케이슨(1)을 인양하여 작업선(10)에서 해체하고(S212), 유압잭(21)을 작동시켜 지지파일(15)로부터 작업선(10)을 하강하게 되고(S213), 유압잭(21)을 작동시켜 암석층(4)에 고정된 지지파일(15)을 뽑아 올리며(S214), 도10에서와 같이 작업선(10)의 결합부(32)를 해제시켜 구조물로부터 작업선(10)을 이탈시키게 된다(S215).Then, as shown in FIG. 9i, the caisson 1 is lifted and dismantled from the work line 10 (S212), and the hydraulic jack 21 is operated to lower the work line 10 from the support pile 15 (S213). The hydraulic jack 21 is operated to pull up the support pile 15 fixed to the rock layer 4 (S214), and as shown in FIG. 10, by releasing the coupling portion 32 of the working line 10 from the working line from the structure. Departed from (10) (S215).

상기한 바와 같이 본 발명은 작업선에서 케이슨을 침설하면서 이를 유압잭으로 견고하게 지지시킴으로써 별도의 작업선 없이 간편하게 케이슨을 침설할 수 있고, 작업선에 설치된 유압잭으로 지지파일을 시공하여 유압잭으로 작업선을 수면으로부터 일정 높이까지 상승시킴으로써 파랑(波浪), 풍향 등에 관계없이 작업을 할 수 있으며, 작업선이 분리/결합되어 구조물로부터 용이하게 이탈되는 효과를 가지 게 되는 것이다.
As described above, the present invention can immerse the caisson easily without a separate working ship by steadily supporting the caisson in the working ship with a hydraulic jack, and by installing the support pile with the hydraulic jack installed on the working ship, the working ship with the hydraulic jack. By raising to a certain height from the surface of the water can work regardless of the wave (wave), wind direction, etc., the work line is separated / combined to have the effect of easily separated from the structure.

Claims (4)

