JPS62244921A - Construction work for concrete structure - Google Patents

Construction work for concrete structure

Info

Publication number
JPS62244921A
JPS62244921A JP8775786A JP8775786A JPS62244921A JP S62244921 A JPS62244921 A JP S62244921A JP 8775786 A JP8775786 A JP 8775786A JP 8775786 A JP8775786 A JP 8775786A JP S62244921 A JPS62244921 A JP S62244921A
Authority
JP
Japan
Prior art keywords
caisson
foundation
work
concrete
seabed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8775786A
Other languages
Japanese (ja)
Inventor
Takeo Kasai
笠井 武雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP8775786A priority Critical patent/JPS62244921A/en
Publication of JPS62244921A publication Critical patent/JPS62244921A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To safely and exactly perform concreting work on sea by a method in which a foundation work is made on the seabed where a concrete structure is to be constructed, a steel caisson fabricated in factory is moored and landed on the foundation work, and concrete is orderly placed on the sea. CONSTITUTION:The seabed as a construction site is dredged, the surface soil is removed out, and a foundation 1 is constructed. A steel caisson 2 fabricated in factory is towed to construction site and settled on the foundation 1, and cement mortar is injected into the space between the foundation 1 and the caisson 2 for stabilization. Rubble 12 is charged to the surrounding of the caisson 2 and compacted. Formwork assembling for the ceiling slab of the caisson 2 and timbering are made, and the ceiling slab 14 is formed. Water in the caisson 2 is discharged to lower the level of water. Concreting work for side walls 15 is made to a given height to complete the structure. The construction work can thus be performed safely and exactly under dry condition.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は海上、海中にコンクート構造物を建設する工法
に関するもので、詳しくは、コンクリート構造物の建設
工事を水中施二[′tiることなくドライの状態で行う
ようにしたコンクリート構造物の建設工法に関するもの
である。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a construction method for constructing concrete structures on the sea or under the sea. This relates to a construction method for concrete structures that is carried out in dry conditions.

[従来の技術] 従来、海上にコンクリート構造物を建設する場合は、第
11図に示す如く、土留用の鋼矢板aとbを二重にして
海底Cに立てて仮締切りを行い、上記鋼矢板aとbの間
を埋め立てて海上に突出するよう築島dし、次に、上記
鋼矢板す内の掘削を行い、地下水をポンプで吸い上げて
底盤よりコンクリートeを打設し、コンクリートeを立
上げる工法が多く採用されて来た。fは土留支保工であ
る。
[Prior Art] Conventionally, when constructing a concrete structure on the sea, as shown in Fig. 11, steel sheet piles a and b for earth retention are doubled and erected on the seabed C to provide a temporary cofferdam. The space between sheet piles a and b is filled in to create a built-up island d that protrudes into the sea. Next, excavation is performed within the steel sheet piles, groundwater is pumped up, concrete e is poured from the bottom, and concrete e is erected. Many raising methods have been adopted. f is the earth retaining shoring.

[発明が解決しようとする問題点] しかし、上記従来の工法では、次のような多くの問題点
がある。
[Problems to be Solved by the Invention] However, the above conventional construction method has many problems as follows.

■ 大掛りな築島工事が必要である。■ Large-scale construction work is required.

■ 鋼矢板による土留工事が必要であり、杭打可能な又
は適度に支持力のある海底地盤を必要とする。
■ Earth retaining work using steel sheet piles is required, and submarine ground that can be piled or has adequate bearing capacity is required.

■ 水深が深いと、矢板の強度が不足する。■ If the water is deep, the strength of the sheet piles will be insufficient.

■ 底部からの水圧が過大になり、掘削中に湧水が多く
なって施工できなくなるa3それがある。
■ The water pressure from the bottom becomes excessive, and a large amount of water springs up during excavation, making construction impossible.

■ 海底地盤が複雑で、矢板による締切りが不可能な岩
盤、石PJ層に問題があった。
■ There was a problem with the bedrock and stone PJ layer, which was difficult to close off with sheet piles due to the complicated seabed ground.

