JPS6143493B2 - - Google Patents

Info

Publication number
JPS6143493B2
JPS6143493B2 JP14372782A JP14372782A JPS6143493B2 JP S6143493 B2 JPS6143493 B2 JP S6143493B2 JP 14372782 A JP14372782 A JP 14372782A JP 14372782 A JP14372782 A JP 14372782A JP S6143493 B2 JPS6143493 B2 JP S6143493B2
Authority
JP
Japan
Prior art keywords
steel plate
cell
plate cell
underwater
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14372782A
Other languages
Japanese (ja)
Other versions
JPS5934332A (en
Inventor
Akira Sano
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP14372782A priority Critical patent/JPS5934332A/en
Publication of JPS5934332A publication Critical patent/JPS5934332A/en
Publication of JPS6143493B2 publication Critical patent/JPS6143493B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • E02D23/10Caissons filled with compressed air

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)

Description

【発明の詳細な説明】 本発明は、橋梁基礎、海洋工事など、水中にコ
ンクリート構造物を施工する際に用いられる潜凾
工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a submerged canopy construction method used when constructing concrete structures underwater, such as bridge foundations and marine construction.

この種の工法としては、オープンケーソン工
法、ニユーマチツクケーソン工法、鋼管失板井筒
工法などが知られている。これらの工法の中でニ
ユーマチツクケーソン工法、オープンケーソン工
法は上部構造が大規模な荷重の場合に多く適用さ
れる。とくに、水深の大きい河川、海中や波浪の
生ずる場所などで締切工費が著しく高い場合、ケ
ーソンを曵航し、つり下げて施工できる。このう
ち、オープンケーソン工法は地盤条件のよい場合
に適用することができ、ニユーマチツクケーソン
工法に比べて低コストであるが、玉石層など、沈
設に際して障害物のある場合には不適であり、水
中でのコンクリート構造物施工には条件がきびし
い。この点、ニユーマチツクケーソン工法では、
高気圧下ではあるが、ドライで作業でき、施工が
確実であり、工程が立てやすい長所がある。しか
し、水中施工であるため築島し、あるいは仮締切
りするなどの仮設備を必要とする。
Known construction methods of this type include the open caisson construction method, the new-machine caisson construction method, and the steel pipe lost plate well construction method. Among these construction methods, the new caisson construction method and the open caisson construction method are often applied when the superstructure is subject to large-scale loads. In particular, when the cost of cofferdam construction is extremely high, such as in deep rivers, underwater areas, or areas where waves occur, the caisson can be towed and suspended for construction. Among these, the open caisson method can be applied when the ground conditions are good and is lower cost than the new caisson method, but it is unsuitable when there are obstacles during sinking, such as a layer of cobblestones. The conditions for constructing concrete structures underwater are severe. In this regard, with the new caisson construction method,
Although it is under high pressure, it has the advantage of being able to work dry, ensuring reliable construction, and making the process easy to set up. However, because it is underwater construction, temporary facilities such as building an island or temporary cofferdams are required.

本発明は上記事情にもとづいてなされたもの
で、筒状の鋼板セルを水中地盤に打設し、上蓋を
取り付け気密状態とした後、内部気圧を水深圧以
上にしたドライの状態を保ちつつ、水中基礎の施
工を行うことにより、大がかりな仮設備を不要と
し、作業工程の短縮を計るなどの利益がある潜凾
工法を提供しようとするものである。
The present invention was made based on the above circumstances, and after driving a cylindrical steel plate cell into underwater ground and attaching a top cover to make it airtight, while maintaining a dry state with the internal pressure above the water depth pressure, By constructing an underwater foundation, we aim to provide a submerged construction method that eliminates the need for large-scale temporary equipment and has the advantage of shortening the work process.

