JPS63197718A - Construction work of in-situ pile - Google Patents

Construction work of in-situ pile

Info

Publication number
JPS63197718A
JPS63197718A JP2915987A JP2915987A JPS63197718A JP S63197718 A JPS63197718 A JP S63197718A JP 2915987 A JP2915987 A JP 2915987A JP 2915987 A JP2915987 A JP 2915987A JP S63197718 A JPS63197718 A JP S63197718A
Authority
JP
Japan
Prior art keywords
hole
earth auger
cement milk
tip
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2915987A
Other languages
Japanese (ja)
Inventor
Akiyoshi Nojiri
野尻 明美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2915987A priority Critical patent/JPS63197718A/en
Publication of JPS63197718A publication Critical patent/JPS63197718A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To form a concrete pile by removing slime by a method in which the tip of earth auger is sufficiently thrust into the bearing layer, cement milk is injected to the bottom of pit and sufficiently mixed to form a gel block, and the gel block is pulled up. CONSTITUTION:By using an earth auger 1, the wall of a pile pit 8 is pressed by the periphery of a drum 5 for troweling treatment, and the pit 8 thrusted through the bearing layer 18 is excavated. Cement milk 9 is injected to the bottom of the pit 8 and mixed with sand and gravel to form a gel block 10. The auger 1 is pulled up with the gel block 10, and cement mortar 11 is injected from the lower end of a rotary shaft 2 and packed into the space to form a pile. The ground of the bearing layer can thus be improved and a highly reliable pile securely joined to the ground and having a great bearing force can be obtained.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、建設工事の基礎工として現場造成杭を施工す
る方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Field of Application] The present invention relates to a method for constructing site-prepared piles as foundation work for construction work.

〔従来の技術とその問題点〕[Conventional technology and its problems]

かかる現場造成杭は、周知なごとくオーガスクリユー等
の掘削機を用いて地中に孔を造成し、この孔内に鉄筋カ
ゴを挿入してからコンクリート又はモルタルを打設して
柱体を形成するものである。
As is well known, such on-site piles are created by creating a hole in the ground using an excavator such as an auger screw, inserting a reinforcing cage into the hole, and then pouring concrete or mortar to form a column. It is something to do.

このような現場造成杭においては、地盤に対する支持力
を良好に保つことが要求され、スライムの処理及びコン
クリート下端と地盤の結合が問題となる。
Such on-site construction piles are required to maintain good bearing capacity with respect to the ground, and problems arise in handling slime and bonding the lower end of the concrete to the ground.

また、削孔時に孔壁が崩壊すると杭の形状が悪くなり、
信顛性が乏しくなる。
Additionally, if the hole wall collapses during drilling, the shape of the pile will deteriorate;
Credibility becomes poor.

スライムの処理については、種々の方法が従来提案され
、例えばこれを機械的に取出す方法やスライム中にセメ
ントミルクを混入してフィルセメントを生成する方法な
どがあるが、独自の装置を用いてスライムを取出すのは
きわめて困難なことであり、フィルセメントにする方法
では通常のコンクリートより強度が低下してしまう。
Various methods have been proposed for processing slime, including a method of mechanically extracting it and a method of mixing cement milk into slime to produce fill cement. It is extremely difficult to remove it, and using fill cement reduces its strength compared to regular concrete.

一方、孔壁崩壊防止として削孔内をベントナイト液で充
填することも行われているが、充分なものではない。
On the other hand, filling the inside of the drilled hole with bentonite liquid has been attempted to prevent the collapse of the hole wall, but this is not sufficient.

本発明の目的は前記従来例の不都合を解消し、孔壁の崩
壊を確実に防止し、またスライムを効果的に除去して少
ない工程で信鯨性に冨むコンクリート又はモルタル杭が
得られる現場造成杭の施工法を提供することにある。
The purpose of the present invention is to solve the above-mentioned disadvantages of the conventional example, reliably prevent the collapse of the hole wall, and effectively remove slime to obtain concrete or mortar piles with high reliability in a few steps. The purpose of this invention is to provide a construction method for constructed piles.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は前記目的を達成するため、掘削羽根を先端に設
け、途中に練付用ドラムを形成した中空回転軸によるア
ースオーガを使用して、該ドラムで杭孔壁を加圧縁付け
しながら孔を形成して先端部が砂や礫層などの支持層に
充分貫入した後、必要に応じて孔底を拡径しながら回転
軸端より孔底にセメントミルクを注入してアースオーガ
の先端で支持層中の砂や礫と十分混練することにより支
持層を改良し、また前記セメントミルクを硬化剤等によ
りゲル化物とし、アースオーガとともに該ゲル化物も引
上げ、同時に孔内にモルタル又はセメントミルクを注入
してこれで孔内を充填し、次いで孔内に鉄筋カゴ又は鋼
材などの芯材を建込むことを要旨とするものである。
In order to achieve the above-mentioned object, the present invention uses an earth auger with a hollow rotary shaft provided with a digging blade at the tip and a kneading drum formed in the middle. After the tip has sufficiently penetrated the supporting layer such as sand and gravel, cement milk is injected into the bottom of the hole from the rotating shaft end while expanding the diameter of the hole bottom as necessary, and the tip of the earth auger is inserted into the bottom of the hole. The support layer is improved by thoroughly kneading it with the sand and gravel in the support layer, and the cement milk is made into a gel by using a hardening agent, etc., and the gel is pulled up together with the earth auger. At the same time, mortar or cement milk is poured into the hole. The gist of this method is to inject the material into the hole, fill it, and then install a core material such as a reinforcing bar cage or steel material inside the hole.

〔作用〕[Effect]

本発明によれば、孔掘削時に掘削土を孔壁に練付けるの
で、孔壁が補強されその崩壊を防止できる。また、孔底
に大量発生するスライムはこれをドラムとセメントミル
クのゲル化物上に乗せてアースオーガを引き上げる時に
排除できる。さらに、孔底に注入されたセメントミルク
は支持層の緩みを改良し、支持力が大きくとれる。
According to the present invention, since the excavated soil is kneaded into the hole wall during hole excavation, the hole wall is reinforced and its collapse can be prevented. In addition, a large amount of slime generated at the bottom of the hole can be removed by placing it on the drum and cement milk gel and pulling up the earth auger. Furthermore, the cement milk injected into the bottom of the hole improves the loosening of the support layer and increases the supporting force.

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.

第1図〜第8図は本発明の現場造成杭の施工法の第1実
施例の各工程を示す断面図で、先に本発明工法で用いる
アースオーガ1について説明する。
FIGS. 1 to 8 are cross-sectional views showing each step of a first embodiment of the method for constructing on-site piles according to the present invention. First, the earth auger 1 used in the method of the present invention will be explained.

該アースオーガ1は、中空回転軸2の先端に、複数の並
列する掘削ビット3を突設したスクリュー状の掘削羽根
4を設け、該軸2の途中の適宜位置に練付用ドラム5を
取付けたものである。さらに、軸2の該ドラム5間には
、放射状に突出する攪拌羽根6やスクリュー羽根(図示
せず)を設けることもある。
The earth auger 1 is provided with a screw-shaped excavation blade 4 having a plurality of parallel excavation bits 3 protruding from the tip of a hollow rotary shaft 2, and a kneading drum 5 is attached at an appropriate position in the middle of the shaft 2. It is something that Furthermore, between the drums 5 of the shaft 2, radially protruding stirring blades 6 or screw blades (not shown) may be provided.

前記ドラム5は、−例として平面において90度の扇形
体が軸2に対称となるように取付けられて形成され、か
つ平面形状とほぼ同一の平面形状を有する蓋を上面に設
けている。
The drum 5 is formed by, for example, a 90 degree fan-shaped body attached symmetrically to the axis 2 in a plane, and is provided with a lid on the top surface having a planar shape substantially the same as the planar shape.

このようなアースオーガ1を用いて、杭孔8の掘削予定
位置へ所定直径の孔を掘削する(第1図)。
Using such an earth auger 1, a hole of a predetermined diameter is excavated at the planned excavation position of the pile hole 8 (FIG. 1).

この場合、掘削土はスクリュー状の掘削羽根4により上
方に運ばれ、攪拌羽根6等で破砕されて細かくなる。さ
らにその一部(掘削土の土質によっても異なるが相当量
)は練付用ドラム5の外周面で杭孔8の壁に加圧状態で
コテ塗りされる。
In this case, the excavated soil is transported upward by a screw-shaped excavation blade 4 and crushed by an agitation blade 6 or the like to become fine. Furthermore, a portion (a considerable amount, although it varies depending on the quality of the excavated soil) is troweled onto the wall of the pile hole 8 on the outer peripheral surface of the kneading drum 5 under pressure.

なお、掘削時に回転軸2の先端から適量の水を噴出すれ
ば、掘削を円滑にすることができるとともに掘削土を泥
土化して前記練付けも一層容易にすることができる。
Incidentally, if an appropriate amount of water is squirted from the tip of the rotary shaft 2 during excavation, the excavation can be made smoother, and the excavated soil can be turned into mud, thereby making the kneading process even easier.

さらに、地盤によっては孔8内にベントナイト液などの
安定液を充填することも考えられる。
Furthermore, depending on the ground, it is also possible to fill the hole 8 with a stabilizing liquid such as bentonite liquid.

このようにして、第2図に示すように前記アースオーガ
1によりその先端部が砂や礫層などの支持711Bに十
分貫入する所定深さの杭孔8を掘削したならば、回転軸
2の中空内部を利用してその先端からセメントミルク9
を杭孔底部に所定量流入すると、該セメントミルク9は
第3図に示すように掘削羽根4を包み込むように充填さ
れ、同時にアースオーガ1を回転すれば、掘削羽根4に
よりセメントミルク9は支持層18の砂や礫などと混練
され、掘削により緩んだ支持層18を改良する。
As shown in FIG. Using the hollow inside, pour cement milk from the tip 9
When a predetermined amount of cement milk 9 flows into the bottom of the pile hole, the cement milk 9 is filled so as to wrap around the excavation blade 4 as shown in FIG. It is mixed with sand, gravel, etc. of the layer 18 to improve the support layer 18 that has become loose due to excavation.

次いで、又は事前に、適量のセメント硬化剤を軸2端よ
り注入する。第4図に示すようにアースオーガ1を上下
動させ、さらにこれを回転するようにすれば、セメント
ミルクとセメント硬化剤とは均一に混合され、硬化剤の
セメントミルクへのン受透性もよくなる。
Next, or in advance, an appropriate amount of cement hardening agent is injected from the two ends of the shaft. As shown in Figure 4, by moving the earth auger 1 up and down and then rotating it, the cement milk and the cement hardening agent are mixed uniformly, and the permeability of the hardening agent to the cement milk is also improved. get well.

10分程度たつと、第5図に示すように硬化剤によりセ
メントミルクはゲル化して全体が円筒状の塊りとなるが
、該ゲル化物10はその内部に杭孔底付近で発生するス
ライムを取込んでしまう。このゲル化物10は、硬化剤
を用いずに時間の経過をまって形成することもできる。
After about 10 minutes, the cement milk is gelled by the hardening agent and becomes a cylindrical lump as shown in FIG. I will take it in. This gelled material 10 can also be formed over time without using a curing agent.

そして、第6図に示すように泥土状のセメントミルクの
ゲル化物10とともにアースオーガ1を引上げると、残
りのスライムは前記ドラム5上やゲル化物10上に乗っ
て孔外へと排出される。
Then, as shown in FIG. 6, when the earth auger 1 is pulled up together with the mud-like cement milk gel 10, the remaining slime rides on the drum 5 and the gel 10 and is discharged out of the hole. .

この引上げ時には回転軸2の下端よりモルタル又はセメ
ントミルク11を注入してゲル化物10が上昇して形成
される空間を充填していく。このうち、モルタルを使用
する場合は硬化遅延剤を使用して短時間で硬化してしま
わないようにすることが望ましい。
At this time of pulling up, mortar or cement milk 11 is injected from the lower end of the rotating shaft 2, and the gelled material 10 rises to fill the space formed. Among these, when using mortar, it is desirable to use a curing retarder to prevent it from curing in a short time.

なお、前記セメントミルクのゲル化物10は杭孔8内で
栓状前となっており、前記モルタル又はセメントミルク
11の注入は、このゲル化物10の上昇でその下方が陰
圧となりアースオーガ1の引上げ負荷が増大することを
防止するとともに、むしろその注入圧でゲル化物10を
積極的に押上げ、アースオーガ1の引上げを助ける役割
をなす。
The cement milk gel 10 is in the form of a plug inside the pile hole 8, and when the mortar or cement milk 11 is injected, the rise of the gel 10 creates a negative pressure below the earth auger 1. It prevents the lifting load from increasing, and rather actively pushes up the gelled material 10 with its injection pressure, thus serving to assist the lifting of the earth auger 1.

、さらに、孔壁は前記のごとくドラム5でならされてい
るので、ゲル化物10の引き上げは引っかかることなく
スムーズに行われる。
Furthermore, since the hole walls are smoothed by the drum 5 as described above, the gelled material 10 can be pulled up smoothly without getting caught.

このようにして、第7図に示すように杭孔8内はモルタ
ル又はセメントミルク11ですべて充填されるが、次い
で、第8図に示すように杭孔8内へ芯材としての鉄筋カ
ゴ12を圧入すれば、杭が形成される。かかる芯材とし
ては、鉄筋カゴ12の他にH型鋼等の綱材を用いてもよ
い。
In this way, the inside of the pile hole 8 is completely filled with mortar or cement milk 11, as shown in FIG. 7. Next, as shown in FIG. By press-fitting, a pile is formed. As such a core material, in addition to the reinforcing bar cage 12, a rope material such as H-shaped steel may be used.

次に、特許請求の範囲第2項の発明について説明すると
、使用するアースオーガとしては前記第1実施例で説明
したオーガ1の掘削羽根4に拡大翼17を設けたもので
ある。
Next, the invention of claim 2 will be explained. The earth auger used is one in which an enlarged blade 17 is provided on the excavation blade 4 of the auger 1 described in the first embodiment.

第9図〜第16図は各工程を示すもので、アースオーガ
1を用いて、杭孔8の掘削予定位置へ線材用ドラム5で
杭孔8の壁に掘削土をコテ塗りしながら所定直径の孔を
掘削する(第9図)。
Figures 9 to 16 show each process. Using the earth auger 1, the wire rod drum 5 is used to trowel the wall of the pile hole 8 with excavated soil to the planned excavation position of the pile hole 8 to a predetermined diameter. Drill a hole (Figure 9).

第10図に示すように前記ア・−スオーガ1によりその
先端部が砂や礫層などの支持層18に充分貫入した所定
深さの杭孔8を掘削したならば、アースオーガ1を逆方
向に回転させると、第11図に示すように拡大翼17が
拡がり、この拡大翼17で杭孔8の底部に拡径部8aが
形成される。そして、その前又は後に回転軸2の中空内
部を利用してその先端からセメントミルク9を杭孔底部
に所定量流入すれば、セメントミルク9は支持層の砂や
礫などと混練され、掘削により緩んだ支持層を改良する
As shown in FIG. 10, once the earth auger 1 has excavated a pile hole 8 of a predetermined depth with its tip sufficiently penetrating the supporting layer 18 such as sand or gravel layer, the earth auger 1 is moved in the opposite direction. When rotated, the enlarged wings 17 expand as shown in FIG. 11, and the enlarged wings 17 form an enlarged diameter portion 8a at the bottom of the pile hole 8. Before or after that, if a predetermined amount of cement milk 9 is flowed into the bottom of the pile hole from the tip using the hollow interior of the rotating shaft 2, the cement milk 9 is mixed with the sand and gravel of the supporting layer, and as a result of excavation. Repair loose support layers.

次いで、第12図に示すようにアースオーガ1を上下動
し、さらにこれを回転するようにして、適量のセメント
硬化剤等で第13図に示すようにセメントミルク9をゲ
ル化して全体が円筒状の塊りとし、第14図に示すよう
にゲル化物10とともにアースオーガ1を引上げる。な
お、前記拡径部8aでセメントミルク11のゲル化物1
0は多少球根状となるが、それ自体比較的柔らかいもの
なので上方へ引上げるには支障ない。
Next, as shown in FIG. 12, the earth auger 1 is moved up and down, and further rotated, and the cement milk 9 is gelled with an appropriate amount of cement hardening agent, etc., as shown in FIG. 13, so that the whole becomes cylindrical. The ground auger 1 is pulled up together with the gelled material 10 as shown in FIG. In addition, the gelled product 1 of the cement milk 11 is formed in the expanded diameter portion 8a.
0 has a somewhat bulbous shape, but since it itself is relatively soft, there is no problem in pulling it upward.

この引上げ時にはオーガ1の引上げで前記ゲル化物10
が上昇して形成される空間にオーガ1の軸2端からモル
タル又はセメントミルク11を圧入してい(。
At this time of pulling up, the gelled material 10 is pulled up by the auger 1.
Mortar or cement milk 11 is press-fitted from the shaft 2 end of the auger 1 into the space created by the rising of the auger (.

−次いで、第16図に示すように杭孔8内へ芯材として
の鉄筋カゴ12又は鋼材を建込めば、先端が拡径した支
持力の高い鉄筋コンクリートの現場造成杭が形成される
- Next, as shown in FIG. 16, by erecting a reinforcing cage 12 or a steel material as a core material into the pile hole 8, a site-made reinforced concrete pile with a large diameter end and high bearing capacity is formed.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明の現場造成杭の施工決は、孔壁
の崩壊を確実に防止して形状が良いコンクリート又はモ
ルタル杭が得られ、またスライムを効果的に除去できて
支持力の低下を招くこともない。さらに、孔底にセメン
トミルクを注入して、支持層の地盤改良を行うので地盤
の結合が確実で支持力の大きい信頼性の高い杭が得られ
るものである。
As mentioned above, the construction of the site-prepared pile of the present invention reliably prevents the collapse of the hole wall and provides a concrete or mortar pile with a good shape, and can effectively remove slime, which reduces the reduction in bearing capacity. There is no invitation. Furthermore, since cement milk is injected into the bottom of the hole to improve the ground of the supporting layer, a highly reliable pile with a high bearing capacity and a secure connection to the ground can be obtained.

加えて、一連の工程を一つのアースオーガで行え、施工
速度の速いものとなり、しかも、アースオーガの引上げ
と同時にその下端からモルタル又はセメントミルクを注
入し、次いで鉄筋カゴを建込むだけで杭が形成できるの
で、工程数が少なく施工の合理化を図ることができるも
のである。
In addition, a series of processes can be performed with one earth auger, resulting in faster construction.Moreover, the piles can be built simply by injecting mortar or cement milk from the lower end at the same time as the earth auger is pulled up, and then erecting the rebar cage. Since it can be formed, the number of steps is small and construction can be streamlined.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第8図は本発明の現場造成杭の施工法の実施例
で、各工程を示す断面図、第9図〜第16図は本発明の
他の実施例の各工程を示す断面図である。 ■・・・アースオーガ 2・・・中空回転軸3・・・掘
削ビット  4・・・掘削羽根5・・・縁付用ドラム 
6・・・攪拌羽根8・・・杭孔     9・・・セメ
ントミルク10・・・ゲル化物 11・・・モルタル又はセメントミルク12・・・鉄筋
カゴ   17・・・拡大翼18・・・支持層
Figures 1 to 8 are cross-sectional views showing each step of the construction method for on-site piles according to the present invention, and Figures 9 to 16 are cross-sectional views showing each step of other embodiments of the present invention. It is a diagram. ■...Earth auger 2...Hollow rotating shaft 3...Drilling bit 4...Drilling blade 5...Edging drum
6... Stirring blade 8... Pile hole 9... Cement milk 10... Gelled material 11... Mortar or cement milk 12... Rebar cage 17... Expanding blade 18... Support layer

Claims (2)

【特許請求の範囲】[Claims] (1)掘削羽根を先端に設け、途中に練付用ドラムを形
成した中空回転軸によるアースオーガを使用して、該ド
ラムで杭孔壁を加圧練付けしながら孔を形成して先端部
が砂や礫層などの支持層に充分貫入した後、回転軸端よ
り孔底にセメントミルクを注入してアースオーガの先端
で支持層中の砂や礫と十分混練することにより支持層を
改良し、また前記セメントミルクを硬化剤等によりゲル
化物とし、アースオーガとともに該ゲル化物も引上げ、
同時に孔内にモルタル又はセメントミルクを注入してこ
れで孔内を充填し、次いで孔内に鉄筋カゴ又は鋼材など
の芯材を建込むことを特徴とする現場造成杭の施工法。
(1) Using an earth auger with a hollow rotary shaft that has a drilling blade at its tip and a kneading drum formed in the middle, the drum pressurizes the wall of the pile hole while forming a hole to form a hole at the tip. After the cement has sufficiently penetrated the support layer such as sand and gravel, cement milk is injected into the bottom of the hole from the end of the rotating shaft and thoroughly mixed with the sand and gravel in the support layer using the tip of the earth auger to improve the support layer. In addition, the cement milk is made into a gel by using a hardening agent, and the gel is pulled up with an earth auger.
A construction method for on-site piles, which is characterized by simultaneously injecting mortar or cement milk into the hole to fill the hole, and then erecting a core material such as a reinforcing bar cage or steel material in the hole.
(2)拡大翼を有する掘削羽根を先端に設け、途中に練
付用ドラムを形成した中空回転軸によるアースオーガを
使用して、該ドラムで杭孔壁を加圧練付けしながら孔を
形成して先端部が砂や礫層などの支持層に充分貫入した
後、アースオーガを逆回転させて拡大翼を広げて孔底を
拡径し、その前後で回転軸端より孔底にセメントミルク
を注入してアースオーガの先端で支持層中の砂や礫と十
分混練することにより支持層を改良し、また前記セメン
トミルクを硬化剤等によりゲル化物とし、アースオーガ
とともに該ゲル化物も引上げ、同時に孔内にモルタル又
はセメントミルクを注入してこれで孔内を充填し、次い
で孔内に鉄筋カゴ又は鋼材などの芯材を建込むことを特
徴とする現場造成杭の施工法。
(2) Using an earth auger with a hollow rotary shaft equipped with a drilling blade with enlarged wings at its tip and a kneading drum formed in the middle, the hole is formed while pressurizing and kneading the pile hole wall with the drum. After the tip has sufficiently penetrated the supporting layer such as sand and gravel, the earth auger is rotated in the opposite direction to spread the expansion wings and expand the diameter of the hole bottom. The support layer is improved by injecting and thoroughly kneading it with sand and gravel in the support layer at the tip of an earth auger, and the cement milk is made into a gel by a hardening agent, etc., and the gel is pulled up with the earth auger. A construction method for on-site piles, which is characterized by simultaneously injecting mortar or cement milk into the hole to fill the hole, and then erecting a core material such as a reinforcing bar cage or steel material in the hole.
JP2915987A 1987-02-09 1987-02-09 Construction work of in-situ pile Pending JPS63197718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2915987A JPS63197718A (en) 1987-02-09 1987-02-09 Construction work of in-situ pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2915987A JPS63197718A (en) 1987-02-09 1987-02-09 Construction work of in-situ pile

Publications (1)

Publication Number Publication Date
JPS63197718A true JPS63197718A (en) 1988-08-16

Family

ID=12268481

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2915987A Pending JPS63197718A (en) 1987-02-09 1987-02-09 Construction work of in-situ pile

Country Status (1)

Country Link
JP (1) JPS63197718A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307628A (en) * 2005-03-31 2006-11-09 Tenox Corp Column replacing construction method and replacing column
CN105019459A (en) * 2015-07-27 2015-11-04 周兆弟 Drill rod feeding device of cement mixing pile driver
JP2020056221A (en) * 2018-10-02 2020-04-09 株式会社奥村組 Ground support force checking method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63103121A (en) * 1986-10-17 1988-05-07 Mitani Sekisan Kk Field piling work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63103121A (en) * 1986-10-17 1988-05-07 Mitani Sekisan Kk Field piling work

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307628A (en) * 2005-03-31 2006-11-09 Tenox Corp Column replacing construction method and replacing column
CN105019459A (en) * 2015-07-27 2015-11-04 周兆弟 Drill rod feeding device of cement mixing pile driver
JP2020056221A (en) * 2018-10-02 2020-04-09 株式会社奥村組 Ground support force checking method

Similar Documents

Publication Publication Date Title
US3530675A (en) Method and means for stabilizing structural layer overlying earth materials in situ
JP4811176B2 (en) Construction method of ready-made piles
JPS63197718A (en) Construction work of in-situ pile
JP4555974B2 (en) Construction method of foundation pile to improve ground around pile head
JPS63315724A (en) Execution work of cast-in-place concrete pile with high yield strength
JPS63197717A (en) Construction work of in-situ pile
JPH01219212A (en) Pile or continuous wall and its constructing method
JPS63197716A (en) Construction work of in-situ pile
JP4200237B2 (en) Construction method of foundation pile
JP6634251B2 (en) Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device
JP3706354B2 (en) Construction method of soil cement pile
JP3524433B2 (en) Improvement method of soft ground with hard layer
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
KR19990048467A (en) Auger pile method using expandable mortar
JPS62178620A (en) Formation of improved angular ground
JPH0325121A (en) Sinking of pile in inner drilling pile method
JPH0627405B2 (en) Ready-made pile burying method
JPH018587Y2 (en)
JPH0442493B2 (en)
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPS58210211A (en) Treatment of extra-banking concrete in head of on-site concrete pile
JPH04360909A (en) Construction of pile
JPH025845B2 (en)
JP2002371550A (en) Construction method of soil cement composite precast pile
JPH0558086B2 (en)