そこで、本発明は、コンクリ−1・構造物の海上又は海
中へのL1!設置こおいて、築島して底盤よリコンクリ
ー1〜を立上げることを一切11わずに、ドライ状態で
コンクリート打設を行ってコンクリート構造物を建設す
る工法を提供しようとするものである。
Therefore, the present invention provides L1! The purpose of the present invention is to provide a construction method for constructing a concrete structure by pouring concrete in a dry state without having to construct an island, build a base plate, and start up reconcrete.

[問題点を解決するための手段] 本発明は、上記目的を達成するため、コンクリ−1〜構
造物を建設しようとする個所の海底に基礎工事を行い、
工場で製作した鋼殻ケーソンを現地まで曳航した後、海
底の基礎上方に係留させ、次いで、上記m殻り一−ソン
内に通水して該鋼殻ケーソンを着底させ、次に海上でコ
ンクリ−1〜工事を、ケーソン天井部スラブから側壁の
順に行い、その都度り゛−ソン内の水を排出して下降さ
せて行き、ケーソン内底部に連結してコンクリート構造
物を完成させるものである。
[Means for Solving the Problems] In order to achieve the above object, the present invention provides foundation work on the seabed at the location where the concrete 1 to structure is to be constructed,
After towing the steel-shelled caisson manufactured at the factory to the site, it is moored above the foundation on the seabed, and then water is passed through the m-shelled caisson to allow the steel-shelled caisson to land on the bottom. Concrete work is carried out in order from the caisson ceiling slab to the side walls, and each time the water in the rift is drained and lowered, and the concrete structure is completed by connecting it to the inner bottom of the caisson. be.

[作  用] 海底の基礎工事と、鋼殻ケーソンの製作ならびに現地へ
の曳航とを別個に行い、m殻ケーソンを沈めて着底さU
るため、着底(多、直らに鋼殻ケーソンの上部にてコン
クリート工事ができ、しか−b、このコンクリート工事
は、ドライ状態で海上施工ができる。これにより水中コ
ンクリートの工事がなくなり、又、鋼殻ケーソンの骨組
材がコンクリートとの合成部材となって鉄骨、鉄筋コン
クリートを構造物とすることができる。
[Function] The foundation work on the seabed, the fabrication of the steel-shelled caisson, and the towing to the site are carried out separately, and the m-shelled caisson is sunk and landed on the bottom.
Therefore, concrete work can be carried out directly on top of the steel-shelled caisson, but this concrete work can be carried out at sea in dry conditions.This eliminates the need for underwater concrete work, and The frame material of the steel shell caisson becomes a composite member with concrete, and the steel frame and reinforced concrete can be used as a structure.

を実 施 例] 以下、本発明の実施例を図面を参照して説明する。Example of implementation] Embodiments of the present invention will be described below with reference to the drawings.

第1図は本発明の工法によるコンクリート構造物の建設
工程の最終工程近くの状態を示寸もので、水中に造った
基礎1上に、工場で製作した鋼殻ケーソン2を通水しな
がら着底し、着底後、海上でのコンクリート工事をケー
ソン天井部スラブから行い、ケーソン内の水位を下げ、
次に、側壁部のコンクリート打設を段階的に行い、その
都度ケーソン内の水位を下げながら下降さヒて打設させ
る。
Figure 1 shows the state near the final stage of the construction process of a concrete structure using the construction method of the present invention, in which a steel shell caisson 2 manufactured in a factory is placed on a foundation 1 built underwater while water is flowing through it. After reaching the bottom, concrete work was carried out at sea starting from the ceiling slab of the caisson to lower the water level inside the caisson.
Next, concrete is poured for the side walls in stages, each time lowering the water level in the caisson and lowering the concrete.

