JPS63521A - Insertion work of steel material of soil-mortar column-line pile - Google Patents

Insertion work of steel material of soil-mortar column-line pile

Info

Publication number
JPS63521A
JPS63521A JP14217386A JP14217386A JPS63521A JP S63521 A JPS63521 A JP S63521A JP 14217386 A JP14217386 A JP 14217386A JP 14217386 A JP14217386 A JP 14217386A JP S63521 A JPS63521 A JP S63521A
Authority
JP
Japan
Prior art keywords
steel material
pit
shaped steel
casing
ruler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14217386A
Other languages
Japanese (ja)
Other versions
JPH0362846B2 (en
Inventor
Nagatomo Ochi
越智 永共
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOTSUKI KOGYO KK
Tokki Industries Co Ltd
Original Assignee
TOTSUKI KOGYO KK
Tokki Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOTSUKI KOGYO KK, Tokki Industries Co Ltd filed Critical TOTSUKI KOGYO KK
Priority to JP14217386A priority Critical patent/JPS63521A/en
Publication of JPS63521A publication Critical patent/JPS63521A/en
Publication of JPH0362846B2 publication Critical patent/JPH0362846B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To prevent damage to the pit wall by a method in which a long I-shaped steel material having a tip with sloped face on its lower end is hung down between rollers under ground for correcting its warping and vertically inserted into the excavated pit when being pulled out of a casing. CONSTITUTION:A tip part 2 with an inclined plate 2a is attached to the lower end of along I-shaped steel material 1 and hung down between rollers 4 in a casing 3 provided in an excavated pit to the bottom of the pit for correcting the warping of the steel material 1. A rectangular flat scale 6 of a given length, having angular steels 6a on its four corners, is vertically penetrated into an excavated pit 5 for soil mortar column-line pile. The steel material 1 in the casing 3 is lifted up and moved to the pit 5, and the tip part 2 on the lower end is inserted into the scale 6, and the material 1is inserted into the pit 5. These processes are repeated to move it to the inserting position of the steel material. The steel material can thus be easily penetrated until the soil mortar hardens.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は山止及び止水用として地中に造成されるソイ
ルモルタル柱列杭用の長尺の鋼材を、モルタルを注入し
た掘削孔に!r!直に挿入する方法に関するものである
[Detailed Description of the Invention] [Industrial Application Field] This invention applies long steel materials for soil mortar column piles, which are constructed underground for mountain and water stop purposes, to an excavated hole into which mortar has been injected. ! r! This relates to a direct insertion method.

(従来の技術) 通常モルタルを注入した掘削孔へのI型鋼材の挿入は、
紀削孔の中央に1型鋼材を吊り下して行っている。また
一部では挿入位置の精度を出すために、掘削孔の上に枠
組によりI型鋼材の1Φ入穴を形成した定規を設置して
行っている。
(Prior art) Insertion of I-beam steel into an excavated hole with mortar injected is usually done by
This is done by suspending Type 1 steel material in the center of the drilling hole. In some cases, in order to ensure precision in the insertion position, a ruler with a 1Φ hole made of I-beam steel is installed on top of the excavation hole using a framework.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

通常I型鋼材は運搬時の積卸しに際して自単による反り
が生じ易い。このためI型鋼材のト・瑞を掘削孔の開口
部に垂直位首させて挿入してら、反りによって途中でI
型鋼材のフランジ先端が礼装に接し、I型鋼材の挿入を
困難となすばかりか、孔壁が崩れるなどの問題があった
Normally, I-shaped steel materials tend to warp due to self-stretching during loading and unloading during transportation. For this reason, when inserting an I-type steel member vertically into the opening of a drilling hole, the
The tip of the flange of the I-shaped steel came into contact with the formal attire, making it difficult to insert the I-shaped steel, as well as causing problems such as the hole wall collapsing.