以下、本発明の工法を基礎杭打設と併用した実
施例について図面を参照しつつ具体的に説明す
る。先づ、施工すべき水中地盤に対して、コンク
リート杭などの基礎杭1の打設を行う(第1図参
照)。次に筒状の鋼板セル2を曵航、吊持して、
施工場所にもたらし、鋼板セル2上端に設けたフ
レーム3に設置したバイブロハンマー4で、上記
鋼板セル2を打設し、根入れを行う(第2図参
照)。この場合、沈設の平衡を保つため、上記バ
イブロハンマーは互いに連通されるように連動装
置を設けるとよい。次に、鋼板セル2内で所要の
掘削を行い、デイープウエル5を設置した後、均
しコンクリートAを水中で施工する(第3図参
照)。次に陸上にて予め構成されたフーチングの
鉄筋または鉄骨Bをクレーン船にて上記コンクリ
ートA上に設置する(第4図参照)。そして、上
記鋼板セル2に対して蓋6およびロツクを取付け
る(第5図参照)。この状態で、鋼板セル2内は
大気と遮断されるので、デイープウエル5で排水
を開始した後、コンプレツサなどでセル2内圧を
上昇させ水深圧に対応させつつ、セル2内の水を
抜く(第6図参照)。これによつて、セル2内は
ドライになる。次にフーチングコンクリートCを
施工し(第7図参照)、立上りコンクリートDを
施工する(第8図参照)。次にセル2内部に注水
し、内部圧力を常圧にし、デイープウエル排水を
中止する(第9図参照)。そして、最後にフーチ
ング上部より鋼板セル2を切り離し、鋼板セル2
および蓋6などをクレーン船にて吊り上げ徹去す
る。同じくデイープウエル5も徹去する。次に立
上りコンクリート上部を施工する(第10図参
照)。この場合、鋼板セル2の一部を切り離すた
めに、予め、上記鋼板セル2を容易に分離できる
構成にして置くとよい。
Hereinafter, an example in which the construction method of the present invention is used in conjunction with foundation pile driving will be specifically described with reference to the drawings. First, foundation piles 1 such as concrete piles are driven into the underwater ground to be constructed (see Figure 1). Next, the cylindrical steel plate cell 2 is towed and suspended,
The steel plate cell 2 is brought to the construction site, and the steel plate cell 2 is driven and embedded using a vibro hammer 4 installed on a frame 3 provided at the upper end of the steel plate cell 2 (see FIG. 2). In this case, in order to maintain balance during sinking, it is preferable to provide an interlocking device so that the vibrohammers communicate with each other. Next, a required amount of excavation is performed within the steel plate cell 2, a deep well 5 is installed, and leveled concrete A is constructed underwater (see FIG. 3). Next, the reinforcing bars or steel frame B of the footing, which has been constructed in advance on land, is installed on the concrete A using a crane ship (see Fig. 4). Then, a lid 6 and a lock are attached to the steel plate cell 2 (see FIG. 5). In this state, the inside of the steel plate cell 2 is cut off from the atmosphere, so after starting drainage in the deep well 5, the internal pressure of the cell 2 is increased using a compressor or the like to correspond to the deep water pressure, and the water inside the cell 2 is drained ( (See Figure 6). This makes the inside of the cell 2 dry. Next, footing concrete C is constructed (see Figure 7), and standing concrete D is constructed (see Figure 8). Next, water is poured into the cell 2 to bring the internal pressure to normal pressure, and the deep well drainage is stopped (see Figure 9). Finally, the steel plate cell 2 is separated from the upper part of the footing, and the steel plate cell 2
The lid 6 and the like will be lifted and removed by a crane ship. Similarly, Deep Well 5 will also be eliminated. Next, construct the upper part of the standing concrete (see Figure 10). In this case, in order to separate a portion of the steel plate cell 2, it is preferable to prepare the steel plate cell 2 in advance so that it can be easily separated.

なお、上記の実施例では、セル2内部の土層に
デイープウエル5を設置し、浮力を生じさせない
ようにしたが、基礎杭1と鋼板セル2の下部とを
接続する方法もある。また、アースアンカーでセ
ル2を抑える方法もある。また、この実施例では
フーチングの鉄筋あるいは鉄骨Bを予め陸上で構
築し、これをクレーン船でセル2内に降ろした
が、現場において構築してもよいこと勿論であ
る。
In the above embodiment, the deep well 5 was installed in the soil layer inside the cell 2 to prevent buoyancy, but there is also a method of connecting the foundation pile 1 and the lower part of the steel plate cell 2. There is also a method of suppressing cell 2 with an earth anchor. Further, in this embodiment, the reinforcing bars or steel frame B of the footing were constructed in advance on land and lowered into the cell 2 by a crane ship, but it is of course possible to construct them on site.

本発明は、以上詳述したように、筒状の鋼板セ
ルを水中地盤に打設し、上蓋を取り付け気密状態
とした後、内部気圧を水深圧以上にしたドライの
状態を保ちつつ、水中基礎の施工を行うことを特
徴とする。その結果、次のような効果が得られ
る。
As described in detail above, the present invention enables the underwater foundation to be constructed by driving a cylindrical steel plate cell into underwater ground, attaching a top cover to make it airtight, and then maintaining a dry state with internal pressure higher than water depth pressure. It is characterized by the construction of As a result, the following effects can be obtained.

(1) フーチングコンクリートがドライ施工できる
ので品質の良い構造物となる。
(1) Footing concrete can be constructed dry, resulting in a high-quality structure.

(2) ニマーマチツクケーソン工法のような築島、
仮締切などの大がかりな仮設備を必要としな
い。
(2) Tsukishima such as the Nimamachitsuku caisson construction method;
There is no need for large-scale temporary equipment such as temporary cofferdams.