詳述するに、第2図乃至第10図は第1図に至るまでの
本発明の工法を実施する場合の工程順序を具体的に示し
たもので、この順序に従って説明すると、先ず、コンク
リート構造物を建設しようとする個所の海底地盤(軟岩
)3を浚渫して表土4の撤去を行い(第2図)、次いで
、基礎1の構築を行う。この場合、基礎1が捨石基礎の
場合は第3図(A)のように、又、基v11がシェル基
礎の場合は第3図g3)のように構築する。
To be more specific, FIGS. 2 to 10 specifically show the process order when implementing the construction method of the present invention up to FIG. 1. To explain according to this order, first, the concrete structure The seabed ground (soft rock) 3 at the location where the object is to be constructed is dredged and the topsoil 4 is removed (Figure 2), and then the foundation 1 is constructed. In this case, if the foundation 1 is a rubble foundation, it will be constructed as shown in Figure 3 (A), and if the foundation v11 is a shell foundation, it will be constructed as shown in Figure 3 g3).

上記の海底への基礎1横築工事とは別個に、本発明では
工場でt!A殻ケーソンを製作した後、建設現場まで曵
航する作業を行う。
Separately from the above-mentioned foundation 1 horizontal construction work on the seabed, in the present invention, t! After manufacturing the A-shell caisson, work will be done to tow it to the construction site.

tjA殻ケーソンの製作は、第4図に示1如く、造船ド
ック5内でt!A殻材6、骨組材7を組み立てて函体を
作り、函体内の底部にコンクリートを打設して底盤コン
クリート8とし、更に内側壁部の底盤コンクリート8上
に立上り壁9をコンクリート打設にて造り、図示の如き
鋼殻ケーソン2を製作する。次に、造船ドック5内に通
水して鋼殻ケーソン2を浮上さl!(第5図)、造船ド
ック5から現地まで曵航する(第6図)。
The tjA shell caisson is manufactured in the shipbuilding dock 5 as shown in FIG. A box is made by assembling the shell material 6 and the frame material 7, concrete is poured into the bottom of the box to form the bottom concrete 8, and rising walls 9 are concreted on top of the bottom concrete 8 on the inner wall. A steel shell caisson 2 as shown in the figure is manufactured. Next, water is passed into the shipbuilding dock 5 to float the steel shell caisson 2! (Fig. 5) and towed from shipbuilding dock 5 to the site (Fig. 6).

現地まで曵航された鋼殻ケーソン2は、鋼殻ケーソン2
の製作と併行して工事が行われた基礎1の上方に位置さ
せるため、係留索10にて仮係留されると共にilll
l−ソン2を据え付けるための仮支持盤11を基礎1上
に設置プる(第7図)。
The steel shell caisson 2 that was towed to the site is the steel shell caisson 2.
In order to position it above the foundation 1, which was constructed in parallel with the fabrication of the illll
A temporary support board 11 for installing the L-son 2 is installed on the foundation 1 (Fig. 7).

次に、鋼殻ケーソン2内に通水して該lllll−ソン
2を沈下させ、基礎1上の仮支持盤11上に着底させる
。着底後、基礎1とwA殻ケーソン2の底盤との間の隙
間にモルタルを注入して鋼殻ケーソン2を安定させる(
第8図)。この際、鋼殻ケーソン2に対する外水圧と内
水圧をバランスさせ、ケーソン2に過大な水圧がかから
ないように水位調整を行う。
Next, water is passed through the steel shell caisson 2 to cause the lllll-son 2 to sink and land on the temporary support plate 11 on the foundation 1. After landing on the bottom, inject mortar into the gap between the foundation 1 and the bottom of the wA shell caisson 2 to stabilize the steel shell caisson 2 (
Figure 8). At this time, the water level is adjusted so that the external water pressure and internal water pressure to the steel shell caisson 2 are balanced, and excessive water pressure is not applied to the caisson 2.

鋼殻ケーソン20着底が終ると、捨石12をケーソン2
まわりに施して根固めを行うと共に、桟橋13の架設を
行い、陸上から鋼殻ケーソン2までの間を往来できるよ
うにする(第9図〉。
When the steel shell caisson 20 has bottomed out, the rubble 12 is placed in the caisson 2.
At the same time, the pier 13 will be constructed to allow traffic from the land to the steel shell caisson 2 (Figure 9).

