JPS63181899A - Shield excavator - Google Patents

Shield excavator

Info

Publication number
JPS63181899A
JPS63181899A JP62013432A JP1343287A JPS63181899A JP S63181899 A JPS63181899 A JP S63181899A JP 62013432 A JP62013432 A JP 62013432A JP 1343287 A JP1343287 A JP 1343287A JP S63181899 A JPS63181899 A JP S63181899A
Authority
JP
Japan
Prior art keywords
outer shell
press ring
concrete
shield excavator
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP62013432A
Other languages
Japanese (ja)
Other versions
JPH0578637B2 (en
Inventor
富雄 田村
林 寿夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP62013432A priority Critical patent/JPS63181899A/en
Publication of JPS63181899A publication Critical patent/JPS63181899A/en
Publication of JPH0578637B2 publication Critical patent/JPH0578637B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明は、トンネルにおける覆工を、現場打ちコンクリ
ートで構築する際に適用するに好適なシールド掘削機に
関する。
DETAILED DESCRIPTION OF THE INVENTION (a) Industrial Application Field The present invention relates to a shield excavator suitable for use in constructing a tunnel lining using cast-in-place concrete.

(b)、従来の技術 最近、シールド掘削機により掘削されたトンネルの覆工
を、現場打ちコンクリートで構築するための種々の提案
がなされている。
(b). Prior Art Recently, various proposals have been made for constructing the lining of a tunnel excavated by a shield excavator using cast-in-place concrete.

(C)0発明が解決しようとする間急点しかし、いまだ
カーブ施工(ここで、カーブ施工とは、新たな覆工を既
設の覆工に対して所定角度だけズラす形で打ち継ぎ形成
してゆくことを意味する。以下同様である。)を円滑に
行う技術が確立されておらず、当該カーブ施工をする際
にも円滑に作業を進めて行くことが出来るシールド掘削
機の開発が急がれている。
(C) 0 A sudden point while the invention is trying to solve the problem.However, curve construction is still being carried out (here, curve construction is a method of forming a new lining by shifting it by a predetermined angle with respect to the existing lining). The technology to smoothly carry out this work has not yet been established, and there is an urgent need to develop a shield excavator that can smoothly carry out the work when constructing the curve. It's broken.

本発明は、上記事情に2み、カーブ施工をする際にも円
滑に作業を行うことが出来るシールド掘削機を提供する
ことを目的とする。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a shield excavator that can smoothly perform work even when constructing a curve.

(d)8問題点を解決するための手段 即ち、本発明は、外殻(2)を有し、該外殻(2)の内
側にプレスリング(7)を、前記外殻(2)の掘進方向
に移動駆動自在に設け、該プレスリング(7)の内側に
型枠支持部材(11)を。
(d) Means for solving 8 problems, that is, the present invention has an outer shell (2), and a press ring (7) inside the outer shell (2). A formwork support member (11) is provided inside the press ring (7) so as to be freely movable and driven in the excavation direction.

前記外殻(2)に対して移動駆動自在に設け、更に、少
なくとも前記型枠支持部材(11)を複数個に分割する
と共に、該分割部分(11a、11b)が独立して前記
外殻(2)の掘進方向に移動し得るようにして構成され
る。
It is provided so as to be movable and driveable with respect to the outer shell (2), and furthermore, at least the formwork support member (11) is divided into a plurality of parts, and the divided parts (11a, 11b) are independently connected to the outer shell (2). 2) It is constructed so that it can move in the excavation direction.

なお、括弧内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下の「(e)0
作用」の欄についても同様である。
Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions on the drawings. Below “(e)0
The same applies to the column "Effect".

(e)6作用 上記した構成により、本発明は、カーブ施工を行なう際
にも、シールド掘削機(1)が、型枠支持部材(11)
の分割部分(lla、1lb)を介して斜めに設置され
た型枠(13)から安定的に反力を取る形で掘進するよ
うに作用する。
(e) 6 Effects With the above configuration, the present invention allows the shield excavator (1) to move the formwork support member (11) even when performing curve construction.
The excavation works by stably taking reaction force from the diagonally installed formwork (13) through the divided parts (lla, 1lb).

(f)、実施例 以下、本発明の実施例を図面に基づき説明する。(f), Example Embodiments of the present invention will be described below based on the drawings.

第1図は本発明によるシールド掘削機の一実施例を示す
平断面図、 第2図は第1図の■−■線による断面図。
FIG. 1 is a plan sectional view showing an embodiment of a shield excavator according to the present invention, and FIG. 2 is a sectional view taken along the line ■-■ in FIG.

第3図は第1図のm−m線に′よる断面図、第4図はシ
ールド掘削機のジヤツキ部分の拡大図。
FIG. 3 is a sectional view taken along the line m-m in FIG. 1, and FIG. 4 is an enlarged view of the jacking part of the shield excavator.