원형, 각형 등의 형상에 따라 그 중앙에 케이슨 삽입공을 형성하고, 지지파일의 측면에서 지지파일을 지지하는 제1유압잭과, 그 상면에 지지파일을 상승,하강시키는 제2유압잭이 설치된 작업선을 예인선으로 작업현장에 이동시키는 단계와, 제2유압잭의 작동으로 토사층(암석층)에 지지파일을 견고하게 고정시키는 단계와, 제2유압잭의 작동으로 고정된 지지파일을 따라 작업선이 수면으로부터 일정 높이만큼 상승시키는 단계와, 작업선의 상면에서 케이슨을 조립하여 상기 케이슨 삽입공으로 케이슨을 침설시켜 제1유압잭으로 이를 견고하게 지지하는 단계와, 케이슨 내부에 교각 등의 구조물을 시공한 다음 제2유압잭으로 케이슨을 부상시켜 이를 분리하는 단계와, 제2유압잭을 작동시켜 지지파일로부터 작업선을 수면으로 하강시키는 단계와, 이후 토사층(암석층)에 고정된 지지파일을 제2유압잭의 작동으로 인양시키는 단계와, 작업선의 결합부를 분리시킨 후 힌지부를 중심으로 좌우 분리시켜 구조물로부터 작업선을 이탈시키는 단계로 이루어지는 것을 특징으로 하는 수중 건식 구조물 시공방법.Work vessel provided with a caisson insertion hole in the center of the circular or square shape, the first hydraulic jack for supporting the supporting pile from the side of the supporting pile, and the second hydraulic jack for raising and lowering the supporting pile on the upper surface thereof. Moving to the work site by the tugboat, and firmly fixing the support pile to the soil layer (rock layer) by the operation of the second hydraulic jack, and the work line is fixed from the surface along the support pile fixed by the operation of the second hydraulic jack. Ascending by height, and assembling the caisson from the upper surface of the working ship to immerse the caisson with the caisson insertion hole to firmly support it with the first hydraulic jack, and to construct a structure such as a pier inside the caisson and then to the second hydraulic jack Floating the caisson to separate it, activating the second hydraulic jack to lower the working line from the support pile to the surface, and then Lifting the supporting pile fixed to the four layers (rock layer) by the operation of the second hydraulic jack, and separating the coupling part of the work line and separating the work line from the structure by separating the work line from the left and right around the hinge. Dry structure construction method. 청구항1에 있어서,The method according to claim 1, 작업선이 수면으로부터 상승시킨 단계 이후에 작업선에 말뚝기초를 시공하는 장비를 설치하여 말뚝기초을 고정시키는 단계와, 조립된 케이슨을 토사층에 지지하는 단계와, 케이슨의 하상으로부터 토사를 제거시키며 이 하상을 굴착기로 평탄하 게 고르는 단계와, 케이슨 하상에 소정 크기의 레벨링 콘크리트를 타설하여 이를 양생시키는 단계와, 케이슨 내부로 외수의 유입을 차단하는 팽창튜브를 케이슨 하부에 설치하는 단계와, 이 팽창튜브를 팽창시켜 케이슨 내부로 외수의 유입을 차단시키고 케이슨 내부에 수용된 물을 배수시켜 건식하는 단계와, 말뚝기초의 두부를 정리하여 그 상면에 교각 등의 설치하고자 하는 구조물을 시공하는 단계와, 외수의 유입을 차단하는 팽창튜브를 철거하여 외수를 유입시키는 단계를 포함하는 것을 특징으로 하는 수중 건식 구조물 시공방법.After the work line has been raised from the surface, installing the pile foundation on the work line to fix the pile foundation, supporting the assembled caisson on the soil layer, and removing the soil from the caisson bed. Flattening with an excavator, placing a leveling concrete of a predetermined size on the bottom of the caisson to cure it, and installing an expansion tube at the bottom of the caisson to block the inflow of external water into the caisson, and the expansion tube To expand and block the inflow of external water into the caisson, drain the water contained in the caisson to dry it, and to arrange the head of the pile foundation to construct a structure to be installed such as a piers on the upper surface, and Demolishing the expansion tube that blocks the inflow of the external water; Underwater dry structure construction method. 청구항1에 있어서,The method according to claim 1, 작업선이 수면으로부터 상승시킨 단계 이후에 하상으로부터 토사층을 준설하는 단계와, 이 토사층 하부의 암석층을 굴착기로 굴착하여 암석층을 평탄하게 고르는 단계와, 암석층에 소정 크기의 레벨링 콘크리트를 타설하여 양생시키는 단계와, 조립된 케이슨의 바라스트 탱크에 물을 주입하여 침설하는 단계와, 케이슨에 수밀재를 압착하여 외수의 유입을 차단하는 단계와, 케이슨 내부의 물을 배수시키는 단계와, 이후 일정 깊이로 암석층을 굴착기로 굴착하여 이를 평탄하게 고르는 단계와, 지반암 상면에 시공하고자 하는 교각 등의 구조물을 시공하는 단계와, 바라스트 탱크로부터 물을 배수시키는 단계를 포함하는 특징으로 하는 수중 건식 구조물 시공방법.Dredging the soil layer from the bottom after the work line is lifted from the surface, excavating the rock layer under the soil layer with an excavator to flatten the rock layer, and pouring and curing a leveling concrete of a predetermined size in the rock layer. And, injecting water into the assembled caisson barast tank, immersing, squeezing the watertight material into the caisson to block the inflow of external water, draining the water inside the caisson, and then rock layer to a predetermined depth. A method of constructing an underwater dry structure comprising the steps of excavating with an excavator to flatten it, constructing a structure such as a pier to be installed on the upper surface of the ground rock, and draining water from the ballast tank. 케이슨의 조립 및 분리가 가능한 작업공간을 가지는 크기로 이루어지고 그 중앙에 케이슨의 형상에 따라 형성된 케이슨 삽입공과, 그 길이방향을 따라 분리/결합되고 일측에는 회전 가능하게 설치된 힌지부와, 타측에는 볼트와 너트로 분리/결합되게 형성된 결합부와, 그 상면에 케이슨의 침설 후 케이슨을 지지하도록 설치된 제1유압잭과, 지지파일을 하상에 고정시킨 후 지지파일을 따라 수면으로부터 일정 높이만큼 승하강되게 설치된 제2유압잭으로 이루어진 것을 특징으로 하는 기능성 작업선.A caisson insertion hole formed in a size having a working space for assembling and detaching the caisson and formed in the center thereof according to the shape of the caisson, a hinge part separated / coupled along the longitudinal direction and rotatably installed at one side, and a bolt at the other side. A coupling part formed to be separated / coupled with a nut and a first hydraulic jack installed to support the caisson after immersion of the caisson on the upper surface thereof, and the support pile is fixed on the lower side, and installed up and down by a predetermined height from the water along the support pile. Functional working ship, characterized in that consisting of a second hydraulic jack.
KR1020040097038A 2004-11-24 2004-11-24 Under Water Dry Structure Construction Method and Functional Working Ship KR100617950B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040097038A KR100617950B1 (en) 2004-11-24 2004-11-24 Under Water Dry Structure Construction Method and Functional Working Ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040097038A KR100617950B1 (en) 2004-11-24 2004-11-24 Under Water Dry Structure Construction Method and Functional Working Ship

