JPS649404B2 - - Google Patents
Info
- Publication number
- JPS649404B2 JPS649404B2 JP1971680A JP1971680A JPS649404B2 JP S649404 B2 JPS649404 B2 JP S649404B2 JP 1971680 A JP1971680 A JP 1971680A JP 1971680 A JP1971680 A JP 1971680A JP S649404 B2 JPS649404 B2 JP S649404B2
- Authority
- JP
- Japan
- Prior art keywords
- main truss
- pouring
- concrete
- floorboard
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 description 19
- 238000007796 conventional method Methods 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
【発明の詳細な説明】
本発明は、プレストレス工法による橋梁、高
架、建築物、その他桁で支持した構造物、特に桁
で支持した幅広な床板を打設するのに用いて好適
な構造物の構築工法に関する。[Detailed Description of the Invention] The present invention is a structure suitable for use in pouring bridges, viaducts, buildings, and other girder-supported structures using the prestressing method, particularly for pouring wide girder-supported floor plates. Concerning construction methods.
かかる工法により例えば長大橋を建設するに
は、通常フオルバウワーゲンと称する移動式の足
場、すなわちメイントラスを使用し、コンクリー
トを順次打設しながら長大橋を建設する。 In order to construct a long bridge using this construction method, for example, a movable scaffold called a "Falbauwagen", that is, a main truss, is usually used, and the long bridge is constructed by sequentially pouring concrete.
メイントラスは既設橋体部分の床板上に設けた
レール上を移動し得るようになし、メイントラス
を用いて所定区間のコンクリートの打設、固化を
終えれば、レールを新たに継ぎ足した橋体部分の
床板上に移動させ、そのレールに沿つてメイント
ラスを前進させ、メイントラスを用いて型枠取
付、コンクリート打設、プレストレス導入などの
作業を進めて行く。 The main truss is movable on rails installed on the deck of the existing bridge body, and once the concrete has been poured and hardened in a designated section using the main truss, the bridge body with new rails attached can be moved. The main truss is moved forward along the rail, and the main truss is used to carry out work such as installing formwork, pouring concrete, and introducing prestress.
ところで、構築する長大橋の床板幅が広い場合
には、それだけ大型のメイントラスを必要とし、
また橋桁にかかる荷重も大きい。 By the way, if the deck width of the long bridge being constructed is wide, a larger main truss will be required.
Also, the load on the bridge girder is large.
本発明は、長大橋のように桁で支持した構造物
において床板幅の広い場合、床板の打設を分割し
て行うことにより従来用いられたメイントラスよ
りも小型のメイントラスおよび側部打設用メイン
トラスで施行でき、かつ橋桁にかかる荷重も小さ
くし得るようにしたものである。 In the case of a structure supported by girders, such as a long bridge, where the width of the floorboard is wide, the present invention enables the construction of a smaller main truss than the conventionally used main truss and side castings by dividing the floorboards into parts. This design allows the construction to be carried out using the main truss, and also reduces the load on the bridge girder.
このため本発明では、床板の中央部分のコンク
リート打設をメイントラスを用いて所定長だけ行
ない、コンクリートが固化すれば打設を終えた床
板中央部の両側の床板のコンクリート打設を中央
部打設に用いられるものよりも小型の側部打設用
メイントラスを用いて行う。 Therefore, in the present invention, concrete is poured in the center of the floorboard for a predetermined length using a main truss, and once the concrete has solidified, concrete is poured in the center of the floorboard on both sides of the finished floorboard center. This is done using a main truss for side pouring that is smaller than the one used for the construction.
このような施工法を採れば、床板中央部分のコ
ンクリート打設、床板側部のコンクリート打設
と、連続施工が可能であり、工期もむしろ従来工
法に比べ短縮できる。 If such a construction method is adopted, it is possible to perform continuous construction, including pouring concrete in the center of the floorboard and pouring concrete on the sides of the floorboard, and the construction period can even be shortened compared to conventional methods.
以下、図面を参照し本発明の工法により幅広の
長大橋を建築する場合を例に挙げ、本発明の実施
例を説明する。 Embodiments of the present invention will be described below with reference to the drawings, taking as an example a case where a wide and long bridge is constructed using the construction method of the present invention.
