JP3830362B2 - Overhang construction method of PC box girder bridge - Google Patents
Overhang construction method of PC box girder bridge Download PDFInfo
- Publication number
- JP3830362B2 JP3830362B2 JP2001190019A JP2001190019A JP3830362B2 JP 3830362 B2 JP3830362 B2 JP 3830362B2 JP 2001190019 A JP2001190019 A JP 2001190019A JP 2001190019 A JP2001190019 A JP 2001190019A JP 3830362 B2 JP3830362 B2 JP 3830362B2
- Authority
- JP
- Japan
- Prior art keywords
- block
- floor slab
- box girder
- concrete
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、移動式作業車を用いて1ブロックごと桁を張り出して構築する形式の、特に波形鋼板ウェブPC箱桁橋の張出施工方法に関するものである。
【0002】
【従来の技術】
PC箱桁橋の張出施工はカンチレバー式架設工法とも呼ばれ、支保工を用いず橋体を橋軸方向に数メートルのブロックに分割し、橋脚に近い部分から移動式作業車などの架設機械を用いて桁を両側に張り出して架設していくものである。
PC箱桁橋の張出施工は、架設地点の地形などに左右されず、工事規模に対し架設装置などが比較的小規模で、安全且つ経済的な工法であるためよく使用されている。
従来、1ブロックごと桁を張り出して構築する波形鋼板ウェブPC箱桁橋の張出施工は、図3に示すように移動式作業車aを用いて1ブロックごとに波形鋼板ウェブb、横桁、下床版c及び上床版dを構築していた。
この移動式作業車aは、フレーム、作業台などで構成し、桁上面に敷設したレール上を前進移動して1ブロックごとにコンクリートを打設するもので、波形鋼板ウェブb・下床版cを施工してから横桁・上床版dの順に施工を進める。
即ち、一つのブロックeに対応するように移動式作業車aを前進して据え付けし、このブロックeに波形鋼板ウェブbを設置し、さらに下床版cの型枠を構築する(図3(a))。
次に、このブロックeの上床版d及び横桁の型枠を構築する(図3(b))。
次いでこのブロックeの下床版cの型枠、上床版d及び横桁の型枠に順次コンクリートを打設する(図3(c))。なお、横桁は波形鋼板または平鋼板の場合もある。
再び移動式作業車aを前進して据え付けし、同様の手順を繰り返しながら1ブロックごとに波形鋼板ウェブb、下床版c及び上床版dを張り出して橋を構築する。
【0003】
【発明が解決しようとする課題】
しかしながら、前記した従来のPC箱桁橋の張出施工方法にあっては、次のような問題点がある。
<イ>1サイクル内で1ブロックずつの施工方法であり、1ブロックごとに下床版cのコンクリートを養生してから横桁のコンクリートを打設し、さらに横桁のコンクリートを養生してから上床版dのコンクリートを打設するため、各作業ごとの待ち時間が多く、工期が長くなる。また、1回のコンクリート打設で下床版、横桁、上床版の全ての打設を行う場合には、特に横桁、上床版の型枠支保工の構造が複雑となり、組立て、解体の手間が大きくなる。
<ロ>下床版cの型枠構築作業が完全に終了しないうちに、上床版dの作業を開始すると上下作業となり、危険である。
【0004】
【本発明の目的】
本発明は上記したような従来の問題点に鑑みて考えられたもので、待ち時間を少なくして効率化し、工期の短縮を可能にしたPC箱桁橋の張出施工方法を提供することを目的とする。
また本発明は、安全に作業を行うことのできるようにしたPC箱桁橋の張出施工方法を提供することを目的とする。
本発明は、上記目的のうち少なくとも一つを達成するようにしたものである。
