CN110067205A - A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing - Google Patents
A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing Download PDFInfo
- Publication number
- CN110067205A CN110067205A CN201910401047.1A CN201910401047A CN110067205A CN 110067205 A CN110067205 A CN 110067205A CN 201910401047 A CN201910401047 A CN 201910401047A CN 110067205 A CN110067205 A CN 110067205A
- Authority
- CN
- China
- Prior art keywords
- bridge pier
- pile casting
- steel pile
- wall
- pilot hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 238000012946 outsourcing Methods 0.000 title claims abstract description 10
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 76
- 239000010959 steel Substances 0.000 claims abstract description 76
- 238000005266 casting Methods 0.000 claims abstract description 70
- 238000005553 drilling Methods 0.000 claims abstract description 18
- 239000004927 clay Substances 0.000 claims abstract description 16
- 239000002985 plastic film Substances 0.000 claims abstract description 10
- 229920006255 plastic film Polymers 0.000 claims abstract description 10
- 238000009933 burial Methods 0.000 claims abstract description 5
- 238000001514 detection method Methods 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 3
- 239000003973 paint Substances 0.000 claims description 3
- 239000002689 soil Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 9
- 238000010586 diagram Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000004033 plastic Substances 0.000 description 2
- 229920003023 plastic Polymers 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
The invention belongs to technical field of bridge construction, propose a kind of permanent protecting tube embedding construction method of bridge pier column outsourcing.The permanent protecting tube embedding construction method of a kind of bridge pier column outsourcing proposed: 4~6 layers of plastic film are wound in bridge pier steel pile casting outer wall;Surveying and locating determines the burial place of bridge pier steel pile casting;Rotary drilling rig is in place and starts to perform construction pilot hole;When drilling to bridge pier protecting tube embedding bottom absolute altitude, downward outdrill 50cm;To the clay for the construction pilot hole bottom backfill 100cm being drilled with, is inverted using rotary drilling rig and be compacted clay;The bridge pier steel pile casting that outside wall surface is wound with plastic film is hung in construction pilot hole, and is accurately positioned, bridge pier steel pile casting is then pressed into clay 50cm;Bridge pier steel pile casting and perform wall is poured in gap between pilot hole inner wall between concrete;After concrete reaches intensity between wall, boring steel pile casting is installed.The characteristics of present invention is adaptable strong, convenient for construction, simple process.
Description
Technical field
The invention belongs to technical field of bridge construction, and in particular to a kind of permanent protecting tube embedding construction of bridge pier column outsourcing
Method, the method for excavating exposed permanent protecting tube embedding construction afterwards of first constructing especially suitable for bridge pier column.
Background technique
General protecting tube embedding method, using vibration hammer inserting piling steel pile casting.When vibration hammer operates, under the action of eccentric hammer
High-frequency vibration is generated, high frequency vibrating power acts on steel pile casting by hydraulic gripper, then the ground being in contact with it is transmitted to by steel pile casting
Layer makes the contact surface for contacting stratum generate " liquefaction ".Vibration hammer clamper and steel pile casting are under the action of exciting force and self weight, no
It is disconnected to sink to stratum, to then hollow out soil in steel pile casting in steel pile casting inserting piling to soil layer, sinking frictional resistance is reduced, so
After continue with vibration hammer inserting piling until inserting piling branch design altitude.But since geological layering is uneven, situations such as containing erratic boulder, vibration
Inserting piling steel pile casting is hammered into shape it is difficult to ensure that the accurate positioning of steel pile casting is spent with vertical, and steel pile casting is easily deformed, damaged.
Summary of the invention
To solve the existing deficiency of engineering technology, the purpose of the present invention is to propose to a kind of bridge pier column outsourcing permanent steel shield
Cylinder burial and construction method.
The present invention adopts the following technical solutions to accomplish the above objectives:
A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing, the specific steps of which are as follows:
1) bridge pier steel pile casting is processed, winds 4~6 layers of plastic film in bridge pier steel pile casting outer wall;
2) surveying and locating determines the burial place of bridge pier steel pile casting;
3) rotary drilling rig is in place and starts to perform construction pilot hole, the big 40cm of aperture ratio bridge pier steel pile casting outer diameter;
4) when drilling to bridge pier protecting tube embedding bottom absolute altitude, downward outdrill 50cm;
5) it to the clay for the construction pilot hole bottom backfill 100cm being drilled with, is inverted using rotary drilling rig and is compacted clay;
6) the bridge pier steel pile casting that outside wall surface is wound with plastic film is hung in construction pilot hole, and be accurately positioned, then by bridge
Pier steel pile casting is pressed into clay 50cm;
7) bridge pier steel pile casting upper surface is open and is accurately positioned and is fixed with timber wedge, the timber wedge is outside bridge pier steel pile casting
Wall surface and the multiple bolts for performing between pilot hole inner wall, being uniformly distributed along the circumference, in bridge pier steel pile casting and perform pilot hole inner wall
Concrete between wall is poured in gap between face;
8) after concrete reaches intensity between wall, the bolt is taken down, boring steel pile casting is installed;Boring steel pile casting
Internal diameter is greater than the internal diameter of bridge pier steel pile casting;The lower end of the boring steel pile casting is supported between the wall on concrete, on
Distal process backfills clay for described performs pilot hole, in the gap between pilot hole and boring steel pile casting and tamps;
9) rotary drilling rig continues drilling to stake bottom absolute altitude, and bridge pile foundation steel bar cage is installed in hole, pours pile foundation concrete to setting
Absolute altitude, and superfilled 50cm are counted, boring steel pile casting is pulled out;
10) after pile foundation concrete reaches intensity, pile crown is excavated and cut, carries out pile measurement, bent cap of constructing after detection is qualified
And superstructure;
11) after the completion of the construction of other structures object, the earthwork under bridge is excavated, by steel pile casting outer wall concrete chisel removal, it is thin to remove plastics
Film brushes antirusting paint.
The permanent protecting tube embedding construction method of a kind of bridge pier column outsourcing proposed by the present invention, by adopting the above technical scheme,
Compared to existing protecting tube embedding construction method, the present invention is accurately positioned simultaneously fixed steel pile casting by construction pilot hole, and hole wall with
The method of concrete perfusion between steel pile casting outer wall, while guaranteeing that steel pile casting is accurately positioned and spends vertically, steel pile casting is not variable
Shape, damage, and image appearance is good after excavation;The characteristics of this method is adaptable strong, convenient for construction, simple process simultaneously.
Detailed description of the invention
Fig. 1 is bridge pier protecting tube embedding of the present invention and fixed schematic diagram;
Fig. 2 is the A-A cross-sectional view of Fig. 1.
Fig. 3 is that the present invention pours concrete and the boring steel pile casting schematic diagram of installation between wall;
Fig. 4 is the B-B cross-sectional view of Fig. 3.
Fig. 5 is the C-C cross-sectional view of Fig. 3.
In figure: 1, bridge pier steel pile casting;2, plastic film;3, construction pilot hole;4, clay;5, timber wedge;6, concrete between wall;7,
Boring steel pile casting.
Specific embodiment
The present invention is illustrated with reference to the drawings and specific embodiments:
As shown in Figure 1, and combine Fig. 2, a kind of permanent protecting tube embedding construction method of bridge pier column outsourcing, specific steps are such as
Under:
1) bridge pier steel pile casting 1 is processed, winds 4~6 layers of plastic film 2 in 1 outer wall of bridge pier steel pile casting;
2) surveying and locating determines the burial place of bridge pier steel pile casting 1;
3) rotary drilling rig is in place and starts to perform construction pilot hole 3, the 1 big 40cm of outer diameter of aperture ratio bridge pier steel pile casting;
4) when drilling buries bottom absolute altitude to bridge pier steel pile casting 1, downward outdrill 50cm;
5) it to the clay 4 for 3 bottom of the construction pilot hole backfill 100cm being drilled with, is inverted using rotary drilling rig and is compacted clay;
6) the bridge pier steel pile casting 1 that outside wall surface is wound with plastic film is hung in construction pilot hole 3, and be accurately positioned, then will
Bridge pier steel pile casting 1 is pressed into clay 50cm;
7) bridge pier steel pile casting upper surface is open and is accurately positioned and is fixed with timber wedge 5, the timber wedge is positioned at bridge pier steel pile casting
Outside wall surface and the multiple bolts for performing between pilot hole inner wall, being uniformly distributed along the circumference, in bridge pier steel pile casting and perform in pilot hole
Concrete 6 between wall is poured in gap between wall surface;
8) it combines shown in Fig. 3, Fig. 4, Fig. 5, after concrete reaches intensity between wall, takes down the bolt, install boring
Steel pile casting 7;The internal diameter of boring steel pile casting is greater than the internal diameter of bridge pier steel pile casting;The lower end of the boring steel pile casting is supported on
Between the wall on concrete, upper end protrude from it is described perform pilot hole, in the gap between pilot hole and boring steel pile casting
Backfill clay is simultaneously tamped;
9) rotary drilling rig continues drilling to stake bottom absolute altitude, and bridge pile foundation steel bar cage is installed in hole, pours pile foundation concrete to setting
Absolute altitude, and superfilled 50cm are counted, boring steel pile casting is pulled out;
10) after pile foundation concrete reaches intensity, pile crown is excavated and cut, carries out pile measurement, bent cap of constructing after detection is qualified
And superstructure;
11) after the completion of the construction of other structures object, the earthwork under bridge is excavated, by steel pile casting outer wall concrete chisel removal, it is thin to remove plastics
Film brushes antirusting paint.
Preferred embodiment above is only used to illustrate the technical scheme of the present invention and not to limit it, although passing through above-mentioned preferred implementation
Example is described in detail the present invention, however, those skilled in the art should understand that, can be in the form and details
The selection that concrete material between various changes, such as steel pile casting material, wall is made to it, without departing from right of the present invention
Claim limited range.
Claims (1)
1. a kind of permanent protecting tube embedding construction method of bridge pier column outsourcing, it is characterised in that: the specific steps of construction method are such as
Under: 1) bridge pier steel pile casting is processed, winds 4~6 layers of plastic film in bridge pier steel pile casting outer wall;2) surveying and locating determines bridge pier
The burial place of steel pile casting;3) rotary drilling rig is in place and starts to perform construction pilot hole, and aperture ratio bridge pier steel pile casting outer diameter is big
40cm;4) when drilling to bridge pier protecting tube embedding bottom absolute altitude, downward outdrill 50cm;5) it is returned to the construction pilot hole bottom being drilled with
The clay for filling out 100cm is inverted using rotary drilling rig and is compacted clay;6) the bridge pier steel that outside wall surface is wound with plastic film is protected
Cylinder is hung in construction pilot hole, and is accurately positioned, and bridge pier steel pile casting is then pressed into clay 50cm;It 7) will be on bridge pier steel pile casting
End face opening is accurately positioned and is fixed with timber wedge, and the timber wedge is positioned at bridge pier steel pile casting outside wall surface and to perform pilot hole inner wall
Between, multiple bolts for being uniformly distributed along the circumference, in bridge pier steel pile casting and perform in gap between pilot hole inner wall and pour wall
Between concrete;8) after concrete reaches intensity between wall, the bolt is taken down, boring steel pile casting is installed;Boring steel
The internal diameter of casing is greater than the internal diameter of bridge pier steel pile casting;The lower end of the boring steel pile casting is supported on concrete between the wall
On, upper end protrude from it is described perform pilot hole, clay is backfilled in the gap between pilot hole and boring steel pile casting and is tamped;
9) rotary drilling rig continues drilling to stake bottom absolute altitude, and bridge pile foundation steel bar cage is installed in hole, pours pile foundation concrete to designing mark
Height, and superfilled 50cm, pull out boring steel pile casting;10) after pile foundation concrete reaches intensity, pile crown is excavated and cut, is carried out
Pile measurement, construct after detection is qualified bent cap and superstructure;11) after the completion of the construction of other structures object, soil under bridge is excavated
Steel pile casting outer wall concrete chisel removal is removed plastic film by side, brushes antirusting paint.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910401047.1A CN110067205B (en) | 2019-05-15 | 2019-05-15 | Construction method for embedding permanent steel pile casing wrapped outside bridge pier stud |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910401047.1A CN110067205B (en) | 2019-05-15 | 2019-05-15 | Construction method for embedding permanent steel pile casing wrapped outside bridge pier stud |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN110067205A true CN110067205A (en) | 2019-07-30 |
| CN110067205B CN110067205B (en) | 2020-07-24 |
Family
ID=67370826
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910401047.1A Active CN110067205B (en) | 2019-05-15 | 2019-05-15 | Construction method for embedding permanent steel pile casing wrapped outside bridge pier stud |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110067205B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110468832A (en) * | 2019-08-01 | 2019-11-19 | 上海建工七建集团有限公司 | Abolish the structure and its construction method of the outer concrete of steel pile casting |
| CN112482201A (en) * | 2020-10-16 | 2021-03-12 | 中铁十九局集团第五工程有限公司 | Permanent steel casing and using method thereof |
| CN117845905A (en) * | 2024-01-29 | 2024-04-09 | 甘肃路桥建设集团有限公司 | A construction method for loose piled empty fill pile foundation steel-concrete composite retaining wall |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH09184303A (en) * | 1995-12-28 | 1997-07-15 | Tokyu Constr Co Ltd | Lining steel plate and reinforcing method for existing columnar body |
| RU2386744C1 (en) * | 2009-04-02 | 2010-04-20 | Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов" - "Гипротрансмост" | Method for bridge erection |
| CN102071645A (en) * | 2010-12-31 | 2011-05-25 | 中铁大桥局集团有限公司 | Bridge bored pile hole wall opening protection method |
| CN103088814A (en) * | 2013-02-27 | 2013-05-08 | 路桥华祥国际工程有限公司 | Rotary drilling rig coordinated with percussion drill hole-forming construction method |
| CN204530694U (en) * | 2015-04-14 | 2015-08-05 | 中交一公局第六工程有限公司 | Pier stud pile foundation steel pile casting under a kind of single pile water receiving |
| CN109281253A (en) * | 2018-10-22 | 2019-01-29 | 中交路桥华南工程有限公司 | Steel casing device and lowering construction method thereof |
-
2019
- 2019-05-15 CN CN201910401047.1A patent/CN110067205B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH09184303A (en) * | 1995-12-28 | 1997-07-15 | Tokyu Constr Co Ltd | Lining steel plate and reinforcing method for existing columnar body |
| RU2386744C1 (en) * | 2009-04-02 | 2010-04-20 | Открытое акционерное общество ОАО "Институт по изысканиям и проектированию мостовых переходов" - "Гипротрансмост" | Method for bridge erection |
| CN102071645A (en) * | 2010-12-31 | 2011-05-25 | 中铁大桥局集团有限公司 | Bridge bored pile hole wall opening protection method |
| CN103088814A (en) * | 2013-02-27 | 2013-05-08 | 路桥华祥国际工程有限公司 | Rotary drilling rig coordinated with percussion drill hole-forming construction method |
| CN204530694U (en) * | 2015-04-14 | 2015-08-05 | 中交一公局第六工程有限公司 | Pier stud pile foundation steel pile casting under a kind of single pile water receiving |
| CN109281253A (en) * | 2018-10-22 | 2019-01-29 | 中交路桥华南工程有限公司 | Steel casing device and lowering construction method thereof |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110468832A (en) * | 2019-08-01 | 2019-11-19 | 上海建工七建集团有限公司 | Abolish the structure and its construction method of the outer concrete of steel pile casting |
| CN112482201A (en) * | 2020-10-16 | 2021-03-12 | 中铁十九局集团第五工程有限公司 | Permanent steel casing and using method thereof |
| CN117845905A (en) * | 2024-01-29 | 2024-04-09 | 甘肃路桥建设集团有限公司 | A construction method for loose piled empty fill pile foundation steel-concrete composite retaining wall |
Also Published As
| Publication number | Publication date |
|---|---|
| CN110067205B (en) | 2020-07-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2022502586A (en) | Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles | |
| CN107023002A (en) | Down-the-hole impacts churning composite pile pile making method | |
| JP2022528743A (en) | Wall subsidence construction method | |
| CN102888834B (en) | A kind of construction method of major diameter broken stone pile | |
| KR101071958B1 (en) | underground excuvation pile construction method using percussion rotary drill | |
| CN108842802A (en) | Piles in Karst Region base construction method | |
| CN204199335U (en) | A kind of pressure release well reducing PHC tube pile construction soil compaction effect | |
| CN113431039A (en) | Construction method of bridge implanted pile | |
| CN110387879A (en) | A kind of concrete filling pile construction method of hydraulic vibration hammer hidden pipe | |
| CN104532853A (en) | Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning | |
| US10487468B2 (en) | Mandrel and a method for soil compaction | |
| CN108775036A (en) | A kind of construction method for replacing bored concrete pile | |
| CN112281880A (en) | A kind of construction method of long spiral guide hole inserting and locking steel pipe pile cofferdam in complex stratum | |
| CN112064751A (en) | Deep groove construction method for drainage pipeline | |
| CN209958343U (en) | Connecting joint for connecting reinforced concrete cast-in-place piles | |
| CN110067205B (en) | Construction method for embedding permanent steel pile casing wrapped outside bridge pier stud | |
| CN102953392A (en) | Pile foundation structure of photovoltaic power station and construction process of pile foundation | |
| CN109653196A (en) | A kind of depth mound backfill reaming casing method | |
| CN203007940U (en) | Tubular pile protection structure in side slope hammering construction | |
| CN105002912A (en) | Construction method for splicing type caisson structure based on prefabricated hollow piles | |
| CN108330964A (en) | Complicated landform steel pile casting mounting device and its installation method | |
| CN110206026B (en) | A method of backfilling deep hills to form holes and piles | |
| CN112878315A (en) | End-bearing rotary-digging hole-forming cast-in-place pile based on Civil 3D technology and construction method | |
| CN115748729A (en) | PC (polycarbonate) composite pile construction method based on large-particle-size stone backfill layer | |
| CN116716879A (en) | An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |