JPH02132295A - Constructing method for tunnel lining work - Google Patents

Constructing method for tunnel lining work

Info

Publication number
JPH02132295A
JPH02132295A JP63287275A JP28727588A JPH02132295A JP H02132295 A JPH02132295 A JP H02132295A JP 63287275 A JP63287275 A JP 63287275A JP 28727588 A JP28727588 A JP 28727588A JP H02132295 A JPH02132295 A JP H02132295A
Authority
JP
Japan
Prior art keywords
concrete
outer shell
press ring
water
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP63287275A
Other languages
Japanese (ja)
Inventor
Kikuo Ishida
石田 喜久雄
Yutaka Okamoto
豊 岡本
Kazuhiko Matsuzaki
和彦 松崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP63287275A priority Critical patent/JPH02132295A/en
Publication of JPH02132295A publication Critical patent/JPH02132295A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To construct a tunnel in its lining work of high quality avoiding contact of concrete with water by constituting the tunnel providing a press ring and a mold supporting member and charging between the concrete and the natural ground with a water stopping member injected. CONSTITUTION:A press ring 7 is movably provided inside an outer shell 2, and a mold supporting member 11, movably provided inside the press ring 7, is moved to the front of the outer shell 2. Next in concrete depositing space 31 generated by the movement, concrete 21 is injected and deposited, moving the press ring 7 to the front of the shell 2. Subsequently, space 32, generated in accordance with the movement, is charged with a water stopping member 5 injected through a delivery pipe 10. And moving the press ring 7 in a direction of arrow head A, digging is started by a shield excavator 1. Thus forming a water stopping layer cylindrically surrounding the periphery of the concrete 21, its contact with groundwater or the like can be prevented.

Description

【発明の詳細な説明】 (a).産業上の利用分野 本発明は、トンネル覆工を構成するコンクリートと地山
との間に正水性部材からなる筒状の止水層を設けること
により、トンネル覆工を高品質化することが出来るトン
ネル覆工の構築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (a). Industrial Application Field The present invention can improve the quality of tunnel lining by providing a cylindrical water-stopping layer made of a water-promoting material between the concrete and the ground constituting the tunnel lining. Concerning methods for constructing tunnel linings.

(b).従来の技術 第14図は従来のシールド工法におけるコンクリート打
設の方法を示す図である。
(b). BACKGROUND ART FIG. 14 is a diagram showing a concrete placement method in the conventional shield construction method.

従来、現場打ちコンクリートを用いてシールド掘削機に
より掘削したトンネルに覆工を構築する際には、例えば
特開昭62−0194399に開示されているように,
コンクリート打設工程において、第14図に示すように
、シールド掘削機1のプレスリング7、ゲージリング1
1及び型枠13に囲まれた円環状のコンクリート打設空
間31に、型枠13に接続されたコンクリート供給管2
5から1次コンクリート21Aを打設した後,プレスリ
ング7を矢印八方向に移動させつつ、供給ホース30か
らプレスリング7の吐出管10を介して2次コンクリー
ト21Cを打設することにより,1次及び2次コンクリ
ート21A、21Cからなるトンネル覆工20を構築し
ていく。
Conventionally, when constructing a lining for a tunnel excavated by a shield excavator using cast-in-place concrete, for example, as disclosed in Japanese Patent Application Laid-Open No. 62-0194399,
In the concrete pouring process, as shown in FIG. 14, the press ring 7 and gauge ring 1 of the shield excavator 1
A concrete supply pipe 2 connected to the formwork 13 is placed in an annular concrete placement space 31 surrounded by the formwork 1 and the formwork 13.
After placing the primary concrete 21A from No. 5, the secondary concrete 21C is placed from the supply hose 30 through the discharge pipe 10 of the press ring 7 while moving the press ring 7 in the eight directions of the arrows. The tunnel lining 20 consisting of the next and second concrete 21A and 21C is constructed.

(C).発明が解決しようとする問題点しかし、こうし
て構築されたトンネル覆工20には、特に滞水地盤にお
いて、地山19側から水圧がかかり、該トンネル覆工2
0が地下水等の水と接触することにより、品質の低下を
招く恐れがある。
(C). Problems to be Solved by the Invention However, water pressure is applied to the tunnel lining 20 constructed in this way from the ground 19 side, especially in water-stagnant ground, and the tunnel lining 20 is
When 0 comes into contact with water such as groundwater, there is a risk that quality may deteriorate.

本発明は,上記の問題点を解消すべく,トンネル覆工を
構成するコンクリートと地山との間に止水性部材からな
る筒状の止水層を設けることにより,該コンクリートと
水との接触を避け、トンネル覆工を高品質化することが
出来るトンネル覆工の構築方法を提供することを目的と
する。
In order to solve the above-mentioned problems, the present invention provides a cylindrical water-stop layer made of a water-stop material between the concrete constituting the tunnel lining and the ground, thereby preventing contact between the concrete and water. The purpose of the present invention is to provide a method for constructing a tunnel lining that can avoid this and improve the quality of the tunnel lining.

(d),問題点を解決するための手段 即ち、本発明は、外殻(2)を有し、該外殻(2)の内
側にプレスリング(7)を前記外殻(2)の掘進方向に
移動自在に設け、該プレスリング(7)の内側に型枠支
持部材(11)を前記外殻(2)に対して移動自在に設
け、該型枠支持部材(11)と前記外殻(2)の間に掘
進用ジャッキ(6)を設けたシールド掘削機(1)を用
いてトンネル覆工(20)を構築する際は、プレスリン
グ(7)を外殻(2)後方に突出させた状態で、型枠支
持部材(11)を外殻(2)前方に移動させ,該型枠支
持部材(11)と既にコンクリート(21)の打設が完
了した型枠(13A)と+71ニ. 型枠(,1 3 
B )を設置してコンクリート打設空間(31)を形成
し、次いで該コンクリート打設空間(31)中にコンク
リート(21)を注入打設し,その後プレスリング(7
)を外殻(2)前方に移動させつつ,Mプレスリング(
7)の移動に伴なって生じる空間(32)中に止水性部
材(5)を注入充填し、その後シールド掘削機(1)に
よる掘進を開始して、掘進用ジャッキ(6)により外殻
(2)の前方への移動を開始すると共に,プレスリング
(7)を後方に突出させて、前記充填された止水性部材
(5)を加圧することにより,前記外殻(2)の移動に
伴なって生じるテールボード(27)中に該止水性部材
(5)を充填させるようにして構成される。
(d) Means for solving the problem, that is, the present invention has an outer shell (2), and a press ring (7) is provided inside the outer shell (2) by drilling the outer shell (2). A mold support member (11) is provided inside the press ring (7) so as to be movable with respect to the outer shell (2), and the mold support member (11) and the outer shell When constructing a tunnel lining (20) using a shield excavator (1) equipped with a digging jack (6) between (2), the press ring (7) should be protruded to the rear of the outer shell (2). In this state, the formwork support member (11) is moved forward of the outer shell (2), and the formwork support member (11) and the formwork (13A) on which concrete (21) has already been poured are connected to +71. D. Formwork (,1 3
B) is installed to form a concrete casting space (31), then concrete (21) is poured into the concrete casting space (31), and then a press ring (7
) while moving the outer shell (2) forward, press the M press ring (
The water-stopping member (5) is injected and filled into the space (32) created by the movement of the shell (7), and then excavation by the shield excavator (1) is started, and the excavation jack (6) is used to remove the outer shell ( 2) starts moving forward, and at the same time causes the press ring (7) to protrude rearward and pressurizes the filled water-stopping member (5). The structure is such that the water-stopping member (5) is filled into the resulting tail board (27).

なお,括弧内の番号等は、図面における対応する要素を
示す便宜的なものであり、従って、本記述は図面上の記
載に限定拘束されるものではない.以下のr (e).
作用」の欄についても同様である。
Note that numbers in parentheses are for convenience to indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions on the drawings. The following r(e).
The same applies to the column "Effect".

(e).作用 上記した構成により、本発明は、トンネル覆工(20)
を構成するコンクリート(21)と地山(19)との間
に形成された止水性部材(5)により、該コンクリート
(21)が水と接触する事態が発生しないように作用す
る。
(e). Effect With the above-described configuration, the present invention provides tunnel lining (20)
The water-stopping member (5) formed between the concrete (21) and the ground (19) that constitute the concrete (21) acts to prevent the concrete (21) from coming into contact with water.

(f).実施例 以下、本発明の実施例を図面に基づき説明する。(f). Example Embodiments of the present invention will be described below based on the drawings.

第1図は本発明によるトンネル覆工の構築方法が適用さ
れるシールド掘削機の一例を示す正断面図、 第2図は第1図の■一■線による断面図、第3図は第1
図のm一■線による断面図、第4図は第1図に示すシー
ルド掘削機のジャッキ部分の拡大図、 第5図は第4図の■−v線による断面図、第6図乃至第
13図は本発明によるトンネル覆工の構築方法の一例を
示す工程図である。
Fig. 1 is a front sectional view showing an example of a shield excavator to which the tunnel lining construction method according to the present invention is applied, Fig. 2 is a sectional view taken along line
Fig. 4 is an enlarged view of the jack part of the shield excavator shown in Fig. 1, Fig. 5 is a sectional view taken along line -v in Fig. FIG. 13 is a process diagram showing an example of a method for constructing a tunnel lining according to the present invention.

シールド掘削機1は、第1図に示すように、円筒状に形
成された外殻2を有しており,外殼2の前面、即ち第1
図左側面にはカッター3が回転自在に支持されている。
As shown in FIG. 1, the shield excavator 1 has a cylindrical outer shell 2, and the front surface of the outer shell 2, that is, the first
A cutter 3 is rotatably supported on the left side of the figure.

カッター3は、外殻2内部の空間を図中左右方向に遮断
する形で設けられた隔壁2aに設けられた駆動モーター
3aと接続しており、更に隔壁2aには掘進用ジャッキ
6が複数個,第1図及び第2図に示すように,外殻2に
沿った形で円環状に配列設置されている.掘進用ジャッ
キ6にはラム6aが矢印A.B方向に突出後退自在に設
けられており、更に外殻2の内側には、円筒状に形成さ
れたプレスリング7が、外殻2内面と接する形で矢印A
,B方向に摺動自在に設けられている。プレスリング7
には.第2図に示すように,所定の間隔でプレスリング
ジャッキ9が外殻2に沿った形で円環状に複数個配置さ
れており,更にそれ等プレスリングジャッキ9の間には
,第2図及び第5図に示すように、複数の吐出管10が
先端の吐出口10aをプレスリング7の側面7a.即ち
シールド掘削機1の後方に向けた形で設けられている。
The cutter 3 is connected to a drive motor 3a provided on a partition wall 2a provided to block the space inside the outer shell 2 in the horizontal direction in the figure, and a plurality of digging jacks 6 are installed on the partition wall 2a. , as shown in Figures 1 and 2, are arranged in a circular ring along the outer shell 2. A ram 6a is attached to the excavation jack 6 in the direction of arrow A. A cylindrical press ring 7 is provided inside the outer shell 2 so as to be able to protrude and retreat in the direction B, and is in contact with the inner surface of the outer shell 2 in the direction indicated by the arrow A.
, B so as to be slidable in the directions B. press ring 7
for. As shown in FIG. 2, a plurality of press ring jacks 9 are arranged in an annular shape along the outer shell 2 at predetermined intervals, and between the press ring jacks 9, as shown in FIG. As shown in FIG. 5, the plurality of discharge pipes 10 have discharge ports 10a at their tips connected to the side surface 7a of the press ring 7. That is, it is provided facing toward the rear of the shield excavator 1.

吐出管10には、吐出管内清掃用のシリンダー10bが
ロッド10cを矢印A.B方向に突出後退自在にした形
で設けられており、更に吐出管10には供給ホース3o
が接続されている。
In the discharge pipe 10, a cylinder 10b for cleaning the inside of the discharge pipe is connected to a rod 10c in the direction of arrow A. The discharge pipe 10 is provided with a supply hose 3o that can protrude and retreat freely in the direction B.
is connected.

ところで、掘進用ジャッキ6のラム6aの先端には、円
環状に形成されたゲージリング11が装着されており、
ゲージリング11には、第4図に示すように,係合溝1
1aがゲージリング11の全周に互って環状に穿設形成
されている。また,ゲージリング11には,第2図及び
第3図に示すように、円環状に組立てられた型枠13が
第1図左右方向に接続された形で設けられている.シー
ルド掘削機1は、以上のような構成を有するので、トン
ネル15の掘削に際しては、踵動モーター3aを駆動し
てカッター3を回転させると共に、掘進用ジャッキ6の
ラム6aを第1図矢印B方向に突出させて、隔壁2a及
び外殻2を介〜してカッター3ゑ切羽16方向,即ち矢
印八方向に押圧する。すると、その押圧力により,切羽
l6と回転するカッター3は所定の接触圧力で接し,切
羽16はカッター3により掘削されると同時に,外殻2
は矢印八方向に推進してトンネル15がシールト掘削機
上の後方,即ち図中右方に形成されていく。
By the way, a gauge ring 11 formed in an annular shape is attached to the tip of the ram 6a of the digging jack 6.
The gauge ring 11 has an engagement groove 1 as shown in FIG.
1a are annularly bored and formed around the entire circumference of the gauge ring 11. Further, as shown in FIGS. 2 and 3, the gauge ring 11 is provided with a formwork 13 assembled in an annular shape and connected in the left-right direction in FIG. 1. Since the shield excavator 1 has the above configuration, when excavating the tunnel 15, the heel motor 3a is driven to rotate the cutter 3, and the ram 6a of the excavation jack 6 is moved in the direction indicated by the arrow B in FIG. The cutter 3 is pushed in the direction of the face 16 of the cutter 3 through the partition wall 2a and the outer shell 2, that is, in the eight directions of the arrows. Then, due to the pressing force, the face l6 and the rotating cutter 3 come into contact with each other with a predetermined contact pressure, and at the same time the face 16 is excavated by the cutter 3, the outer shell 2
is propelled in the eight directions of the arrow, and a tunnel 15 is formed behind the seal excavator, that is, to the right in the figure.

こうして,トンネル15が形成されていくにつれ,掘削
された地山19の崩壊を防止するためにトンネル覆工2
0を構築する必要があるが、このトンネル覆工20の構
築は以下の手順で行なわれる。即ち、シールド掘削機1
が、型枠13の1リング分の長さL1だけ矢印A方向に
掘進した状態では,掘進用ジャッキ6のラム6aは、第
6図に示すように,矢印B方向に突出した状態となって
おり、またプレスリング7も矢印B方向に移動した状態
となっている。
In this way, as the tunnel 15 is formed, the tunnel lining 2 is installed to prevent the excavated ground 19 from collapsing.
The tunnel lining 20 needs to be constructed using the following procedure. That is, shield excavator 1
However, when the excavation is carried out by the length L1 corresponding to one ring of the formwork 13 in the direction of arrow A, the ram 6a of the excavation jack 6 protrudes in the direction of arrow B, as shown in FIG. In addition, the press ring 7 is also moved in the direction of arrow B.

この状態で,第7図に示すように、掘進用ジャッキ6の
ラム6aを矢印A方向に距離L1だけ後退させる。する
と、直前にコンクリート21の打設された部分の妻止め
22A及び型枠13Aからゲージリング11が離九て矢
印A方向に移動し,妻止め22A及び型枠13Aとゲー
ジリング11との間に距離L1なる空間が形成される.
そこで、該空間部分に,図中想像線で示すように、パン
チプレートや鉄筋等からなる補強部材12を係合溝11
aを介して妻止め22Bと共に設置し、更に型枠13A
に接する形で型枠13Bを組立て設置し、該型枠13B
、ゲージリング11(妻止め22B)、プレスリング7
及び妻止め22Aの間に円筒状のコンクリート打設空間
31を形成する。
In this state, as shown in FIG. 7, the ram 6a of the digging jack 6 is moved back by a distance L1 in the direction of arrow A. Then, the gauge ring 11 separates from the end stop 22A and formwork 13A of the part where the concrete 21 was placed just before and moves in the direction of arrow A, and a gap is formed between the end stop 22A and formwork 13A and the gauge ring 11. A space with distance L1 is formed.
Therefore, a reinforcing member 12 made of a punch plate, reinforcing bar, etc. is inserted into the engagement groove 11 in the space, as shown by the imaginary line in the figure.
Installed with end stop 22B via a, and further formwork 13A
The formwork 13B is assembled and installed in contact with the formwork 13B.
, gauge ring 11 (end stop 22B), press ring 7
A cylindrical concrete placement space 31 is formed between the end stop 22A and the end stop 22A.

この状態で、第8図に示すように、型枠13Bにコンク
リート供給管25を接続して,コンクリート供給管25
よりコンクリート打設空間31中にコンクリート21を
打設する。なお、この際コンクリート打設空間31中の
空気は、型枠13に適宜設けられたエアー抜き管13a
により外部に排出されるので、コンクリート21のコン
クリート打設空間31中への注入打設動作は円滑に行な
われる。
In this state, as shown in FIG. 8, the concrete supply pipe 25 is connected to the formwork 13B.
Concrete 21 is poured into the concrete placement space 31. At this time, the air in the concrete casting space 31 is removed through an air vent pipe 13a provided in the formwork 13 as appropriate.
Since the concrete 21 is discharged to the outside, the pouring operation of the concrete 21 into the concrete placement space 31 is performed smoothly.

こうして、コンクリート打設空間31中にコンクリート
21が打設されたところで、第9図に示すように、プレ
スリングジャッキ9を邪動してプレスリング7を矢印八
方向に徐々に後退させる。
When the concrete 21 has been placed in the concrete placement space 31 in this manner, the press ring jack 9 is moved to gradually retreat the press ring 7 in the eight directions of the arrows, as shown in FIG.

すると、プレスリング7の通過した後には,外殻2と注
入されたコンクリート21との間に円環状の充填部材打
設空間32が形成される。そこで、プレスリング7の矢
印A方向への移動と共に、第10図に示すように、供給
ホース30から、ベントナイトモルタル等の止水性部材
5を吐出管10を介して充填部材打設空間32中に注入
し、該充填部材打設空間32を止水性部材Sで充填する
Then, after the press ring 7 passes, an annular filling member casting space 32 is formed between the outer shell 2 and the poured concrete 21. Therefore, as the press ring 7 moves in the direction of arrow A, a water-stopping member 5 such as bentonite mortar is introduced from the supply hose 30 into the filling member casting space 32 through the discharge pipe 10, as shown in FIG. The filling member casting space 32 is filled with the water-stopping member S.

プレスリング7が矢印八方向に移動して、第11図に示
すように、側面7aがゲージリング11側の妻止め22
Bの設置位置とほぼ一致したところで、第12図に示す
ように、掘進用ジャッキ6のラム6aを矢印B方向に突
出駆動させると共に、カツター3を回転させて掘削動作
を開始する。
The press ring 7 moves in the eight directions of the arrow, and as shown in FIG.
When the excavation position is substantially aligned with the installation position B, as shown in FIG. 12, the ram 6a of the excavation jack 6 is driven to protrude in the direction of arrow B, and the cutter 3 is rotated to start the excavation operation.

すると,既に述べたように、外殻2が矢印八方向に移動
を開始し、外殻2が移動した後には、打設充填された止
水性部材5と地山19との間にテールボード27が形成
される。そこで、外殼2が矢印A方向に移動するにつれ
てプレスリングジャッキ9を北動して、プレスリング7
を外殻2の移動に同期した形で矢印B方向に徐々に移動
させる。すると、先程打設された充填部材打設空間32
内の未硬化の止水性部材5は、プレスリンク7に押圧さ
れて,テールポイド27を充填する形で流動する.こう
して、第13図に示すように、外殻2の矢印八方向への
移動につれて、プレスリング7を矢印B方向に移動させ
ていくと、外殻2の移動の結果発生するテールボード2
7は、効果的に充填されていく。この際、止水性部材5
がプレスリング7のプレス圧力により、コンクリート打
設空間31中のコンクリート21の粒子間及び地山19
を構成する土砂等の粒子間に詰まる形で移動し,コンク
リート打設空間31に打設されたコンクリート21のR
Hを筒状に取り囲む形で止水廖を形成する。また、プレ
スリング7は円筒状に形成されているので、止水性部材
5はリング全周に亙り均一に加在され、従ってテールボ
ード27の充填動作は外殻2の全周に亙り均一で良好な
状態で行なわれる。このようにして、外殻2が型枠13
の1リング分の長さL1だけ推進すると、プレスリング
7は,第6図に示すように、その側面7aが外殻2の後
端部2bに一致した形となり、1リング分のトンネル覆
工20の構築が完了する.なお、1リング分のトンネル
覆工20が構築されると、次の1リング分のトンネル覆
工20を構築するため、既に述べたように、この状態で
掘進用ジャッキ6のラム6aを,第7図に示すように、
矢印A方向に距離L1だけ後退させるが、この際には,
妻止め22Bと接触している部分のコンクリート21は
、既に円環状に十分に固化しているので、打ち継ぎ面2
9は崩壊することなく妻止め22Bと共に自立し、その
後の補強部材12の設置作業も円滑に行なわれる。
Then, as described above, the outer shell 2 starts to move in the eight directions of the arrow, and after the outer shell 2 moves, the tail board 27 is placed between the poured and filled water-stopping member 5 and the ground 19. is formed. Therefore, as the outer shell 2 moves in the direction of arrow A, the press ring jack 9 is moved north, and the press ring 7
is gradually moved in the direction of arrow B in synchronization with the movement of the outer shell 2. Then, the filling member casting space 32 that was cast earlier is
The uncured waterproof member 5 inside is pressed by the press link 7 and flows to fill the tail poid 27. In this way, as shown in FIG. 13, when the press ring 7 is moved in the direction of the arrow B as the outer shell 2 moves in the eight directions of the arrows, the tail board 2 generated as a result of the movement of the outer shell 2
7 is effectively filled. At this time, the water-stopping member 5
Due to the press pressure of the press ring 7, the particles of the concrete 21 in the concrete placement space 31 and the ground 19
R of the concrete 21 placed in the concrete placement space 31.
Form a water stop wall surrounding H in a cylindrical shape. In addition, since the press ring 7 is formed in a cylindrical shape, the water-stopping member 5 is uniformly applied over the entire circumference of the ring, so that the filling operation of the tail board 27 is uniform and good over the entire circumference of the outer shell 2. It is carried out under such conditions. In this way, the outer shell 2 is attached to the formwork 13
When the press ring 7 is propelled by a length L1 corresponding to one ring, the side surface 7a of the press ring 7 matches the rear end 2b of the outer shell 2, as shown in FIG. 20 construction is completed. In addition, when the tunnel lining 20 for one ring is constructed, in order to construct the tunnel lining 20 for the next one ring, in this state, the ram 6a of the excavation jack 6 is As shown in Figure 7,
It is moved back by a distance L1 in the direction of arrow A, but at this time,
The concrete 21 in the part that is in contact with the end stop 22B has already hardened sufficiently into an annular shape, so the concrete 21 is in contact with the end stop 22B.
9 stands on its own together with the end stop 22B without collapsing, and the subsequent installation work of the reinforcing member 12 can be carried out smoothly.

なお、上述の実施例においては,コンクリート打設空間
31中に打設されたコンクリート21と地山19の間に
形成された充填部材打設空間32及びテールボード27
内に、ベントナイトモルタル等からなる止水性部材5を
注入充填した場合について説明したが、該充填部材打設
空間32及びテールボード27内に、二液性の可塑状系
クラウト材や発泡モルタルを止水性部材5として注入充
填することも出来る。二液性の可塑状系グラウト材を用
いた場合,該二液性の可塑状系グラウト材の充填部材打
設空間32内への注入方法は,各種考えられるが、充填
部材打設空間32内で二液を混合して止水性部材5を形
成することが出来る限り、どのような方法でもよい。ま
た、混合された止水性部材5は、柔軟性を有するホモゲ
ル状となった後、硬化するので、プレスIJング7によ
るテールボード27への圧入動作はホモゲル状態下で円
滑に行なわれる。
In addition, in the above-mentioned embodiment, the filling member casting space 32 and the tail board 27 formed between the concrete 21 placed in the concrete casting space 31 and the ground 19 are
A case has been described in which a water-stopping member 5 made of bentonite mortar or the like is injected and filled into the filling member placement space 32 and the tailboard 27. It can also be injected and filled as the aqueous material 5. When a two-component plastic grout material is used, there are various methods of injecting the two-component plastic grout material into the filling member placement space 32; Any method may be used as long as the water-stopping member 5 can be formed by mixing the two liquids. Moreover, since the mixed water-stopping member 5 becomes a flexible homogel and then hardens, the press-fitting operation into the tail board 27 by the press IJ ring 7 is smoothly performed in the homogel state.

(g).発明の効果 以上、説明したように,本発明は、外殻2を有し,該外
殻2の内偏にプレスリング7を前記外殻2の促進方向に
移動自在に設け、該プレスリング7の内側にゲージリン
グ11等の型枠支持部材を前記外殻2に対して移動自在
に設け、該型枠支持部材と前記外殻2の間に掘進用ジャ
ッキ6を設けたシールド掘削機1を用いてトンネル覆工
20を構築する際は,プレスリング7を外殻2後方に突
出させた状態で、型枠支持部材を外殻2前方に移動させ
,該型枠支持部材と既にコンクリート21の打設が完了
した型枠13Aとの間に、型枠13Bを設置してコンク
リート打設空間31を形成し、次いで該コンクリート打
設空間31中にコンクリート21を注入打設し,その後
プレスリング7を外殻2前方に移動させつつ、該プレス
リンク7の移動に伴なって生じる充填部材打設空間32
中にベントナイトモルタル,可塑状系グラウト材、発泡
モルタル等からなる止水性部材5を注入充填し、その後
シールド掘削機1による掘進を開始して、掘進用ジャッ
キ6により外殻2の前方への移動を開始すると共に、プ
レスリング7を後方に突出させて、前記充填された止水
性部材Sを加圧することにより、前記外殻2の移動に伴
なって生じるテールボード27中に該止水性部材Sを充
填させるようにして構成したので、コンクリート打設空
間31内のコンクリート21と地山19との間に筒状に
充填された止水性部材5が,コンクリート打設空間31
内のコンクリート21と地下水等の水との接触を防止し
て該コンクリート21の品質を低下させる事態の発生を
未然に防止することが出来る。従って、特に滞水地盤に
トンネル覆工20を構築する際に、コンクリート打設空
間31内のコンクリート21から形成さ九る覆工20部
分のみを有効覆工厚と考える場合には、高品質のコンク
リートにより覆工を構築することが可能となり,信頼性
の高い施工を行なうことが出来る。
(g). Effects of the Invention As described above, the present invention has an outer shell 2, and a press ring 7 is provided on the inner side of the outer shell 2 so as to be movable in the direction of promoting the outer shell 2. A shield excavator 1 is provided, in which a formwork support member such as a gauge ring 11 is provided inside the shell 2 so as to be movable with respect to the outer shell 2, and a jack 6 for excavation is provided between the formwork support member and the outer shell 2. When constructing the tunnel lining 20 using the press ring 7, the formwork supporting member is moved to the front of the outer shell 2 with the press ring 7 protruding to the rear of the outer shell 2, and the formwork supporting member and the concrete 21 are already in contact with each other. A formwork 13B is installed between the formwork 13A for which pouring has been completed to form a concrete placing space 31, and then concrete 21 is poured into the concrete placing space 31, and then the press ring 7 While moving the press link 7 forward to the outer shell 2, the filling member placement space 32 created as the press link 7 moves.
A water-stopping member 5 made of bentonite mortar, plastic grout, foamed mortar, etc. is injected and filled inside, and then excavation by the shield excavator 1 is started, and the outer shell 2 is moved forward by the excavation jack 6. At the same time, by protruding the press ring 7 rearward and pressurizing the filled water-stopping member S, the water-stopping member S is formed in the tail board 27 generated as the outer shell 2 moves. Since the water-stopping member 5 filled in a cylindrical shape between the concrete 21 and the ground 19 in the concrete placement space 31 is configured to fill the concrete placement space 31 with
It is possible to prevent the occurrence of a situation in which the quality of the concrete 21 is degraded by preventing the concrete 21 inside from coming into contact with water such as underground water. Therefore, especially when constructing the tunnel lining 20 on water-logged ground, if only the portion of the lining 20 formed from the concrete 21 in the concrete placement space 31 is considered as the effective lining thickness, high-quality It is possible to construct a lining using concrete, and construction can be performed with high reliability.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明によるトンネル覆工の構築方法が適用さ
れるシールト掘削機の一例を示す正断面図. 第2図は第1図の■−■線による断面図、第3図は第1
図の■一■線による断面図、第4図は第1図に示すシー
ルド掘削機のジャッキ部分の拡大図、 第5図は第4図のV−Vaによる断面図、第6図乃至第
13図は本発明によるトンネル覆工の構築方法の一例を
示す工程図、 第14図は従来のシールド工法におけるコンクリート打
設の方法を示す図である。 27・・・・・・テールボード 31・・・・・・コンクリート打設空間32・・・・・
・充填部材打設空間
FIG. 1 is a front sectional view showing an example of a seal excavator to which the tunnel lining construction method according to the present invention is applied. Figure 2 is a cross-sectional view taken along the line ■-■ in Figure 1, and Figure 3 is a cross-sectional view of Figure 1.
Figure 4 is an enlarged view of the jack part of the shield excavator shown in Figure 1, Figure 5 is a cross-sectional view taken along line V-Va in Figure 4, Figures 6 to 13 Figure 14 is a process diagram showing an example of the method for constructing a tunnel lining according to the present invention, and Figure 14 is a diagram showing a concrete pouring method in the conventional shield construction method. 27...Tail board 31...Concrete placement space 32...
・Filling material placement space

Claims (1)

【特許請求の範囲】 外殻を有し、 該外殻の内側にプレスリングを前記外殻の掘進方向に移
動自在に設け、 該プレスリングの内側に型枠支持部材を前記外殻に対し
て移動自在に設け、 該型枠支持部材と前記外殻の間に掘進用ジャッキを設け
たシールド掘削機を用いてトンネル覆工を構築する際は
、 プレスリングを外殻後方に突出させた状態で、型枠支持
部材を外殻前方に移動させ、 該型枠支持部材と既にコンクリートの打設が完了した型
枠との間に、型枠を設置してコンクリート打設空間を形
成し、 次いで、該コンクリート打設空間中にコンクリートを注
入打設し、 その後、プレスリングを外殻前方に移動させつつ、該プ
レスリングの移動に伴なって生じる空間中に止水性部材
を注入充填し、 その後、シールド掘削機による掘進を開始して、掘進用
ジャッキにより外殻の前方への移動を開始すると共に、 プレスリングを後方に突出させて、前記充填された止水
性部材を加圧することにより、前記外殻の移動に伴なっ
て生じるテールボード中に該止水性部材を充填させるよ
うにして構成したトンネル覆工の構築方法。
[Scope of Claims] It has an outer shell, a press ring is provided inside the outer shell so as to be movable in the excavation direction of the outer shell, and a form support member is provided inside the press ring with respect to the outer shell. When constructing a tunnel lining using a movable shield excavator equipped with a digging jack between the formwork support member and the outer shell, the press ring should be protruded to the rear of the outer shell. , move the formwork support member to the front of the outer shell, and install the formwork between the formwork support member and the formwork into which concrete has already been poured to form a concrete pouring space; Concrete is poured into the concrete placement space, and then, while moving the press ring to the front of the outer shell, a water-stopping member is injected and filled into the space created by the movement of the press ring, and then, The shield excavator starts digging, and the excavation jack starts moving the outer shell forward, and the press ring is protruded rearward to pressurize the filled water-stopping member. A method for constructing a tunnel lining in which the water-stopping member is filled in a tail board that is generated as the shell moves.
JP63287275A 1988-11-14 1988-11-14 Constructing method for tunnel lining work Pending JPH02132295A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63287275A JPH02132295A (en) 1988-11-14 1988-11-14 Constructing method for tunnel lining work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63287275A JPH02132295A (en) 1988-11-14 1988-11-14 Constructing method for tunnel lining work

Publications (1)

Publication Number Publication Date
JPH02132295A true JPH02132295A (en) 1990-05-21

Family

ID=17715293

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63287275A Pending JPH02132295A (en) 1988-11-14 1988-11-14 Constructing method for tunnel lining work

Country Status (1)

Country Link
JP (1) JPH02132295A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105065009A (en) * 2015-08-17 2015-11-18 中国地质大学(武汉) Method for shield expanding construction of subway station
CN105240023A (en) * 2015-09-23 2016-01-13 中国地质大学(武汉) Method of adopting curved pipe-jacking supporting structure for extension of shield-driven subway station
CN110259468A (en) * 2019-05-31 2019-09-20 江苏锐成机械有限公司 Driving engineering method of the shield machine in full ground consisting of hard rock
CN111779493A (en) * 2020-07-07 2020-10-16 中铁隧道集团二处有限公司 Full-section rock stratum construction method for slurry shield in fracture development

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62194399A (en) * 1986-02-20 1987-08-26 三井建設株式会社 Construction method for coating tunnel

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62194399A (en) * 1986-02-20 1987-08-26 三井建設株式会社 Construction method for coating tunnel

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105065009A (en) * 2015-08-17 2015-11-18 中国地质大学(武汉) Method for shield expanding construction of subway station
CN105240023A (en) * 2015-09-23 2016-01-13 中国地质大学(武汉) Method of adopting curved pipe-jacking supporting structure for extension of shield-driven subway station
CN110259468A (en) * 2019-05-31 2019-09-20 江苏锐成机械有限公司 Driving engineering method of the shield machine in full ground consisting of hard rock
CN111779493A (en) * 2020-07-07 2020-10-16 中铁隧道集团二处有限公司 Full-section rock stratum construction method for slurry shield in fracture development

Similar Documents

Publication Publication Date Title
JPS62194399A (en) Construction method for coating tunnel
JPH02132295A (en) Constructing method for tunnel lining work
JP2004052467A (en) Tunnel construction method
JPH0519000B2 (en)
JP2634883B2 (en) Construction method of tunnel lining
JPH02132297A (en) Lining work constructing method
JP2676691B2 (en) Construction method of shield and lining using shield
JPH0333398A (en) Lining work for tunnel
JPH01312199A (en) Construction of tunnel linining work
JPH02225799A (en) Lining construction
JPS63103199A (en) Shield excavator
JPS62206198A (en) Method of constructing tunnel lining
JP3299904B2 (en) Wife formwork in shielded excavators
JP2704891B2 (en) Construction method of shield excavator and tunnel lining
JPH0369799A (en) Constructing method for tunnel lining and shield excavator
JPH02178500A (en) Shield excavator and lining constructing method
JPH02178493A (en) Shield excavator
JPH02153198A (en) Shield excavator
JPS63181895A (en) Shield excavator
JPH0377000A (en) Reinforcing member for tunnel lining and constructing method of tunnel lining by using said reinforcing member
JPH0518999B2 (en)
JPH02183095A (en) Constructing method of tunnel lining
JPS63189598A (en) Shield excavator
JPS63156198A (en) Shielding excavator
JPH02292497A (en) Shield excavator and lining constructing method using its shield excavator