JP2001081770A - Pile foundation work - Google Patents

Pile foundation work

Info

Publication number
JP2001081770A
JP2001081770A JP26201799A JP26201799A JP2001081770A JP 2001081770 A JP2001081770 A JP 2001081770A JP 26201799 A JP26201799 A JP 26201799A JP 26201799 A JP26201799 A JP 26201799A JP 2001081770 A JP2001081770 A JP 2001081770A
Authority
JP
Japan
Prior art keywords
pile
grout
improved body
ground
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP26201799A
Other languages
Japanese (ja)
Inventor
Kenjiro Oka
憲二郎 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toray Engineering Co Ltd
Original Assignee
Toyo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyo Construction Co Ltd filed Critical Toyo Construction Co Ltd
Priority to JP26201799A priority Critical patent/JP2001081770A/en
Publication of JP2001081770A publication Critical patent/JP2001081770A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To stably construct a pile foundation having sufficient bearing power in the vertical direction and the horizontal direction efficiently. SOLUTION: An injection rod 2 is rotated and moved in the axial direction in a ground 3, an improved body 4 is formed in the ground 3 by a high-pressure injection agitation construction method, and a pit 6 is excavated to the improved body 4 by using an earth auger 5. The inside of the pit 6 is supplied with a fixed quantity of cubic expansion type grout 7, a concrete pile 8 with knots, in which a front end is closed, is inserted into the pit 6, the grout 7 is pushed up into voids in the periphery of the pile 8, and the concrete pile 8 is joined and unified with the improved body 4 through a fixing layer 9.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明が属する技術分野】本発明は、構造物の基礎を構
築するための杭基礎工法に係り、より詳しくは埋込み杭
工法と高圧噴射攪拌工法との併用により杭基礎を構築す
る杭基礎工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pile foundation method for constructing a foundation for a structure, and more particularly, to a pile foundation method for constructing a pile foundation by using an embedded pile method and a high-pressure jet stirring method in combination. .

【0002】[0002]

【従来の技術】杭基礎工法の一つである埋込み杭工法
は、低騒音、低振動での施工が可能であるところから、
近年、市街地での施工に多用されている。埋込み工法の
代表的なものとしては、プレボーリング工法、中掘り工
法があるが、これら工法はさらに、杭の固定様式により
最終打撃工法、根固め工法、拡大根固め工法等に分類さ
れている。このうち、プレボーリング根固め工法は、掘
削機により地盤に竪穴を掘削した後、掘削機先端から根
固め用グラウトを注入し、掘削機を竪穴から引上げて杭
周り固定用グラウトを補給した後、竪穴内に既製杭を建
込むもので、その拡大根固め工法は、前記竪穴を杭径よ
りもかなり大きく形成することを特徴とする。一方、中
掘り根固め工法は、既製杭内に挿入した掘削機により地
盤を削孔しながら既製杭を所定深度まで沈下させた後、
掘削機先端からグラウトを注入して根固め球根を造成す
る工法で、その拡大根固め工法は、前記根固め球根をよ
り大型に造成することを特徴とする。そして、これら根
固め工法または拡大根固め工法によれば、少なくとも既
製杭の先端部がグラウトの硬化した根固め層を介して地
盤に接合されるので、大きな支持力が得られるという利
点がある。
2. Description of the Related Art The embedded pile method, which is one of the pile foundation methods, can be constructed with low noise and low vibration.
In recent years, it is frequently used for construction in urban areas. Typical examples of the embedding method include a pre-boring method and a mid-digging method, and these methods are further classified into a final hammering method, a root consolidation method, an expanded root consolidation method, and the like according to a pile fixing method. Of these, pre-boring consolidation method, after excavating a pit in the ground with an excavator, injecting grout for consolidation from the excavator tip, pulling up the excavator from the pit and supplying grout for fixing around the pile, A ready-made pile is built in a pit, and the method of expanding the roots is characterized by forming the pit considerably larger than the pile diameter. On the other hand, the mid-digging method is to sink the pre-made pile to a predetermined depth while drilling the ground with an excavator inserted in the pre-made pile,
A method of constructing a root compaction bulb by injecting grout from the tip of an excavator. The enlarged root compaction method is characterized in that the root compaction bulb is formed in a larger size. In addition, according to the above-mentioned method of solidification or the method of enlarged solidification, at least the tip of the ready-made pile is joined to the ground through the hardened layer of grout, so that there is an advantage that a large supporting force can be obtained.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記し
た根固めを行うプレボーリング工法または中掘り工法に
よれば、安定した支持力を得るには、支持層まで既製杭
を建て込む必要があり、支持層が深い場合には、削孔距
離並びに杭長が大幅に延長して、施工に長期間を要する
という問題があった。また、根固め用グラウトを注入し
た際、ボイリングが生じて杭先端付近の地盤が緩んでし
まったり、あるいは、地下流水によりグラウトが流出し
てしまうなどのトラブルも発生し易く、安定した施工を
行うには、使用するグラウトの品質(水セメント比な
ど)はもとより、その注入量、注入圧力等に厳密な管理
が必要で、その上、事前の地盤調査、地下水位の確認な
ども必要となって、施工が面倒であるという問題があっ
た。さらに、プレボーリング工法の場合は、穴壁の崩落
による高止まりの危険もあり、施工の安定性を確保する
のが困難であるという問題もあった。また、根固め層と
杭周りのグラウト定着層とにより大きな支持力が得られ
るとはいえ、それは主として鉛直方向の支持力であり、
水平方向の支持力としてみると十分とはいえず、耐震性
に劣るという問題があった。
However, according to the pre-boring method or the digging method for performing the above-mentioned root consolidation, in order to obtain a stable supporting force, it is necessary to build a ready-made pile up to the supporting layer. When the layer is deep, there is a problem that the drilling distance and the pile length are greatly extended, and the construction takes a long time. In addition, when grouting for consolidation is injected, troubles such as loosening of the ground near the tip of the pile due to boiling or outflow of grout due to groundwater downstream easily occur, and stable construction is performed. In addition to the quality of the grout used (water-cement ratio, etc.), it is necessary to strictly control the injection amount, injection pressure, etc. In addition, prior ground surveys and confirmation of the groundwater level are required. However, there was a problem that the construction was troublesome. Further, in the case of the pre-boring method, there is a danger that the hole wall will stop at a high level due to the collapse, and there is a problem that it is difficult to secure the stability of the construction. In addition, although a larger bearing capacity can be obtained by the root consolidation layer and the grout fixing layer around the pile, it is mainly a vertical bearing capacity,
There was a problem that the bearing capacity in the horizontal direction was not sufficient, and the earthquake resistance was poor.