以上の工事が終ると、引続いて鋼殻ケーソン2のコンク
リート工事に移る。このコンクリート工事は、先ず、ケ
ーソン天井部スラブの型枠組みと、ケーソン2の骨組と
しての社、梁を支持材として使用した支保工を行い、次
いで、海上コンクリートポンプ船を利用してケーソン天
井部スラブのコンクリートを連続打設し、ケーソン天井
部スラブ14を造る(第10図)。ケーソン天井部スラ
ブ硬化後、ケーソン2内の水を、上記ケーソン天井部ス
ラブ14のコンクリート重量に見合った水旧だけ排出し
てケーソン内の水位を下げる。次に、側壁用型枠、鉄筋
工を行って側壁部15のコンクリート工事を側壁の所定
高さ分だけ行い(第1図)、コンクリート硬化後、ポン
プにてケーソン内の排水を行って沈下させ、同様な工事
を2次、3次、4次と順次杓って下降さ゛V、R終的に
ケーソン2内の立上り壁9と連結さゼることによってコ
ンクリ−1〜構造物を完成させる。
Once the above construction is completed, concrete work for steel shell caisson 2 will begin. In this concrete work, we first constructed the formwork for the caisson ceiling slab and shoring using the framework and beams of caisson 2 as supporting materials, and then used a marine concrete pump ship to construct the caisson ceiling slab. concrete is poured continuously to create the caisson ceiling slab 14 (Fig. 10). After the caisson ceiling slab has hardened, the water inside the caisson 2 is discharged in an amount corresponding to the concrete weight of the caisson ceiling slab 14 to lower the water level inside the caisson. Next, the formwork for the side wall and reinforcing steel work are carried out, and the concrete work for the side wall part 15 is carried out for the specified height of the side wall (Fig. 1). After the concrete has hardened, the water inside the caisson is drained using a pump to allow it to settle. , similar construction is carried out in the secondary, tertiary, and quaternary stages and lowered in sequence. ``V,R'' Finally, by connecting with the rising wall 9 in the caisson 2, the concrete 1~ structure is completed.

[発明の効果] 以上述べた如く本発明のコンクリート構造物の建設工法
によれば、海底の基礎工事とは別個に工場で鋼殻ケーソ
ンの製作を行い、鋼殻ケーソンを曳航して現地まで運ん
だ後、該tIA殻クーりンを沈めて固定し、しかる後、
海上でのコンクリート工事を行って順次扛下ろして行く
ことによってコンクリート構造物の建設を行うようにす
るので、次の如き優れた効果を奏し得る。
[Effects of the Invention] As described above, according to the concrete structure construction method of the present invention, a steel shell caisson is manufactured in a factory separately from the foundation work on the seabed, and the steel shell caisson is towed and transported to the site. After that, the tIA shell cooler is submerged and fixed, and then,
Since the concrete structure is constructed by performing concrete work on the sea and successively lowering it, the following excellent effects can be achieved.

(D  海上で築島を準備することなく施工でき、仮設
工事が少ない。
(D) Construction can be done without preparing the island at sea, and there is less temporary construction work.

(fi)  1!!体のコンクリート工事が海上でドラ
イ状態で施工でき、安全、確実な工事ができる。
(fi) 1! ! Concrete work for the body can be carried out in dry conditions at sea, allowing for safe and reliable construction.

(至)り゛−ソンが鋼殻構造であり完全止水ができ、ケ
ーソン内で安全に作業できる。
The caisson has a steel shell structure and can be completely watertight, making it possible to work safely inside the caisson.

(へ)海底の基礎工事とtJA殻ケーソンの製作工事を
併行して行うことができて工期の短縮が図れる。
(f) Submarine foundation work and tJA shell caisson fabrication work can be done simultaneously, shortening the construction period.

(V)  鋼殻の骨組材を、鉄筋コンクリートとの合成
構造とすることができ、鉄筋工事の軽減が図れる。
(V) The frame material of the steel shell can be made into a composite structure with reinforced concrete, reducing the need for reinforcing steel work.

・D 施工時、土圧、水圧の影響が少ない。・D: There is little influence of earth pressure and water pressure during construction.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の工法により建設を行うコン1    
  クリート構造物の最終工程近くの状態を示す側i′ 面図、第2図乃至第10図は本発明の工法による建設工
程の順序を示す説明図、第11図は従来の工法によりコ
ンクリート構造物を建設する状態を示す断面図である。 1は基礎、2はWA鋼殻ケーソン5は造船ドック、8は
底盤コンクリート、13は桟橋を示す。
Figure 1 shows a construction site 1 constructed using the construction method of the present invention.
2 to 10 are explanatory diagrams showing the order of the construction process according to the method of the present invention. FIG. 1 is the foundation, 2 is the WA steel shell caisson 5 is the shipbuilding dock, 8 is the concrete base, and 13 is the pier.

Claims (1)

【特許請求の範囲】[Claims] 1)コンリート構造物を建設しようとする個所の海底に
基礎工事を行い、工場で製作した鋼殻ケーソンを現地ま
で曳航した後、海底の基礎上方に係留させ、次いで、上
記鋼殻ケーソン内に通水して該鋼殻ケーソンを着底させ
、次に海上でコンクリート工事を、ケーソン天井部スラ
ブから側壁の順に行い、その都度ケーソン内の水を排出
して下降させて行き、ケーソン内底部に連結してコンク
リート構造物を完成させることを特徴とするコンクリー
ト構造物の建設工法。
1) Foundation work is carried out on the seabed at the location where the concrete structure is to be constructed, and the steel shell caisson manufactured at the factory is towed to the site, moored above the foundation on the seabed, and then passed through the steel shell caisson. The steel shell caisson is then placed on the bottom with water, and then concrete work is carried out at sea from the caisson ceiling slab to the side walls, draining the water inside the caisson and lowering it each time, and connecting it to the inner bottom of the caisson. A method of constructing a concrete structure, which is characterized by completing the concrete structure.
JP8775786A 1986-04-16 1986-04-16 Construction work for concrete structure Pending JPS62244921A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8775786A JPS62244921A (en) 1986-04-16 1986-04-16 Construction work for concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8775786A JPS62244921A (en) 1986-04-16 1986-04-16 Construction work for concrete structure

Publications (1)

Publication Number Publication Date
JPS62244921A true JPS62244921A (en) 1987-10-26

Family

ID=13923815

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8775786A Pending JPS62244921A (en) 1986-04-16 1986-04-16 Construction work for concrete structure

Country Status (1)

Country Link
JP (1) JPS62244921A (en)

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
JP3599431B2 (en) Construction method of temporary deadline
US3618327A (en) Caisson structure and pier construction methods
RU2386755C1 (en) Method for arrangement of shallow subway at water area bottom
CN109518674B (en) Artificial island segment, assembled artificial island and construction method of assembled artificial island
JPH06146305A (en) Underwater foundation and installation method thereof
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
JPS6143493B2 (en)
JP2000290936A (en) Method and caisson for constructing bridge pier footing
JPH0930487A (en) Artificial island having half-floating structure
JPS62244921A (en) Construction work for concrete structure
US3906735A (en) Foundation method for caissons
JPH09316894A (en) Bridge pier foundation structure, and construction method thereof
JPH0381422A (en) Caisson method
RU2816995C1 (en) Method for construction of hydraulic structures on rocky soils
JPH1046597A (en) Execution work method of steel shell caisson
KR20040084126A (en) Dry Construction Method of Underwater Structure Using Watertight Caisson
JPH116164A (en) Construction method for underground structure
JP2953823B2 (en) Construction method of offshore substructure
JPS598835A (en) Footing type steel plate cell caisson work
JP2536108B2 (en) Foundation construction method for offshore structures
SU785413A1 (en) Quay
JP2581602B2 (en) Waste treatment method