まずメイントラスを用いて桁上に長大橋中央部
分の床板のコンクリート打設を所定長(所定区
分)行う。コンクリートが固化すれば側部の床板
のコンクリート打設を所定長行う。すなわち、図
において1は既設の橋桁、2aはメイントラスを
用いて打設を終えた長大橋中央部分の床板を示
す。中央部分の床板を打設するメイントラスとし
ては、既設の床板上に敷設したレール上を長手方
向に走行し、かつ進行方向側に作業足場を備えた
従来公知のメイントラスを用いることができる。 First, the main truss is used to pour concrete for the central part of the long bridge onto the girder for a predetermined length (predetermined sections). Once the concrete has hardened, concrete is poured for the side floorboards for a specified length. That is, in the figure, 1 shows the existing bridge girder, and 2a shows the floorboard of the central part of the long bridge, which has been poured using the main truss. As the main truss for pouring the central floorboard, a conventionally known main truss that runs in the longitudinal direction on rails laid on the existing floorboard and is equipped with a work scaffold on the advancing direction side can be used.
中央部分の床板2aの打設に続き、中央部打設
に用いられるメイントラスよりも小型の側部打設
用メイントラス3を用い中央部の床板2aに続く
側部の床板2bの打設を行う。側部打設用メイン
トラス3は進行方向と直交する側に突出したフレ
ーム4を有し、フレーム4からワイヤロープ5あ
るいは棒体6で作業足場7が吊下されている。こ
の作業足場7を利用して型枠取付、コンクリート
打設、プレストレス導入などの作業を行い側部の
床板2bを所定長さ打設する。図では片側のみ示
されているが通常両側の床板2b,2bの打設を
同時に行うようにする。 Following the pouring of the central floorboard 2a, the side floorboards 2b following the central floorboard 2a are cast using the main truss 3 for side pouring, which is smaller than the main truss used for central pouring. conduct. The main truss 3 for side pouring has a frame 4 projecting to the side perpendicular to the direction of movement, and a work scaffold 7 is suspended from the frame 4 with a wire rope 5 or a rod 6. Using this work scaffold 7, work such as formwork installation, concrete pouring, prestress introduction, etc. is carried out, and the side floorboards 2b are poured to a predetermined length. Although only one side is shown in the figure, the floor plates 2b, 2b on both sides are normally poured at the same time.
側部打設用メイントラス3は既設の床板中央部
2aに敷設した2本のレール8,8(第1図)上
を走行し得るようになつていて、側部2bのコン
クリート打設が進むにつれて側部打設用メイント
ラス3を長手方向に移動させる。 The main truss 3 for side pouring is designed to be able to run on two rails 8, 8 (Fig. 1) laid at the center of the existing floorboard 2a, and concrete pouring for the side portions 2b progresses. The main truss 3 for side pouring is then moved in the longitudinal direction.
側部打設用メイントラス3にはそれで支持した
作業足場7などによる荷重により側部打設用メイ
ントラス3を転倒させようとするモーメントを生
じるので、側部打設用メイントラス3の後端にア
ンカージヤツキ9を設け、そのアンカージヤツキ
9により側部打設用メイントラス3の後端を床板
2aの方向に押圧しておく。 The rear end of the main truss 3 for side pouring generates a moment that tends to overturn the main truss 3 for side pouring due to the load from the work scaffold 7 etc. supported by the main truss 3 for side pouring. An anchor jack 9 is provided at , and the anchor jack 9 presses the rear end of the main truss 3 for side pouring in the direction of the floorboard 2a.
このようにして所定長の側部床板2bの打設を
終えれば再び側部打設用メイントラス3よりも大
きな中央部打設用のメイントラスを用いて中央部
の床板2bを所定長さ打設する。この場合、メイ
ントラスをジヤツキで上昇させレールを継ぎ足し
た中央部分の床板2a側に移動させそのレールに
沿つてメイントラスを前進させコンクリート打設
を行うことは従来方法と同様である。 When the side floor plate 2b of a predetermined length has been cast in this way, the central floor plate 2b is recast to a predetermined length using the main truss for center pouring, which is larger than the main truss 3 for side pouring. Pour concrete. In this case, the main truss is raised with a jack, moved to the floor plate 2a side of the central part where the rails have been added, and the main truss is advanced along the rails to perform concrete pouring, which is the same as in the conventional method.