この発明は上記従来の問題点を解決するために考えられ
たものであって、その目的は長尺になるほど挿入作業が
困難となるI型鋼材を手際よくモルタルを注入した掘削
孔に挿入することができる新たな工法を提供することに
ある。
This invention was devised to solve the above-mentioned conventional problems, and its purpose is to skillfully insert I-shaped steel materials, which become difficult to insert as they become longer, into an excavated hole into which mortar has been injected. The goal is to provide a new construction method that allows for

〔問題点を解決するための手段〕[Means for solving problems]

上記目的によるこの発明は、長尺のl型鋼材の下端に先
端部材を取付番プで、フランジ下端を傾斜面に形成し、
そのl型鋼材を地中に垂直に設けたケーシング内の所要
数のローラの間に吊り入れて、鋼材に生じたそりを直す
ぐに修正する一方、モルタルを注入した地中の柱列杭用
の掘削孔に、平面が長方形で四隅にl型鋼材の案内を有
する所要長さの定規を垂直に挿入し、その定規を作業台
により保持したのち、上記l型鋼材をケーシングから抜
き出し、上記定規を通して上記掘削孔に吊り持ちながら
垂直に挿入することを要旨とするものである。
The present invention according to the above-mentioned object has a tip member attached to the lower end of a long L-shaped steel member, and the lower end of the flange is formed into an inclined surface.
The L-shaped steel material is suspended between the required number of rollers in a casing installed vertically underground, and any warping that occurs in the steel material is immediately corrected. A ruler of the required length with a rectangular plane and guides for the L-shaped steel material at the four corners is vertically inserted into the excavation hole, and after holding the ruler on a workbench, the L-shaped steel material is extracted from the casing and the ruler is inserted into the hole. The gist of this method is to insert it vertically into the excavation hole while hanging it through the hole.

〔実施例〕〔Example〕

第1図に示すように、まず長尺(10m以上)の1型鋼
材1の下端に、フランジ1aの下端を内方へ傾斜形成す
る傾斜板2aを両側に有する先端部材2aを取付けて置
く。
As shown in FIG. 1, first, a tip member 2a having inclined plates 2a on both sides of which the lower end of the flange 1a is inclined inward is attached to the lower end of a long type 1 steel material 1 (10 m or more).

このIを鋼材1を、後記するソイルモルタル柱列杭用の
掘削孔とほぼ深さを同じくする掘削孔内に予め設けたケ
ーシング3内のローラ4の間に吊り下す。
This steel material 1 is suspended between rollers 4 in a casing 3 previously provided in an excavation hole having approximately the same depth as an excavation hole for soil mortar column piles to be described later.

上記ロー54は第2図及び第3図に示すように、ケーシ
ング3内に設けたフレーム3aに、一対ごと所要間隔を
空けて多段に設けられ、そのローラ4の間をl型鋼材1
はケーシング底部にまで吊り下されて、積卸しの際に生
じた反りが真すぐに修正される。
As shown in FIGS. 2 and 3, the rows 54 are provided in multiple stages at required intervals in pairs on the frame 3a provided in the casing 3, and between the rollers 4, an L-shaped steel member 1
is suspended to the bottom of the casing, and any warping that occurs during loading and unloading is straightened out.

また既に掘削されていて、モルタル(図面では省略)を
注入したソイルモルタル柱列杭用の掘削孔5には、第4
図に示すように、所要長さの定規6をI直に挿入する。
In addition, there is a fourth hole in the excavated hole 5 for soil mortar column piles that has already been drilled and injected with mortar (not shown in the drawing).
As shown in the figure, a ruler 6 of the required length is inserted directly into I.

この定規6は第8図に示すように、四隅に山型鋼材6a
による案内を有する平面形状が長方形のもので、各山型
鋼材6aは一定間隔ごとに鋼板6bにより囲繞されて一
体に連結されている。
As shown in FIG. 8, this ruler 6 has angle-shaped steel members 6a at the four corners.
The angle-shaped steel members 6a are surrounded by steel plates 6b at regular intervals and are integrally connected.

この定規6は上記に掘削孔5に垂直に挿入されたのち、
地上に設置した作業台7の垂直部材7aにて保持し、挿
入作業時に位置がずれないようにしである。
After this ruler 6 is inserted vertically into the excavation hole 5,
It is held by a vertical member 7a of a workbench 7 installed on the ground to prevent it from shifting during insertion work.

また作業台7には上記垂直部材7aと直交した水平部材
7bにジVツキ8が設けられ、これにより作業台7は地
面に対して水平に設置されている。
Further, the workbench 7 is provided with a jib 8 on a horizontal member 7b orthogonal to the vertical member 7a, so that the workbench 7 is installed horizontally with respect to the ground.

上記定規6の挿入と垂直保持作業が完了したならば、上
記ケーシング2内のl型鋼材1を地上に吊り上げそのま
ま掘削孔5の所まで移送する。
When the insertion of the ruler 6 and the vertical holding work are completed, the L-shaped steel member 1 in the casing 2 is lifted above the ground and transported to the excavation hole 5 as it is.

そして第5図に示すように、先端部材2を有する下端を
定規6に挿入し、その定規6を通してl型鋼材1を掘削
孔5に挿入する。
Then, as shown in FIG. 5, the lower end having the tip member 2 is inserted into a ruler 6, and the L-shaped steel material 1 is inserted into the excavated hole 5 through the ruler 6.

l型鋼材1の挿入が終ったならば、定規6を作業台7の
垂直部tJ7aから外し、第6図に示すように、上方へ
と吊り上げて掘削孔5から抜き出ず。
When the insertion of the L-shaped steel material 1 is completed, the ruler 6 is removed from the vertical part tJ7a of the workbench 7, and as shown in FIG. 6, it is lifted upward and not removed from the excavation hole 5.

その後、作業台7をも吊り上げて定規6と共に次の1型
鋼材の挿入位置に移動する。
Thereafter, the workbench 7 is also lifted and moved together with the ruler 6 to the insertion position for the next type 1 steel material.

以上のようにケーシング2内のローラ4により積卸時な
どに生じた反りを無くし、予め掘削孔5に挿入した定規
6を通して掘削孔5に挿入されたl型鋼材1は、それが
著しく長尺のものであっても、フランジ下端によって孔
壁をj負傷することなく、第7図に示すように、掘削孔
5に中央に設置される。
As described above, the L-shaped steel material 1 that is inserted into the excavated hole 5 through the ruler 6 inserted into the excavated hole 5 in advance is made to have a significantly long length. Even if it is a flange, it can be installed centrally in the borehole 5, as shown in FIG. 7, without damaging the borehole wall by the lower end of the flange.

〔発明の効果〕〔Effect of the invention〕

この発明は上述のように、長尺のl型鋼材の下端に、フ
ランジ下端を傾斜面となす傾斜板を有する。先端部材を
取付けたので、この先端部材により定規への挿入が容易
となるばかりか、フランジ下端によって、孔壁が損傷を
受けるようなこともない。
As described above, the present invention has an inclined plate at the lower end of the elongated L-shaped steel member, with the lower end of the flange serving as an inclined surface. Since the tip member is attached, the tip member not only facilitates insertion into the ruler, but also prevents the hole wall from being damaged by the lower end of the flange.

また掘削孔への挿入前に、l型鋼材の反りを真すぐに修
正したことから、反りによる挿入困難はなく、モルタル
が固化するまでの間に挿入作業を手際よ〈実施すること
ができるなどの特長を右する。
In addition, since we straightened the warpage of the L-shaped steel before inserting it into the excavation hole, there was no difficulty in inserting it due to warpage, and the insertion work could be carried out quickly and efficiently before the mortar solidified. Right features.

【図面の簡単な説明】 図面はこの発明に係る方法を示すもので、第1図はI型
m月の下端部の斜視図、第2図はケーシングの平面図、
第3図は同じく断面図、第4図から第7図は掘削孔への
挿入工程を順に示す断面図、第8図は定規の平面図であ
る。 1・・・・・・I型鋼材、   1a・・・・・・フラ
ンジ、2・・・・・・先端部材、   2a・・・・・
・傾斜板。 3・・・・・・ケーシング、  4・・・・・・ローラ
、5・・・・・・掘削孔、    6・−・・・・定規
、7・・・・・・作業台、    7a・・・・・・垂
直部材。
[BRIEF DESCRIPTION OF THE DRAWINGS] The drawings show the method according to the present invention, in which FIG. 1 is a perspective view of the lower end of the I-type moon, FIG. 2 is a plan view of the casing,
3 is a sectional view, FIGS. 4 to 7 are sectional views sequentially showing the process of inserting the ruler into an excavated hole, and FIG. 8 is a plan view of the ruler. 1...I type steel material, 1a...flange, 2...tip member, 2a...
・Slanted board. 3... Casing, 4... Roller, 5... Drilling hole, 6... Ruler, 7... Workbench, 7a... ...Vertical member.

Claims (1)

【特許請求の範囲】[Claims] 長尺のI型鋼材の下端に先端部材を取付けてフランジ下
端を傾斜面に形成し、そのI型鋼材を地中に垂直に設け
たケーシング内の所要数のローラの間に吊り入れて、鋼
材に生じたそりを直すぐに修正する一方、モルタルを注
入した地中の柱列杭用の掘削孔に、平面が長方形で四隅
にI型鋼材の案内を有する所要長さの定規を垂直に挿入
し、その定規を作業台により保持したのち、上記I型鋼
材をケーシングから抜き出し、上記定規を通して上記掘
削孔に吊り持ちながら垂直に挿入することを特長とする
ソイルモルタル柱列杭の鋼材挿入工法。
A tip member is attached to the lower end of a long I-shaped steel material, the lower end of the flange is formed into an inclined surface, and the I-shaped steel material is suspended between the required number of rollers in a casing installed vertically underground. While immediately correcting the warpage that occurred, a ruler of the required length with a rectangular plane and I-shaped steel guides at the four corners was inserted vertically into the mortar-injected underground column pile excavation hole. After holding the ruler on a workbench, the I-shaped steel material is extracted from the casing, and inserted into the excavation hole vertically while being suspended through the ruler.
JP14217386A 1986-06-18 1986-06-18 Insertion work of steel material of soil-mortar column-line pile Granted JPS63521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14217386A JPS63521A (en) 1986-06-18 1986-06-18 Insertion work of steel material of soil-mortar column-line pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14217386A JPS63521A (en) 1986-06-18 1986-06-18 Insertion work of steel material of soil-mortar column-line pile

Publications (2)

Publication Number Publication Date
JPS63521A true JPS63521A (en) 1988-01-05
JPH0362846B2 JPH0362846B2 (en) 1991-09-27

Family

ID=15309055

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14217386A Granted JPS63521A (en) 1986-06-18 1986-06-18 Insertion work of steel material of soil-mortar column-line pile

Country Status (1)

Country Link
JP (1) JPS63521A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5281213B1 (en) * 2013-03-15 2013-09-04 鹿島建設株式会社 Core material and soil cement continuous wall method using the same
CN104746510A (en) * 2015-03-24 2015-07-01 浙江省长城建设集团有限公司 Profile steel insertion positioning device and construction method thereof
JP2021011695A (en) * 2019-07-04 2021-02-04 鹿島建設株式会社 Core material for mountain retention wall and its installation method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5281213B1 (en) * 2013-03-15 2013-09-04 鹿島建設株式会社 Core material and soil cement continuous wall method using the same
CN104746510A (en) * 2015-03-24 2015-07-01 浙江省长城建设集团有限公司 Profile steel insertion positioning device and construction method thereof
CN104746510B (en) * 2015-03-24 2016-08-24 浙江省长城建设集团有限公司 A kind of shaped steel inserts positioner and construction method thereof
JP2021011695A (en) * 2019-07-04 2021-02-04 鹿島建設株式会社 Core material for mountain retention wall and its installation method

Also Published As

Publication number Publication date
JPH0362846B2 (en) 1991-09-27

Similar Documents

Publication Publication Date Title
US4146348A (en) Method for executing impermeable construction joints for diaphragm walls
CN108643918A (en) A kind of side wall template of launching shaft and the installation method of support system
JPS63521A (en) Insertion work of steel material of soil-mortar column-line pile
JPH0768705B2 (en) Soil retaining method and its retaining pile
CN111042104A (en) Method for constructing diaphragm wall at existing underground structure
JPH02282511A (en) Construction of sol pile column crest stop wall
US1895985A (en) Construction of retaining walls
GB1481186A (en) Concrete casting
CN110805046A (en) Foundation pit support steel sheet pile driving and arranging support structure and foundation pit support steel sheet pile driving and arranging method
CN211285657U (en) Double-walled steel cofferdam picture peg underwater anchoring structure based on finish rolling deformed steel bar
CN109469073B (en) Chute equipment and construction method thereof, and construction method of backfilling engineering
CN211421151U (en) Double-walled steel cofferdam based on picture peg
JPS6088724A (en) Sheathing work of excavated trench
JPS594723A (en) Sheathing and timbering work for excavated trench
JP2622597B2 (en) Rail connection method for elevators in pits
CN116856447A (en) Foundation pit template construction method
JPS6310250B2 (en)
JPH02274916A (en) Method for disassembling earth supporting timbering
JPH0673727A (en) Method of constructing soil pile column row earth retaining wall and special h-shaped steel bar
JP2794069B2 (en) Anchor construction method
JP2017197951A (en) Countermeasure wall against drawn-in subsidence and construction method thereof
SU1377354A1 (en) Modular forms
JPS61286414A (en) Constructing method for multispindle soil cement column line
JP3183992B2 (en) Jig for loading riser unit
JPS6335968A (en) Method of constructing underground chamber