【0005】
【課題を解決するための手段】
上記のような目的を達成するために、本発明のPC箱桁橋の張出施工方法は、移動式作業車を用いて1ブロックごと桁を張り出して構築するPC箱桁橋の張出施工方法において、前記移動式作業車を前方ブロックへ移動し、前記前方ブロックの波形鋼板ウェブの設置及び下床版の型枠の構築を行うと同時に後方ブロックの上床版の型枠を構築し、前記前方ブロックの下床版型枠にコンクリートを打設するとともに後方ブロックの上床版型枠にコンクリートを打設し、二つのブロックを同時に施工することを特徴とするものである。
また、本発明は、波形鋼板ウェブの場合だけでなく、コンクリートウェブの場合にも適用できる方法である。
【0006】
【本発明の実施の形態】
以下図面を参照しながら、本発明に係る実施の形態について説明する。
【0007】
<イ>PC箱桁橋
PC箱桁橋1は、橋桁を橋軸方向に数メートルのブロック2に分割し、このブロック2を橋脚に近い部分から移動式作業車7を用いて両側に張り出して架設するものである。
一つのブロック2は、下床版3と上床版4及びこれらを結ぶ波形鋼板ウェブ5、横桁6などからなる。なお、ウェブはコンクリートウェブの場合もある。また横桁6はコンクリートの場合、波形鋼板や平鋼板の場合がある。
図1は、移動式作業車7でPC箱桁橋1を施工する状態を示す説明図で、前方ブロック2aの下床版3の型枠にコンクリートを打設し、後方ブロック2bの上床版4の型枠にコンクリートを打設した状態を示す。
本発明では、前方ブロック2aと後方ブロック2bの二つのブロックを同時に施工するものである。
【0008】
<ロ>移動式作業車
移動式作業車7は、PC箱桁橋1を跨ぐように両側に配置した支持体71と、この支持体71に下支えで連結したトラス構造の作業台72とからなる。
支持体71の上部にローラ73を組み込み、このローラ73がPC箱桁橋1上部に敷設したレール78上を転がって、移動式作業車7全体が前進移動する。
前進移動は、後方ローラ77をPC箱桁橋1(下床版3)下面に当接してこれを反力として、公知のジャッキなどを伸長することによって行うことができる。
前進移動後、その位置で昇降ジャッキ74により作業台72のジャッキアップを行い、移動式作業車7を固定する。
作業台72の前部に型枠受け75を調整ジャッキ76で調整可能に載置しており、この型枠受け75によって下床版3の型枠などを構築する。
さらに、この移動式作業車7を用いてコンクリートを打設した後、プレストレスを与えて、順次移動式作業車7を前方へ移動してPC箱桁橋1を張り出して架設していく。
なお、実施例の移動式作業車7は、下支え式のものを示しているが、図3に示す形式の移動式作業車を用いてもよい。
【0009】
次に、図2を参照してPC箱桁橋の張出施工方法について説明する。
【0010】
<イ>移動式作業車の前進(図2(a))
ジャッキなどを伸長することによって、移動式作業車7を1ブロック分だけ前進移動する。
なお、前進移動する前の移動式作業車7は、第N番目ブロック(前方ブロック2a)と、この一つ手前の第N−1番目ブロック(後方ブロック2b)とを同時に施工することができる位置にあり、この状態で、第N番目ブロックの下床版3と第N−1番目ブロックの上床版4にコンクリートを同時に打設しておく。
移動式作業車7が1ブロック分だけ前進移動することによって、PC箱桁橋1の下側に配置されている作業台72も1ブロック分だけ前進移動し、作業台72上において一つ先の第N+1番目ブロック(新たな前方ブロック2a)を施工できる状態となる。
【0011】
<ロ>波形鋼板ウェブの設置(図2(b))
作業台72上で、第N+1番目ブロックに波形鋼板ウェブ5を設置する。
波形鋼板ウェブ5は、下床版3と上床版4をつなぐためのもので、強度の高い波形鋼板を用いる。
コンクリートウェブの場合には、鉄筋組立と型枠組立の工程となり、この場合は、下床版3の型枠、鉄筋組立を先に行う。
【0012】
<ハ>下床版型枠と上床版型枠の構築(図2(b))
作業台72の型枠受け75の上に下床版3の型枠を構築する。
構築された下床版3の型枠は、前記の第N+1番目ブロックに設置した波形鋼板ウェブ5の下方に設置される。