中央部分の床板2aのコンクリートが固化すれ
ば、側部打設用メイントラス3を図示されていな
いジヤツキで上昇させて2本のレール8,8(第
1図)を移動し、その2本のレール8,8(第1
図)に沿つて側部打設用メイントラス3を前進さ
せ、側部床板2bの打設を行う。爾後、同様の工
程を繰り返し、長大橋を構築する。 Once the concrete on the floor plate 2a in the central part has solidified, the main truss 3 for side pouring is raised using jacks (not shown), the two rails 8, 8 (Fig. 1) are moved, and the two rails 8, 8 (Fig. 1) are moved. Rails 8, 8 (first
The main truss 3 for side pouring is moved forward along the direction shown in the figure), and the side floor plate 2b is poured. Afterwards, the same process is repeated to build a long bridge.
なお、床板中央部の全長を予め施工し終え、次
いで床板側部の施工を行うようにしてもよく、ま
た床板中央部の施工を行いつつそれに続き床板側
部の施工を行うようにしてもよい。要は床板の打
設を中央部分とそれに続く側部とに分割施工し、
中央部分の床板の打設に続き側部の床板の打設を
行うようにする。 Note that the entire length of the center portion of the floor board may be completed in advance and then the side portions of the floor board may be constructed, or the center portion of the floor board may be constructed and then the side portions of the floor board may be constructed. . The key is to install the floorboards in two parts: the center part and the side parts.
Following the pouring of the center floor plates, the side floor plates will be poured.
以上説明したように本発明の工法によれば、床
板幅の広い構造物であつても従来工法において用
いられるメイントラスよりも小型のメイントラス
および側部打設用メイントラスによつて施工で
き、また桁にかかる荷重も小さく桁などに悪影響
を与えることがない。また床板中央部の施工と既
設中央部に続く床板側部の施工とを同時に行うこ
ともでき、大型のメイントラス1台による施工よ
りもむしろ能率的に作業を進めることができ工期
を短縮することができる。 As explained above, according to the construction method of the present invention, even a structure with a wide floor plate can be constructed using a main truss and a main truss for side pouring that are smaller than the main truss used in the conventional construction method. In addition, the load applied to the girder is small and does not have any negative impact on the girder. In addition, the construction of the central part of the floorboard and the construction of the side parts of the floorboard following the existing central part can be carried out at the same time, allowing the work to proceed more efficiently and shortening the construction period rather than construction using a single large main truss. I can do it.
図面は本発明の工法を実施した実施例を示し、
第1図は本発明の工法により長大橋を構築してい
る状態を示す正面図、第2図は同側面図である。
1……桁、2a……中央部の床板、2b……側
部の床板、3……側部打設用メイントラス、4…
…フレーム、5……ワイヤロープ、6……棒体、
7……作業足場、8,8……レール、9……アン
カージヤツキ。
The drawings show an example of implementing the construction method of the present invention,
FIG. 1 is a front view showing a long span bridge being constructed using the construction method of the present invention, and FIG. 2 is a side view of the same. 1...Girder, 2a...Central floor plate, 2b...Side floor plate, 3...Main truss for side pouring, 4...
... Frame, 5... Wire rope, 6... Rod body,
7...Work scaffold, 8,8...Rail, 9...Anchor jack.
1 高架構造物の桁が位置する既設床板上にレー
ルを敷設し、そのレールに沿つて移動可能な左右
一対のメイントラスを設け、そのメイントラスに
横梁を掛け渡し固定してコンクリート重量などを
支え、メイントラスを順次移動させて床板の継ぎ
足しを行う高架構造物の構築工法に於いて、一方
のメイントラスと横梁とをメイントラスと横梁と
が水平面で相対回転し得るようにピン連結し、他
方のメイントラスと横梁とをメイントラスと横梁
とが水平面で相対回転し得るようにピン連結する
と共に、メイントラスと横梁とが水平面で横方向
に相対移動し得るようにスライド連結し、桁の間
隔が変化しそれに伴いレール間隔が変化すること
により生じるメイントラスと横梁との横方向変位
および角度変位をメイントラスと横梁との相対移
動および相対回転により吸収し、コンクリート重
量などを常に直接桁で支持しつつ順次床板を継ぎ
足して行くことを特徴とする高架構造物の構築工
法。
1. Rails are laid on the existing floorboards where the girders of the elevated structure are located, a pair of left and right main trusses are installed that can move along the rails, and cross beams are fixed across the main trusses to support the weight of concrete, etc. In a construction method for an elevated structure in which the main truss is moved one after another to add floor plates, one main truss and the cross beam are connected with pins so that the main truss and the cross beam can rotate relative to each other in a horizontal plane, and the other The main truss and the cross beam are connected by pins so that the main truss and the cross beam can rotate relative to each other in the horizontal plane, and the main truss and the cross beam are connected by sliding so that they can move relative to each other in the horizontal direction in the horizontal plane. The lateral and angular displacements between the main truss and cross beams caused by changes in the rail spacing due to changes in rail spacing are absorbed by the relative movement and rotation between the main truss and cross beams, and the weight of concrete is always supported directly by the girder. A construction method for elevated structures characterized by adding floor plates one after another.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1971680A JPS56119005A (en) | 1980-02-21 | 1980-02-21 | Construction of elevated structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1971680A JPS56119005A (en) | 1980-02-21 | 1980-02-21 | Construction of elevated structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS56119005A JPS56119005A (en) | 1981-09-18 |
JPS649404B2 true JPS649404B2 (en) | 1989-02-17 |
Family
ID=12007012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1971680A Granted JPS56119005A (en) | 1980-02-21 | 1980-02-21 | Construction of elevated structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS56119005A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0443307U (en) * | 1990-08-17 | 1992-04-13 | ||
WO2021171380A1 (en) | 2020-02-25 | 2021-09-02 | 三菱電機株式会社 | Wireless distance measurement system, distance measurement terminal, control circuit, recording medium, and wireless distance measurement method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5484983B2 (en) * | 2010-03-25 | 2014-05-07 | 株式会社錢高組 | Method for assembling and dismantling bridge moving work device |
-
1980
- 1980-02-21 JP JP1971680A patent/JPS56119005A/en active Granted
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0443307U (en) * | 1990-08-17 | 1992-04-13 | ||
WO2021171380A1 (en) | 2020-02-25 | 2021-09-02 | 三菱電機株式会社 | Wireless distance measurement system, distance measurement terminal, control circuit, recording medium, and wireless distance measurement method |
Also Published As
Publication number | Publication date |
---|---|
JPS56119005A (en) | 1981-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2007315077A (en) | Construction method for corrugated steel web bridge using girder wagon | |
JP4928342B2 (en) | Corrugated steel web bridge erection device and corrugated steel web bridge erection method | |
EP1111135A2 (en) | Method of building viaducts | |
JPS649404B2 (en) | ||
JPH0959932A (en) | Construction method of column head of overhanging erection girder bridge | |
JP2001200510A (en) | Method for constructing overhangingly erected bridge using corrugated steel plate web | |
JPS6282147A (en) | Novel prestressed synthetic beam and its construction | |
KR20040012496A (en) | Method for construction of steel-pc-synthesized bridge | |
JP2000104221A (en) | Combined truss bridge and erection method of the same | |
JP2000104219A (en) | Erection of combined truss bridge | |
JP3830362B2 (en) | Overhang construction method of PC box girder bridge | |
JP7134133B2 (en) | Bridge railing construction method | |
JP2556247B2 (en) | Construction method of concrete bridge and its construction equipment | |
JP2004225275A (en) | Erection apparatus for corrugated steel plate web box girder bridge, and construction method for corrugated steel plate web box girder bridge | |
JP7012486B2 (en) | Bridge construction method | |
JPS649403B2 (en) | ||
JP2000104220A (en) | Erection of combined truss bridge | |
JPH046450Y2 (en) | ||
JPH0336362B2 (en) | ||
JPS649405B2 (en) | ||
JPS5845522B2 (en) | How to build a bridge | |
JP2565573Y2 (en) | Volberwagen reaction force support device | |
JP3873101B2 (en) | Equipment for placing slabs | |
JPH07102524A (en) | Method for building concrete cable-stayed bridge and form supporting truck using the same | |
JP3069879B2 (en) | System formwork |