(3) 支持層が深くても、基礎杭が施工できる範囲
迄なら、施工が可能である。
(3) Even if the supporting layer is deep, construction is possible within the range where foundation piles can be constructed.

(4) 鋼板セルの一部を切離すことで、フーチング
と一体化するので、地盤への横抵抗が増大し、
耐震上も有利である。
(4) By separating a part of the steel plate cell, it becomes integrated with the footing, increasing the lateral resistance to the ground.
It is also advantageous in terms of earthquake resistance.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第10図は本発明の潜凾工法の一
実施例を順序に図解する側面概略図である。 2……鋼板セル、4……バイブロハンマー、5
……デイープウエル、6……蓋。
1 to 10 are schematic side views sequentially illustrating an embodiment of the canopy construction method of the present invention. 2... Steel plate cell, 4... Vibrohammer, 5
...Deep well, 6...lid.

Claims (1)

【特許請求の範囲】[Claims] 1 筒状の鋼板セルを水中地盤に打設し、上蓋を
取り付け気密状態とした後、内部気圧を水深圧以
上にしたドライの状態を保ちつつ、水中基礎の施
工を行うことを特徴とする潜凾工法。
1 A submersible method in which a cylindrical steel plate cell is cast into the underwater ground, a top cover is attached to make it airtight, and then the underwater foundation is constructed while maintaining a dry state with the internal pressure higher than the water depth pressure. Kan construction method.
JP14372782A 1982-08-19 1982-08-19 Caisson work Granted JPS5934332A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14372782A JPS5934332A (en) 1982-08-19 1982-08-19 Caisson work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14372782A JPS5934332A (en) 1982-08-19 1982-08-19 Caisson work

Publications (2)

Publication Number Publication Date
JPS5934332A JPS5934332A (en) 1984-02-24
JPS6143493B2 true JPS6143493B2 (en) 1986-09-27

Family

ID=15345592

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14372782A Granted JPS5934332A (en) 1982-08-19 1982-08-19 Caisson work

Country Status (1)

Country Link
JP (1) JPS5934332A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS639987U (en) * 1986-07-03 1988-01-22
JPH04287U (en) * 1990-04-19 1992-01-06
CN102454167A (en) * 2010-10-21 2012-05-16 五冶集团上海有限公司 Construction method for large ultra-deep well

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02104229A (en) * 1988-10-13 1990-04-17 Shiitex:Kk Fish culture device of automatic feeding and oxygenating
CN102619231A (en) * 2012-03-15 2012-08-01 中冶天工上海十三冶建设有限公司 Underground water pressure reducing valve
CN107642101B (en) * 2017-09-27 2020-01-07 中铁二十局集团第一工程有限公司 Rock riverbed steel cofferdam bottom sealing and water drainage preventing construction method
CN113668587A (en) * 2021-09-03 2021-11-19 中建安装集团南京建设有限公司 Construction method suitable for excavation and pressure sinking of deep and large open caisson of water-rich stratum

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS639987U (en) * 1986-07-03 1988-01-22
JPH04287U (en) * 1990-04-19 1992-01-06
CN102454167A (en) * 2010-10-21 2012-05-16 五冶集团上海有限公司 Construction method for large ultra-deep well
CN102454167B (en) * 2010-10-21 2015-09-02 五冶集团上海有限公司 The construction method of especially big & deep open caisson

Also Published As

Publication number Publication date
JPS5934332A (en) 1984-02-24

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
EP3118374A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
JP4409357B2 (en) Construction method for underwater foundation
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
JPS6143493B2 (en)
JP3603193B2 (en) How to build an underwater foundation
JPH06146305A (en) Underwater foundation and installation method thereof
JP3518379B2 (en) Construction method for underwater structures
US2317016A (en) Bridge foundation and method of making same
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
JPS58143023A (en) Caisson for pile supporting type breakwater
JP2002121754A (en) Method for constructing underwater foundation
CN212405161U (en) Foundation pit supporting system
JP2718241B2 (en) Foundation construction method on soft submarine ground
JPH09316894A (en) Bridge pier foundation structure, and construction method thereof
JPH0381422A (en) Caisson method
CN111485555A (en) Foundation pit supporting system
KR20040084126A (en) Dry Construction Method of Underwater Structure Using Watertight Caisson
SU885446A1 (en) Method of constructing pile foundation on sagging soil
JP3449279B2 (en) Construction method of underwater substructure
JP2953823B2 (en) Construction method of offshore substructure
JPS58113423A (en) Construction of cell-type underwater structure
JP2536108B2 (en) Foundation construction method for offshore structures
JPS62244921A (en) Construction work for concrete structure
JP2512744B2 (en) How to place underwater concrete