なお、下床版3の型枠を構築してから、前記<ロ>の波形鋼板ウェブ5を設置してもよい。コンクリートウェブの場合は、この手順となる。
作業台72は第N番目ブロック(新たな後方ブロック2b)を施工できる位置でもあるので、第N番目ブロックの上床版4の型枠を構築する。
なお、第N番目ブロックに横桁6(コンクリートの場合、波形鋼板または平鋼板の場合)を構築するように設計している場合は、上床版4の型枠に先立って横桁6の型枠を構築するか、あるいは横桁6の鋼板を組み立てる。
横桁6を構築するように設計している場合は、上床版4の支保工を軽減できる利点がある。
【0013】
<ニ>コンクリートの打設(図2(c))
前記<ハ>で構築した第N+1番目ブロックの下床版3の型枠にコンクリートを打設し、同時に第N番目ブロックの上床版4の型枠にコンクリートを打設する。
なお、第N番目ブロックにコンクリート横桁6を構築するように設計している場合は、前記<ハ>で述べたごとく横桁6の型枠を構築しているので、横桁6のコンクリートを上床版4のコンクリートと同時に打設する。
これによって、第N+1番目ブロックの下床版3にコンクリートを打設するとともに第N番目ブロックの上床版4及び横桁6にコンクリートを打設することになる。
即ち、二つのブロック(前方ブロック2a、後方ブロック2b)に同時にコンクリートを打設する。
なお、横桁6は、前方ブロック2aにおいて下床版3及び波形鋼板ウェブ5と同時に施工する方法も考えられる。
【0014】
<ホ>再び移動式作業車を前進(図2(c))
第N番目ブロックの上床版4のコンクリートの養生を終え、PC鋼材の緊張が終了したら、上床版4の上にレール78を敷設して、移動式作業車7の移動準備を整える。
再び移動式作業車7を1ブロック分だけ前進移動し、図2(a)の状態に至る。
移動式作業車7を固定した後、作業台72では前記した型枠の構築、さらにコンクリートの打設作業が行われる。
これを順次繰り返すことによって、二つのブロック(前方ブロック2a、後方ブロック2b)を同時に施工することができる。
【0015】
本発明では、1サイクル内で1ブロックずつ施工していく従来の張出施工と比較して、1サイクル内で二つのブロック2a、2bを同時に施工しているので、工期を3割から4割程度短縮することができる。
【0016】
【本発明の効果】
本発明のPC箱桁橋の張出施工方法は、以上説明したようになるから次のような効果を得ることができる。
<イ>前方ブロックの下床版を施工すると同時に後方ブロックの上床版を施工し、また前方ブロックの下床版にコンクリートを打設するとともに後方ブロックの上床版にコンクリートを打設して、二つのブロックを同時に施工するようにしたので、待ち時間を少なくし、工期の短縮を可能にすることができる。
<ロ>後方ブロックと前方ブロックの二つのブロックを同時に施工する際に、前方ブロックでは下床版を施工し、後方ブロックでは上床版を施工するようにしているので、危険な上下作業とならず、安全に作業を行うことができる。
<ハ>2ブロック分の全てを同時に施工するものでないため、移動式作業車に作用する力が軽減され、移動式作業車の鋼材重量を軽減することができるなどの合理化が可能となる。
【図面の簡単な説明】
【図1】移動式作業車でPC箱桁橋を施工する状態を示す説明図。
【図2】PC箱桁橋の施工手順を示す説明図。
【図3】従来のPC箱桁橋の施工手順を示す説明図。
【符号の説明】
1・・・PC箱桁橋
2・・・ブロック
2a・・前方ブロック
2b・・後方ブロック
3・・・下床版
4・・・上床版
5・・・波形鋼板ウェブ
6・・・横桁
7・・・移動式作業車
72・・作業台[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for projecting a corrugated steel sheet web PC box girder bridge, particularly in a form in which a girder is constructed for each block using a mobile work vehicle.
[0002]
[Prior art]
The overhang construction of PC box girder bridge is also called a cantilever type construction method. The bridge body is divided into blocks of several meters in the direction of the bridge axis without using support work, and the construction machine such as a mobile work vehicle from the part near the pier. The girder is built over both sides using
The PC box girder bridge overhang construction is often used because it is a safe and economical construction method because the construction equipment is relatively small relative to the construction scale, regardless of the topography of the construction site.
Conventionally, the corrugated steel web PC box girder bridge constructed by projecting the girders for each block is constructed by using a mobile work vehicle a as shown in FIG. A lower floor plate c and an upper floor plate d were constructed.
This movable work vehicle a is composed of a frame, a work table, and the like, and moves forward on a rail laid on the upper surface of a girder to place concrete on a block-by-block basis. After the construction, proceed with construction in the order of cross beam and upper floor slab d.
That is, the mobile work vehicle a is moved forward and installed so as to correspond to one block e, the corrugated steel sheet web b is installed in the block e, and the formwork of the lower floor slab c is constructed (FIG. 3 ( a)).
Next, the upper floor slab d of this block e and the formwork of a cross beam are constructed | assembled (FIG.3 (b)).
Next, concrete is sequentially cast on the form of the lower floor slab c, the upper floor slab d, and the cross girder form of the block e (FIG. 3C). In addition, a cross beam may be a corrugated steel plate or a flat steel plate.
The mobile work vehicle a is again advanced and installed, and the bridge is constructed by projecting the corrugated steel sheet web b, the lower floor slab c, and the upper floor slab d for each block while repeating the same procedure.
[0003]
[Problems to be solved by the invention]
However, the above-described conventional PC box girder overhang construction method has the following problems.
<I> It is a construction method for each block in one cycle. After curing the concrete of the lower floor slab c for each block, placing the concrete of the cross beam and further curing the concrete of the cross beam Since the concrete of the upper floor slab d is placed, the waiting time for each operation is long and the construction period is long. In addition, when all the lower floor slabs, cross girders, and upper floor slabs are cast in a single concrete placement, the structure of the frame support work for the cross girders and upper floor slabs is particularly complicated. Time and effort is increased.
<B> If the work of the upper floor slab d is started before the work for constructing the form of the lower floor slab c is completely finished, it is dangerous because it is an up / down work.
[0004]
[Object of the present invention]
The present invention has been conceived in view of the above-described conventional problems, and provides a method for extending a PC box girder bridge that is efficient by reducing waiting time and shortening the construction period. Objective.
It is another object of the present invention to provide a PC box girder bridge overhanging method that enables safe work.
The present invention is intended to achieve at least one of the above objects.
[0005]
[Means for Solving the Problems]
In order to achieve the above-described object, the PC box girder bridge overhang construction method of the present invention is a PC box girder bridge overhang construction method constructed by overhanging each block using a mobile work vehicle. The movable work vehicle is moved to the front block, the corrugated steel sheet web of the front block is installed and the form of the lower floor slab is constructed, and simultaneously the form of the upper floor slab of the rear block is constructed, and the front The concrete is characterized in that concrete is placed in the lower floor formwork of the block and concrete is placed in the upper floor formwork of the rear block, and two blocks are constructed simultaneously.
Further, the present invention is a method applicable not only to a corrugated steel web but also to a concrete web.
[0006]
[Embodiments of the Invention]
Embodiments according to the present invention will be described below with reference to the drawings.
[0007]
<A> PC box girder bridge PC
One
FIG. 1 is an explanatory view showing a state in which a PC
In the present invention, two blocks, the
[0008]
<B> Mobile Work Vehicle The mobile work vehicle 7 includes a support 71 arranged on both sides so as to straddle the
A
The forward movement can be performed by abutting the
After the forward movement, the
A formwork holder 75 is placed on the front portion of the work table 72 so as to be adjustable by an
Furthermore, after placing concrete using the mobile work vehicle 7, prestress is applied, and the mobile work vehicle 7 is sequentially moved forward to project the PC
In addition, although the mobile work vehicle 7 of an Example has shown the support type, the mobile work vehicle of the format shown in FIG. 3 may be used.
[0009]
Next, a method for extending a PC box girder bridge will be described with reference to FIG.
[0010]
<A> Advancement of mobile work vehicle (FIG. 2 (a))
By extending the jack or the like, the mobile work vehicle 7 is moved forward by one block.
The movable work vehicle 7 before moving forward is a position where the Nth block (
When the mobile work vehicle 7 moves forward by one block, the work table 72 arranged on the lower side of the PC
[0011]
<B> Installation of corrugated steel web (Fig. 2 (b))
On the work table 72, the
The
In the case of a concrete web, the rebar assembly and formwork assembly steps are performed. In this case, the formwork and rebar assembly of the
[0012]
<C> Construction of lower floor formwork and upper floor formwork (Fig. 2 (b))
The formwork of the
The formwork of the constructed
In addition, after constructing the formwork of the
Since the
In addition, when it is designed to construct a cross beam 6 (in the case of concrete, a corrugated steel plate or a flat steel plate) in the Nth block, the form of the cross beam 6 prior to the form of the
When it is designed to construct the cross beam 6, there is an advantage that the support work of the
[0013]
<D> Placing concrete (Figure 2 (c))
Concrete is placed on the formwork of the
In addition, when the concrete cross beam 6 is designed to be constructed in the Nth block, the form of the cross beam 6 is constructed as described in <c> above. It is placed at the same time as the concrete of the
As a result, concrete is placed on the
That is, concrete is simultaneously placed in two blocks (the
In addition, the method of constructing the cross beam 6 simultaneously with the
[0014]
<E> Move the mobile work vehicle forward again (Fig. 2 (c))
When the concrete curing of the
The mobile work vehicle 7 is again moved forward by one block, and the state shown in FIG.
After the mobile work vehicle 7 is fixed, the
By repeating this sequentially, two blocks (the
[0015]
In the present invention, compared to the conventional overhang construction in which one block is constructed in one cycle, two
[0016]
[Effect of the present invention]
Since the extension construction method of the PC box girder bridge of the present invention is as described above, the following effects can be obtained.
<B> At the same time as installing the lower floor slab of the front block, construct the upper floor slab of the rear block, cast concrete on the lower floor slab of the front block, and cast concrete on the upper floor slab of the rear block. Since two blocks were constructed at the same time, the waiting time can be reduced and the construction period can be shortened.
<B> When two blocks, the rear block and the front block, are constructed at the same time, a lower floor slab is constructed on the front block and an upper floor slab is constructed on the rear block. Can work safely.
<C> Since not all two blocks are constructed at the same time, the force acting on the mobile work vehicle is reduced, and the weight of the steel material of the mobile work vehicle can be reduced.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing a state in which a PC box girder bridge is constructed with a mobile work vehicle.
FIG. 2 is an explanatory view showing a construction procedure of a PC box girder bridge.
FIG. 3 is an explanatory view showing a construction procedure of a conventional PC box girder bridge.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
前記移動式作業車を前方ブロックへ移動し、
前記前方ブロックの波形鋼板ウェブの設置及び下床版の型枠の構築を行うと同時に後方ブロックの上床版の型枠を構築し、
前記前方ブロックの下床版型枠にコンクリートを打設するとともに後方ブロックの上床版型枠にコンクリートを打設し、
二つのブロックを同時に施工することを特徴とする、
PC箱桁橋の張出施工方法。In the extension construction method of PC box girder bridge constructed by overhanging the girder for each block using a mobile work vehicle,
Moving the mobile work vehicle to the front block;
Constructing the form of the corrugated steel sheet web of the front block and the form of the lower floor slab, and simultaneously constructing the form of the upper floor slab of the rear block,
Placing concrete in the lower floor formwork of the front block and placing concrete in the upper floor formwork of the rear block;
It is characterized by constructing two blocks at the same time.
