JPS63134713A - Temporary coffering construction with continuous wall - Google Patents
Temporary coffering construction with continuous wallInfo
- Publication number
- JPS63134713A JPS63134713A JP28063286A JP28063286A JPS63134713A JP S63134713 A JPS63134713 A JP S63134713A JP 28063286 A JP28063286 A JP 28063286A JP 28063286 A JP28063286 A JP 28063286A JP S63134713 A JPS63134713 A JP S63134713A
- Authority
- JP
- Japan
- Prior art keywords
- continuous wall
- cofferdam
- temporary
- construction
- coffering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 20
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 13
- 238000005266 casting Methods 0.000 abstract 1
- 229910000831 Steel Inorganic materials 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000001035 drying Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 239000000654 additive Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は連続地中壁による仮締切工法に関し、特に締
切工の内部をドライアップする際に適用される仮締切工
法の改良に関するものである。[Detailed Description of the Invention] (Industrial Application Field) This invention relates to a temporary cofferdam construction method using a continuous underground wall, and particularly relates to an improvement in a temporary cofferdam construction method applied when drying up the inside of a cofferdam. .
(従来の技術)
周知のように、河川あるいは海中に橋脚フーチングなど
の構造物を構築する場合、水域内に仮締切工を形成し、
締切工内の水を排水してドライな状態にし、陸上と同じ
条件で工事を行なうことがある。(Prior Art) As is well known, when constructing a structure such as a bridge pier footing in a river or the sea, a temporary cofferdam is formed in the water body,
The water inside the cofferdam may be drained to make it dry, and construction work may be carried out under the same conditions as on land.
この種の仮締切工としては、鋼矢板を用いた工法が広く
採用されている。As this type of temporary cofferdam, construction methods using steel sheet piles are widely adopted.
鋼矢板を用いる仮締切工法は、施工が容易で取扱いが簡
単ではあるが、深度が深くしかも大規模な水域を締切る
には外力に対する抵抗が十分に得られなかった。Temporary cofferdam construction methods using steel sheet piles are easy to construct and handle, but they do not provide sufficient resistance to external forces for sealing off large and deep bodies of water.
そこで、鋼矢板で水域を締切り、締切工内に中詰土砂を
投入した状態で、締切工中に海底地盤中から水面上まで
達するコンクリート類の連続壁を形成する仮締切工法が
提案されている。Therefore, a temporary cofferdam method has been proposed in which a water body is closed off with steel sheet piles, and filler soil is poured into the cofferdam, and a continuous wall of concrete that reaches from the seabed ground to above the water surface is formed during the cofferdam construction. .
しかしながら、このような連続壁を用いた仮締切工法に
は、特に、締切工内の水を排水してドライアップする場
合に、以下に説明する問題があった。However, such a temporary cofferdam construction method using a continuous wall has the following problems, particularly when water in the cofferdam is drained and dried up.
(発明が解決しようとする問題点)
すなわち、仮締切工内をドライアップすると、仮締切工
にはその周囲の土・水圧が作用するが、これらの外力は
連続壁を用いた仮締切工事が、前述したように大深度且
つ大規模な工事に適用されるので、かなり大きなものと
なる。従って、ドライアップした時に仮締切工に加わる
外力に抵抗するためには、必然的に連続壁の壁厚を大き
くしなければならなかった。(Problem to be solved by the invention) In other words, when the inside of a temporary cofferdam is dried up, the surrounding soil and water pressure acts on the temporary cofferdam, but these external forces cannot be overcome by temporary cofferdam construction using continuous walls. As mentioned above, it is applied to deep and large-scale construction, so it is quite large. Therefore, in order to resist the external force applied to the temporary cofferdam when it dries up, the wall thickness of the continuous wall must necessarily be increased.
ところで、この種の仮締切工は、通常工事目的物を安全
且つ迅速に施工するための仮設備であり、工事完了後に
は撤去が予定されており、安全性などが確保されればで
きる限り経済的なものが望ましく、いかに安価に安全な
仮締切工を構築するかは極めて重要な技術的関心事であ
る。By the way, this type of temporary cofferdam is usually temporary equipment used to safely and quickly construct a construction object, and is scheduled to be removed after the construction is completed. It is desirable to have a temporary cofferdam that is safe, and how to construct a safe temporary cofferdam at low cost is an extremely important technical concern.
しかるに、前述した工法では連続壁の壁厚を大きくしな
ければならないので経済的な面で大きな問題があった。However, the above-mentioned construction method requires increasing the wall thickness of the continuous wall, which poses a major economic problem.
ここで、連続壁の壁厚を薄くしておき、締切工の内部を
ドライアップする際に、連続壁の内側に逆巻壁を形成す
ることも考えられるが、この工法では仮締切工の構築に
時間がかかるという問題がある。Here, it is possible to reduce the wall thickness of the continuous wall and form a reverse wall on the inside of the continuous wall when drying up the inside of the cofferdam, but this construction method The problem is that it takes time.
この発明はこのような従来の問題点に鑑みてなされたも
のであって、その目的とするところは、経済的にしかも
短期間に構築できる連続壁による仮締切工法を提供する
ことにある。The present invention has been made in view of these conventional problems, and its purpose is to provide a temporary cofferdam construction method using continuous walls that can be constructed economically and in a short period of time.
(問題点を解決するための手段)
上記の目的を達成するために、この発明は、水域内に締
切工を形成し、この締切工内に連続壁を形成した後、前
記連続壁で囲んだ内側をドライアップする工法において
、前記連続壁と前記締切工との間に形成される内外間隙
部のいずれか一方に予め補強梁を設置することを特徴と
する。(Means for Solving the Problems) In order to achieve the above object, the present invention forms a cofferdam in a water body, forms a continuous wall within the cofferdam, and then surrounds the cofferdam with the continuous wall. In the construction method of drying up the inside, a reinforcing beam is installed in advance in either the inner or outer gap formed between the continuous wall and the cofferdam.
(作 用)
上記構成の仮締切工法によれば、連続壁の内・外側のい
ずれか一方に補強梁が設けであるので、締切工の内部を
ドライアップした時に、締切工に加わる外力に対して連
続壁と補強梁とが協動して抵抗するので、連続壁の壁厚
は大きくしなくて済む。(Function) According to the temporary cofferdam construction method with the above configuration, reinforcing beams are provided on either the inside or the outside of the continuous wall, so when the inside of the cofferdam is dried up, it will resist external forces applied to the cofferdam. Since the continuous wall and the reinforcing beam cooperate to provide resistance, there is no need to increase the wall thickness of the continuous wall.
また、補強梁は締切工の構築時に予め設置するので、仮
締切工の工期も長期化することはない。Furthermore, since the reinforcing beams are installed in advance when constructing the cofferdam, the construction period for the temporary cofferdam will not be prolonged.
(実施例)
以下、この発明の好適な実施例について添附図面を参照
にして詳細に説明する。(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
第1図はこの発明に係る連続壁による仮締切工法の一実
施例を工程順に示す縦断面図である。FIG. 1 is a vertical sectional view showing an embodiment of the temporary cofferdam construction method using continuous walls according to the present invention in the order of steps.
同図に示す工法では、まず、第1図(a )に示すよう
に、鋼矢板、m管矢板などの締切材10が、海底地!I
!Eの所定深度まで打設され、締切材10−10間に中
詰土砂12が投入される。In the construction method shown in FIG. 1, first, as shown in FIG. I
! It is poured to a predetermined depth of E, and filling earth and sand 12 is placed between the cofferdams 10 and 10.
中詰土砂12が海底地盤E上に所定の厚みだけ堆積する
と、第1の補強梁14aが設置され、その後再び中詰土
砂12を投入して第2および第3の補強梁14b、14
Cを設置する。When the filling soil 12 is deposited to a predetermined thickness on the seabed ground E, the first reinforcing beam 14a is installed, and then the filling soil 12 is put in again and the second and third reinforcing beams 14b, 14 are installed.
Install C.
ここで、各補強梁14a、b、cは、それぞれ締切材1
0−10間のほぼ中心位置に設けられる連続壁16と締
切工10との外側間隙部17にあって、連続壁16の外
側に位置しており、連続壁16の外周形状に沿うように
して設置される。Here, each reinforcing beam 14a, b, c is a cofferdam 1.
It is located in the outer gap 17 between the continuous wall 16 and the cofferdam 10 provided at approximately the center position between 0 and 10, and is located on the outside of the continuous wall 16 so as to follow the outer peripheral shape of the continuous wall 16. will be installed.
