JPS63189598A - Shield excavator - Google Patents

Shield excavator

Info

Publication number
JPS63189598A
JPS63189598A JP62019461A JP1946187A JPS63189598A JP S63189598 A JPS63189598 A JP S63189598A JP 62019461 A JP62019461 A JP 62019461A JP 1946187 A JP1946187 A JP 1946187A JP S63189598 A JPS63189598 A JP S63189598A
Authority
JP
Japan
Prior art keywords
outer shell
formwork
press ring
concrete
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP62019461A
Other languages
Japanese (ja)
Inventor
石田 喜久雄
潔 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP62019461A priority Critical patent/JPS63189598A/en
Publication of JPS63189598A publication Critical patent/JPS63189598A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明はトンネルの覆工を、現場打ちコンクリートによ
り構築する際に用いるに好適なシールド掘削機に関する
DETAILED DESCRIPTION OF THE INVENTION (a) Field of Industrial Application The present invention relates to a shield excavator suitable for use in constructing tunnel linings using cast-in-place concrete.

(b)、従来の技術 最近、シールド掘削機によ抄掘削されたトンネルの覆工
を現場打ちコンクリートで#R築するための種々の提案
がなされている。
(b), Prior Art Recently, various proposals have been made for lining a tunnel excavated by a shield excavator with cast-in-place concrete.

(C)0発明が解決しようとする問題点しかし、いまt
!デテールイドを有効に充填する技術が確立されておら
ず、当該テールボイドの充填を確実に行うことの出来る
シールド掘削機の開発が急がれている。
(C)0The problem that the invention aims to solveHowever, now t
! The technology for effectively filling detail voids has not been established, and there is an urgent need to develop a shield excavator that can reliably fill the tail voids.

本発明は、ヒ記事情に鑑み、テールボイドの充填を確実
に行うことの出来るシールド開削機を提供することを目
的とするものである。
SUMMARY OF THE INVENTION In view of the above circumstances, an object of the present invention is to provide a shield drilling machine that can reliably fill tail voids.

(d)、四層点を解決するための手段 即ち、本発明は、外殻(2)を有し、該外殻(2)の内
側にプレスリング(7)を前記外殻(2)の掘進方向t
ζ移動自在に設け、更に該プレスリング(7)の内側に
型枠支持部材(11)を前記外殻(2)に対して移動自
在に設けると共に、前記型枠支持部材(11) lと型
枠の位置調整手段(11c)を設け、前記型枠支持部材
(11)に掘進用ジヤツキ(6)を設けて構成される。
(d) Means for solving the four-layer point, that is, the present invention has an outer shell (2), and a press ring (7) is installed inside the outer shell (2). Excavation direction t
A mold support member (11) is provided inside the press ring (7) so as to be movable with respect to the outer shell (2), and the mold support member (11) l and the mold are provided so as to be movable. A frame position adjustment means (11c) is provided, and an excavation jack (6) is provided on the formwork support member (11).

なお、括弧内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されろものではない。以下のr (el
 、作用」の欄についても同様である。
Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description should not be limited to the descriptions in the drawings. The following r (el
The same applies to the column ``, action''.

(e)0作用 上記した構成により、本発明は、プレスリング(7)が
、注入された充填部材(21)を加圧してテールボイド
(27)内に押し込む形で充填してゆくように作用する
(e) 0 effect With the above-described configuration, the present invention acts so that the press ring (7) pressurizes the injected filling member (21) and fills it into the tail void (27). .

(f)、実施例 以下、本発明の実施例を図面に基づき説明する。(f), Example Embodiments of the present invention will be described below based on the drawings.

第1図は本発明によるシールド1!′iI削機の一実施
例を示す正断面図、 第2図は第1図のn−II線による断面図、第3図は第
1図の■−■綿による断面図、第4図はシールド掘削機
のジヤツキ部分の拡大図、 第5図は第4図■−■綿による断面図、第6図乃至第1
3図は本発明によるシール掘削機削機を用いて覆工を構
築する際の一例を示す工程図である。
FIG. 1 shows a shield 1 according to the present invention! Figure 2 is a cross-sectional view taken along line n-II in Figure 1, Figure 3 is a cross-sectional view taken along line ■-■ in Figure 1, and Figure 4 is a cross-sectional view showing one embodiment of the iI cutting machine. An enlarged view of the jacking part of the shield excavator, Figure 5 is a cross-sectional view of Figure 4 ■-■
FIG. 3 is a process diagram showing an example of constructing a lining using the seal excavator cutting machine according to the present invention.

シールド掘削機1は、第】図に示すように、円筒状に形
成された外殻2を有しており、外殻2の前面、即ち第1
図左側面にはカッタ3が回転自在に支持されている。カ
ッタ3は、外殻2内部の空間を左右方向に遮断する形で
設けられた外殻2の隔壁2aに設けられた駆動モータ5
と接続しており、更に隔壁2aには間道用ジヤツキ6が
複数個、第1図及び第2図に示すように、外殻2に沿っ
た形で円環状に配列設置されている。旧道用ジヤツキ6
にはラム6aが矢印A、B方向に突出後退自在に設けら
れており、更に外殻2の内側には円筒状に形成されたプ
レスリング7が、外殻2内面と接する形で、矢印A、B
方向に摺動自在に設けられている。プレスリング7には
、第2図に示すように、所定の間隔でプレスリングジヤ
ツキ9が、外殻2°に沿った形で複数個配置されており
、更に、それ等プレスリングジヤツキ9の間には、第2
図及び第5図に示すように、複数のコンクリート吐出管
10が先端の吐出口10aをプレスリング7の側面7a
、即ちシールド掘削機1の後方に向けた形で設けられて
いる。コンクリート吐出管]0(ごは、111出管内清
掃用のシリンダ10bがロッド10cを矢印C,D方向
に突出後退自在にした形で設けられており、更に吐出管
10にはコンクリート供給ホース30が接続している。
The shield excavator 1 has a cylindrical outer shell 2, as shown in FIG.
A cutter 3 is rotatably supported on the left side of the figure. The cutter 3 is driven by a drive motor 5 provided on a partition wall 2a of the outer shell 2, which is provided to block the space inside the outer shell 2 in the left-right direction.
Furthermore, a plurality of road jacks 6 are arranged on the partition wall 2a in an annular arrangement along the outer shell 2, as shown in FIGS. 1 and 2. Old road jack 6
A ram 6a is provided to be able to protrude and retreat in the directions of arrows A and B, and a press ring 7 formed in a cylindrical shape is provided inside the outer shell 2 so as to be in contact with the inner surface of the outer shell 2. , B
It is provided so as to be slidable in the direction. As shown in FIG. 2, the press ring 7 has a plurality of press ring jacks 9 arranged at predetermined intervals along the outer shell 2°. In between the second
As shown in the figures and FIG.
, that is, it is provided facing toward the rear of the shield excavator 1. Concrete discharge pipe] 0 (111) A cylinder 10b for cleaning the inside of the discharge pipe is provided with a rod 10c that can protrude and retreat in the directions of arrows C and D, and furthermore, a concrete supply hose 30 is attached to the discharge pipe 10. Connected.

ところで、i尿道用ジヤツキ6のラム6aの先端には、
円環状に形成されたゲージリング11が装着されており
、ゲ・シリング11には、第4図に示すように、係合f
il 11 aがゲージリング11の全周にわたり環状
に穿設形成されている。また、ゲージリング11の、図
中下端には、鍔11bが円環状に形成されており、鍔1
1bには、第2図に示すように、型枠の位置調整手段と
しての位置決めボルト11Cが、90°ピツチで4個螺
合している。更に、ゲージリング11には、第2図及び
第3図に示すように、円環状に組立られt:型枠13が
、第1図左右方向に接続された形で設けられている。
By the way, at the tip of the ram 6a of the i-urethral jack 6,
A gauge ring 11 formed in an annular shape is attached, and the gauge ring 11 has an engagement f as shown in FIG.
il 11 a is formed in an annular shape around the entire circumference of the gauge ring 11 . Further, at the lower end of the gauge ring 11 in the figure, a collar 11b is formed in an annular shape.
As shown in FIG. 2, four positioning bolts 11C serving as formwork position adjustment means are screwed into 1b at 90° pitches. Furthermore, as shown in FIGS. 2 and 3, the gauge ring 11 is provided with a mold 13 assembled in an annular shape and connected in the left-right direction in FIG.

シールド18削機1は、以上のような構成を有するので
、トンネル15の罰則に際しては、駆動モータ5により
カッタ3を回転させると共に、掘進用ジヤツキ6のラム
6aを、第1図B方向に突出させて、隔壁2a及び外殻
2を介してカッタ3を切羽16方向、即ち矢印A方向に
押圧する。すると、その押圧力により、カッタ3と切羽
16は所定の接触圧力で接し、切羽16はカッタ3によ
り堀割され、それと同時に、外殻2はA方向に推進して
トンネル15がシールド掘削機1の後方、即ち第1図右
方に形成され−ζゆく。
Since the shield 18 excavator 1 has the above configuration, when penalizing the tunnel 15, the cutter 3 is rotated by the drive motor 5, and the ram 6a of the excavation jack 6 is projected in the direction B in FIG. Then, the cutter 3 is pressed in the direction of the face 16, that is, in the direction of arrow A, via the partition wall 2a and the outer shell 2. Then, due to the pressing force, the cutter 3 and the face 16 come into contact with each other with a predetermined contact pressure, and the face 16 is excavated by the cutter 3. At the same time, the outer shell 2 is propelled in the direction A, and the tunnel 15 is moved toward the shield excavator 1. It is formed at the rear, that is, to the right in FIG.

こうして、トンネル15が形成されてゆくにつれ、掘削
された地山19の崩壊を防止するために覆工20を構築
する必要が有るが、この覆工20の構築は、以下の手順
で行われる。即ち、シールド掘削機1が、型枠13の1
リング分の長さLlだけA方向に掘進した状態では、掘
進用ジヤツキ6のラム6aは、第6図に示すように、B
方向に突出した状態となっており、またプレスリング7
もB方向に移動した状態となっている。
In this way, as the tunnel 15 is formed, it is necessary to construct the lining 20 to prevent the excavated earth 19 from collapsing, and the construction of the lining 20 is performed in the following steps. That is, the shield excavator 1
When the excavation has been carried out in the A direction by the length Ll of the ring, the ram 6a of the excavation jack 6 is in the direction B as shown in FIG.
It is in a state of protruding in the direction, and the press ring 7
has also moved in the B direction.

この状態で、位置決めボルト11ciellめて図中下
方、即ちシールド掘削機1の中心方向に移動させ、位置
決めボルトllcと型枠13 との当接係合状態を解除
する。次に、第7図に示すように、ラム6aをA方向に
距1aL1だけ後退させる。
In this state, the positioning bolt 11ciell is moved downward in the figure, that is, toward the center of the shield excavator 1, and the abutment and engagement between the positioning bolt llc and the formwork 13 is released. Next, as shown in FIG. 7, the ram 6a is moved back in the A direction by a distance 1aL1.

すると、直前にコンクリート21の打設された部分の要
止め22A及び型枠13Aからゲージリング11が離れ
てA方向に移動し、妻止め22A及び型枠13Aとゲー
ジリング11の間に距glL1なる空間が形成される。
Then, the gauge ring 11 moves in the A direction away from the stop 22A and the formwork 13A of the part where the concrete 21 was placed just before, and a distance glL1 is created between the end stop 22A and the formwork 13A and the gauge ring 11. A space is formed.

そこで、該空間部分に、第7図想像線で示すように、鉄
板や鉄筋等からなる補強部材12を係合溝11aを介し
て要、止め226と共に設置し、更に型枠13Aに接す
る形で型枠138を組立設置し、該型枠13 、ゲージ
リング11(l!止め22 )、プレスリング7及び妻
止め224との間にコンクリート打設空間23を形成す
る。
Therefore, as shown by the imaginary line in FIG. 7, a reinforcing member 12 made of a steel plate, reinforcing bar, etc. is installed in the space along with a stopper 226 via the engagement groove 11a, and is further placed in contact with the formwork 13A. The formwork 138 is assembled and installed, and a concrete placement space 23 is formed between the formwork 13 , the gauge ring 11 (l! stop 22 ), the press ring 7 and the end stop 224 .

この際、型枠13 のゲージリング11に対する位置関
係の調整は、第2図に示すように、ゲージリング11に
装着された4本の位置決めボルト11Cを適宜回転させ
て、型枠138と当接係合させ、その状態で更にボルト
llcを回転させることにより、型枠13 を該ボルト
11Cを介して第3図矢印E、F及びG、H方向に移動
させることにより調整することが出来る。これにより、
型枠13により打設形成される覆工20の内面20aが
設計に基づく正確な位置に形成されるように調整するこ
とが出来る。
At this time, the positional relationship of the formwork 13 with respect to the gauge ring 11 is adjusted by appropriately rotating the four positioning bolts 11C attached to the gauge ring 11, as shown in FIG. By engaging and further rotating the bolt llc in this state, the formwork 13 can be adjusted by moving it in the directions of arrows E, F, G, and H in FIG. 3 via the bolt 11C. This results in
Adjustment can be made so that the inner surface 20a of the lining 20 cast and formed by the formwork 13 is formed at an accurate position based on the design.

こうして、型枠138が所定の位置に設置されたところ
で、第8図に示すように、型枠13 にコンクリート供
給管25を接続して、コンクリート供給管25によりコ
ンクリート打設空間23中にコンクリート21を打設す
る。なお、この際、コンクリート打設空間23中の空気
は、型枠13に適宜設けられたエア抜き管13aにより
外部に排出されるので、コンクリート21のコンクリー
ト打設空間23中への注入打設動作は円滑に行われる。
When the formwork 138 is installed in the predetermined position, the concrete supply pipe 25 is connected to the formwork 13 as shown in FIG. to be poured. At this time, the air in the concrete placement space 23 is discharged to the outside through the air vent pipe 13a provided appropriately in the formwork 13, so that the pouring operation of the concrete 21 into the concrete placement space 23 is performed. is carried out smoothly.

こうして、コンクリート打設空間23中にコンクリート
21が打設されたところで、第9図に示すように、今度
はプレスリングジヤツキ9を駆動してプレスリング7を
A方向に徐々に後退させる。すると、プレスリング7が
通過した後には、外殻2と注入されたコンクリート21
との間に空間26が形成される。そこで、プレスリング
7のA方向の移動と共に、第10図に示すように、コン
クリート吐出管10からコンクリート21を、該空間2
6中に注入し、該空間26をコンクリ−1・21で充填
する。プレスリング7が六方向に移動して、第11図に
示すように、側面7aがゲージリング11側の要止め2
2.の設置位置とほぼ一致したところで、第12図に示
すように、掘進用ジヤツキ6のラム6 a t−B方向
に突出駆動させると共に、カッタ3を回転させて掘削動
作を開始する。
After the concrete 21 has been placed in the concrete placement space 23 in this way, the press ring jack 9 is driven to gradually retreat the press ring 7 in the direction A, as shown in FIG. Then, after the press ring 7 passes, the outer shell 2 and the poured concrete 21
A space 26 is formed between them. Therefore, as the press ring 7 moves in the A direction, the concrete 21 is delivered from the concrete discharge pipe 10 to the space 2, as shown in FIG.
6 and fills the space 26 with concrete 1 and 21. The press ring 7 moves in six directions, and as shown in FIG.
2. As shown in FIG. 12, when the excavation jack 6 is driven to protrude in the ram 6a-t-B direction, the cutter 3 is rotated to start the excavation operation.

すると、既に述べたように、外殻2が六方向に移動を開
始し、外殻2が移動した後に、打設充填されたコンクリ
ート21と地山19との間にテールボイド27が形成さ
れる。従って、外殻2が六方向に移動するにつれてプレ
スリングジヤツキ9を駆動してプレスリング7を、外殻
2の移動に同期した形でB方向に徐々に移動させる。す
ると、先程打設されたコンクリート打設空間23及び空
間26内の未硬化のコンクリートは、プレスリング7に
押圧されて、テールボイド2フを充填する形で流動する
。こうして、第13図に示すように、外殻2のA方向の
移動につれて、プレスリング7をB方向に移動させてゆ
くと、外殻2の移動の結果発生するテールボイド27は
、効果的に充填されてゆく。なお、プレスリング7は全
体円環状に 。
Then, as described above, the outer shell 2 starts moving in six directions, and after the outer shell 2 moves, a tail void 27 is formed between the poured and filled concrete 21 and the ground 19. Therefore, as the outer shell 2 moves in six directions, the press ring jack 9 is driven to gradually move the press ring 7 in the B direction in synchronization with the movement of the outer shell 2. Then, the unhardened concrete in the concrete placement space 23 and the space 26 that was previously placed is pressed by the press ring 7 and flows to fill the tail void 2f. In this way, as shown in FIG. 13, when the press ring 7 is moved in the direction B as the outer shell 2 moves in the A direction, the tail void 27 that occurs as a result of the movement of the outer shell 2 can be effectively filled. It is being done. Note that the press ring 7 has an annular shape as a whole.

形成されているので、コンクリート21等の充填部材は
リング全周に亙り均一な圧力で押圧され、従ってテール
ボイド27の充填動作は外殻2の全周に亙り均一で良好
な状態で行われる。こうして、1リング分外殻2が推進
すると、プレスリング7は、第6図に示すように、その
側面7aが外殻2の後端部に一致した形となり、1リン
グ分の覆工20の構築が完了する。
As a result, the filling member such as the concrete 21 is pressed with uniform pressure over the entire circumference of the ring, and therefore the filling operation of the tail void 27 is performed uniformly and in good condition over the entire circumference of the outer shell 2. In this way, when the outer shell 2 is propelled by one ring, the press ring 7 has its side surface 7a aligned with the rear end of the outer shell 2, as shown in FIG. Construction is complete.

なお、この際の、コンクリート21の打ち継ぎ面29は
、第1図に示すように、プレスリング7の移動動作によ
り、階段状に形成される。
At this time, the pouring surface 29 of the concrete 21 is formed into a step-like shape by the movement of the press ring 7, as shown in FIG.

(g)0発明の効果 以上、説明したように、本発明によれば、外殻2を有し
、該外殻2の内側にプレスリング7を前記外殻2の掘進
方向に移動自在に設け、更に該プレスリング7の内側に
ゲージリング11等の型枠支持部材を前記外殻2に対し
て移動自在に設けると共に、前記型枠支持部材11に位
置決めポル1−11 c等の型枠の位置調整手段を設け
、前記型枠支持部材11に掘進用ジヤツキ6を設けて構
成したので、テールボイド27が、プレスリング7によ
り加圧された状態の充填部材により有効に充填され、信
頼性の高いトンネル覆工の構築が可能となる。また、覆
工20における充填部材の打ち継ぎ面29が、階段状に
形成されるので、止水効果が大きい。
(g) 0 Effects of the Invention As explained above, according to the present invention, the outer shell 2 is provided, and the press ring 7 is provided inside the outer shell 2 so as to be movable in the excavation direction of the outer shell 2. Furthermore, a formwork support member such as a gauge ring 11 is provided inside the press ring 7 so as to be movable with respect to the outer shell 2, and a formwork support member such as a positioning pole 1-11c is provided on the formwork support member 11. Since the position adjusting means is provided and the digging jack 6 is provided on the formwork support member 11, the tail void 27 is effectively filled with the filling member pressurized by the press ring 7, resulting in high reliability. It becomes possible to construct a tunnel lining. Moreover, since the pouring surface 29 of the filling member in the lining 20 is formed in a step-like shape, the water-stopping effect is large.

また、型枠支持部材に型枠の位置調整手段を設けたので
、型枠13を正確な覆工20の構築位置に位置決めする
ことが出来るようになり、信頼性の高い施工が可能とな
るばかりか、カーブ施工の場合等において、型枠として
変形型枠を用いた場合にも゛、位置調整手段により適切
な位置に型枠を保持位置決めすることが出来るようにな
る。なお、型枠の位置調整手段としては、型枠13の、
第3図矢印E、F及びG、H方向の位置の調整が出来れ
ばどのようなものでもよいことは勿論であり、位置決め
ボルト11cの他にも、油圧ジヤツキ等も使用が可能で
ある。
In addition, since the formwork support member is provided with a means for adjusting the position of the formwork, it becomes possible to position the formwork 13 at the exact construction position of the lining 20, and highly reliable construction becomes possible. Furthermore, even when a deformed formwork is used as a formwork in the case of curve construction, etc., the formwork can be held and positioned at an appropriate position by the position adjustment means. In addition, as the position adjustment means of the formwork, the formwork 13,
Of course, any device may be used as long as the position in the directions of arrows E, F, G, and H in FIG. 3 can be adjusted, and in addition to the positioning bolt 11c, a hydraulic jack or the like may also be used.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明によるシールド掘削機の一実施例を示す
正断面図、 第2図は第1図の■−■線による断面図、第3図は第1
図の■−■線による断面図、第4図はシールドl屈削機
のジヤツキ部分の拡大図、 第5図は第4図■−■線による断面図、第6図乃至第1
3図は本発明によるシールド掘削機を用いて覆工を構築
する際の一例を示す工程図である。 1・・・・・・シールド掘削機 2・・・・・外殻 6・・・・・1!!進用ジヤツキ 7・・・・・プレスリング 11・・・・・・型枠支持部材(ゲージリング)11c
・・・・・・位置調整手段(位置決めボルト)13・・
・・・・型枠 20・・・・・・覆工 出願人     三井建設株式会社 代理人   弁理士  相1)呻二 第2図 第6図 第7図 第8図 第10図 第11図 第12図
FIG. 1 is a front sectional view showing an embodiment of a shield excavator according to the present invention, FIG. 2 is a sectional view taken along the line ■-■ in FIG. 1, and FIG.
Figure 4 is an enlarged view of the jacking part of the shield l bending machine; Figure 5 is a cross-sectional view taken along line ■-■ in Figure 4; Figures 6 to 1
FIG. 3 is a process diagram showing an example of constructing a lining using the shield excavator according to the present invention. 1...Shield excavator 2...Outer shell 6...1! ! Advance jack 7...Press ring 11...Form support member (gauge ring) 11c
...Position adjustment means (positioning bolt) 13...
... Formwork 20 ... Lining applicant Mitsui Construction Co., Ltd. agent Patent attorney Phase 1) Figure 2 Figure 6 Figure 7 Figure 8 Figure 10 Figure 11 Figure 12 figure

Claims (1)

【特許請求の範囲】 外殻を有し、 該外殻の内側にプレスリングを前記外殻の 掘進方向に移動自在に設け、 更に該プレスリングの内側に型枠支持部材 を前記外殻に対して移動自在に設けると共に、前記型枠
支持部材に型枠の位置調整手段を 設け、 前記型枠支持部材に掘進用ジャッキを設け て構成したシールド掘削機。
[Claims] It has an outer shell, a press ring is provided inside the outer shell so as to be movable in the excavation direction of the outer shell, and a form support member is provided inside the press ring relative to the outer shell. What is claimed is: 1. A shield excavator, wherein the formwork support member is provided with a formwork position adjustment means, and the formwork support member is provided with an excavation jack.
JP62019461A 1987-01-29 1987-01-29 Shield excavator Pending JPS63189598A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62019461A JPS63189598A (en) 1987-01-29 1987-01-29 Shield excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62019461A JPS63189598A (en) 1987-01-29 1987-01-29 Shield excavator

Publications (1)

Publication Number Publication Date
JPS63189598A true JPS63189598A (en) 1988-08-05

Family

ID=11999963

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62019461A Pending JPS63189598A (en) 1987-01-29 1987-01-29 Shield excavator

Country Status (1)

Country Link
JP (1) JPS63189598A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60126494A (en) * 1983-12-13 1985-07-05 株式会社間組 Control apparatus and method of shield drilling machine

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60126494A (en) * 1983-12-13 1985-07-05 株式会社間組 Control apparatus and method of shield drilling machine

Similar Documents

Publication Publication Date Title
JPS62194399A (en) Construction method for coating tunnel
JPS63189598A (en) Shield excavator
JPH02132295A (en) Constructing method for tunnel lining work
JPS62121299A (en) Method for covering casting of tunnel and shield excavator used therein
JPH0519000B2 (en)
JP2953312B2 (en) Cast-in-place lining shield method and shield excavator
JP2634883B2 (en) Construction method of tunnel lining
JPS63181895A (en) Shield excavator
JPS62206198A (en) Method of constructing tunnel lining
JPH01312199A (en) Construction of tunnel linining work
JPS63103199A (en) Shield excavator
JPS63156199A (en) Shielding excavator
JP2676691B2 (en) Construction method of shield and lining using shield
JPH0637836B2 (en) Tunnel lining method
JPS63161300A (en) Method of constructing tunnel lining
JPS63161298A (en) Shield excavator
JPH0578637B2 (en)
JPS63161297A (en) Shield excavator
JPS6221996A (en) Shielding excavator
JPH0377000A (en) Reinforcing member for tunnel lining and constructing method of tunnel lining by using said reinforcing member
JPH055039B2 (en)
JPS63156198A (en) Shielding excavator
JPH02178500A (en) Shield excavator and lining constructing method
JPS63122898A (en) Method of casting lining
JPH0692719B2 (en) Lining construction method