【0004】本発明は、上記した従来の問題点に鑑みて
なされたもので、その目的とするところは、鉛直方向お
よび水平方向の支持力が十分な杭基礎を、安定してかつ
効率よく構築できるようにすることにある。
The present invention has been made in view of the above-mentioned conventional problems, and an object of the present invention is to stably and efficiently construct a pile foundation having sufficient vertical and horizontal support forces. To be able to do it.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するた
め、本発明は、高圧噴射攪拌工法により地盤に改良体を
形成した後、該改良体に竪穴を掘削し、しかる後、前記
竪穴に既製杭を挿入すると共に、該既製杭の周りの空隙
にグラウトを充填することを特徴とする。
In order to achieve the above object, the present invention relates to a method for forming an improved body in a ground by a high-pressure jet stirring method, and then excavating a pit in the improved body. The method is characterized in that a pile is inserted and grout is filled in a space around the ready-made pile.

【0006】高圧噴射攪拌工法は、注入ロッドを地盤中
に回転および軸方向移動させながら、その先端の噴射ノ
ズルから注入ロッドと直角方向へグラウト(地盤改良
材)を単独に、あるいは高圧水または圧縮エアと混合し
て高圧噴射し、地盤改良材と周辺土砂とを攪拌混合して
改良体を形成する工法で、小型の施工機械を用いて大径
の改良体を形成できる利点がある。本発明は、この高圧
噴射攪拌工法により形成した改良体に竪穴を掘削し、そ
の後、この竪穴内に既製杭を建込むことを特徴とする
が、前記竪穴の掘削とこれに続く既製杭の建込みには、
既存のプレボーリング根固め工法または拡大根固め工法
はもとより、既存のマイクロパイル工法をそのまま利用
することができる。しかして、本発明によれば、前記高
圧噴射攪拌工法により形成した改良体内に既製杭を建込
むので、支持層に杭を根入れする必要はなく、その上、
ボイリング、グラウト流出、孔壁の崩落などのトラブル
が生じることはない。また、構築された杭基礎は、大径
の改良体と基礎杭とが一体となって鉛直方向および水平
方向に大きく抵抗するので、鉛直方向の支持力はもちろ
ん、水平方向の支持力も十分となる。
[0006] In the high-pressure injection stirring method, grout (ground improvement material) is applied to the injection rod at the tip thereof in a direction perpendicular to the injection rod while rotating and axially moving the injection rod into the ground, or by high-pressure water or compression. This is a method of forming an improved body by mixing with air and injecting with high pressure, and stirring and mixing the ground improvement material and the surrounding earth and sand, which has an advantage that a large diameter improved body can be formed using a small-sized construction machine. The present invention is characterized in that a pit is excavated in the improved body formed by the high-pressure injection stirring method, and thereafter, a ready-made stake is built in the pit. Including
In addition to the existing pre-boring method or the expanded method, the existing micropile method can be used as it is. Thus, according to the present invention, since the ready-made pile is built in the improved body formed by the high-pressure jet stirring method, it is not necessary to insert the pile into the support layer.
No troubles such as boiling, grout outflow, and collapse of the hole wall will occur. In addition, the constructed pile foundation, the large diameter improved body and the foundation pile are integrated and greatly resist in the vertical and horizontal directions, so that not only the vertical bearing capacity but also the horizontal bearing capacity is sufficient .