また、各補強梁14a、b、cは、例えば締切工内に構
築する目的物が円形断面であれば、適当な幅と厚みを有
する鋼材をリング状に結合したものが最も実際的である
が、補強梁14a、b、CのI11位置に対応した割合
の中詰土砂12を、水中での分離を抑制するための特殊
添加剤を加えた固化剤で固結して補強梁14a、b、c
としてもよい。Furthermore, if the object to be constructed within the cofferdam has a circular cross-section, the most practical way for each of the reinforcing beams 14a, b, and c is to form a ring of steel members having an appropriate width and thickness. , reinforcing beams 14a, b, C are solidified with a solidifying agent containing special additives to suppress separation in water. c.
You can also use it as
補強梁14a、b、cが段状に設置されると、第1図(
b)に示すように、締切材10−10間のほぼ中心に連
続壁16が構築される。When the reinforcing beams 14a, b, and c are installed in steps, as shown in FIG.
As shown in b), a continuous wall 16 is constructed approximately in the center between the cofferdams 10-10.
連続壁16は、中詰土砂12および海底地盤Eを泥水を
満たしながら掘削し、掘削孔内に鉄筋を建込んだ後、コ
ンクリートを打設することによって形成される。The continuous wall 16 is formed by excavating the filling earth 12 and the seabed E while filling it with muddy water, erecting reinforcing bars in the excavated hole, and then pouring concrete.
連続壁16の構築が終了すると仮締切工が完了するので
、第1図(C)に示すように、補強!814a、b、c
が設置されていない方、つまり仮締切工で仕切った内側
の水を排水してドライアップし、仮締切工中に目的物を
構築する。When the construction of the continuous wall 16 is completed, the temporary cofferdam is completed, so as shown in Fig. 1(C), reinforcement is completed! 814a, b, c
Water is drained and dried from the area where the cofferdam is not installed, that is, inside the cofferdam, and the target object is constructed while the cofferdam is being constructed.
さて、以上の如き方法で仮締切工を(n築すれば、第1
図(C)に示した、仮締切工中をドライアップした時に
、これに作用する外力に対しては、補強梁14a、b、
cと連続壁16とが協働して対抗することになるので、
補強梁14a、t+、cで分担する分だけ、連続壁16
の壁厚を薄くすることができる。Now, if you construct the temporary cofferdam (n) using the method described above, the first
As shown in Figure (C), when the temporary cofferdam is dried up, the reinforcement beams 14a, b,
c and the continuous wall 16 will cooperate and oppose each other,
The continuous wall 16 is divided by the reinforcement beams 14a, t+, and c.
The wall thickness of the can be reduced.
また、仮締切工中に内部コンクリートを構築する場合に
も、下方から上方に向けてコンクリートを打設する順巻
工法が採用できるので、工期の短縮も可能となる。Furthermore, when constructing internal concrete during temporary cofferdam construction, a sequential method of pouring concrete from the bottom to the top can be used, which also shortens the construction period.
第2図はこの発明に係る連続壁による仮締切工法の他の
実施例を示しており、その特徴点についてのみ以下に説
明する。FIG. 2 shows another embodiment of the temporary cofferdam construction method using a continuous wall according to the present invention, and only its characteristic points will be described below.
この実施例では補強梁148〜14cを、速続壁16と
締切工10との間に形成される内側間隙部18に予め埋
設しておく。In this embodiment, reinforcing beams 148 to 14c are buried in advance in the inner gap 18 formed between the fastening wall 16 and the cofferdam 10.
そして、締切工1.0−10間の内部をドライアップす
る時に、上段側から順次補強梁14a〜14Cが露出す
ると、補強梁14a〜14Cと連続壁16との間にコン
クリートなどの連結材20を充填して、第2図(b)に
示すように、補強梁14a〜14cと連続壁16とを一
体化させる。When the interior of the cofferdam 1.0-10 is dried up, when the reinforcing beams 14a to 14C are sequentially exposed from the upper side, a connecting material 2 such as concrete is inserted between the reinforcing beams 14a to 14C and the continuous wall 16. The reinforcing beams 14a to 14c and the continuous wall 16 are integrated with each other as shown in FIG. 2(b).
以上のようにして仮締切工を造成しても、上記実施例と
同等な作用効果を1qることができる。Even if the temporary cofferdam is created as described above, the same effect as in the above embodiment can be achieved.
(発明の効果)
以上、説明したように、この発明に係る速続壁による仮
締切工法によれば、この種の工法で最も重要な経済的な
而で有利な条件下で、大深度且つ大規模な仮締切工が構
築できる。(Effects of the Invention) As explained above, according to the temporary cofferdam construction method using a rapid extension wall according to the present invention, it is possible to achieve deep and large cofferdam construction under economical and advantageous conditions, which is the most important aspect of this type of construction method. Large-scale temporary cofferdams can be constructed.
第1図は本発明工法の工程を順に示す縦断面図、第2図
は同工法の他の実施例を工程順に示す縦断面図である。
10・・・・・・締切材 12・・・・・・中詰
土砂14a、b、c・・・・・・補強梁
16・・・・・・連続壁FIG. 1 is a longitudinal sectional view showing the steps of the construction method of the present invention in order, and FIG. 2 is a longitudinal sectional view showing another embodiment of the same method in order of steps. 10... Cofferdam material 12... Filling earth and sand 14a, b, c... Reinforcement beam 16... Continuous wall
Claims (2)
を形成した後、前記連続壁で囲んだ内側をドライアップ
する工法において、前記連続壁と前記締切工との間に形
成される内外間隙部のいずれか一方に予め補強梁を設置
することを特徴とする連続壁による仮締切工法。(1) In a construction method in which a cofferdam is formed in a body of water, a continuous wall is formed within the cofferdam, and the inside surrounded by the continuous wall is dried up, the cofferdam is formed between the continuous wall and the cofferdam. A temporary cofferdam construction method using a continuous wall characterized by installing a reinforcing beam in advance on either the inner or outer gap.
の間隔を置いて多段状に埋設することを特徴とする連続
壁による仮締切工法。(2) A temporary cofferdam construction method using a continuous wall, characterized in that the reinforcing beams are buried in multiple stages at predetermined intervals in the depth direction along the continuous wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28063286A JPS63134713A (en) | 1986-11-27 | 1986-11-27 | Temporary coffering construction with continuous wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28063286A JPS63134713A (en) | 1986-11-27 | 1986-11-27 | Temporary coffering construction with continuous wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63134713A true JPS63134713A (en) | 1988-06-07 |
JPH0366454B2 JPH0366454B2 (en) | 1991-10-17 |
Family
ID=17627755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP28063286A Granted JPS63134713A (en) | 1986-11-27 | 1986-11-27 | Temporary coffering construction with continuous wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63134713A (en) |
-
1986
- 1986-11-27 JP JP28063286A patent/JPS63134713A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPH0366454B2 (en) | 1991-10-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2000290936A (en) | Method and caisson for constructing bridge pier footing | |
JPS63134713A (en) | Temporary coffering construction with continuous wall | |
JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
CN205557573U (en) | Underground structure | |
JPH0381422A (en) | Caisson method | |
JP4146250B2 (en) | Open caisson bottom plate construction method | |
JPS5851092B2 (en) | Earth retaining installation method using advance shoring frame | |
JPS63181804A (en) | Breakwater and its construction and concrete caisson therefor | |
JPS5841227Y2 (en) | Element for mountain retainer | |
JPH07216903A (en) | Bulkhead caisson and construction method of bulkhead | |
JPH0329922B2 (en) | ||
JP2556380B2 (en) | Construction method of revetment structure | |
JPS5949974B2 (en) | Construction methods for foundations such as abutments and piers | |
JPH0572481B2 (en) | ||
JPS63312417A (en) | Water construction of continuous wall using steel caisson | |
JPS60246910A (en) | Method of building underwater concrete block-coupled wall body | |
SU1689521A1 (en) | Method for construction of open caisson | |
SU844693A1 (en) | Pile foundation constructing method | |
JPH0258631A (en) | Execution of caisson | |
JPH07180127A (en) | Construction method of retaining wall for water-storage dam, checkdam, etc. | |
JPH0469252B2 (en) | ||
JPH0510084A (en) | Execution method of deeper depth man hole | |
JPS5953404B2 (en) | Mound foundation construction method for underwater structures | |
JPH01268920A (en) | Caisson construction work | |
JPH0376922A (en) | Construction of continuous underground wall and steel panel therefor |