第5図は第4図の■−■線による断面図、第6図乃至第
13図は本発明によるシールド掘削機を用いて、直線的
に覆工を打ち継ぎ形成する様子を示す工程図、 第14図は本発明によるシールド掘削機を用いてカーブ
施工する様子を示す平断面図である。
FIG. 5 is a sectional view taken along the line ■-■ in FIG. 4, and FIGS. 6 to 13 are process diagrams showing how the lining is spliced and formed in a straight line using the shield excavator according to the present invention. FIG. 14 is a plan sectional view showing how a curve is constructed using the shield excavator according to the present invention.

シールド掘削機1は、第1図に示すように、円筒状に形
成された外殻2を有しており、外殻2の前面、即ち第1
図左側面にはカッタ3が回転自在に支持されている。カ
ッタ3は、外殻2内部の空間を左右方向に遮断する形で
設けられた外殻2の隔壁2aに設けられた駆動モータ5
と接続しており、更に隔壁2aには、それぞれ複数個の
掘進用ジヤツキ6A、6Bが、第2図に示すように。
As shown in FIG. 1, the shield excavator 1 has a cylindrical outer shell 2, and the front surface of the outer shell 2, that is, the first
A cutter 3 is rotatably supported on the left side of the figure. The cutter 3 is driven by a drive motor 5 provided on a partition wall 2a of the outer shell 2, which is provided to block the space inside the outer shell 2 in the left-right direction.
Further, a plurality of digging jacks 6A and 6B are connected to the partition wall 2a, respectively, as shown in FIG.

図中左右に区分され、しかも外殻2に沿った形で所定の
間隔で配列設置されている。掘進用ジヤツキ6A、6B
には、第1図に示すようにそれぞれラム6a、6bが、
矢印A、B方向に突出後退自在に設けられており、更に
外殻2の内側には1円筒状に形成されたプレスリング7
が、外殻2内面と接する形で、矢印A、B方向に摺動自
在に設けられている。
They are divided into left and right sections in the figure, and are arranged along the outer shell 2 at predetermined intervals. Excavation jack 6A, 6B
As shown in FIG. 1, the rams 6a and 6b are
It is provided so as to be able to protrude and retreat in the directions of arrows A and B, and further inside the outer shell 2 is a press ring 7 formed in a cylindrical shape.
is provided in contact with the inner surface of the outer shell 2 and is slidable in the directions of arrows A and B.

プレスリング7は、第2図及び第3図に示すように、図
中左右に2分割されており、該プレスリング7は5半円
筒状に形成さ九た2個のプレスリング片7a、7bを有
している。なお、プレスリング片7a、7bは、それぞ
れ独立して外殻2の掘進方向、即ち図中紙面と直角な方
向に移動し得る形で組み合わされており、プレスリング
片7a、7bには、それぞれ複数個のプレスリングジヤ
ツキ9a、9bが、外殻2に沿った形で所定の間隔で配
置されている。
As shown in FIGS. 2 and 3, the press ring 7 is divided into two parts on the left and right in the figure, and the press ring 7 is formed into a semi-cylindrical shape and has two press ring pieces 7a and 7b. have. Note that the press ring pieces 7a and 7b are combined in such a manner that they can each independently move in the excavation direction of the outer shell 2, that is, in the direction perpendicular to the plane of the paper in the figure, and the press ring pieces 7a and 7b each have a A plurality of press ring jacks 9a, 9b are arranged along the outer shell 2 at predetermined intervals.

また、プレスリング片7a、7bには、それぞれ複数個
のコンクリート吐出管10が、第2図及び第5図に示す
ように、先端の吐出口10aをプレスリング片7a、7
bの側面7c、7d、即ちシールド掘削機1の後方に向
けた形で設けられており、各コンクリート吐出管10に
は、吐出管清掃用のシリンダ10bがロッド10cを矢
印C1D方向に突出後退自在にした形で設けられている
Further, each of the press ring pieces 7a, 7b has a plurality of concrete discharge pipes 10 connected to the press ring pieces 7a, 7b through a discharge port 10a at the tip, as shown in FIGS. 2 and 5.
b side faces 7c and 7d, that is, facing the rear of the shield excavator 1, and each concrete discharge pipe 10 has a discharge pipe cleaning cylinder 10b with a rod 10c protruding in the direction of arrow C1D so as to be freely retractable. It is set up in the shape of

なお、吐出管10にはコンクリート供給ホース30が接
続している。
Note that a concrete supply hose 30 is connected to the discharge pipe 10.

更に、掘進用ジヤツキ6A、6Bの各ラム6a、6bの
先端には1円環状に形成されたゲージリング11が装着
されており、ゲージリング11は、第2図及び第3図に
示すように、プレスリング片7a、7bと整合する形で
図中左右に2分割されている。即ち、ゲージリング11
は、半円環状に形成されたゲージリング片11a、ll
bから構成されており、ゲージリング片11a、11b
は、それぞれ掘進用ジヤツキ6A、6Bにより独立して
外殻2の掘進方向、即ち図中紙面と直角な方向に移動し
得る形で組み合わされている。なお、ゲージリング片1
1a、llbには係合溝11c、lidが、それぞれゲ
ージリング片11a、11bの外周に沿って半円状に穿
設形成されており、係合溝11c、lidには、第1図
に示すように、鉄筋等の補強部材12が嵌入している。
Further, a gauge ring 11 formed in an annular shape is attached to the tip of each ram 6a, 6b of the excavation jacks 6A, 6B, and the gauge ring 11 has a ring shape as shown in FIGS. 2 and 3. , is divided into two parts on the left and right in the figure in a manner that is aligned with the press ring pieces 7a and 7b. That is, the gauge ring 11
are gauge ring pieces 11a, ll formed in a semicircular shape.
gage ring pieces 11a, 11b.
are combined in such a manner that they can be moved independently by excavation jacks 6A and 6B in the excavation direction of the outer shell 2, that is, in the direction perpendicular to the plane of the paper in the figure. In addition, gauge ring piece 1
Engagement grooves 11c and lids are formed in semicircular shapes along the outer peripheries of gauge ring pieces 11a and 11b, respectively, and engagement grooves 11c and lids are formed in the engagement grooves 11c and lid as shown in FIG. As shown, a reinforcing member 12 such as a reinforcing bar is inserted.

更に、ゲージリング11には、第2図及び第3図に示す
ように1円環状に組立られた型枠13が、第1図左右方
向に接続された形で設けられている。
Furthermore, as shown in FIGS. 2 and 3, the gauge ring 11 is provided with a mold 13 that is assembled into a ring shape and connected in the left-right direction in FIG.

シールド掘削機1は1以上のような構成を有するので、
トンネル15の掘削に際しては、駆動モータ5によりカ
ッタ3を回転させると共に、掘進用ジヤツキ6A、6B
を同期的に駆動して、各ラム6a、6bを、同一速度で
、かつ同一距離だけ第1図B方向に突出させて、隔壁2
a及び外殻2を介してカッタ3を切羽16方向、即ち矢
印A方向に押圧する6すると、その押圧力により、カッ
タ3と切羽16は所定の接触圧力で接し、切羽16はカ
ッタ3により掘削され、それと同時に、外殻2は入方向
に直線的に掘進して、トンネル15がシールド掘削機1
の後方、即ち第1図右方に直線的に形成されてゆく。
Since the shield excavator 1 has one or more configurations,
When excavating the tunnel 15, the drive motor 5 rotates the cutter 3, and the excavation jacks 6A, 6B
are driven synchronously to cause each ram 6a, 6b to protrude in the direction B of FIG. 1 at the same speed and by the same distance.
When the cutter 3 is pressed in the direction of the face 16, that is, in the direction of arrow A, through the outer shell 2 and the outer shell 2, the cutter 3 and the face 16 come into contact with a predetermined contact pressure, and the face 16 excavates with the cutter 3. At the same time, the outer shell 2 excavates linearly in the entrance direction, and the tunnel 15 is excavated by the shield excavator 1.
It is formed linearly to the rear of , that is, to the right in Figure 1.

こうして、トンネル15が直線的に形成されてゆくにつ
れ、掘削された地山19の崩壊を防止するために覆工2
0を構築する必要が有るが、この覆工20の構築は、以
下の手順で行なわれる。
In this way, as the tunnel 15 is formed linearly, the lining 2 is installed to prevent the excavated ground 19 from collapsing.
Although it is necessary to construct the lining 20, the construction of the lining 20 is performed in the following steps.

即ち、シールド掘削機1が、型枠13の1リング分の長
さLlだけ入方向に掘進した状態では、掘進用ジヤツキ
6A、6Bの各ラム6a、6bは、第6図に示すように
、それぞれB方向に突出した状態となっており、またプ
レスリング7も、プレスリング片7a、7bが整合した
状態でB方向に移動した状態どなっている。なお、ラム
6a(従って、ゲージリング片11a)とラム6b(従
って、ゲージリング片11b)との移動動作は全く同一
であるので、第6図においては、掘進用ジヤツキ6A−
ラム6a及びゲージリング片11aのみを図示する。ま
た、プレスリング7についても。
That is, when the shield excavator 1 has excavated in the inward direction by a length Ll corresponding to one ring of the formwork 13, the rams 6a and 6b of the excavation jacks 6A and 6B, as shown in FIG. Each of them is in a state of protruding in the B direction, and the press ring 7 is also in a state of being moved in the B direction with the press ring pieces 7a and 7b aligned. Incidentally, since the moving operations of the ram 6a (therefore, the gauge ring piece 11a) and the ram 6b (therefore, the gauge ring piece 11b) are exactly the same, in FIG.
Only the ram 6a and the gauge ring piece 11a are shown. Also, regarding press ring 7.

同様の理由によりプレスリング片7aのみを図示する。For the same reason, only the press ring piece 7a is illustrated.

以下、第7図乃至第13図においても同様である。The same applies to FIGS. 7 to 13 below.

この状態で、ラム6a、6bを共にA。方向に距!LL
だけ後退させる(第7図参照)。すると、直前にコンク
リート21の打設された部分の妻止め22A及び型枠1
3Aから、ゲージリング11が、離れてA方向に移動し
、妻止め22A及び型枠13Aとゲージリング11との
間に距離L1なる空間が形成される。なお、この際ラム
6a、6bの移動量は同一であるので、ゲージリング片
11a、llbは、互いに矢印A、B方向にズレること
なく整合した状態で移動する。
In this state, both rams 6a and 6b are set to A. Distance in the direction! LL
(see Figure 7). Then, the end stop 22A and formwork 1 of the part where concrete 21 was poured just before
3A, the gauge ring 11 moves away from the gauge ring 11 in the direction A, and a space of distance L1 is formed between the gauge ring 11 and the end stop 22A and the formwork 13A. At this time, since the moving distances of the rams 6a and 6b are the same, the gauge ring pieces 11a and llb move in alignment with each other without shifting in the directions of arrows A and B.

次に、その状態で該空間部分に、第7図想像線で示すよ
うに、補強部材12を係合溝11c、lidを介して妻
止め22Bと共に設置する。更に、型枠i3Aに接する
形で型枠13Bを組立設置し、該型枠13Bとゲージリ
ング11(妻止め22B)、プレスリング7及び妻止め
22Aとの間にコンクリート打設空間23を形成する。
Next, in this state, the reinforcing member 12 is installed in the space through the engagement groove 11c and the lid, together with the end stop 22B, as shown by the imaginary line in FIG. Furthermore, a formwork 13B is assembled and installed in contact with the formwork i3A, and a concrete placement space 23 is formed between the formwork 13B and the gauge ring 11 (end stop 22B), press ring 7, and end stop 22A. .

この状態で、第8図に示すように、型枠13Bにコンク
リート供給管25を接続して、コンクリート供給管25
によりコンクリート打設空間23中にコンクリート21
を打設する。なお、この際、コンクリート打設空間23
中の空気は、型枠13に適宜設けられたエア抜き管13
 aにより外部に排出さ九るので、コンクリート21の
コンクリート打設空間23中への注入打設動作は円滑に
行なわれる。
In this state, as shown in FIG. 8, the concrete supply pipe 25 is connected to the formwork 13B.
Concrete 21 is placed in concrete placing space 23 by
to be poured. In addition, at this time, the concrete placement space 23
The air inside is removed through an air vent pipe 13 appropriately provided in the formwork 13.
Since the concrete 21 is discharged to the outside by a, the pouring operation of the concrete 21 into the concrete placement space 23 is performed smoothly.

こうして、コンクリート打設空間23中にコンクリート
21が打設されたところで、第9図に示すように、今度
はプレスリングジヤツキ9a、9bを同期的に駆動して
、プレスリング片7a。
When the concrete 21 has been placed in the concrete placement space 23 in this way, as shown in FIG. 9, the press ring jacks 9a and 9b are driven synchronously to release the press ring piece 7a.

7bを同一距離だけ入方向に徐々に後退させる。7b is gradually retreated in the incoming direction by the same distance.

すると、プレスリング片7a、7bが通過した後には、
外殻2と注入されたコンクリート21との間に空間26
が形成される。そこで、プレスリング片7a、7b(即
ち、プレスリング7)の入方向の移動と共に、第10図
に示すように、コンクリート吐出管10からコンクリー
ト21を、該空間26中に注入し、該空間26をコンク
リート21で充填する。
Then, after the press ring pieces 7a and 7b pass,
A space 26 between the outer shell 2 and the poured concrete 21
is formed. Therefore, as the press ring pieces 7a and 7b (that is, the press ring 7) move in the incoming direction, concrete 21 is injected into the space 26 from the concrete discharge pipe 10, as shown in FIG. is filled with concrete 21.

プレスリング片7a、7bが入方向に移動して、第11
図に示すように、側面7c、7dがゲージリング11側
の妻止め22 Bの設置位置と略一致したところで、第
12図に示すよ°うに、掘進用ジヤツキ6A、6Bを同
期的に駆動して、ラム6a、6bを同一速度でB方向に
突出駆動させると共に、カッタ3を回転させて掘削動作
を開始する。すると、既に述べたように、外殻2がA方
向に移動を開始し、外殻2が移動した後に、打設充填さ
れたコンクリート21と地山19との間にテールボイド
27が形成される。従って、外殻2が入方向に移動する
につれて、プレスリングジヤツキ9a、9bを同期的に
駆動して、プレスリング7a、7bを、外殻2の移動に
同期した形でB方向に徐々に同一速度で移動させる。す
ると、プレスリング片7a、7bの側面7c、7dは、
整合した状態でB方向に移動し、該側面7c、7dによ
って、先程打設されたコンクリート打設空間23及び空
間26内の未硬化のコンクリート21はB方向に押圧さ
れて、テールボイド27を充填する形で流動する。
The press ring pieces 7a and 7b move in the inward direction, and the 11th
As shown in the figure, when the side surfaces 7c and 7d are approximately aligned with the installation position of the end stop 22B on the gauge ring 11 side, the digging jacks 6A and 6B are driven synchronously as shown in FIG. Then, the rams 6a and 6b are driven to protrude in the B direction at the same speed, and the cutter 3 is rotated to start the excavation operation. Then, as described above, the outer shell 2 starts moving in the direction A, and after the outer shell 2 moves, the tail void 27 is formed between the poured and filled concrete 21 and the ground 19. Therefore, as the outer shell 2 moves in the entry direction, the press ring jacks 9a and 9b are synchronously driven to gradually move the press rings 7a and 7b in the B direction in synchronization with the movement of the outer shell 2. move at the same speed. Then, the side surfaces 7c and 7d of the press ring pieces 7a and 7b are as follows.
They move in the B direction in an aligned state, and the unhardened concrete 21 in the concrete placement space 23 and space 26 that was placed earlier is pressed in the B direction by the side surfaces 7c and 7d, filling the tail void 27. Flowing in shape.

こうして、第13図に示すように、外殻2のA方向の移
動につれて、プレスリング7をB方向に移動させてゆく
と、外殻2の移動の結果発生するテールボイド27は、
効果的に充填されてゆく。
In this way, as shown in FIG. 13, when the press ring 7 is moved in the direction B as the outer shell 2 moves in the A direction, the tail void 27 generated as a result of the movement of the outer shell 2 is
It is filled effectively.

こうして、1リング分外殻2が推進すると、プレスリン
グ7は、第6図に示すように、その側面7c、7dが外
殻2の後端部に一致した形となり、1リング分の覆工2
0の構築が完了する。なお、この際の、コンクリート2
1の打ち継ぎ面29は、第1図に示すように、プレスリ
ング7の移動動作により1階段状に形成される。
In this way, when the outer shell 2 is propelled by one ring, the press ring 7 has its side surfaces 7c and 7d aligned with the rear end of the outer shell 2, as shown in FIG. 2
Construction of 0 is completed. In addition, at this time, concrete 2
As shown in FIG. 1, the first pouring surface 29 is formed into a single step shape by the movement of the press ring 7.

なお、上述した実施例においては、覆工20を、A方向
に直線的に打ち継ぎ形成した場合について述べたが、シ
ールド掘削機1の掘進方向を、入方向から徐々に左方(
第14図においては図中左肩め下方)に変えてカーブ施
工する場合について以下説明する。なお、第1図乃至第
13図において説明した部分と同一の部分は、同一の符
号を付してその部分の説明を省略する。
In addition, in the above-mentioned embodiment, a case was described in which the lining 20 was formed in a straight line in the A direction, but the excavation direction of the shield excavator 1 was gradually changed from the entry direction to the left (
In Fig. 14, the case where the curve is constructed instead of the lower left shoulder in the figure will be explained below. Note that the same parts as those explained in FIGS. 1 to 13 are given the same reference numerals, and the explanation of the parts will be omitted.

即ち、シールド掘削機1が、型枠13Bの1リング分の
長さLlだけA方向に掘進した状態では、掘進用ジヤツ
キ6A、6Bの各ラム6a、6bは、B方向に突呂した
状態となっており、またプレスリング7も、プレスリン
グ片7a、7bが整合した状態でB方向に移動した状態
となっている(第6図参照)。   ・ そこで、掘進用ジヤツキ6A、6Bを駆動して、B方向
に突出したラム6a、6bを、第14図に示すように、
それぞれ距@L3、L2(但し1、L 3>L 2>L
 i)だけA方向に後退させる。するど、ゲージリング
片11a、llbは、直前にコンクリート21の打設さ
れた部分の妻止め22B及び型枠13Bから離乳、更に
A方向に距離L3、L2だけ移動して、妻止め22B及
び型枠13Bとゲージリング片11a、llbとの間に
空間が形成される。
That is, when the shield excavator 1 has dug in the A direction by a length Ll corresponding to one ring of the formwork 13B, the rams 6a and 6b of the excavation jacks 6A and 6B are in a state where they are thrust in the B direction. The press ring 7 is also moved in the direction B with the press ring pieces 7a and 7b aligned (see FIG. 6).・Therefore, the digging jacks 6A and 6B are driven to cause the rams 6a and 6b to protrude in the direction B, as shown in FIG.
Distance @L3, L2 (however, 1, L 3>L 2>L
i) retreat in direction A. Then, the gauge ring pieces 11a and llb are separated from the end stop 22B and formwork 13B of the part where the concrete 21 was placed just before, and further moved in the A direction by distances L3 and L2, and are removed from the end stop 22B and the formwork 13B. A space is formed between the frame 13B and the gauge ring pieces 11a, llb.

そこで、該空間部分に、第14図に示すように、補強部
材12を係合溝11c、lidを介して設置すると共に
、妻止め22Dti−設置する。更に、型枠13Dを、
型枠13Bに図中下方に向けて厚さが次第に薄くなる円
環状の矯正用ブロック32を介して接続する形で設置す
る。すると、型枠13Dの図中外周面13dは一矢印A
方向から所定角度だけ図中左肩め下方にズした状態で保
持されることになり、外周面13d、ゲージリング片1
1a、11b(妻止め22D)、プレスリング片7a、
7b及び妻止め22Bとの間にコンクリート打設空間2
3が形成される。なお、この際ゲージリング片11bは
、ゲージリング片ILaよりも外殻2の後方(矢印B方
向)にズした位置に位置決めされているので、図中斜め
になる形で設置された型枠13Dは、これ等ゲージリン
グ片11a、llbにその図中左側面を当接する形で支
持されることになる。
Therefore, as shown in FIG. 14, the reinforcing member 12 is installed in the space through the engagement groove 11c and the lid, and the end stop 22Dti is installed. Furthermore, formwork 13D,
It is installed so as to be connected to the formwork 13B via an annular straightening block 32 whose thickness gradually decreases downward in the figure. Then, the outer circumferential surface 13d of the formwork 13D in the figure is indicated by one arrow A.
It will be held in a state shifted downward from the left shoulder in the figure by a predetermined angle from the direction, and the outer peripheral surface 13d and the gauge ring piece 1
1a, 11b (end stop 22D), press ring piece 7a,
Concrete placement space 2 between 7b and end stop 22B
3 is formed. At this time, the gauge ring piece 11b is positioned at a position shifted to the rear of the outer shell 2 (in the direction of arrow B) than the gauge ring piece ILa, so the formwork 13D installed obliquely in the figure are supported by the gauge ring pieces 11a and 11b with their left side surfaces in contact with the gauge ring pieces 11a and llb.

この状態で、コンクリート打設空間23中にコンクリー
ト21を打設充填する。コンクリート21が充填された
ところで、プレスリングジヤツキ9a、9bを駆動して
、プレスリング片7a、7bをA方向に徐々に後退させ
ると共に、コンクリート吐出管10から、コンクリート
21をB方向に吐出して、プレスリング片7a、7bの
移動によって生じる空間26(第9図参照)を充填する
In this state, concrete 21 is cast and filled into the concrete casting space 23. When the concrete 21 is filled, the press ring jacks 9a and 9b are driven to gradually retreat the press ring pieces 7a and 7b in the A direction, and the concrete 21 is discharged from the concrete discharge pipe 10 in the B direction. Then, the space 26 (see FIG. 9) created by the movement of the press ring pieces 7a, 7b is filled.

こうして、プレスリング片7a、7bが入方向に移動し
て、鍔面7c、7dがゲージリング11何の妻止め22
Dの設置位置と略一致したところで、ラム6a、6bを
、それぞれ独立してB方向に所定距離だけ突出駆動させ
る。すると、シールド掘削機1は、外殻2及びゲージリ
ング片11a、llb等を介して、型枠13Dから反力
を取る形で、その掘進方向を入方向から徐々に左方(第
14図においては図中左肩め下方)に変えつつ、カッタ
3により掘削動作を開始する。すると、外殻2も入方向
から徐々に左方に向きを変えて、外殻2が移動した後に
、打設充填されたコンクリート21と地山19との間に
テールボイド27が形成さ九る(第12図参照)。従っ
て、外殻2が移動するにつれて、プレスリングジヤツキ
9a、9bを駆動して、プレスリング片7a、7bを。
In this way, the press ring pieces 7a and 7b move in the inward direction, and the collar surfaces 7c and 7d are aligned with the end stop 22 of the gauge ring 11.
When the rams 6a and 6b are approximately aligned with the installation position D, the rams 6a and 6b are each independently driven to protrude a predetermined distance in the B direction. Then, the shield excavator 1 gradually changes its excavation direction to the left from the entry direction (in FIG. (lower left shoulder in the figure), and the cutter 3 starts the excavation operation. Then, the outer shell 2 also gradually changes direction to the left from the input direction, and after the outer shell 2 moves, a tail void 27 is formed between the poured and filled concrete 21 and the ground 19. (See Figure 12). Therefore, as the outer shell 2 moves, the press ring jacks 9a, 9b are driven to release the press ring pieces 7a, 7b.

それぞれ外殻2の移動に同期した形で、外殻2後方に徐
々に移動させる。すると、コンクリート打設空間23及
び空間26の未硬化のコンクリート21は、これ等プレ
スリング片7a、7bに押圧されて、テールボイド27
を充填する形で流動する。
The outer shell 2 is gradually moved rearward in synchronization with the movement of the outer shell 2. Then, the unhardened concrete 21 in the concrete placement space 23 and the space 26 is pressed by these press ring pieces 7a and 7b, and the tail void 27
It flows in the form of filling.

こうして、外殻2の移動につれて、プレスリング片7a
、7bを外殻2の後方に移動させてゆくと、該テールボ
イド27は効果的に充填されてゆく6なお、外殻2がA
方向から左方、即ち第14図中左肩め下方に徐々に向き
を変えて移動するので、コンクリート21の充填量をテ
ールボイド27の図中上部にゆくにしたがって増やす必
要があるが、プレスリング片7aを、プレスリング片7
bよりも所定距離だけ長くB方向に突出させて充填量を
増加させることにより、テールボイド27を満遍無く充
填することが出来る。
In this way, as the outer shell 2 moves, the press ring piece 7a
, 7b to the rear of the outer shell 2, the tail void 27 is effectively filled6.
Since the press ring piece 7a gradually changes direction and moves from the direction to the left, that is, downward to the left shoulder in FIG. , press ring piece 7
The tail void 27 can be evenly filled by increasing the filling amount by protruding in the direction B by a predetermined distance longer than b.

なお、上述した実施例においては、ゲージリング11と
プレスリング7とを共に2分割した場合について述べた
が、ゲージリング11のみを2分割し、プレスリング7
は2分割せずに単体でシール1(掘削機1を構成しても
よい。
In the above-mentioned embodiment, the case where both the gauge ring 11 and the press ring 7 were divided into two parts was described, but only the gauge ring 11 was divided into two parts and the press ring 7 was divided into two parts.
The seal 1 (excavator 1 may be constructed by itself) without being divided into two parts.

更に、上述した実施例においては、ゲージリング11等
を、2分割した場合について述べたが、カーブ施工の状
況に応じて、それ以上に分割してもよいことは勿論であ
る。
Further, in the above-described embodiment, the case where the gauge ring 11 etc. was divided into two parts was described, but it goes without saying that it may be divided into more parts depending on the situation of curve construction.

(g)0発明の効果 以上、説明したように本発明は、外殻2を有し、該外殻
2の内側にプレスリング7を、前記外殻2の掘進方向に
移動駆動自在に設け、該プレスリング7の内側にゲージ
リング11′等の型枠支持部材を、前記外殻2に対して
移動駆動自在に設け。
(g) 0 Effects of the Invention As explained above, the present invention has an outer shell 2, and a press ring 7 is provided inside the outer shell 2 so as to be freely movable and driven in the excavation direction of the outer shell 2, A mold support member such as a gauge ring 11' is provided inside the press ring 7 so as to be movable relative to the outer shell 2.

更に、小なくとも前記型枠支持部材を複数個に分〜割す
ると共に、該分割部分(例えば、ゲージリング片11a
、11b)が独立して前記外殻2の掘なくとも型枠支持
部材を1分割部分毎に独立して移動させることが出来る
。このため、カーブ施工する際にもシールド掘削機1を
、該分割部分を介して、斜めに設置された型枠13がら
安定的に反力を取る形で掘進させることが可能となり、
該力、−ブ施工作業を円滑に行なうことが出来る。更に
、プレスリング7を複数個に分割した場合には、テール
ボイド27の部位に応じてコンクリート21等の充填部
材の充填量を加減することが出来るので、カーブ施工時
においてもテールボイド27を有効に充填することが出
来る。
Furthermore, at least the formwork support member is divided into a plurality of parts, and the divided parts (for example, the gauge ring pieces 11a
, 11b) can independently move the formwork support member for each divided portion without digging the outer shell 2 independently. Therefore, even when performing curve construction, it is possible to allow the shield excavator 1 to excavate through the divided portion while stably absorbing the reaction force through the diagonally installed formwork 13.
This force allows construction work to be carried out smoothly. Furthermore, when the press ring 7 is divided into multiple pieces, the amount of filling material such as concrete 21 can be adjusted depending on the location of the tail void 27, so the tail void 27 can be effectively filled even when constructing a curve. You can.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明によるシールド掘削機の一実施例を示す
平断面図、 第2図は第1図の■−■線による断面図、第3図は第1
図の■−■線による断面図、第4図はシールド掘削機の
ジヤツキ部分の拡大図、 1□ t−1”!1JLJ□  +  FM −−、−
−+^、   、  −−−第6図乃至@13図は本発
明によるシールド掘削機を用いて、直線的に覆工を打ち
継ぎ形成する様子を示す工程図、 第14図は本発明によるシールド掘削機を用いてカーブ
施工する様子を示す平断面図である。 1・・・・・・シールド掘削機 2・・・・・−外殻 7・・・・・・プレスリング 11・・・・・・型枠支持部材(ゲージリング)1.1
a、41b・・・・・・分割部分(ゲージリング片) 出原人    三井建設株式会社 代理人  弁理士  相1)伸二 (ほか2名) 第6図 第8図 第10図
FIG. 1 is a plan sectional view showing one embodiment of a shield excavator according to the present invention, FIG. 2 is a sectional view taken along the line ■-■ in FIG. 1, and FIG.
A cross-sectional view taken along the line ■-■ in the figure, Figure 4 is an enlarged view of the jacking part of the shield excavator, 1□ t-1"!1JLJ□ + FM - -, -
-+^, , --- Figures 6 to 13 are process diagrams showing how the shield excavator according to the present invention is used to form the lining in a straight line, and Figure 14 is the shield according to the present invention. FIG. 2 is a plan cross-sectional view showing how a curve is constructed using an excavator. 1...Shield excavator 2...-Outer shell 7...Press ring 11...Form support member (gauge ring) 1.1
a, 41b...Split part (gauge ring piece) Original person Mitsui Construction Co., Ltd. agent Patent attorney Phase 1) Shinji (and 2 others) Figure 6 Figure 8 Figure 10

Claims (1)

【特許請求の範囲】 外殻を有し、 該外殻の内側にプレスリングを、前記外殼 の掘進方向に移動駆動自在に設け、 該プレスリングの内側に型枠支持部材を、 前記外殻に対して移動駆動自在に設け、 更に、少なくとも前記型枠支持部材を複数 個に分割すると共に、該分割部分が独立して前記外殻の
掘進方向に移動し得るようにして構成したシールド掘削
機。
[Scope of Claims] It has an outer shell, a press ring is provided inside the outer shell so as to be movable and driven in the excavation direction of the outer shell, a form support member is provided inside the press ring, and a formwork support member is provided on the inner side of the press ring, and a form support member is provided on the inner side of the press ring. A shield excavator is provided so as to be freely movable and driveable relative to the outer shell, and the shield excavator is further configured such that at least the form support member is divided into a plurality of parts, and the divided parts can be independently moved in a direction in which the outer shell is excavated.
JP62013432A 1987-01-23 1987-01-23 Shield excavator Granted JPS63181899A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62013432A JPS63181899A (en) 1987-01-23 1987-01-23 Shield excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62013432A JPS63181899A (en) 1987-01-23 1987-01-23 Shield excavator

Publications (2)

Publication Number Publication Date
JPS63181899A true JPS63181899A (en) 1988-07-27
JPH0578637B2 JPH0578637B2 (en) 1993-10-29

Family

ID=11832972

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62013432A Granted JPS63181899A (en) 1987-01-23 1987-01-23 Shield excavator

Country Status (1)

Country Link
JP (1) JPS63181899A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60126494A (en) * 1983-12-13 1985-07-05 株式会社間組 Control apparatus and method of shield drilling machine

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60126494A (en) * 1983-12-13 1985-07-05 株式会社間組 Control apparatus and method of shield drilling machine

Also Published As

Publication number Publication date
JPH0578637B2 (en) 1993-10-29

Similar Documents

Publication Publication Date Title
JPS62194399A (en) Construction method for coating tunnel
JPS63181899A (en) Shield excavator
JPS62215799A (en) Shield excavator
JPS62121299A (en) Method for covering casting of tunnel and shield excavator used therein
JPH02132295A (en) Constructing method for tunnel lining work
JPH02101296A (en) Shield drilling machine and construction method using shield drilling machine
JPS6145037B2 (en)
JP2634883B2 (en) Construction method of tunnel lining
JP3153852B2 (en) Tunnel lining equipment
JPS62206198A (en) Method of constructing tunnel lining
JPS63161297A (en) Shield excavator
JPS63103199A (en) Shield excavator
JPH0361000B2 (en)
JPS60141997A (en) Assembling of iron wire cage for reinforcing tunnel wall lining material
JP2951895B2 (en) Cast-in-place lining type shield method
JPS6221991A (en) Method of excavating tunnel and shielding excavator used forsaid method
JP2676691B2 (en) Construction method of shield and lining using shield
JPH01312199A (en) Construction of tunnel linining work
JPH0447280Y2 (en)
JPH055039B2 (en)
JPH0364039B2 (en)
JPH01299998A (en) Shielded propulsion and shielding construction method in lining on-site lining
JPS63156198A (en) Shielding excavator
JPH0377000A (en) Reinforcing member for tunnel lining and constructing method of tunnel lining by using said reinforcing member
JPH04353195A (en) Tunnel lining device and lining method