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0033609U Division KR200382622Y1 (en) 2004-11-26 2004-11-26 Functional Working Ship for Under Water Dry Structure

Publications (2)

Publication Number Publication Date
KR20060057851A KR20060057851A (en) 2006-05-29
KR100617950B1 true KR100617950B1 (en) 2006-08-29

Family

ID=37153113

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040097038A KR100617950B1 (en) 2004-11-24 2004-11-24 Under Water Dry Structure Construction Method and Functional Working Ship

Country Status (1)

Country Link
KR (1) KR100617950B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100916749B1 (en) * 2007-08-31 2009-09-14 (주)힘틀 Lifter
KR100973090B1 (en) * 2009-11-26 2010-07-30 (주) 선암기술연구소 Construction method and bridge safeguard for vessel guidance apparatus
KR101247754B1 (en) 2010-08-31 2013-03-25 삼성중공업 주식회사 Elevating system for leg and wind turbine installation vessel with the same
KR101540519B1 (en) * 2013-11-06 2015-07-30 현대건설주식회사 Maintenance apparatus for underwater tidal current generator
KR101576504B1 (en) * 2015-10-26 2015-12-21 에스앤에스이앤지 주식회사 Barge having jackup device

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101247753B1 (en) * 2010-08-31 2013-03-25 삼성중공업 주식회사 Elevating system for leg and wind turbine installation vessel with the same
KR101050824B1 (en) * 2011-01-31 2011-07-20 혜림엔지니어링(주) Pier constructing method for expanding using oscillator on brideg expanding of upper part over water
BE1024096B1 (en) * 2013-10-29 2017-11-14 Baggerwerken Decloedt En Zoon N.V. DEVICE AND METHOD FOR APPLYING TO A UNDERWATER FLOOR OF A LOW MATERIAL WITH PRIOR DETERMINED LEVEL LEVEL
CN104787706A (en) * 2015-04-09 2015-07-22 江苏华夏重工有限公司 Positioning pile lifting system
CN113562140A (en) * 2021-07-23 2021-10-29 舟山长宏国际船舶修造有限公司 Wood pier pressing tool

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100916749B1 (en) * 2007-08-31 2009-09-14 (주)힘틀 Lifter
KR100973090B1 (en) * 2009-11-26 2010-07-30 (주) 선암기술연구소 Construction method and bridge safeguard for vessel guidance apparatus
KR101247754B1 (en) 2010-08-31 2013-03-25 삼성중공업 주식회사 Elevating system for leg and wind turbine installation vessel with the same
KR101540519B1 (en) * 2013-11-06 2015-07-30 현대건설주식회사 Maintenance apparatus for underwater tidal current generator
KR101576504B1 (en) * 2015-10-26 2015-12-21 에스앤에스이앤지 주식회사 Barge having jackup device

Also Published As

Publication number Publication date
KR20060057851A (en) 2006-05-29

Similar Documents

Publication Publication Date Title
JP5057223B2 (en) Temporary wall construction method using steel segments
KR100617950B1 (en) Under Water Dry Structure Construction Method and Functional Working Ship
US4063426A (en) Three column tower
KR100714179B1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
CN100535264C (en) Steel boxed cofferdam and recovery method thereof
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
KR20140058951A (en) Caisson tube water-tight structure and under water structure construction method for soft ground
KR200382622Y1 (en) Functional Working Ship for Under Water Dry Structure
KR100733082B1 (en) Device of Bridge Pier Mould Construction and methed thereof
JPS58143023A (en) Caisson for pile supporting type breakwater
JP4260448B2 (en) Connection method and structure of submerged shaft and horizontal shaft
JP2001348888A (en) Method and device for constructing underwater foundation structure
KR200404677Y1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
KR100556302B1 (en) Caisson Installed Support Means and Construction Method of Underwater Structure Using It
KR100621410B1 (en) Dry Construction Method of Underwater Structure Using Watertight Caisson
JP2004190374A (en) Soft ground improving method and soft ground improving unit
KR101154623B1 (en) Device for constructing pier in the water and pier constructing method using the same
JPS6143493B2 (en)
KR20020081530A (en) Well form for the base operation of pier and it's operation method
KR101158035B1 (en) caisson and construction method of underwater structure using it
JP2001317060A (en) Construction method for underwater foundation
KR100581403B1 (en) Method for constructing for a soft-ground breakwater
KR20080065207A (en) A direct base construction method of underwater concrete using a hollow cylindrical steel mold having a buoyancy
CN113605465B (en) Prestress tensioning structure and method for anti-floating construction
CN216007009U (en) A auxiliary device for foundation ditch precipitation

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110822

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20120823

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee