JP2794069B2 - Anchor construction method - Google Patents

Anchor construction method

Info

Publication number
JP2794069B2
JP2794069B2 JP1029182A JP2918289A JP2794069B2 JP 2794069 B2 JP2794069 B2 JP 2794069B2 JP 1029182 A JP1029182 A JP 1029182A JP 2918289 A JP2918289 A JP 2918289A JP 2794069 B2 JP2794069 B2 JP 2794069B2
Authority
JP
Japan
Prior art keywords
drilling
anchor
construction
work
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP1029182A
Other languages
Japanese (ja)
Other versions
JPH02210114A (en
Inventor
昭 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TONE CHIKA GIJUTSU KK
Original Assignee
TONE CHIKA GIJUTSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONE CHIKA GIJUTSU KK filed Critical TONE CHIKA GIJUTSU KK
Priority to JP1029182A priority Critical patent/JP2794069B2/en
Publication of JPH02210114A publication Critical patent/JPH02210114A/en
Application granted granted Critical
Publication of JP2794069B2 publication Critical patent/JP2794069B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はアンカー施工方法に係り、特に削孔作業空間
の確保が困難な急斜面や堀削面の土留工事やよう壁工事
などに対して好適なアンカー施工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to an anchor construction method, and is particularly suitable for digging work on steep slopes and excavation surfaces where it is difficult to secure a drilling work space, and wall construction. Anchor construction method.

〔従来の技術〕[Conventional technology]

一般にアンカー工法は、地盤を削孔してアンカー体を
挿入し、セメントペースト等を注入して施工する。
Generally, the anchor method is performed by drilling a ground, inserting an anchor body, and injecting a cement paste or the like.

従来は、急斜面や堀削面の土留、あるいは斜面安定
工、地辷り抑止工などにアンカーを施工する場合、第3
図に示すように、根切底を基盤として削孔機を据付ける
か、削孔面に対面して作業用の足場又は構台などを仮設
し、その上に削孔機を据付けるのが通常であった。図中
の符号は、2が土留材、4は根切底又は仮設足場、6は
削孔機、8は削孔ハンマ、10は動力設備である。
Conventionally, when anchors are installed on steep slopes or excavations, or when stabilizing slopes or preventing landslides,
As shown in the figure, it is usual to install a drilling machine based on the root incision or to temporarily set up a work scaffold or gantry facing the drilling surface and install the drilling machine on it Met. In the drawings, reference numeral 2 denotes a retaining material, 4 denotes a root-cut bottom or a temporary scaffold, 6 denotes a drilling machine, 8 denotes a drilling hammer, and 10 denotes a power facility.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

しかしながら、削孔面の前面に作業空間を確保するの
が困難なときや、地辷り抑止工事のように勾配のある急
な斜面上での施工の場合には、大がかりな足場が必要と
なるという問題点があった。
However, when it is difficult to secure a working space in front of the drilling surface, or when performing construction on steep slopes such as landslide prevention work, a large scaffold is required. There was a problem.

また、そのため斜面に樹木などが生い茂っているとき
は、広範囲の伐採によって地山の強度が弱められ、更に
は環境上も問題があった。
In addition, when trees and the like are overgrown on the slope, the strength of the ground is reduced by extensive logging, and there is also an environmental problem.

この発明の目的は上記問題点に鑑みなされたもので、
削孔面の前面に削孔機等の重機を配置する必要のないア
ンカー施工方法を提供することである。
The object of the present invention has been made in view of the above problems,
It is an object of the present invention to provide an anchor construction method that does not require a heavy machine such as a drilling machine to be disposed in front of a drilling surface.

〔課題を解決するための手段〕[Means for solving the problem]

上記の目的を達成するために本発明のアンカー施工方
法は、急斜面又は堀削面等の土留工事におけるアンカー
施工方法であって、前記急斜面又は堀削面の上方に、バ
ックホーを位置せしめ、該バックホーの先端に取付けた
削孔ハンマによって該急斜面又は堀削面に削孔するアン
カー施工方法において、前記削孔ハンマに作業台を取付
けることを特徴とするものである。
In order to achieve the above object, the anchor construction method of the present invention is an anchor construction method in earth retaining work such as a steep slope or excavation surface, in which a backhoe is located above the steep slope or excavation surface, and the tip of the backhoe is An anchoring method for drilling a steep slope or excavation surface with a drilling hammer attached to a work surface, wherein a workbench is attached to the drilling hammer.

