JPS62121299A - Method for covering casting of tunnel and shield excavator used therein - Google Patents

Method for covering casting of tunnel and shield excavator used therein

Info

Publication number
JPS62121299A
JPS62121299A JP60261892A JP26189285A JPS62121299A JP S62121299 A JPS62121299 A JP S62121299A JP 60261892 A JP60261892 A JP 60261892A JP 26189285 A JP26189285 A JP 26189285A JP S62121299 A JPS62121299 A JP S62121299A
Authority
JP
Japan
Prior art keywords
lining
positioning
shield excavator
formwork
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP60261892A
Other languages
Japanese (ja)
Inventor
渉 川嶋
栄 中井
和彦 松崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP60261892A priority Critical patent/JPS62121299A/en
Publication of JPS62121299A publication Critical patent/JPS62121299A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明はシールド掘削機によりl屈削されたトンネルの
覆工を現場打ちコンクリートで打設形成する際に用いら
れる、トンネル覆工の打設方法及びそれに使用するシー
ルド掘削機に関する。
DETAILED DESCRIPTION OF THE INVENTION (a) Industrial Field of Application The present invention relates to a tunnel lining, which is used when forming a tunnel lining with cast-in-place concrete, which has been cut by a shield excavator. This invention relates to a pouring method and a shield excavator used therefor.

(b)、従来の技術 最近、シールド掘削機により掘削されたトンネルの覆工
を現場打ちコンクリートで打設形成して、繁雑で時間の
掛かるセグメントの組立作業を行わないようにする提案
がなされている。
(b), Prior Art Recently, a proposal has been made to form the lining of a tunnel excavated by a shield excavator using cast-in-place concrete to avoid the complicated and time-consuming assembly work of segments. There is.

(C)0発明が解決しようとする問題点しかし、覆工を
現場打ちコンクリートで構築する場合、構築すべき覆工
は、コンクリート内の補強材の位置や、覆工の厚さ等の
点において、設計寸法通りに構築されなければならない
。ところが、そうした覆工の打設手順等は、いまだ確立
されておらず、従って現場打ちコンクリートにょる覆工
の打設形成作業を正確に施工することの出来ろトンネル
覆工の打設方法およびそれに使用するシールド掘削機の
開発が望まれていた。
(C) 0 Problems to be Solved by the Invention However, when constructing a lining with cast-in-place concrete, the lining to be constructed has a number of issues such as the position of reinforcing materials in the concrete and the thickness of the lining. , shall be constructed to design dimensions. However, the procedure for placing such a tunnel lining has not yet been established, and therefore it is difficult to accurately perform the pouring and forming work of the tunnel lining using cast-in-place concrete. There was a desire to develop a shield excavator for use.

本発明は上記した事情に鑑み、補強材の設置位置や打設
される覆工の厚さ等を正確に施工することの出来ろトン
ネル覆工の打設方法及びそれに使用するシールド掘削機
を提供することを目的とするものである。
In view of the above-mentioned circumstances, the present invention provides a method for constructing a tunnel lining that can accurately determine the installation position of reinforcing materials, the thickness of the lining, etc., and a shield excavator used therein. The purpose is to

(d)0問題点を解決するための手段 即ち、本発明の内、トンネル覆工の打設方法は、推進ジ
ヤツキ(6)のラム(6a)に補強材(15)の位置決
め保持手段(6b)を設け、覆工(11)の打設構築時
に、補強材を、前記位置決め保持手段と既に構築済みの
覆工(11)との間に設置し、その後型枠(17)を推
進ジヤツキ(6,7)のラム(6a、7a)により型枠
位置決め手段(16)を介して保持し、それにより形成
されるコンクリート打設空間(19)中にコンクリート
を打設して覆工(11)を構築するようにして構成され
る。
(d) Means for solving the zero problem, that is, the tunnel lining casting method of the present invention is a means for positioning and holding the reinforcing material (15) on the ram (6a) of the propulsion jack (6). ), and when the lining (11) is cast and constructed, a reinforcing material is installed between the positioning and holding means and the already constructed lining (11), and then the formwork (17) is moved by a propelling jack ( The rams (6a, 7a) of 6, 7) hold the formwork through the formwork positioning means (16), and concrete is poured into the concrete placement space (19) formed thereby to form the lining (11). It is configured by constructing.

また、本発明の内、シールド掘削機の発明は、推進ジヤ
ツキ(6,7)のラム(6a、7a)に補強材(15)
の位置決め保持手段(6b)を設けて構成され、更には
型枠位置決め手段(16)を前記推進ジヤツキ(6,7
)のラム(6a、7a)に対して着脱自在に設けて構成
される。
Further, in the invention of the shield excavator, reinforcing material (15) is attached to the rams (6a, 7a) of the propulsion jack (6, 7).
positioning and holding means (6b), and furthermore, the formwork positioning means (16) is connected to the propelling jacks (6, 7).
) is configured to be detachably attached to the rams (6a, 7a).

なお、括弧内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下のr (el
 、作用」の欄についても同様である。
Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions on the drawings. The following r (el
The same applies to the column ``, action''.

(e)0作用 上記した構成により、本発明は、補強材(15)は位置
決め保持手段(6b)により、型枠(17)は型枠位置
決め手段(16)により適正な位置に保持され、設計寸
法通りの覆工(11)の構築が出来るように作用する。
(e) 0 effect With the above-described configuration, the present invention allows the reinforcing material (15) to be held at an appropriate position by the positioning and holding means (6b), the formwork (17) to be held at an appropriate position by the formwork positioning means (16), and the design It acts so that the lining (11) can be constructed according to the dimensions.

(f)、実施例 以下、本発明の実施例を図面に基づき説明する。(f), Example Embodiments of the present invention will be described below based on the drawings.

第1図乃至第5図は本発明によるトンネル覆工の打設方
法の一実施例を示す工程図、第6図は本発明によるシー
ルド掘削機の一実施例を示す断面図、 第7図(よトンネルの断面図である。
1 to 5 are process diagrams showing an embodiment of the tunnel lining construction method according to the present invention, FIG. 6 is a sectional view showing an embodiment of the shield excavator according to the present invention, and FIG. 7 ( It is a sectional view of the tunnel.

シールド掘削機1は、第6図に示すように、全体が円筒
形状に形成された外殻2を有しており、外殻2の図中左
方にはカッタ3が駆動モータ5により回転駆動自在に設
けられている。外殻2の内側には、複数の推進ジヤツキ
6.7が、外殻2の周囲に沿った形で同心円状に2重に
設けられており、各推進ジヤツキ6.7にはラム6a、
7aが、矢印A、B方向に突出後退自在に設けられてい
る。
As shown in FIG. 6, the shield excavator 1 has an outer shell 2 formed into a cylindrical shape as a whole, and a cutter 3 is rotatably driven by a drive motor 5 on the left side of the outer shell 2 in the figure. It is set freely. Inside the outer shell 2, a plurality of propulsion jacks 6.7 are provided in a concentric double layer along the circumference of the outer shell 2, and each propulsion jack 6.7 has a ram 6a,
7a is provided so as to be able to protrude and retreat in the directions of arrows A and B.

推進ジヤツキ6.7の内、外側、即ち外殻2側の推進ジ
ヤツキ6のラム6aの先端には、第1図に示すように、
補強鉄板の位置決め溝6bが穿設形成されており、更に
外殻2の、第6図右端、即ちシールド掘削機1の後端部
には、テールボイド注入装置9が設けられている。
At the tip of the ram 6a of the propulsion jack 6 on the inside and outside of the propulsion jack 6.7, that is, on the outer shell 2 side, as shown in FIG.
A positioning groove 6b is formed in the reinforcing iron plate, and a tail void injection device 9 is provided at the right end of the outer shell 2 in FIG. 6, that is, at the rear end of the shield excavator 1.

シールド掘削機1は、以上のような構成を有するので、
シールド掘削機]、によりトンネル10を開削する場合
には、第6図に示すように、駆動モータ5によりカッタ
3を回転駆動させろと共に、推進ジヤツキ6.7のラム
6a、7aを矢印B方向に突出させて、既に構築済みの
覆工11及び型枠17を足場にする形で、外殻2をA方
向に押圧する。入方向に外殻2が押圧されると、カッタ
3は切羽13方向に所定の罰則圧力で押され、これによ
り切羽部分の土砂は掘削されろ。切羽13部分の土砂が
掘削されると、外殻2は切羽13が掘削された分だけ推
進ジヤツキ6.7の押圧力でA方向に推進し、トンネル
10が形成される。推進ジヤツキ6.7は、外殻2が所
定距離LllけA方向に進む間、外殻2の移動速度に合
わせた形で、ラム6a、7aをB方向に突出駆動させ、
カッタ3に常に所定の1屈削圧力が作用するようにして
いる。
Since the shield excavator 1 has the above configuration,
When excavating the tunnel 10 with a shield excavator], as shown in FIG. The outer shell 2 is pushed in the direction A by protruding and using the already constructed lining 11 and formwork 17 as scaffolding. When the outer shell 2 is pressed in the entry direction, the cutter 3 is pushed in the direction of the face 13 with a predetermined penalty pressure, thereby excavating the earth and sand at the face. When the earth and sand in the face 13 portion is excavated, the outer shell 2 is propelled in the direction A by the pressing force of the propulsion jack 6.7 by the amount that the face 13 is excavated, and the tunnel 10 is formed. The propulsion jack 6.7 drives the rams 6a and 7a to protrude in the B direction in accordance with the moving speed of the outer shell 2 while the outer shell 2 moves a predetermined distance Lll in the A direction.
A predetermined one-bending cutting pressure is always applied to the cutter 3.

こうして、所定距fiL1だけトンネル10がA方向に
掘削されたところで、第1図に示すように、ラム6a、
7aをA方向に後退させ、補強鉄板15を、既に構築済
みの覆工11内に設置された補強鉄板15とラム6aの
位置決め溝6bとの間に、妻止め20と共に設置する。
In this way, when the tunnel 10 has been excavated by a predetermined distance fiL1 in the direction A, as shown in FIG.
7a is retreated in the direction A, and the reinforcing iron plate 15 is installed together with the end stop 20 between the reinforcing iron plate 15 installed in the already constructed lining 11 and the positioning groove 6b of the ram 6a.

この補強鉄板15は、幅がL2の板状に形成された平板
部15aと該平板部15aに対して植設された多数のス
タッド15bを有しており、平板部15aは、第7図に
示すように、打設形成すべき覆工11の形状に適合させ
た形で、円弧状に形成されている。
This reinforcing iron plate 15 has a flat plate part 15a formed in a plate shape with a width L2 and a large number of studs 15b planted on the flat plate part 15a. As shown, it is formed into an arcuate shape that matches the shape of the lining 11 to be cast and formed.

また、ラム6aには、補強鉄板15を位置決め支持する
ための位置決め溝6bが形成されているので、補強鉄板
15を該位置決め溝6bに、第1図に示すように、その
図中左端部15cを嵌入係合させ、更に右端部15dを
構築済みのコンクリ−ト中に設置固定された状態の補強
鉄板15の先端とボルト等により接続することにより、
補強鉄板15は、第6図及び第7図に示すように、所定
の位置に確実に設置支持されろ。なお、補強鉄板15の
平板部15aには、コンクリートの流通を確保するため
に多数の穴(図示せず)が貫通穿設されている。
Further, since a positioning groove 6b for positioning and supporting the reinforcing iron plate 15 is formed in the ram 6a, the reinforcing iron plate 15 is placed in the positioning groove 6b as shown in FIG. By fitting and engaging the right end portion 15d, and further connecting the right end portion 15d to the tip of the reinforcing iron plate 15 installed and fixed in the constructed concrete with bolts or the like,
The reinforcing iron plate 15 must be securely installed and supported at a predetermined position, as shown in FIGS. 6 and 7. Note that a large number of holes (not shown) are drilled through the flat plate portion 15a of the reinforcing iron plate 15 in order to ensure the flow of concrete.

こうして、複数の補強鉄板15が、第7図に示すように
、設置されたところで、第2図に示すように、推進ジヤ
ツキ6のラム6aの先端下部に、型枠位置決め保持用の
ゲージリング16をボルト等を用いて装着する。このゲ
ージリング16は、打設すべき覆工11の形状に沿った
形で円環状に形成されており、その第2図右側面には、
位置決め溝16aが同様に円環状に形成されている。従
って、該位置決め溝6bに沿って、組立型枠17を設置
すると、外殻2と組立型枠17の間に円環状のコンクリ
ート打設空間19が形成される。組立型枠17は、既に
述べたように、位置決め溝16aに沿って配置位置決め
されるので、コンクリート打設空間19は所定の厚さT
(第6図参照)を外殻2との間に全周に亙り均一に保持
した形で形成される。
After the plurality of reinforcing iron plates 15 have been installed as shown in FIG. 7, a gauge ring 16 for positioning and holding the formwork is placed at the lower end of the ram 6a of the propulsion jack 6, as shown in FIG. Attach using bolts, etc. This gauge ring 16 is formed in an annular shape following the shape of the lining 11 to be cast, and on the right side in FIG.
The positioning groove 16a is similarly formed in an annular shape. Therefore, when the assembly form 17 is installed along the positioning groove 6b, an annular concrete placement space 19 is formed between the outer shell 2 and the assembly form 17. As already mentioned, the assembly formwork 17 is arranged and positioned along the positioning groove 16a, so that the concrete placement space 19 has a predetermined thickness T.
(See FIG. 6) is formed in such a way that it is held uniformly over the entire circumference between it and the outer shell 2.

この状態で、ゲージリング16をラム7aでB方向に押
圧し、第3図に示すように、妻止め20側の所定の位置
にコンクリート打設ホース21を接続し、コンクリート
打設空間19中にコンクリートを打設注入する。この際
、組立型枠17のコンクリート打設空間19に対応する
適宜な位置にパイブレーク22を装着して、コンクリー
ト打設空間19中に注入されるコンクリートに対して振
動を与え、コンクリートが隅々にまで充填されるように
する。
In this state, the gauge ring 16 is pressed in the direction B by the ram 7a, and as shown in FIG. Place and pour concrete. At this time, a pie break 22 is attached to an appropriate position corresponding to the concrete pouring space 19 of the assembly form 17, and vibration is applied to the concrete poured into the concrete pouring space 19, so that the concrete is poured in every corner. Make sure it is filled to the top.

こうして、コンクリート打設空間19中にコンクリート
が打設され、当該打設されたコンクリートが凝固したと
ころで、シールド掘削@1はカッタ3を回転させて、再
度、矢印A方向への掘削動作を再開する。この際、既に
に述べたように、推進ジヤツキ6.7のラム6a、7a
を第4図矢印B方向に突出させて、外殻2をA方向に移
動させろが、外殻2が移動した後には、地山23と打設
形成された覆工11との間に、テールボイドが生じろの
で、テールボイド注入装置9から充填剤をテールボイド
に注入して地山23の崩壊を防止する。こうして、テー
ルボイドを充填しながら、所定距fiL1だけA方向に
18進したところで、第5図に示すように、ラム6a、
7aをA方向に後退させて、前回構築された覆工11に
連続させる形で、第1図に示すように、新たな覆工11
の構築作業に入る。
In this way, concrete is placed in the concrete placement space 19, and when the placed concrete has solidified, the shield excavation@1 rotates the cutter 3 and restarts the excavation operation in the direction of arrow A. . At this time, as already mentioned, the rams 6a and 7a of the propulsion jack 6.7
protrude in the direction of arrow B in FIG. Therefore, filler is injected into the tail void from the tail void injection device 9 to prevent the collapse of the ground 23. In this way, while filling the tail void, the ram 6a,
7a in the direction A and continue with the previously constructed lining 11, as shown in Fig. 1, a new lining 11 is constructed.
construction work begins.

(g)0発明の効果 以上、説明したように、本発明によれば、推進ジヤツキ
6のラム6aに位置決め溝6b等の、補強鉄板15等の
補強材の位置決め保持手段を設け、覆工11の打設構築
時に、補強材を前記位置決め保持手段と既に構築済みの
覆工11との間に設置し、その後組立型枠17等の型枠
を推進ジヤツキ6.7のラム6a、7aによりゲージリ
ング16等の型枠位置決め手段を介して保持し、それに
より形成されるコンクリート打設空間19中にコンクリ
ートを打設して覆工11を構築するように構成したので
、補強材は位置決め保持手段により、更に型枠は型枠位
置決め手段により設計寸法通りの適正な位置に設置する
ことが可能となり、現場打ちコンクリートによる覆工1
1の打設形成作業を正確に施工することが出来る。
(g) 0 Effects of the Invention As explained above, according to the present invention, the ram 6a of the propulsion jack 6 is provided with positioning and holding means for reinforcing materials such as the reinforcing iron plate 15, such as the positioning groove 6b, and the lining 11 At the time of pouring and construction, a reinforcing material is installed between the positioning and holding means and the already constructed lining 11, and then the formwork such as the assembly formwork 17 is gauged by the rams 6a and 7a of the propelling jack 6.7. Since the structure is configured such that the lining 11 is constructed by holding the formwork through a formwork positioning means such as a ring 16 and pouring concrete into the concrete placement space 19 formed thereby, the reinforcing material is held by means of positioning and holding means such as the ring 16. Furthermore, the formwork can be installed at the appropriate position according to the design dimensions using the formwork positioning means, and the lining with cast-in-place concrete 1
It is possible to accurately carry out the pouring and forming work in step 1.

また、補強材として平板部15を有する補強鉄板15を
用いると、補強材の設置を板状の平板部15を介して行
うことが出来るので、通常の鉄筋等を補強材として用い
た場合に比して、その作業性が良く、また現場における
鉄筋の曲げ加工等の作業も無くすことが出来るので迅速
に打設作業を行うことが可能となる。
Furthermore, if the reinforcing iron plate 15 having the flat plate part 15 is used as a reinforcing material, the reinforcing material can be installed through the plate-shaped flat part 15, compared to the case where ordinary reinforcing bars or the like are used as the reinforcing material. Therefore, the workability is good, and since work such as bending of reinforcing bars on site can be eliminated, it is possible to carry out the casting work quickly.

また、シールド掘削機として、推進ジヤツキのラムに位
置決め溝6b等の補強材の位置決め保持手段を設けて構
成すると、補強材の設置を前記位置決め手段により容易
に行うことが出来る。
Furthermore, if the shield excavator is constructed by providing a means for positioning and holding the reinforcing material such as a positioning groove 6b on the ram of the propulsion jack, the reinforcing material can be easily installed by the positioning means.

更に、型枠位置決め手段を前記推進ジャ・ツキのラムに
対して着脱自在に設けて構成すると、型枠17の設置時
に前記型枠位置決め手段を装着することにより、型枠1
7を正確な位置に設置することが出来る。
Furthermore, if the formwork positioning means is provided to be detachably attached to the ram of the propulsion jack, by attaching the formwork positioning means when installing the formwork 17, the formwork 1
7 can be placed in the correct position.

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第5図は本発明によるトンネル覆工の打設方
法の一実施例を示す工程図、第6図は本発明によるシー
ルド掘削機の一実施例を示す断面図、 第7図はトンネルの断面図である。 1・・・シールド掘削機 6.7・・・・・・推進ジヤツキ 6a、7a・・・・・ラム 6b・・・・・・位置決め保持手段(位置決め溝)10
・・・・・トンネル 11・・・・・覆工 15・・・・・補強鉄板 15a・・・・平板部 16・・・・型枠位置決め手段(ゲージリング)19・
・・・・コンクリート打設空間 出願人    三井建設株式会社 代理人  弁理士  相1)伸二 (ほか1名) −1,j”
1 to 5 are process diagrams showing an embodiment of the tunnel lining construction method according to the present invention, FIG. 6 is a sectional view showing an embodiment of the shield excavator according to the present invention, and FIG. It is a sectional view of a tunnel. 1... Shield excavator 6.7... Propulsion jacks 6a, 7a... Ram 6b... Positioning and holding means (positioning groove) 10
...Tunnel 11 ... Lining 15 ... Reinforcement iron plate 15a ... Flat plate part 16 ... Formwork positioning means (gauge ring) 19 ...
...Concrete pouring space Applicant Mitsui Construction Co., Ltd. Agent Patent attorney Phase 1) Shinji (and 1 other person) -1,j”

Claims (3)

【特許請求の範囲】[Claims] (1)、推進ジャッキが設けられたシールド掘削機によ
り掘削されたトンネルに、現場打ちコンクリートにより
覆工を構築する際において、 推進ジャッキのラムに補強材の位置決め保 持手段を設け、 覆工の打設構築時に、補強材を、前記位置 決め保持手段と既に構築済みの覆工との間に設置し、 その後型枠を前記推進ジャッキのラムによ り型枠位置決め手段を介して保持し、 それにより形成されるコンクリート打設空 間中にコンクリートを打設して覆工を構築するように構
成したトンネル覆工の打設方法。
(1) When constructing a lining with cast-in-place concrete for a tunnel excavated by a shield excavator equipped with a propulsion jack, the ram of the propulsion jack is provided with means for positioning and holding the reinforcing material, and the lining is During construction, reinforcing material is installed between the positioning and holding means and the already constructed lining, and then the formwork is held by the ram of the propulsion jack via the formwork positioning means, whereby the formed A method for placing a tunnel lining in which the lining is constructed by placing concrete in a concrete placement space.
(2)、推進ジャッキが設けられたシールド掘削機にお
いて、 前記推進ジャッキのラムに補強材の位置決 め保持手段を設けて構成したシールド掘削機。
(2) A shield excavator equipped with a propulsion jack, wherein the ram of the propulsion jack is provided with means for positioning and holding a reinforcing material.
(3)、推進ジャッキが設けられたシールド掘削機にお
いて、 型枠位置決め手段を前記推進ジャッキのラ ムに対して着脱自在に設けて構成したシールド掘削機。
(3) A shield excavator equipped with a propulsion jack, wherein a formwork positioning means is detachably attached to the ram of the propulsion jack.
JP60261892A 1985-11-21 1985-11-21 Method for covering casting of tunnel and shield excavator used therein Pending JPS62121299A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60261892A JPS62121299A (en) 1985-11-21 1985-11-21 Method for covering casting of tunnel and shield excavator used therein

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60261892A JPS62121299A (en) 1985-11-21 1985-11-21 Method for covering casting of tunnel and shield excavator used therein

Publications (1)

Publication Number Publication Date
JPS62121299A true JPS62121299A (en) 1987-06-02

Family

ID=17368214

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60261892A Pending JPS62121299A (en) 1985-11-21 1985-11-21 Method for covering casting of tunnel and shield excavator used therein

Country Status (1)

Country Link
JP (1) JPS62121299A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6378998A (en) * 1986-09-24 1988-04-09 佐藤工業株式会社 Shield excavator
JPS641895A (en) * 1987-06-23 1989-01-06 Daiho Constr Co Ltd Shield tunneling method and shield machine
JPS6466399A (en) * 1987-09-04 1989-03-13 Mitsui Constr Lining constructing device
JPH01125498A (en) * 1987-11-09 1989-05-17 Daiho Constr Co Ltd Method of constructing concrete lining body into ground and segment used for said construction
JPH01165900A (en) * 1987-12-22 1989-06-29 Daiho Constr Co Ltd Method of constructing concrete lining body in ground and segment used for said construction

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6378998A (en) * 1986-09-24 1988-04-09 佐藤工業株式会社 Shield excavator
JPH0458876B2 (en) * 1986-09-24 1992-09-18 Sato Kogyo
JPS641895A (en) * 1987-06-23 1989-01-06 Daiho Constr Co Ltd Shield tunneling method and shield machine
JPS6466399A (en) * 1987-09-04 1989-03-13 Mitsui Constr Lining constructing device
JPH0541799B2 (en) * 1987-09-04 1993-06-24 Mitsui Constr
JPH01125498A (en) * 1987-11-09 1989-05-17 Daiho Constr Co Ltd Method of constructing concrete lining body into ground and segment used for said construction
JPH01165900A (en) * 1987-12-22 1989-06-29 Daiho Constr Co Ltd Method of constructing concrete lining body in ground and segment used for said construction

Similar Documents

Publication Publication Date Title
JPS62121299A (en) Method for covering casting of tunnel and shield excavator used therein
JPS62194399A (en) Construction method for coating tunnel
JPS62215799A (en) Shield excavator
JP3584416B2 (en) Tunnel and its construction method
JPH09119131A (en) Construction method of column row type underground continuous wall and guide plate structure of multishaft auger machine used therefor
JPH02101296A (en) Shield drilling machine and construction method using shield drilling machine
JPH02132295A (en) Constructing method for tunnel lining work
JPH0772476B2 (en) How to build a tunnel lining
JPH0364039B2 (en)
JPH0637836B2 (en) Tunnel lining method
JPS63189598A (en) Shield excavator
JPS63300200A (en) Method of cast-in-place lining shielding construction
JPS63181895A (en) Shield excavator
JP2676691B2 (en) Construction method of shield and lining using shield
JPS6221996A (en) Shielding excavator
JPS63103199A (en) Shield excavator
JPS6354875B2 (en)
JPS63156199A (en) Shielding excavator
JPS62206198A (en) Method of constructing tunnel lining
JP2634883B2 (en) Construction method of tunnel lining
JPS61134441A (en) Method of reinforcing foundation ground of building
JPS63161298A (en) Shield excavator
JPS63181899A (en) Shield excavator
JPH0332658B2 (en)
JPH05179804A (en) Concrete placing joint method in reverse depositing