JPS63197717A - Construction work of in-situ pile - Google Patents
Construction work of in-situ pileInfo
- Publication number
- JPS63197717A JPS63197717A JP2915887A JP2915887A JPS63197717A JP S63197717 A JPS63197717 A JP S63197717A JP 2915887 A JP2915887 A JP 2915887A JP 2915887 A JP2915887 A JP 2915887A JP S63197717 A JPS63197717 A JP S63197717A
- Authority
- JP
- Japan
- Prior art keywords
- hole
- earth auger
- tip
- drum
- auger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 10
- 238000011065 in-situ storage Methods 0.000 title 1
- 239000004567 concrete Substances 0.000 claims abstract description 23
- 238000000034 method Methods 0.000 claims abstract description 10
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 7
- 239000003381 stabilizer Substances 0.000 claims abstract description 5
- 239000004568 cement Substances 0.000 claims description 35
- 239000008267 milk Substances 0.000 claims description 29
- 210000004080 milk Anatomy 0.000 claims description 29
- 235000013336 milk Nutrition 0.000 claims description 29
- 239000007788 liquid Substances 0.000 claims description 19
- 238000004898 kneading Methods 0.000 claims description 12
- 239000004576 sand Substances 0.000 claims description 10
- 239000003795 chemical substances by application Substances 0.000 claims description 8
- 238000005553 drilling Methods 0.000 claims description 6
- 238000005086 pumping Methods 0.000 claims description 3
- 230000000087 stabilizing effect Effects 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims 1
- 229910000278 bentonite Inorganic materials 0.000 abstract description 12
- 239000000440 bentonite Substances 0.000 abstract description 12
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 abstract description 12
- 230000015556 catabolic process Effects 0.000 abstract 1
- 238000006731 degradation reaction Methods 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 description 13
- 239000000463 material Substances 0.000 description 8
- 239000002689 soil Substances 0.000 description 6
- 230000000694 effects Effects 0.000 description 5
- 239000011150 reinforced concrete Substances 0.000 description 4
- 230000002093 peripheral effect Effects 0.000 description 3
- 238000003756 stirring Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000013505 freshwater Substances 0.000 description 2
- 239000000047 product Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000007423 decrease Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000010419 fine particle Substances 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000012466 permeate Substances 0.000 description 1
- 239000004848 polyfunctional curative Substances 0.000 description 1
- 239000011371 regular concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、建設工事の基礎工として鉄筋コンクリートの
現場造成杭を施工する方法に関する。DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method for constructing reinforced concrete field-prepared piles as foundation work for construction work.
かかる現場造成杭は、周知なごとくオーガスクリユー等
の掘削機を用いて地中に孔を造成し、この孔内に鉄筋カ
ゴを挿入してからコンクリートを打設して鉄筋コンクリ
ート柱体を形成するものである。As is well known, such on-site piles are created by creating a hole in the ground using an excavator such as an auger screw, inserting a reinforcing bar cage into the hole, and then pouring concrete to form a reinforced concrete column. It is something.
このような現場造成杭においては、地盤に対する支持力
を良好に保つことが要求され、スライムの処理及びコン
クリート下端と地盤の結合が問題となる。Such on-site construction piles are required to maintain good bearing capacity with respect to the ground, and problems arise in handling slime and bonding the lower end of the concrete to the ground.
また、削孔時に孔壁が崩壊すると杭の形状が悪くなり、
信頼性が乏しくなる。Additionally, if the hole wall collapses during drilling, the shape of the pile will deteriorate;
Reliability becomes poor.
スライムの処理については、種々の方法が従来提案され
、例えばこれを機械的に取出す方法やスライム中にセメ
ントミルクを混入してソイルセメントを生成する方法な
どがあるが、独自の装置を用いてスライムを取出すのは
きわめて困難なことであり、フィルセメントにする方法
では通常のコンクリートより強度が低下してしまう。Various methods have been proposed for the treatment of slime, including a method of mechanically extracting it and a method of mixing cement milk into the slime to produce soil cement. It is extremely difficult to remove it, and using fill cement reduces its strength compared to regular concrete.
一方、孔壁崩壊防止として削孔内をベントナイト液で充
填することも行われているが、充分なものではない。On the other hand, filling the inside of the drilled hole with bentonite liquid has been attempted to prevent the collapse of the hole wall, but this is not sufficient.
さらに、地盤が軟弱なものであると地盤の沈下に伴って
造成したコンクリート杭自体も引きづられて下がり、杭
としての信頼性を欠くおそれもある。Furthermore, if the ground is soft, the constructed concrete piles themselves may be dragged down as the ground subsides, and the reliability of the piles may be lost.
本発明の目的は前記従来例の不都合を解消し、孔壁の崩
壊を確実に防止し、またスライムを効果的に除去でき、
さらに杭先端の地盤との結合が良、好で、しかも机側面
と地盤との縁を切って地盤沈下の影響を受けにくい信頼
性に冨むコンクリート杭が得られる現場造成杭の施工法
を提供することにある。The purpose of the present invention is to eliminate the disadvantages of the conventional example, reliably prevent collapse of the hole wall, and effectively remove slime.
Furthermore, we provide a construction method for site-prepared piles that allows you to obtain highly reliable concrete piles that have a good connection with the ground at the tip of the pile, and are less susceptible to ground subsidence by cutting the edge between the desk side and the ground. It's about doing.
本発明は前記目的を達成するため、掘削羽根を先端に設
け、途中に練付用ドラムを形成した中空回転軸によるア
ースオーガを使用して、該ドラムで杭孔壁を加圧縁付け
しながら孔を形成して先端部が砂や礫層などの支持層に
充分貫入した後、必要に応じて孔底を拡径しながら回転
軸端より孔底にセメントミルクを注入してアースオーガ
の先端で支持層中の砂や礫と十分混練することにより支
持層を改良し、また前記セメントミルクを硬化剤等によ
りゲル化物とし、アースオーガとともに該ゲル化物も引
上げ、同時に孔内に高濃度の安定液を注入し、再度アー
スオーガを孔内に挿入して、ドラムで孔壁を加圧縁付け
て安定液マッドケーキ層を形成し、次いで孔内に鉄筋カ
ゴを建込んだ後、生コンクリートを打設することを要旨
とするものである。In order to achieve the above-mentioned object, the present invention uses an earth auger with a hollow rotary shaft provided with a digging blade at the tip and a kneading drum formed in the middle. After the tip has sufficiently penetrated the supporting layer such as sand and gravel, cement milk is injected into the bottom of the hole from the rotating shaft end while expanding the diameter of the hole bottom as necessary, and the tip of the earth auger is inserted into the bottom of the hole. The support layer is improved by thoroughly kneading it with the sand and gravel in the support layer, and the cement milk is made into a gel by using a hardening agent, etc., and the gel is pulled up together with the earth auger. At the same time, a highly concentrated stable liquid is added into the hole. was injected, the earth auger was inserted into the hole again, and the hole wall was pressurized and edged with a drum to form a stabilized liquid mud cake layer. Then, after erecting a reinforcing bar cage in the hole, ready-mixed concrete was poured. The gist of this is to
本発明によれば、孔掘削時に掘削土を孔壁に練付けるの
で、孔壁が補強されその崩壊を防止できる。また、孔底
に大量発生するスライドはこれをドラムとセメントミル
クのゲル化物上に乗せてアースオーガを引き上げる時に
排除できる。さらに、孔底に注入されたセメントミルク
は支持層の緩みを改良し、また、孔孔壁に形成された安
定液マッドケーキ層はコンクリート杭に対しネガティブ
フリクションカット材として作用して地盤との縁を切り
、地盤が軟弱で沈下があってもその悪影響を受けないで
すむ。According to the present invention, since the excavated soil is kneaded into the hole wall during hole excavation, the hole wall is reinforced and its collapse can be prevented. In addition, a large amount of slide generated at the bottom of the hole can be removed by placing it on the drum and cement milk gel and pulling up the earth auger. Furthermore, the cement milk injected into the bottom of the hole improves the loosening of the supporting layer, and the stabilizer mud cake layer formed on the hole wall acts as a negative friction cut material for the concrete pile, thereby reducing the edge of the ground. This way, even if the ground is soft and subsides, it will not be affected by the negative effects.
以下、図面について本発明の実施例を詳細に説明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.
第1図〜第12図は本発明の現場造成杭の施工法の第1
実施例の各工程を示す断面図で、先に本発明工法で用い
るアースオーガ1について説明する。Figures 1 to 12 show the first method of constructing on-site piles of the present invention.
First, the earth auger 1 used in the construction method of the present invention will be explained using cross-sectional views showing each step of the embodiment.
該アースオーガlは、中空回転軸2の先端に1、複数の
並列する掘削ビット3を突設したスクリュー状の掘削羽
根4を設け、該軸2の途中の適宜位置に練付用ドラム5
を取付けたものである。さらに、軸2の該ドラム5間に
は、放射状に突出する攪拌羽根6やスクリュー羽根(図
示せず)を設けることもある。The earth auger l is provided with a screw-shaped excavation blade 4 protruding from one or more parallel excavation bits 3 at the tip of a hollow rotary shaft 2, and a kneading drum 5 at an appropriate position in the middle of the shaft 2.
This is the one with the . Furthermore, between the drums 5 of the shaft 2, radially protruding stirring blades 6 or screw blades (not shown) may be provided.
前記ドラム5は、−例として平面において90度の扇形
体が軸2に対称となるように取付けられて形成され、か
つ平面形状とほぼ同一の平面形状を有する蓋を上面に設
け、また該ドラム5の径は扇形体を取替えるなどして必
要に応じて可変できるものとする。The drum 5 is formed by, for example, a 90 degree fan-shaped body attached symmetrically to the axis 2 in a plane, and is provided with a lid having a planar shape substantially the same as the planar shape on the upper surface, and the drum The diameter of 5 can be changed as necessary by replacing the fan-shaped body.
このようなアースオーガ1を用いて、杭孔8の掘削予定
位置へ所定直径の孔を掘削する(第1図)。この場合、
掘削土はスクリュー状の掘削羽根4により上方に運ばれ
、攪拌羽根6等で破砕されて細かくなる。さらにその一
部(掘削土の土質によっても異なるが相当量)は練付用
ドラム5の外周面で杭孔8の壁に加圧状態でコテ塗りさ
れる。Using such an earth auger 1, a hole of a predetermined diameter is excavated at the planned excavation position of the pile hole 8 (FIG. 1). in this case,
The excavated soil is carried upward by a screw-shaped excavation blade 4, and is crushed by a stirring blade 6 and the like into fine particles. Furthermore, a portion (a considerable amount, although it varies depending on the quality of the excavated soil) is troweled onto the wall of the pile hole 8 on the outer peripheral surface of the kneading drum 5 under pressure.
なお、掘削時に回転軸2の先端から適量の水を噴出すれ
ば、掘削を円滑にすることができるとともに掘削土を泥
土化して前記練付けも一層容易にすることができる。Incidentally, if an appropriate amount of water is squirted from the tip of the rotary shaft 2 during excavation, the excavation can be made smoother, and the excavated soil can be turned into mud, thereby making the kneading process even easier.
さらに、地盤によっては孔8内にベントナイト液などの
安定液を充填することも考えられる。Furthermore, depending on the ground, it is also possible to fill the hole 8 with a stabilizing liquid such as bentonite liquid.
このようにして、第2図に示すように前記アースオーガ
1によりその先端部が砂や礫層などの支持層18に十分
貫入する所定深さの杭孔8を掘削したならば、回転軸2
の中空内部を利用してその先端からセメントミルク9を
杭孔底部に所定量流入すると、該セメントミルク9は第
3図に示すように掘削羽根4を包み込むように充填され
、同時にアースオーガ1を回転すれば、掘削羽根4によ
りセメントミルク9は支持層18の砂や礫などと混練さ
れ、掘削により緩んだ支持層18を改良する。In this way, as shown in FIG. 2, once the earth auger 1 has excavated a pile hole 8 of a predetermined depth so that its tip sufficiently penetrates the support layer 18 such as sand or gravel layer, the rotary shaft 2
When a predetermined amount of cement milk 9 flows into the bottom of the pile hole from the tip using the hollow interior, the cement milk 9 is filled so as to wrap around the excavation blade 4 as shown in FIG. When rotated, the cement milk 9 is mixed with sand, gravel, etc. of the support layer 18 by the excavation blades 4, and the support layer 18 loosened by the excavation is improved.
次いで、又は事前に、必要に応じて適量のセメント硬化
剤を軸2端より注入する。第4図に示すようにアースオ
ーガ1を上下動させ、さらにこれを回転するようにすれ
ば、セメントミルクとセメント硬化剤とは均一に混合さ
れ、硬化剤のセメントミルクへの浸透性もよくなる。Next, or in advance, if necessary, an appropriate amount of cement hardener is injected from the two ends of the shaft. If the earth auger 1 is moved up and down and then rotated as shown in FIG. 4, the cement milk and the cement hardening agent are mixed uniformly, and the hardening agent permeates into the cement milk.
10分程度たつと、第5図に示すように硬化剤によりセ
メントミルクはゲル化して全体が円筒状の塊りとなるが
、該ゲル化物10はその内部に杭孔底付近で発生するス
ライムを取込んでしまう。このゲル化物10は、硬化剤
を用いずに時間の経過をまって形成することもできる。After about 10 minutes, the cement milk is gelled by the hardening agent and becomes a cylindrical lump as shown in FIG. I will take it in. This gelled material 10 can also be formed over time without using a curing agent.
そして、第6図に示すように泥土状のセメントミルクの
ゲル化物10とともにアースオーガ1を引上げると、残
りのスライムは前記ドラム5上やゲル化物10上に乗っ
て孔外へと排出される。Then, as shown in FIG. 6, when the earth auger 1 is pulled up together with the mud-like cement milk gel 10, the remaining slime rides on the drum 5 and the gel 10 and is discharged out of the hole. .
この引上げ時にはセメントミルク9′を注入してこれを
杭孔8の底に充填し、またオーガ1の引上げで前記ゲル
化物10が上昇して形成される空間にはオーガ1の軸2
端から高濃度のベントナイト液11又はその他の安定液
を圧入していく。During this pulling up, cement milk 9' is injected to fill the bottom of the pile hole 8, and the shaft of the auger 1 is placed in the space created by the gelled material 10 rising when the auger 1 is pulled up.
Highly concentrated bentonite liquid 11 or other stable liquid is forced in from the end.
なお、前記セメントミルクのゲル化物10は杭孔8内で
栓状前となっており、前記ベントナイト液11の注入は
、このゲル化物10の上昇でその下方が陰圧となりアー
スオーガ1の引上げ負荷が増大することを防止するとと
もに、むしろ該ベントナイト液11の注入圧でゲル化物
10を積極的に押上げ、アースオーガlの引上げを助け
る役割をなす。The cement milk gel 10 is in the form of a plug inside the pile hole 8, and when the bentonite liquid 11 is injected, the rise of the gel 10 creates a negative pressure below it, which reduces the lifting load of the earth auger 1. In addition to preventing the increase of the bentonite liquid 11, the injection pressure of the bentonite liquid 11 actively pushes up the gelled material 10 and serves to assist in pulling up the earth auger 1.
さらに、孔壁は前記のごとくドラム5でならされている
ので、ゲル化物10の引上げは引っかかることなくスム
ーズに行われる。Furthermore, since the hole walls are smoothed by the drum 5 as described above, the gelled material 10 can be pulled up smoothly without getting caught.
また、杭孔8の孔底に充填されたセメントミルク9′は
支持Ji18の地盤改良の作用と上部コンクリートとの
嵌合製を発揮する。Further, the cement milk 9' filled in the bottom of the pile hole 8 exerts the effect of improving the ground of the support Ji 18 and the fit with the upper concrete.
次いで、第7図に示すように一度地上に引上げ前記ゲル
化物10を取除いたアースオーガ1又は同タイプの別の
オーガー1を、再度杭孔8内に回転挿入する。この時前
記高濃度のベントナイト液11は、練付用のドラム5の
外周面で杭孔8の壁にコテ塗りされ、壁面に安定液マッ
ドケーキ層12が形成される。Next, as shown in FIG. 7, the earth auger 1 or another auger 1 of the same type, which has been lifted above the ground and the gelled material 10 has been removed, is rotated and inserted into the pile hole 8 again. At this time, the high concentration bentonite liquid 11 is troweled onto the wall of the pile hole 8 on the outer peripheral surface of the kneading drum 5, and a stabilized liquid mud cake layer 12 is formed on the wall surface.
なお、該安定液マッドケーキ層12を形成するためのド
ラム5は、その径は第1図、第2図での孔削切時のドラ
ム径よりも多少小さめの径として、一度初期に練付は加
圧された壁面にこのマツドケ=キ120層が必要厚さに
形成できるように配慮した。The diameter of the drum 5 used to form the stabilizer mud cake layer 12 is slightly smaller than the diameter of the drum at the time of drilling and cutting in FIGS. We took care to form this 120-layer layer of Matsudoke-Ki to the required thickness on the pressurized wall surface.
、その後、第8図に示すように杭孔8内を清水16と置
換して後述の鉄筋カゴ13に安定液が付着するのを防止
する。このようにしてから、第9図に示すように杭孔8
内へ鉄筋カゴ13を建込み、さらに第1O図に示すよう
にトレミー管14を挿入する。このトレミー管14はプ
ランジャ一式のものではなく底ぶた方式のものを用いる
が、該トレミー管14の内部に予めセメントミルクや生
コンクリートを注入して充填しておくことにより、清水
16内での浮上がりを防止した。Thereafter, as shown in FIG. 8, the inside of the pile hole 8 is replaced with clean water 16 to prevent the stabilizing liquid from adhering to the reinforcing bar cage 13, which will be described later. After doing this, as shown in Figure 9, the pile hole 8
A reinforcing bar cage 13 is built inside, and a tremie pipe 14 is further inserted as shown in FIG. 1O. This tremie tube 14 uses a bottom lid type rather than a plunger set, but by filling the inside of the tremie tube 14 with cement milk or fresh concrete in advance, it is possible to prevent it from floating in the fresh water 16. Prevented the rise.
そして、第11図に示すように前記トレミー管14を用
いてこれを引上げながら生コンクリート15を打設する
。該生コンクリート15の打設は、初期においては加圧
状態で行うことにより、前記セメントミルク9′との接
合部等で断層を生じることを防止でき、さらにセメント
ミルク9′の一部を生コンクリート15の上端で押し上
げることで、スライムの排除もできる。Then, as shown in FIG. 11, fresh concrete 15 is poured while being pulled up using the tremie pipe 14. By placing the ready-mixed concrete 15 under pressure at the initial stage, it is possible to prevent faults from occurring at the joints with the cement milk 9', and furthermore, a part of the cement milk 9' is poured into the ready-mixed concrete. You can also remove slime by pushing it up with the top of 15.
また、生コンクリート15の加工前での打設は、トレミ
ー管14を用いる他にポンプ打ちにより行うことも可能
である。In addition to using the tremie pipe 14, the fresh concrete 15 can be placed by pumping before processing.
このようにして、第12図に示すような鉄筋コンクリー
トの現場造成杭が形成される。In this way, reinforced concrete field-built piles as shown in FIG. 12 are formed.
次に、特許請求の範囲第2項の発明について説明すると
、使用するアースオーガとしては前記第1実施例で説明
したオーガ1の掘削羽根4に拡大翼17を設けたもので
ある。Next, the invention of claim 2 will be explained. The earth auger used is one in which an enlarged blade 17 is provided on the excavation blade 4 of the auger 1 described in the first embodiment.
第13図〜第24図は各工程を示すもので、アースオー
ガ1を用いて、杭孔8の掘削予定位置へ線材層ドラム5
で杭孔8の壁に掘削土をコテ塗りしながら所定直径の孔
を掘削する(第13図)。13 to 24 show each process. Using the earth auger 1, the wire layer drum 5 is moved to the planned excavation position of the pile hole 8.
Then, a hole of a predetermined diameter is excavated while applying excavated soil to the wall of the pile hole 8 with a trowel (Fig. 13).
第14図に示すように前記アースオーガ1によりその先
端部が砂や礫層などの支持層18に充分貫入したする所
定深さの杭孔8を掘削したならば、アースオーガ1を逆
方向に回転させると、第15図に示すように拡大翼17
が拡がり、この拡大翼17で杭孔8の底部に拡径部8a
が形成される。そして、その前又は後に回転軸2の中空
内部を利用してその先端からセメントミルク9を杭孔底
部に所定量流入すれば、セメントミルク9は支持層の砂
や礫などと混練され、掘削により緩んだ支持層を改良す
る。As shown in FIG. 14, once the earth auger 1 has excavated a pile hole 8 of a predetermined depth with its tip sufficiently penetrating the supporting layer 18 such as sand or gravel layer, the earth auger 1 is turned in the opposite direction. When rotated, the enlarged wing 17 as shown in FIG.
expands, and the enlarged wings 17 form an enlarged diameter portion 8a at the bottom of the pile hole 8.
is formed. Before or after that, if a predetermined amount of cement milk 9 is flowed into the bottom of the pile hole from the tip using the hollow interior of the rotating shaft 2, the cement milk 9 is mixed with the sand and gravel of the supporting layer, and as a result of excavation. Repair loose support layers.
次いで、第16図に示すようにアースオーガ1を上下動
し、さらにこれを回転するようにして、通量のセメント
硬化剤等で第17図に示すようにセメントミルク9をゲ
ル化して全体が円筒状の塊りとし、第18図に示すよう
にゲル化物10とともにアースオーガ1を引上げる。な
お、前記拡径部8aでセメントミルク9のゲル化物10
は多少球根状となるが、それ自体比較的柔らかいものな
ので上方へ引上げるには支障ない。Next, as shown in FIG. 16, the earth auger 1 is moved up and down and further rotated, and the cement milk 9 is gelatinized with a constant amount of cement hardening agent, etc., as shown in FIG. A cylindrical mass is formed, and the earth auger 1 is pulled up together with the gelled material 10 as shown in FIG. Note that the gelled product 10 of the cement milk 9 is formed in the enlarged diameter portion 8a.
Although it becomes somewhat bulbous, it is relatively soft in itself, so there is no problem in pulling it upward.
この引上げ時にはセメントミルク9′を注入してこれを
杭孔8の底に充填し、またオーガ1の引上げで前記ゲ化
物10が上昇して形成される空間にはオーガ1の軸2端
から高濃度のベントナイト液11を圧入していく。At the time of this pulling up, cement milk 9' is injected to fill the bottom of the pile hole 8, and the space created by the auger 1 being raised by the lifting of the auger 1 has a high height from the shaft 2 end of the auger 1. A concentrated bentonite liquid 11 is then pressurized.
次いで、第19図に示すように一度地上に引上げ前記ゲ
ル化物10を取除いたアースオーガ1又は同タイプの別
のオーガー1を、再度杭孔8内に回転挿入し、前記高濃
度のベントナイト液11を、練性用のドラム5の外周面
で杭孔8の壁にコテ塗りして、壁面に安定液マッドケー
キ層工2を形成する。Next, as shown in FIG. 19, the earth auger 1 or another auger 1 of the same type, which has been lifted above the ground and the gelled material 10 has been removed, is rotated and inserted again into the pile hole 8, and the highly concentrated bentonite liquid is poured into the pile hole 8. 11 is troweled onto the wall of the pile hole 8 on the outer peripheral surface of the kneading drum 5 to form a stabilized mud cake layer 2 on the wall surface.
次いで、第20図に示すように杭孔8内を清水16と置
換してから、第21図に示すように鉄筋カゴ13を建込
み、そして、第22図、第23図に示すようにトレミー
管14を用いて生コンクリート15を加圧状態で打設す
る。Next, as shown in FIG. 20, the inside of the pile hole 8 is replaced with fresh water 16, and then the reinforcing bar cage 13 is erected as shown in FIG. 21, and the tremie is installed as shown in FIGS. 22 and 23. Fresh concrete 15 is placed under pressure using pipe 14.
生コンクリート15の加圧状態での打設は、トレミー管
13を用いる他にポンプ打ちにより行うことも可能であ
る。The fresh concrete 15 can be placed under pressure by using a tremie pipe 13 or by pumping.
このようにして、第24図に示すような先端が拡径した
支持力の高い鉄筋コンクリートの現場造成杭が形成され
る。In this way, an on-site constructed reinforced concrete pile with a diameter-expanded tip and a high bearing capacity is formed as shown in FIG. 24.
以上述べたように本発明の現場造成杭の施工法は、孔壁
の崩壊を確実に防止して形状が良いコンクリート杭が得
られ、またスライムを効果的に除去できて支持力の低下
を招(こともない。さらに、コンクリート杭の外側と地
盤とは、ベントナイトマッドケーキ層により縁が切れて
いるので、地盤が軟弱で沈下を生じることがあっても杭
はそれに引きづられるなどの悪影響を受けず、孔底には
セメントミルクを注入して支持層の地盤改良を行うので
地盤の結合が確実で支持力の大きい信頼性の高い杭が得
られるものである。As described above, the construction method for on-site piles of the present invention reliably prevents the collapse of the hole wall and provides concrete piles with a good shape, and can also effectively remove slime, which would otherwise cause a decline in bearing capacity. Furthermore, the outside of the concrete pile and the ground are separated by a layer of bentonite mud cake, so even if the ground is soft and subsides, the pile will be dragged by it and have negative effects. Instead, cement milk is injected into the bottom of the hole to improve the ground of the supporting layer, ensuring solid connection to the ground and producing highly reliable piles with large bearing capacity.
しかも、一連の工程を一つのアースオーガで行え、施工
速度の速いものとなる。Furthermore, a series of steps can be performed with one earth auger, resulting in faster construction speed.
第1図〜第12図は本発明の現場造成杭の施工法の実施
例で、各工程を示す断面図、第13図〜第24図は本発
明の他の実施例の各工程を示す断面図である。
1・・・アースオーガ 2・・・中空回転軸3・・・掘
削ビット 4・・・掘削羽根5・・・練付用ドラム
6・・・攪拌羽根8・・・杭孔 、8a・・・
拡径部9.9′・・・セメントミルク 10・・・ゲル
化物11・・・高濃度のベントナイト液
12・・・安定液マッドケーキ層
13・・・鉄筋カゴ 14・・・トレミー管15・
・・生コンクリート
16・・・清水
17・・・拡大翼 18・・・支持層11図
第2図 第3図
口Figures 1 to 12 are cross-sectional views showing each step of the construction method for on-site piles according to the present invention, and Figures 13 to 24 are cross-sectional views showing each step of other embodiments of the present invention. It is a diagram. 1... Earth auger 2... Hollow rotating shaft 3... Drilling bit 4... Drilling blade 5... Drum for kneading
6... Stirring blade 8... Pile hole, 8a...
Expanded diameter part 9.9'... Cement milk 10... Gelled product 11... Highly concentrated bentonite liquid 12... Stable liquid mud cake layer 13... Reinforcement cage 14... Tremy tube 15.
...Ready-mixed concrete 16...Shimizu 17...Enlarged wing 18...Support layer 11 diagram
Figure 2 Figure 3 Exit
Claims (4)
成した中空回転軸によるアースオーガを使用して、該ド
ラムで杭孔壁を加圧練付けしながら孔を形成して先端部
が砂や礫層などの支持層に充分貫入した後、回転軸端よ
り孔底にセメントミルクを注入してアースオーガの先端
で支持層中の砂や礫と十分混練することにより支持層を
改良し、また前記セメントミルクを硬化剤等によりゲル
化物とし、アースオーガとともに該ゲル化物も引上げ、
同時に孔内に高濃度の安定液を注入し、再度アースオー
ガを孔内に挿入して、ドラムで孔壁を加圧練付けて安定
液マッドケーキ層を形成し、次いで孔内に鉄筋カゴを建
込んだ後、生コンクリートを打設することを特徴とする
現場造成杭の施工法。(1) Using an earth auger with a hollow rotary shaft that has a drilling blade at its tip and a kneading drum formed in the middle, the drum pressurizes the wall of the pile hole while forming a hole to form a hole at the tip. After the cement has sufficiently penetrated the support layer such as sand and gravel, cement milk is injected into the bottom of the hole from the end of the rotating shaft and thoroughly mixed with the sand and gravel in the support layer using the tip of the earth auger to improve the support layer. In addition, the cement milk is made into a gel by using a hardening agent, and the gel is pulled up with an earth auger.
At the same time, a highly concentrated stabilizing liquid is injected into the hole, the earth auger is inserted into the hole again, the hole wall is kneaded under pressure with a drum to form a stable liquid mud cake layer, and then a reinforcing bar cage is inserted into the hole. A construction method for on-site preparation piles that is characterized by pouring ready-mixed concrete after erection.
付用ドラムを形成した中空回転軸によるアースオーガを
使用して、該ドラムで杭孔壁を加圧練付けしながら孔を
形成して先端部が砂や礫層などの支持層に充分貫入した
後、アースオーガを逆回転させて拡大翼を広げて孔底を
拡径し、回転軸端より孔底にセメントミルクを注入して
アースオーガの先端で支持層中の砂や礫と十分混練する
ことにより支持層を改良し、また前記セメントミルクを
硬化剤等によりゲル化物とし、アースオーガとともに該
ゲル化物も引上げ、同時に孔内に高濃度の安定液を注入
し、再度アースオーガを孔内に挿入して、ドラムで孔壁
を加圧練付けて安定液マッドケーキ層を形成し、次いで
孔内に鉄筋カゴを建込んだ後、生コンクリートを打設す
ることを特徴とする現場造成杭の施工法。(2) Using an earth auger with a hollow rotary shaft equipped with a drilling blade with enlarged wings at its tip and a kneading drum formed in the middle, the hole is formed while pressurizing and kneading the pile hole wall with the drum. After the tip has sufficiently penetrated the supporting layer such as sand and gravel, the earth auger is rotated in the opposite direction to spread the expansion blades to enlarge the diameter of the hole bottom, and cement milk is injected into the hole bottom from the end of the rotating shaft. The support layer is improved by sufficiently kneading it with the sand and gravel in the support layer at the tip of the earth auger, and the cement milk is made into a gel by using a hardening agent, etc., and the gel is pulled up with the earth auger. A highly concentrated stabilizer was injected into the hole, the earth auger was inserted into the hole again, the hole wall was kneaded under pressure with a drum to form a stabilizer mud cake layer, and then a rebar cage was built inside the hole. A construction method for on-site piles, which is characterized by pouring ready-mixed concrete afterwards.
で打設する特許請求の範囲第1項記載の現場造成杭の施
工法。(3) The method for constructing on-site piles according to claim 1, wherein the ready-mixed concrete is cast under pressure using a tremie pipe.
打設する特許請求の範囲第1項記載の現場造成杭の施工
法。(4) The method for constructing on-site piles according to claim 1, wherein the ready-mixed concrete is poured under pressure by pumping.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62029158A JPH0629509B2 (en) | 1987-02-09 | 1987-02-09 | Construction method of field construction pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62029158A JPH0629509B2 (en) | 1987-02-09 | 1987-02-09 | Construction method of field construction pile |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63197717A true JPS63197717A (en) | 1988-08-16 |
JPH0629509B2 JPH0629509B2 (en) | 1994-04-20 |
Family
ID=12268452
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP62029158A Expired - Lifetime JPH0629509B2 (en) | 1987-02-09 | 1987-02-09 | Construction method of field construction pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0629509B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798528A (en) * | 2018-08-01 | 2018-11-13 | 中地君豪建筑工程有限公司 | Abolish the drill bit of waste and old pile pile and the method abolished waste and old pile pile and new pile is perfused |
JP2019082040A (en) * | 2017-10-30 | 2019-05-30 | 三谷セキサン株式会社 | Foundation pile construction method on ground containing contaminated soil layer |
CN111749230A (en) * | 2020-07-22 | 2020-10-09 | 四川省第十一建筑有限公司 | Ultra-long rotary digging cast-in-place pile and construction method thereof |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63103121A (en) * | 1986-10-17 | 1988-05-07 | Mitani Sekisan Kk | Field piling work |
-
1987
- 1987-02-09 JP JP62029158A patent/JPH0629509B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63103121A (en) * | 1986-10-17 | 1988-05-07 | Mitani Sekisan Kk | Field piling work |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019082040A (en) * | 2017-10-30 | 2019-05-30 | 三谷セキサン株式会社 | Foundation pile construction method on ground containing contaminated soil layer |
CN108798528A (en) * | 2018-08-01 | 2018-11-13 | 中地君豪建筑工程有限公司 | Abolish the drill bit of waste and old pile pile and the method abolished waste and old pile pile and new pile is perfused |
CN108798528B (en) * | 2018-08-01 | 2023-10-20 | 中地君豪高科股份有限公司 | Drill bit for breaking waste pipe piles and method for breaking waste pipe piles and filling new piles |
CN111749230A (en) * | 2020-07-22 | 2020-10-09 | 四川省第十一建筑有限公司 | Ultra-long rotary digging cast-in-place pile and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH0629509B2 (en) | 1994-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3530675A (en) | Method and means for stabilizing structural layer overlying earth materials in situ | |
US4832535A (en) | Process for compaction-reinforcement-grouting or for decompaction-drainage and for construction of linear works and plane works in the soils | |
JP4483998B1 (en) | Steel pipe pile for synthetic pile construction and synthetic pile construction method | |
US3191390A (en) | Method of preparing subsurface and forming concrete column therein | |
JP2000073354A (en) | Preparating method of ground improving body and preparating method of continuous walls | |
JP2004332431A (en) | Method for constructing soil-cement composite pile | |
JP2008031772A (en) | Construction method of precast pile, and cover for use in the construction method | |
JPS63197717A (en) | Construction work of in-situ pile | |
JP2005282063A (en) | Composite field preparation pile, its construction method and device for preparing composite field preparation pile | |
KR20190043709A (en) | Construction Method Soft Surface Treatment And Strength of Reinforced Soil Using Waste Aggregates | |
JPS63197718A (en) | Construction work of in-situ pile | |
JP2001081770A (en) | Pile foundation work | |
JPH07103550B2 (en) | Pile or continuous wall and its construction method | |
JPS63315724A (en) | Execution work of cast-in-place concrete pile with high yield strength | |
JP4200237B2 (en) | Construction method of foundation pile | |
JP2004308411A (en) | Existing concrete pile foundation having large diameter and method for burying existing pile | |
JP2002097636A (en) | Construction method for foundation pile improving ground around pile head, formation method for expanded head part of pile hole, and digging rod | |
JP6634251B2 (en) | Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device | |
JPS63197716A (en) | Construction work of in-situ pile | |
JPH0280710A (en) | Preparing cast-in-place concrete pile | |
JPS62178620A (en) | Formation of improved angular ground | |
KR102260596B1 (en) | Site Construction Method Of Base Top Pile For Ground Reinforcement | |
JP4031967B2 (en) | Box-type buckets used in the construction method of underground underground walls, and impermeable wall construction methods for waste landfills | |
JPH0442493B2 (en) | ||
JPH0627405B2 (en) | Ready-made pile burying method |