Overhang construction method of PC box girder bridge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001190019A JP3830362B2 (en) | 2001-06-22 | 2001-06-22 | Overhang construction method of PC box girder bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001190019A JP3830362B2 (en) | 2001-06-22 | 2001-06-22 | Overhang construction method of PC box girder bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003003424A JP2003003424A (en) | 2003-01-08 |
JP3830362B2 true JP3830362B2 (en) | 2006-10-04 |
Family
ID=19028848
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001190019A Expired - Fee Related JP3830362B2 (en) | 2001-06-22 | 2001-06-22 | Overhang construction method of PC box girder bridge |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3830362B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4928342B2 (en) * | 2007-04-27 | 2012-05-09 | 株式会社ピーエス三菱 | Corrugated steel web bridge erection device and corrugated steel web bridge erection method |
JP5074260B2 (en) * | 2008-03-28 | 2012-11-14 | 三井住友建設株式会社 | Bridge erection method |
CN102747681A (en) * | 2012-06-28 | 2012-10-24 | 贵州桥梁建设集团有限责任公司 | Movable protection platform for constructing bridge |
CN103103929B (en) * | 2013-02-17 | 2015-08-12 | 中铁大桥局集团第八工程有限公司 | Multifunctional movable protective underframe for steel beam cantilever erection |
CN109702366B (en) * | 2018-09-28 | 2021-01-01 | 江苏中铁山桥重工有限公司 | Manufacturing method of large-curve-radius rigid torsional open-slot steel beam |
-
2001
- 2001-06-22 JP JP2001190019A patent/JP3830362B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003003424A (en) | 2003-01-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5179804B2 (en) | Mobile suspension support | |
JP5053589B2 (en) | How to build a bridge girder | |
JP2008088782A (en) | Cantilever overhang erection method of corrugated steel plate web bridge | |
JP4748420B2 (en) | Construction method of corrugated steel web bridge using girder for erection work | |
JP4403051B2 (en) | Corrugated steel web bridge construction method | |
JP2000265417A (en) | Moving timbering construction method for bridge floor slab overhang section | |
JP5106989B2 (en) | Corrugated steel web bridge erection device and corrugated steel web bridge erection method | |
JP2006077521A (en) | Bridge constructing apparatus | |
JP3830362B2 (en) | Overhang construction method of PC box girder bridge | |
JP4928342B2 (en) | Corrugated steel web bridge erection device and corrugated steel web bridge erection method | |
JP3177904B2 (en) | Mobile work vehicle for PC cable-stayed bridge | |
JP4329535B2 (en) | Mobile work vehicle for overhanging slabs | |
EP1111135A2 (en) | Method of building viaducts | |
JP4033871B2 (en) | How to build a bridge girder | |
JP6509096B2 (en) | Extension method | |
JP3536269B2 (en) | Construction method of concrete bridge and feed girder used for the construction method | |
JP2006112179A (en) | Bridge girder installing method | |
JP4351523B2 (en) | Column head construction method | |
JP2000104221A (en) | Combined truss bridge and erection method of the same | |
KR20040012496A (en) | Method for construction of steel-pc-synthesized bridge | |
JP3063548B2 (en) | Formwork method and equipment | |
JP7012486B2 (en) | Bridge construction method | |
JP2000104219A (en) | Erection of combined truss bridge | |
JP2550836B2 (en) | PC cable stayed bridge construction equipment | |
JP2000104220A (en) | Erection of combined truss bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040720 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060612 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060704 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060711 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100721 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110721 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110721 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120721 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130721 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130721 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140721 Year of fee payment: 8 |
|
LAPS | Cancellation because of no payment of annual fees |