〔作用〕[Action]

上記構成によれば、急斜面や堀削面の上方の地盤上に
バックホーを配置し、その先端に取付けた削孔ハンマ
に、削孔作業が容易にできるように作業台を仮設して、
急斜面や堀削面を削孔することができるので、削孔面の
前面に重機を配置するための大がかりな足場等が不要と
なる。
According to the above configuration, the backhoe is arranged on the ground above the steep slope or the excavation surface, and a work table is temporarily provided on the drilling hammer attached to the tip thereof so that the drilling operation can be easily performed.
Since a steep slope or a drilling surface can be drilled, a large-scale scaffold or the like for arranging heavy equipment in front of the drilling surface is not required.

そのために経済的であり、大巾に工期の短縮を図るこ
とができる。
Therefore, it is economical and can greatly shorten the construction period.

〔実施例〕〔Example〕

以下本発明の一実施例を図面に基づいて説明する。 An embodiment of the present invention will be described below with reference to the drawings.

第1図の実施例は、斜面50に土留材52を施工し、埋土
54をしたのち上部に架台56を設け、その上にバックホー
58を配置し、その先端にはクラムシュル(図示せず)を
取外して削孔ハンマ60を取付け、削孔62を施工する。
尚、埋土54は最後に施工する場合もある。
In the embodiment shown in FIG.
After doing 54, set up the gantry 56 on the upper part,
58 is arranged, a clam sur (not shown) is removed from the tip, a drilling hammer 60 is attached, and a drilling hole 62 is formed.
The buried soil 54 may be applied last.

このような方法にすることによって、土留材52の前面
には大がかりな足場などが不要となる。
By adopting such a method, a large-scale scaffold or the like is not required in front of the earth retaining material 52.

図の例では削孔ハンマ60に作業台64を設けてある。こ
うすることによって削孔後も、アンカー体の挿入、セメ
ントペーストの注入等の作業を容易に行うことができ
る。
In the example shown in the figure, a work table 64 is provided on the drilling hammer 60. In this way, even after drilling, operations such as insertion of the anchor body and injection of the cement paste can be easily performed.

本実施例をよう壁工事に適用した例を第2図によって
説明する。第2図(A)〜(E)はよう壁工事の一連の
施工手順を示したものである。
An example in which this embodiment is applied to wall construction will be described with reference to FIG. FIGS. 2 (A) to 2 (E) show a series of construction procedures for wall construction.

まず、第2図(A)に示すように、斜面50にH鋼70を
杭打施工する。次いで第2図(B)に示すように横矢板
72を施工し、埋土54を埋戻し、第2図(C)に示すよう
によう壁74を施工し、アンカー部を箱抜する。
First, as shown in FIG. 2A, an H steel 70 is piled on the slope 50. Next, as shown in FIG.
72 is buried, the buried soil 54 is backfilled, the wall 74 is laid as shown in FIG. 2 (C), and the anchor portion is removed from the box.

次に、第2図(D)に示すように上部に架台56を設置
して、その上に第2図(E)に示すようにバックホー58
を配置して第1図において説明したようにアンカー工を
行う。符号78は施工後のアンカーである。第2図(F)
はアンカー部76の施工後のよう壁工完成を示す。
Next, the gantry 56 is installed on the upper part as shown in FIG. 2 (D), and the backhoe 58 is placed thereon as shown in FIG. 2 (E).
And anchoring is performed as described in FIG. Reference numeral 78 denotes an anchor after construction. FIG. 2 (F)
Indicates completion of the wall work as after the construction of the anchor portion 76.

本例によれば、アンカーの工のための仮設工事を大巾
に省略することができ、しかもなおアンカー自体の精度
は従来の方法によるものと全く変わらない。
According to this example, temporary construction work for anchor work can be largely omitted, and the accuracy of the anchor itself is not different from that of the conventional method.