【0007】本発明において、上記既製杭の周りの空隙
に注入するグラウトの種類は任意であるが、体積膨張型
グラウトを用いるのが望ましい。体積膨張型グラウトを
用いることで、既製杭の周りの空隙内の隅々までグラウ
トが充填され、既製杭の定着はより確実となる。また、
本発明は、上記既製杭として用いる杭の種類も任意であ
り、RC、PC、PHC、SC等のコンクリート杭はも
とより、鋼管杭等を用いることができる。この場合、既
製杭を節付きとすることにより、鉛直方向の支持力をよ
り増大させることができる。
In the present invention, the type of grout injected into the space around the ready-made pile is arbitrary, but it is preferable to use a volume expansion type grout. By using the volume expansion type grout, the grout is filled to every corner in the space around the ready-made pile, and the fixation of the ready-made pile becomes more reliable. Also,
In the present invention, the type of pile used as the above-mentioned ready-made pile is also arbitrary, and concrete piles such as RC, PC, PHC, and SC can be used, as well as steel pipe piles and the like. In this case, the vertical supporting force can be further increased by making the ready-made stakes knotted.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態を添付
図面に基いて説明する。図1は、本発明の第1の実施の
形態を示したものである。本第1の実施の形態は、高圧
噴射攪拌工法とプレボーリング根固め工法とを併用する
もので、同図中、およびの工程は高圧噴射攪拌工法
による施工状況を、からまでの工程はプレボーリン
グ根固め工法による施工状況を示している。
Embodiments of the present invention will be described below with reference to the accompanying drawings. FIG. 1 shows a first embodiment of the present invention. In the first embodiment, the high-pressure injection agitation method and the pre-boring consolidation method are used in combination. In FIG. This shows the construction status by the consolidation method.

【0009】施工に際しては、先端に噴射ノズル1を有
する注入ロッド(単管または二重管)2を用意し、先
ず、この注入ロッド2を回転させながら地盤3中に所定
深さだけ貫入させ、その先端の噴射ノズル1が計画改良
域の上限深さD1 に達したら、注入ロッド2内に超高圧
(30〜40MPa )の水(圧縮空気を併用する場合もあ
る)を供給し、その噴射ノズル1から水平方向へ超高圧
水を噴射させる。この超高圧水の噴射により地盤3が広
範囲に切削攪拌(プレカッティング)され、地盤3内に
は大径の切削攪拌層Aが形成され、この切削攪拌層A
は、注入ロッド2の回転下降に応じて下方へ拡大する
()。なお、この時発生する余剰スライムは流入ロッ
ド2の周りの空隙を通して地上へ排出される。
At the time of construction, an injection rod (single pipe or double pipe) 2 having an injection nozzle 1 at its tip is prepared. First, the injection rod 2 is rotated to penetrate the ground 3 to a predetermined depth. Upon reaching the upper limit the depth D 1 of the injection nozzle 1 is plan improved range of its tip within the infusion rod 2 (sometimes in combination with compressed air) water ultrahigh pressure (30~40MPa) supplies, the injection Ultra high pressure water is jetted from the nozzle 1 in the horizontal direction. The ground 3 is cut and agitated (pre-cutting) over a wide area by the injection of the ultrahigh-pressure water, and a large-diameter cutting and stirring layer A is formed in the ground 3.
Expands downward as the injection rod 2 rotates down (). The surplus slime generated at this time is discharged to the ground through a space around the inflow rod 2.

【0010】そして、前記切削攪拌層Aの形成が計画改
良域の下限深さD2 に達したら、前記超高圧水をグラウ
ト(セメントミルク:水セメント比W/C =60〜70程度)
に切替え、噴射ノズル1から超高圧(40MPa 程度)の
グラウト(圧縮空気を併用する場合もある)を水平方向
へ噴射させながら注入ロッド2を回転上昇させる
()。グラウトの高圧噴射により、前記切削攪拌層A
内の土砂はグラウトと攪拌混合されてグラウト混合層B
に変質し、このグラウト混合層Bは注入ロッド2の回転
上昇に応じて上方へ拡大する。この時、余剰スライムは
地上へ誘導排出されるが、この段階では水の噴射が停止
されているので、その誘導排出の程度はわずかであり、
グラウトの無駄な消費が抑えられる。このようにしてグ
ラウト混合層Bの形成が計画改良域の上限深さD1 に達
したら、注入ロッド2に対するグラウトの供給を停止
し、注入ロッド2を地盤3から引抜き、そのまま養生さ
せる。この養生によりグラウト混合層Bが硬化し、計画
改良域には大径の改良体4()が形成される。
When the formation of the cutting agitating layer A reaches the lower limit depth D 2 of the planned improvement area, the ultrahigh-pressure water is grouted (cement milk: water / cement ratio W / C = about 60 to 70).
And the injection rod 2 is rotated upward while injecting grout (in some cases using compressed air) of ultra high pressure (about 40 MPa) from the injection nozzle 1 in the horizontal direction. By the high pressure injection of grout, the cutting stirrer A
The earth and sand inside is mixed with grout by stirring and grout mixed layer B
The grout mixed layer B expands upward as the injection rod 2 rotates upward. At this time, the excess slime is guided and discharged to the ground, but at this stage, since the injection of water is stopped, the degree of the guided discharge is slight,
Useless consumption of grout is reduced. After thus forming the grout mixed layer B reaches the maximum depth D 1 of the plan improved gamut, the supply of grout stops against injection rod 2, pull the injection rod 2 from the ground 3, to as curing. By this curing, the grout mixed layer B is hardened, and a large-diameter improved body 4 () is formed in the planned improvement area.

【0011】次に、上記のように形成された改良体4
に、例えばアースオーガー5を用いて縦穴6を掘削す
る。この縦穴6の掘削は、改良体4の底面近傍まで行
い、掘削終了後、アースオーガー5を地盤3から引抜き
()、次に、この縦穴5内に、例えば体積膨張型グラ
ウト(例えば、デンカ工業社製の「デンカCSA」)7
を所定量供給する()。その後、縦穴5内に、例えば
先端閉塞の節付きコンクリート杭(既製杭)8を挿入す
る。すると、予め供給されたグラウト7がコンクリート
杭8と縦穴5の内壁との空隙内にオーバーフローし、該
空隙にグラウト7が充填される。このグラウト7は、所
定時間養生させることで硬化して定着層9となり、この
定着層9によりコンクリート杭8は、強固に改良体4に
接合される。
Next, the improved body 4 formed as described above
Then, a vertical hole 6 is excavated using, for example, an earth auger 5. The excavation of the vertical hole 6 is performed to the vicinity of the bottom surface of the improved body 4. After the excavation is completed, the earth auger 5 is pulled out from the ground 3 (), and then, for example, a volume expansion type grout (for example, Denka Kogyo "DENKA CSA" 7
Is supplied in a predetermined amount (). Thereafter, for example, a knotted concrete pile (prefabricated pile) 8 having a closed end is inserted into the vertical hole 5. Then, the grout 7 supplied in advance overflows into the gap between the concrete pile 8 and the inner wall of the vertical hole 5, and the grout 7 is filled in the gap. The grout 7 is cured by curing for a predetermined time to become a fixing layer 9, and the concrete pile 8 is firmly joined to the improved body 4 by the fixing layer 9.

【0012】しかして、この定着層9の形成に用いたグ
ラウト7は体積膨張型となっているので、その硬化に際
して体積膨張し、コンクリート杭8の周りの空隙を十分
に埋め、しかも、コンクリート杭8が節付きとなってい
るので、これと定着層9との摩擦抵抗が著しく増大し、
この結果、コンクリート杭8は、鉛直方向に大きな支持
力を発揮するものとなる。また、このコンクリート杭8
はその周りが大径の改良体4に包まれているので、水平
方向にも大きく抵抗し、水平方向の支持力も十分となっ
て耐震性に著しく優れたものとなる。
However, since the grout 7 used to form the fixing layer 9 is of a volume expansion type, it expands in volume upon hardening, and sufficiently fills the voids around the concrete pile 8, and 8 is knotted, the frictional resistance between this and the fixing layer 9 increases significantly,
As a result, the concrete pile 8 exhibits a large supporting force in the vertical direction. In addition, this concrete pile 8
Is surrounded by the improved body 4 having a large diameter, so that it greatly resists in the horizontal direction, and has a sufficient horizontal supporting force, so that it is extremely excellent in earthquake resistance.

【0013】なお、上記第1の実施の形態における節付
きのコンクリート杭8は、節なしのコンクリート杭に代
えても、あるいは単純な鋼管杭または節付き鋼管杭に代
えてもよいものである。また、上記第1の実施の形態に
おいて、既製杭として先端閉塞のコンクリート杭8を用
いて、予め縦穴6内に供給した定着層用グラウト7を杭
周りの空隙にオーバーフローさせるようにしたが、縦穴
6の口径とコンクリート杭8の外径との比率を大きく設
定、すなわちコンクリート杭8の周りに形成される空隙
の断面積を大きく設定した場合は、縦穴6内に予め大量
のグラウト7を供給して、これに先端開放のコンクリー
ト杭8を建込んで、プレボーリング拡大根固め工法の要
領で、杭基礎を構築することもできる。この場合は、コ
ンクリート杭8が、内・外から定着層で包まれるのでそ
の剛性が著しく増し、水平方向の支持力がより一層増大
するようになる。
The knotted concrete pile 8 in the first embodiment may be replaced with a knotless concrete pile, or may be replaced with a simple steel pipe pile or a knotted steel pipe pile. In the first embodiment, the concrete pile 8 having a closed end is used as a ready-made pile, and the grout 7 for the fixing layer previously supplied into the vertical hole 6 is caused to overflow into the space around the pile. When the ratio between the diameter of the concrete pile 6 and the outer diameter of the concrete pile 8 is set large, that is, the cross-sectional area of the void formed around the concrete pile 8 is set large, a large amount of grout 7 is supplied into the vertical hole 6 in advance. It is also possible to build a concrete pile 8 having an open end into this, and construct a pile foundation in the manner of the pre-boring expansion method. In this case, since the concrete pile 8 is wrapped with the anchoring layer from inside and outside, its rigidity is remarkably increased, and the horizontal supporting force is further increased.

【0014】さらに、上記第1の実施の形態において
は、高圧噴射攪拌工法による計画改良域を地盤3内に設
定して、改良体4を地盤3内に収めるようにしたが、こ
の改良体4は、その上端が地表に露出するように形成し
てもよいものである。この場合は、グラウトの地表への
噴出を抑えるため、地表に盛土して地盤を嵩上げした高
圧噴射攪拌工法を施工し、施工終了後、盛土を排除する
ようにすればよい。このように地表まで改良体4を形成
することで、これに建込んだ既製杭の水平方向の支持力
が大幅に増大し、耐震性の面で極めて優れたものとな
る。
Further, in the first embodiment, the planned improvement area by the high-pressure injection stirring method is set in the ground 3 and the improved body 4 is accommodated in the ground 3. May be formed so that the upper end thereof is exposed on the ground surface. In this case, in order to suppress the grout from escaping to the ground surface, a high-pressure jet stirring method in which the ground surface is embanked and the ground is raised, and the embankment may be removed after completion of the construction. By forming the improved body 4 up to the ground surface in this way, the horizontal supporting force of the ready-made pile built therein is greatly increased, and the pile is extremely excellent in terms of earthquake resistance.

【0015】図2は、本発明の第2の実施の形態を示し
たものである。本第2の実施の形態の特徴とするところ
は、上記第1の実施の形態におけるプレボーリング根固
め工法(図1の〜の工程)に代えて、マイクロパイ
ル工法を利用した点にある。このマイクロパイル工法の
施工に際しては、前記した高圧噴射攪拌工法により形成
された改良体4内に前記アースオーガー5(図1)によ
り縦穴6を掘削した後、この縦穴6内に、管壁に複数の
逆止弁10を有する先端閉塞の鋼管杭11を挿入し
()、次に、この鋼管杭11内に注入機としてのダブ
ルパッカー12を挿入する。
FIG. 2 shows a second embodiment of the present invention. The feature of the second embodiment is that a micropile method is used instead of the pre-boring method (steps 1 to 3 in FIG. 1) in the first embodiment. When the micropile method is applied, a vertical hole 6 is excavated by the earth auger 5 (FIG. 1) into the improved body 4 formed by the high-pressure jet stirring method, and then a plurality of holes are formed in the vertical hole 6 on the pipe wall. A steel pipe pile 11 having a closed end having the check valve 10 is inserted (), and a double packer 12 as an injection machine is inserted into the steel pipe pile 11.

【0016】上記ダブルパッカー12は、膨出変形可能
な一対の膨出体13,13の間に吐出口を備えており、
最初、このダブルパッカー12を鋼管杭11の最深位置
に挿入する。そして、この最深位置で一対の膨出体13
を膨張させてダブルパッカー12を位置固定し、これに
供給管14を通じてグラウト(セメントモルタル)15
を圧送する()。すると、このグラウト15は、前記
ダブルパッカー12の吐出口から一対の膨出体13,1
3の間の密閉室に吐出した後、鋼管杭11の管壁の逆止
弁10を開いて外部に噴出し、その一部が鋼管杭11の
先端側へ回ると共に、当該逆止弁10の近傍の空隙を埋
める。そして、このグラウト15の層は、ダブルパッカ
ー12を所定のピッチで引上げながら前記操作を繰り返
すことで上方へ拡大し()、遂には、鋼管杭11の周
りの空隙の全域がグラウト15で満たされる。その後、
ダブルパッカー12を鋼管杭11から引抜き、所定時間
養生させると、前記グラウト15が硬化して定着層16
となり、この定着層16により鋼管杭11は、強固に改
良体4に接合される。
The double packer 12 has a discharge port between a pair of swellable bodies 13, 13 capable of swelling and deformation.
First, the double packer 12 is inserted into the steel pipe pile 11 at the deepest position. And at this deepest position, a pair of swelling bodies 13
Is expanded to fix the position of the double packer 12 and grout (cement mortar) 15 is supplied to the double packer 12 through a supply pipe 14.
Pumping (). Then, the grout 15 is supplied from the discharge port of the double packer 12 to the pair of swelling bodies 13, 1.
After the discharge into the closed chamber between the three, the check valve 10 on the pipe wall of the steel pipe pile 11 is opened and squirted to the outside, and a part thereof turns to the tip side of the steel pipe pile 11 and the check valve 10 Fill nearby voids. Then, the layer of the grout 15 expands upward by repeating the above operation while pulling up the double packer 12 at a predetermined pitch (), and finally the entire area of the void around the steel pipe pile 11 is filled with the grout 15. . afterwards,
When the double packer 12 is pulled out from the steel pipe pile 11 and cured for a predetermined time, the grout 15 hardens and the fixing layer 16 is fixed.
The steel pipe pile 11 is firmly joined to the improved body 4 by the fixing layer 16.

【0017】本第2の実施の形態によれば、鋼管杭11
に設けた逆止弁10を通じてその周りにグラウト15を
注入するので、グラウトとして、特に体積膨張型のもの
を用いなくても、鋼管杭11の周りの空隙にグラウトが
十分に行きわたる。したがって、鋼管杭11は定着層1
6を介して改良体4に強固に接合一体化され、上記第1
の実施の形態におけるコンクリート杭8と同様に鉛直方
向および水平方向に大きな支持力を発揮するものとな
る。
According to the second embodiment, the steel pipe pile 11
Since the grout 15 is injected around the check valve 10 through the check valve 10, the grout sufficiently spreads into the gap around the steel pipe pile 11 without using a volume expansion type grout. Therefore, the steel pipe pile 11 is the anchoring layer 1
6 and is firmly joined and integrated with the improved body 4 through the first
As with the concrete pile 8 in the embodiment, a large supporting force is exerted in the vertical and horizontal directions.

【0018】図3は、本発明の第3の実施の形態を示し
たものである。本第3の実施の形態は、上記第2の実施
の形態におけるマイクロパイル工法の施工に際し、前記
逆止弁10を先端閉塞の鋼管杭11に代えて、複数の逆
止弁20を有する先端開放の鋼管杭21を用いると共
に、前記ダブルパッカー12に代えてシングルパッカー
22を用いた点にある。シングルパッカー22は、膨出
変形可能な一つの膨出体23を備えており、その吐出口
は膨出体23の下方に設定されている。施工に際して
は、前記第2の実施の形態と同様、改良体4内に掘削し
た縦穴6内に、前記逆止弁20付鋼管杭21を挿入し
()、さらにこの鋼管杭21内にシングルパッカー2
2を挿入する。
FIG. 3 shows a third embodiment of the present invention. In the third embodiment, when the micropile method in the second embodiment is applied, the check valve 10 is replaced with a steel pipe pile 11 having a closed tip, and the open tip having a plurality of check valves 20 is used. And a single packer 22 is used in place of the double packer 12. The single packer 22 has one swellable body 23 that can be swelled and deformed, and its discharge port is set below the swelled body 23. At the time of construction, similarly to the second embodiment, the steel pipe pile 21 with the check valve 20 is inserted into the vertical hole 6 excavated in the improved body 4 (), and a single packer is further inserted into the steel pipe pile 21. 2
Insert 2.

【0019】そして、最初、このシングルパッカー22
を鋼管杭21の最深位置に挿入し、この最深位置で膨出
体23を膨張させてシングルパッカー22を位置固定
し、これに供給管14を通じて前記グラウト15を圧送
する()。すると、このグラウト15は、シングルパ
ッカー22の先端の吐出口から吐出して鋼管杭21の先
端開口から外部へ噴出し、鋼管杭21の前方の空隙を埋
めると共に、その先端部の周りの空隙を埋める。次に、
シングルパッカー22を所定の距離(逆止弁20の配列
ピッチ)だけ上昇させて前記操作を繰り返す。すると、
グラウト15は鋼管杭21の内部を埋めた後、吐出口近
傍の逆止弁20を開いて鋼管杭21の周りの空隙に噴出
し、当該逆止弁20の周りの空隙を埋める。そして、こ
の鋼管杭21の内・外のグラウト15の層は、シングル
パッカー22を所定のピッチで引上げながら前記操作を
繰り返すことで上方へ拡大し()、遂には、鋼管杭2
1の周りの空隙の全域がグラウト15で充填される。そ
の後、シングルパッカー22を鋼管杭21から引抜き、
所定時間養生させると、前記グラウト15が硬化して定
着層24となり、この定着層24により鋼管杭21は、
強固に改良体4に接合される。本第3の実施の形態によ
れば、上記第2の実施の形態と同様の効果を奏する他、
鋼管杭21が、内・外から定着層24で包まれるのでそ
の剛性が著しく増し、水平方向の支持力がより一層増大
するようになる。
At first, this single packer 22
Is inserted into the deepest position of the steel pipe pile 21, the swelling body 23 is expanded at the deepest position to fix the position of the single packer 22, and the grout 15 is fed to the single packer 22 through the supply pipe 14. Then, the grout 15 is discharged from the discharge port at the tip of the single packer 22 and spouts out from the tip opening of the steel pipe pile 21 to fill the gap in front of the steel pipe pile 21 and fill the gap around the tip. fill in. next,
The operation is repeated by raising the single packer 22 by a predetermined distance (the arrangement pitch of the check valves 20). Then
After filling the inside of the steel pipe pile 21, the grout 15 opens the check valve 20 near the discharge port and blows out into the gap around the steel pipe pile 21 to fill the gap around the check valve 20. Then, the layers of the grout 15 inside and outside of the steel pipe pile 21 are expanded upward by repeating the above operation while pulling up the single packer 22 at a predetermined pitch ().
The entire area of the void around 1 is filled with grout 15. After that, the single packer 22 is pulled out from the steel pipe pile 21,
After curing for a predetermined time, the grout 15 hardens to become a fixing layer 24, and the steel pipe pile 21 is fixed by the fixing layer 24.
It is firmly joined to the improved body 4. According to the third embodiment, in addition to the same effects as those of the second embodiment,
Since the steel pipe pile 21 is wrapped in the fixing layer 24 from inside and outside, its rigidity is remarkably increased, and the horizontal supporting force is further increased.

【0020】[0020]

【発明の効果】以上、説明したように、本発明に係る杭
基礎工法によれば、高圧噴射攪拌工法により形成した改
良体内に既製杭を建込むので、支持層に杭を根入れする
必要はなく、その上、ボイリング、グラウト流出、孔壁
の崩落などのトラブルが生じることもなくなって、安定
してかつ効率よく杭基礎を構築できる。しかも、構築さ
れた杭基礎は、大径の改良体と基礎杭とが一体となって
鉛直方向および水平方向に大きな支持力を発揮するもの
となり、その及ぼす効果は大なるものがある。
As described above, according to the pile foundation method according to the present invention, since the ready-made pile is built in the improved body formed by the high-pressure injection stirring method, it is not necessary to insert the pile into the support layer. In addition, troubles such as boiling, grout outflow, and collapse of the hole wall do not occur, and a pile foundation can be stably and efficiently constructed. In addition, the constructed pile foundation is such that the improved body having a large diameter and the foundation pile are integrated to exert a large supporting force in the vertical and horizontal directions, and the effect exerted is large.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施の形態の施工順序を示す断
面図である。
FIG. 1 is a cross-sectional view showing a construction order according to a first embodiment of the present invention.

【図2】本発明の第2の実施の形態の施工順序を示す断
面図である。
FIG. 2 is a cross-sectional view showing a construction order according to a second embodiment of the present invention.

【図3】本発明の第3の実施の形態の施工順序を示す断
面図である。
FIG. 3 is a cross-sectional view illustrating a construction order according to a third embodiment of the present invention.

【符号の説明】[Explanation of symbols]

2 高圧噴射攪拌工法用注入ロッド 3 地盤 4 改良体 5 アースオーガー 6 縦穴 7,15 グラウト 8 節付きコンクリート杭 9,16,24 定着層 10,20 逆止弁 11,21 鋼管杭 12 タブルパッカー(注入機) 22 シングルパッカー(注入機) 2 Injection rod for high-pressure injection stirring method 3 Ground 4 Improved body 5 Earth auger 6 Vertical hole 7,15 Grout 8 Knotted concrete pile 9,16,24 Anchoring layer 10,20 Check valve 11,21 Steel pipe pile 12 Double packer (Injection Machine) 22 single packer (injector)

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 高圧噴射攪拌工法により地盤に改良体を
形成した後、該改良体に竪穴を掘削し、しかる後、前記
竪穴に既製杭を挿入すると共に、該既製杭の周りの空隙
にグラウトを充填することを特徴とする杭基礎工法。
An improved body is formed in the ground by a high-pressure injection stirring method, and a pit is excavated in the improved body. Thereafter, a ready-made stake is inserted into the pit and grout is inserted into a space around the ready-made stake. A pile foundation method characterized by filling.
【請求項2】 グラウトとして、体積膨張型グラウトを
用いることを特徴とする請求項1に記載の杭基礎工法。
2. The pile foundation method according to claim 1, wherein a volume expansion type grout is used as the grout.
【請求項3】 既製杭として、コンクリート杭を用いる
ことを特徴とする請求項1または2に記載の杭基礎工
法。
3. The pile foundation method according to claim 1, wherein a concrete pile is used as the ready-made pile.
【請求項4】 既製杭として、鋼管杭を用いることを特
徴とする請求項1または2に記載の杭基礎工法。
4. The pile foundation method according to claim 1, wherein a steel pipe pile is used as the ready-made pile.
【請求項5】 既製杭が、節付きであることを特徴とす
る請求項3または4に記載の杭基礎工法。
5. The pile foundation method according to claim 3, wherein the ready-made pile is knotted.
JP26201799A 1999-09-16 1999-09-16 Pile foundation work Pending JP2001081770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26201799A JP2001081770A (en) 1999-09-16 1999-09-16 Pile foundation work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26201799A JP2001081770A (en) 1999-09-16 1999-09-16 Pile foundation work

Publications (1)

Publication Number Publication Date
JP2001081770A true JP2001081770A (en) 2001-03-27

Family

ID=17369870

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26201799A Pending JP2001081770A (en) 1999-09-16 1999-09-16 Pile foundation work

Country Status (1)

Country Link
JP (1) JP2001081770A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371550A (en) * 2001-06-18 2002-12-26 Asahi Kasei Corp Construction method of soil cement composite precast pile
JP2003055965A (en) * 2001-08-10 2003-02-26 Tenox Corp Soil cement columnar body with thin steel pipe present as core material and its construction method
CN102953374A (en) * 2012-11-12 2013-03-06 国家电网公司 High pressure rotary jet grouting pile construction method for power transmission line iron tower pile foundation construction
JP2016217119A (en) * 2015-05-20 2016-12-22 鹿島建設株式会社 Pile construction method
CN106917401A (en) * 2017-02-28 2017-07-04 中国二十冶集团有限公司 Rubble, pebble layer high-pressure rotary jet grouting pile do not return the processing method of slurry
CN107435329A (en) * 2017-07-25 2017-12-05 孙文 Cement mixing pile and its construction equipment and construction method with concrete core stake
KR101816006B1 (en) * 2015-10-21 2018-02-21 한국도로공사 Method for supporting an augered pile and apparatus thereof
CN114541457A (en) * 2022-03-09 2022-05-27 华能陕西靖边电力有限公司 Pile foundation for photovoltaic support

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371550A (en) * 2001-06-18 2002-12-26 Asahi Kasei Corp Construction method of soil cement composite precast pile
JP2003055965A (en) * 2001-08-10 2003-02-26 Tenox Corp Soil cement columnar body with thin steel pipe present as core material and its construction method
JP4672209B2 (en) * 2001-08-10 2011-04-20 株式会社テノックス Soil-cement pillars having a small-diameter steel pipe as a core material and construction method
CN102953374A (en) * 2012-11-12 2013-03-06 国家电网公司 High pressure rotary jet grouting pile construction method for power transmission line iron tower pile foundation construction
JP2016217119A (en) * 2015-05-20 2016-12-22 鹿島建設株式会社 Pile construction method
KR101816006B1 (en) * 2015-10-21 2018-02-21 한국도로공사 Method for supporting an augered pile and apparatus thereof
CN106917401A (en) * 2017-02-28 2017-07-04 中国二十冶集团有限公司 Rubble, pebble layer high-pressure rotary jet grouting pile do not return the processing method of slurry
CN107435329A (en) * 2017-07-25 2017-12-05 孙文 Cement mixing pile and its construction equipment and construction method with concrete core stake
CN114541457A (en) * 2022-03-09 2022-05-27 华能陕西靖边电力有限公司 Pile foundation for photovoltaic support

Similar Documents

Publication Publication Date Title
JP3769637B2 (en) Slope stabilization method
KR101332848B1 (en) Method for constructing micro pile using deformed or screw steel pipe and pressure grouting
JP5582497B2 (en) Slope stabilization method and landslide steel pipe restraint pile
JP4974364B2 (en) Pile burying method
KR101977791B1 (en) Construction method of pile with Soil Cement mixing Foundation
JP3752560B2 (en) Basic structure for constructing a new building in an existing basement and its construction method
JP2001081770A (en) Pile foundation work
JP4811176B2 (en) Construction method of ready-made piles
JPS5985028A (en) Steel pipe pile and laying work thereof
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP2002061178A (en) Method of burying existing pile with protrusion in pile installation by inner excavation and foundation pile structure
JP4872561B2 (en) Construction method of ready-made piles
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
KR20100030241A (en) Compaction grouting method
KR102287362B1 (en) Reinforcement method fot tip of PHC pile using loe fluidity mortar
KR20190143205A (en) Construction method of composite pile with extensioned tip
JP2001064958A (en) Foundation constructing method
WO2022134224A1 (en) Construction method for pre-stressed pull-resistant anchor rod of concrete expansion head
KR100996444B1 (en) Method for carrying out improved micro pile and improved micro pile and ribbed section pipe of the improved micro pile
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
KR20190043709A (en) Construction Method Soft Surface Treatment And Strength of Reinforced Soil Using Waste Aggregates
JPS60126423A (en) Pile driving method
KR101080159B1 (en) Enlarged endbearing capacity foundation using cone and it's construction work method
JP4069973B2 (en) Pile burying method
JP2000154540A (en) Bored pile, its work execution method, work execution device, and existing pile for bored pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061031

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061213

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070509