〔発明の効果〕〔The invention's effect〕

上述のとおり本発明によれば、アンカー施工部の上方
に重機を配置することによって、かなりの仮設工事が省
略され、そのため工期が大巾に短縮され、極めて大きい
経済的効果を奏することができる。
As described above, according to the present invention, by arranging the heavy equipment above the anchor construction part, considerable temporary construction work is omitted, so that the construction period is greatly reduced, and a very large economic effect can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明の一実施例を示す説明図、第2図は本実
施例を適用した施工例の手順を示す説明図、第3図は従
来例を示す説明図である。 50……斜面、52……土留材、 54……埋土、56……架台、 58……バックホー、60……削孔ハンマー、 62……削孔、64……作業台、 70……H鋼、72……横矢板、 74……よう壁、76……アンカー部、 78……アンカー。
FIG. 1 is an explanatory diagram showing an embodiment of the present invention, FIG. 2 is an explanatory diagram showing a procedure of a construction example to which the present embodiment is applied, and FIG. 3 is an explanatory diagram showing a conventional example. 50 ... slope, 52 ... earth retaining material, 54 ... buried earth, 56 ... stand, 58 ... backhoe, 60 ... drilling hammer, 62 ... drilling, 64 ... work table, 70 ... H Steel, 72 ... horizontal sheet pile, 74 ... wall, 76 ... anchor, 78 ... anchor.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】急斜面又は堀削面等の土留工事におけるア
ンカー施工方法であって、前記急斜面又は堀削面の上方
にバックホーを位置せしめ、該バツクホーの先端に取付
けた削孔ハンマによって該急斜面又は堀削面に削孔する
アンカー施工方法において、前記削孔ハンマに作業台を
取付けることを特徴とするアンカー施工方法。
1. A method for anchoring a steep slope or excavation surface in an earth retaining work, wherein a backhoe is positioned above the steep slope or excavation surface, and the steep slope or excavation surface is drilled by a drilling hammer attached to a tip of the backhoe. An anchor installation method for drilling holes, wherein a work table is attached to the drilling hammer.
JP1029182A 1989-02-08 1989-02-08 Anchor construction method Expired - Fee Related JP2794069B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1029182A JP2794069B2 (en) 1989-02-08 1989-02-08 Anchor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1029182A JP2794069B2 (en) 1989-02-08 1989-02-08 Anchor construction method

Publications (2)

Publication Number Publication Date
JPH02210114A JPH02210114A (en) 1990-08-21
JP2794069B2 true JP2794069B2 (en) 1998-09-03

Family

ID=12269068

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1029182A Expired - Fee Related JP2794069B2 (en) 1989-02-08 1989-02-08 Anchor construction method

Country Status (1)

Country Link
JP (1) JP2794069B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101839112A (en) * 2010-05-11 2010-09-22 合肥航天液压机械有限公司 Adjusting device of frame pillar drilling machine

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5915928B2 (en) * 2011-12-22 2016-05-11 ライト工業株式会社 Quay reinforcement method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6234914A (en) * 1985-08-07 1987-02-14 Achilles Corp Production of flame-laminatable flame-retardant flexible polyurethane foam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101839112A (en) * 2010-05-11 2010-09-22 合肥航天液压机械有限公司 Adjusting device of frame pillar drilling machine
CN101839112B (en) * 2010-05-11 2013-06-26 合肥航天液压机械有限公司 Adjusting device of frame pillar drilling machine

Also Published As

Publication number Publication date
JPH02210114A (en) 1990-08-21

Similar Documents

Publication Publication Date Title
CN206706783U (en) A kind of reusable foundation pit supporting construction
JP2794069B2 (en) Anchor construction method
CN110067205A (en) A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing
JP6951950B2 (en) How to remove the pile
KR20160008828A (en) Earth retaining structure utilizing in-situ soil and earth retaining structure construction Method
JP6479554B2 (en) Branch line anchor and construction method of branch line anchor
JPH0768707B2 (en) Open caisson method
JPH032488A (en) Anchoring work
JPH059940A (en) Sinking method for caisson
JPH10252080A (en) Method for reinforcing foundation of pier for high level road
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JPS5985022A (en) Underground continuous wall constructing work
JPS6229625A (en) Settling construction for open caisson
KR100669530B1 (en) Construction method of a rataining well
JPS61155519A (en) Settlement work of caisson
JPH02248521A (en) Open shield method
JPS6192235A (en) Fixing of embedded pipe
JPS6133930B2 (en)
JPH07119471B2 (en) Board blister prevention method using an earth anchor
JPS62236922A (en) Method of reinforcing sheet pile-wall structure
SU619572A1 (en) Method of erecting storehouse in sinking soil
JP2586459Y2 (en) Drilling equipment
ATE429545T1 (en) METHOD FOR CREATING AN ANCHORAGE UNDER AN EXISTING BUILDING
JPH0240806B2 (en)
JPS5585731A (en) Method and apparatus for burying pile

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees