JPH0376922A - Construction of continuous underground wall and steel panel therefor - Google Patents

Construction of continuous underground wall and steel panel therefor

Info

Publication number
JPH0376922A
JPH0376922A JP20970189A JP20970189A JPH0376922A JP H0376922 A JPH0376922 A JP H0376922A JP 20970189 A JP20970189 A JP 20970189A JP 20970189 A JP20970189 A JP 20970189A JP H0376922 A JPH0376922 A JP H0376922A
Authority
JP
Japan
Prior art keywords
steel
panels
wall
concrete
muddy water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20970189A
Other languages
Japanese (ja)
Other versions
JPH0647821B2 (en
Inventor
Masayuki Okimoto
沖本 真之
Tetsuji Sonoda
園田 徹士
Susumu Tsuruoka
鶴岡 進
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd, Nippon Steel Corp filed Critical Hazama Gumi Ltd
Priority to JP20970189A priority Critical patent/JPH0647821B2/en
Publication of JPH0376922A publication Critical patent/JPH0376922A/en
Publication of JPH0647821B2 publication Critical patent/JPH0647821B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To improve efficiency of work execution by a method wherein steel panels of hollow double-walled structure formed of an inner and an outer steel plates and steel ribs are connected with one another, being kept afloat in muddy water with buoyancy given thereto, at their right and left and upper and lower ends, and are sunk with additional connections further made thereto. CONSTITUTION:A steel panel 1 is formed in a double wall structure having hollow space therein, and a box-shaped member 6 is formed therein of an inner steel plate 3, an outer steel plate 4 and a plurality of steel ribs 5 that are provided between the inner and the outer steel plates. The box-shaped member 6 is given buoyancy with lightweight filling agent filled therein or with a hollow part 10 formed therein. The steel panels 1 are then connected with one another by welding or the like applied to each of the ends on the right and the left and on the upper and the lower parts of the steel plate 4, while the panels are kept afloat in muddy water 13 in an excavated ditch. The panels 1 are then sunk with additional panels connected further to the right and the left and to the upper and the lower positions thereof, and a steel double wall body in desired shape is formed therewith as the sinking reaches a specified depth. After this, concrete is cast into a space between the outer periphery of the double wall body and the inner wall of the excavated ditch, or the muddy water in the space is solidified. Thereby a space necessary for execution of work can be made small.

Description

【発明の詳細な説明】[Detailed description of the invention] 【産業上の利用分野】[Industrial application field]

本発明は、連続地中壁の構築工法及びその壁材として使
用する鋼製パネルに関する。
The present invention relates to a construction method for a continuous underground wall and a steel panel used as the wall material.

【従来の技fi1 従来の一般の連続地中壁工法では、先行エレメントと後
行エレメントについてそれぞれ次のような作業が必要で
あった。 光丘主と)7上 ■ 先行エレメントの掘削。 ■ インターロッキングパイプ及びジゴイントバイブの
建込み。 ■ 鉄筋カゴの建込み。 ■ コンクリートの打設。 裁五]昌5ξ乙上 ■ 後行エレメントの掘削。 ■ シタインドボックスの引き抜き。 ■ 鉄筋カゴの建込み。 ■ コンクリートの打設。 【発明が解決しようする1llfil そのため、次のような問題点があった。 (1)大深度の立坑を構築する場合、例えば鉄筋カゴの
寸法が幅1m、長さ6.3m、高さ50m程度となると
、その建込みのために150 tクラスの大型クレーン
が必要であった。 (2)15Qtクラスの大型クレーンを使用する場合、
100 mx200 m程度の作業ヤードが必要であっ
た。 (3)鉄筋カゴを組み立てるためのヤードとして、生材
置場、生材加工置場、鉄筋カゴ組立架台鉄筋カゴ仮置場
等が必要なことから、約4500 m ”程度確保する
必要があった。 (4)泥水中でコンクリートを打ち継ぐので、水平継手
付近の止水性の確保が難しかった。 (5)設計上、掘削時に支保工の設置が必要であった。 (6)立坑掘削時、底盤に溜まった水を処理する排水設
備が必要であり、ポンプを掘削状況に合わせて移動しな
ければならず、作業性が悪かった。 (7)地上からポーリングしての底盤地盤改良では、施
工精度や土質状況により時々ボイリング、ヒービイング
の問題が発生することがあった。 (8)工事現場にて鉄筋加工及び鉄筋カゴの製作を行う
ので、現場毎に鉄筋工などの熟練工を集める必要があっ
た。 (9)鉄筋コンクリートのため、設計上立坑の壁厚がか
なり厚くなる傾向があった。 本発明は、大深度の連続壁を上記のような問題なく能率
的にかつ簡単にしかも作業性良く構築できるようにする
ことを目的とする。 【!I題を解決するための手段】 本発明の構築工法では、壁材として縦長の鋼製パネルを
使用する。この鋼製パネルは、中空二重壁構造、つまり
内外のll14viとその間の複数枚の綱リブとで箱形
をなし、その箱形内部に軽量充填材を充填、または空洞
部を形成して浮力を持たせである。このf!A!!lパ
ネルを掘削溝の泥水中に浮かせた状態で、鋼製パネル相
互の鋼板の左右両端及び上下両端を溶接等で連結するこ
とにより、鋼製パネルを左右及び上下に順次継ぎ足しな
がら沈降させ、所望の形体の鋼製二重壁体にして所定深
度まで沈設した後、該調製二重壁体の外周と上記掘削溝
の内壁との間に、コンクリートを打設またはその間の泥
水を固化して固定する。 鋼製パネルの継ぎ足しは千鳥状にすることが好ましい。 所定深度まで沈設後、鋼製パネルの内外の鋼板間にもコ
ンクリートを打設することができる。 鋼製パネルの外側の綱板に開口部を設ければ、鋼製パネ
ルの内外の鋼板の間に打設されたコンクリートを、該開
口部からさらに前記鋼製二重壁体の外周と前記掘削溝の
内壁との間に打設することができる。 鋼製パネルの内外の鋼板の左右両側縁に継手部を設ける
ことができる。
[Conventional Technique fi1] In the conventional general continuous underground wall construction method, the following operations were required for each of the leading and trailing elements. With light hill Lord) 7 top■ Excavation of the preceding element. ■ Installation of interlocking pipes and zigoint vibes. ■ Erection of rebar cage. ■ Placing concrete. 5] Sho 5 ξ Otsu ■ Excavation of the trailing element. ■ Pulling out the tied box. ■ Erection of rebar cage. ■ Placing concrete. [1llfil that the invention aims to solve] Therefore, there were the following problems. (1) When constructing a deep shaft, for example, if the dimensions of the rebar cage are approximately 1 m in width, 6.3 m in length, and 50 m in height, a large crane of 150 t class is required to construct it. Ta. (2) When using a 15Qt class large crane,
A working yard of approximately 100 m x 200 m was required. (3) As a yard for assembling reinforcing bars, it was necessary to secure a yard of approximately 4,500 m, as a raw material storage area, a raw material processing area, a temporary storage area for reinforcing bar cages, etc. were required. (4) ) Because the concrete was poured in muddy water, it was difficult to ensure water-tightness near the horizontal joints. (5) Due to the design, it was necessary to install shoring during excavation. (6) When excavating the shaft, water accumulated on the bottom Drainage equipment was required to treat the water, and the pump had to be moved according to the excavation situation, resulting in poor workability. Problems with boiling and heaving sometimes occurred depending on the situation. (8) Since reinforcing bars were processed and reinforcing bar cages were manufactured at the construction site, it was necessary to gather skilled workers such as reinforcing bar workers at each site. ( 9) Due to reinforced concrete, the wall thickness of the shaft tends to be quite thick due to the design.The present invention enables the construction of continuous walls of great depth efficiently, easily, and with good workability without the above-mentioned problems. [!Means for solving the problem] In the construction method of the present invention, a vertically elongated steel panel is used as a wall material.This steel panel has a hollow double wall structure, In other words, the inner and outer ll14vi and the plurality of rope ribs between them form a box shape, and the inside of the box shape is filled with a lightweight filler or a cavity is formed to give it buoyancy.This f!A!! l While the panels are floating in the muddy water of the excavation trench, the left and right ends and the top and bottom ends of the steel plates of each steel panel are connected by welding, etc., and the steel panels are successively added to the left and right and up and down, allowing them to settle down and form the desired shape. After making a steel double wall in the shape of and sinking it to a predetermined depth, concrete is poured between the outer periphery of the prepared double wall and the inner wall of the excavation trench, or the muddy water in between is solidified and fixed. It is preferable to add steel panels in a staggered manner. After sinking to a specified depth, concrete can also be poured between the steel plates on the outside and inside of the steel panels. If an opening is provided, the concrete placed between the inner and outer steel plates of the steel panel can be further poured from the opening between the outer periphery of the steel double wall and the inner wall of the excavation trench. Joints can be provided on both left and right edges of the steel plates inside and outside the steel panel.

【作  用】[For production]

w4製パネルは、軽量充填材を充填するところまで工場
で製作し、現場では組立作業を要することなくそのまま
建込むことができる。鋼製パネルは、軽量充填材または
中空部により浮力を与えられているので、泥水中に浮か
せて重量を軽減し、小型のクレーンを使用して簡便に施
工できる。鋼製バネル相互は、その内外の鋼板を溶接等
により連結できるため、施工性が非常に良く、また打ち
継ぎ部の止水性も良い、中空二重壁構造の鋼製パネルと
コンクリートとの剛性相乗効果により、構造性能も良好
になる。
W4 panels are manufactured in a factory up to the point where they are filled with lightweight filler, and can be erected as is without any assembly work required on site. Steel panels are given buoyancy by lightweight fillers or hollow sections, so they can be floated in muddy water to reduce weight and can be easily constructed using a small crane. The steel panels can be connected to each other by welding the inner and outer steel plates, making it extremely easy to construct, and also has good water-stopping properties at the joints.The hollow double-wall structure of the steel panel and concrete have synergistic rigidity. The effect also improves structural performance.

【実 施 例】【Example】

以下、本発明の実施例を図面に基づいて詳細に説明する
。 第2図は本発明の工法において使用する鋼製パネルの一
例の斜視図である。先ず、この鋼製パネル1から説明す
ると、それは二枚の鋼矢板と角鋼管とを一体化したよう
な形態になっている。すなわち、左右両側縁に断面U字
状の継手部2をそれぞれ有する内外二枚の縦長の綱板(
鋼矢板)3゜4と、これと同じ上下長さの左右2枚の鋼
リブ5とを井桁状に一体威型して、中央に箱形部(角鋼
管)6、その左右に凹部7を形成し、箱形部6内に、補
強及び浮力を与えるための発泡コンクリート8を充填し
たものである。a製パネル1を左右に継ぎ足したとき円
筒形になるように、外側の鋼板4の幅員は内側の鋼板3
より大きくなっている。 図に示す鋼製パネル1では、外側の綱板4の左右両側部
に、多数の開口部9が上下に所定の間隔をおいて設けら
れている。この開口部9は、後述するように左右の凹部
7に充填されるコンクリートを外部へ流出させるための
もので、これは全ての鋼製パネル1に設ける必要はなく
、全く設けていない鋼製パネルや左右いずれか一方側だ
け設けた鋼製パネルもあるものとする。 なお、発泡コンクリート8は多数の独立気泡を含むコン
クリートであって、例えば発泡剤で泡を作り、それとセ
メント藁ルクとを混練して箱形部6内で硬化させること
により容易に作ることができる。発泡コンクリート8で
はなく、通常のコンクリートを用いた場合には、それに
中空部10を形成して浮力を持たせる。また、同図では
箱形部6が一つのものを例示したが、第8図及び第10
図に示すように左右に複数連設したものでも良い。いず
れの形態の鋼製パネル1も工場で製作され、適宜の長さ
にして現場に持ち込まれる。 第3図は本発明の工法の一例の作業手順を示す説明図、
第1図はその途中の過程を詳細に示す斜視図である。第
3図において、(a)のようにパワーショベル11等で
後記ガイドウオールのための事前掘削を行い、(b)及
び(C)のように掘削機12で孔の掘削を繰り返し、(
dlのように泥水13が入った所定深さのリング状の溝
14を掘設する。 (d)のように鋼製パネル1をクレーン15で吊持した
状態で、鋼製パネル1同士の継手部2を溶接して鋼製パ
ネルlを左右に順次止水連結し、最下段の円筒形二重胴
ニレメン)16.を形成する。そしてこれをクレーン1
5で吊持したまま泥水13中に浮かべる9円周方向に隣
接する鋼製パネル1相互は、それらの凹部7を連続させ
て縦長の空洞を形成するが、図の例では、開口部9のあ
る鋼製パネル1と、それが無いまたは片側だけある鋼製
パネルlとを併用することから、開口部9のある空洞1
7とそれが無い空洞18とができる。!!下段の円筒形
二重網ニレメン−6,に限っては、開口部9の無い空洞
17の下端を密閉しておく。 次に、最下段の円筒形二重胴ニレメンH6+の鋼製パネ
ル1の上端に、(e)のように2段目の鋼製パネル1の
下端を溶接し、さらに2段目でも同様にクレーン15で
鋼製パネル1を吊持したまま継手部2において左右に連
結して、2段目の円筒形二重胴エレメント16.を継ぎ
足し、2段の円筒形二重胴エレメント16. 、16□
が連続した円筒形の鋼製二重壁体である二重胴殻16を
構成する。この場合、上下の鋼製パネル1の継ぎ目は強
度を考慮して千鳥配列になるように、しかも開口部9の
ある空洞17とそれが無い空洞18とがそれぞれ別々に
上下に連続するようにする。 開口部9が無い空洞18中に注水して上記二重胴殻16
を、(f)のように所要深さまでガイドリング19(第
1図)で案内して沈降させ、この状態で3段目(7)円
LJ形二重胴エレメント163を継ぎ足し、以下同様の
作業を繰り返して(5)のように、設計段数の円筒形二
重胴エレメントによる二重胴殻16を所定深度まで沈設
する。なお、二重胴殻16の重量が、その自重だけで泥
水13中に自然に沈降していく重さの場合には、例えば
エアーパッカ等により外部から浮力を与えるか、または
ガイドリング19に支持して泥水13中に浮かせた状態
に保持し、継ぎ足し作業を行う。また、第2図に示すよ
うな中空部10を設けた鋼製パネルについては、この中
空部10に注水して沈降させることができる。この場合
は、開口部9の無い空洞18は必ずしも必・要ではない
。 上記の如く所定深度までの沈設が終了したら、開口部9
が無い空洞18中の水を排水し、必要に応じてその空洞
18中に第4図のようにコンクリート20を打設し、剛
性の強化を図る。なお、21はガイドウオールである。 また、開口部9のある空洞I7中にトレミー管22から
コンクリートを注入し、そのコンクリートを開口部9を
通じて流出させ、二重胴殻16と溝14の内壁との間及
び空洞17内に第5図のようにコンクリート23を打設
するか、またはこれらの中の泥水を固化させ、二重胴殻
16を地中に固定する。これによって、鋼製の二重壁構
造をなす全体円筒形の連続地中壁24が構築される。 次に、第6図に示すようにこの連続地中壁24の所要箇
所に残しておいた空間部(空洞)25から、地盤改良用
の水平ポーリング装置26及び地上への配管27を設置
し、連続地中壁24で囲まれた底盤28の地盤改良を行
う。 この後、第7図に示すように連続地中壁24で囲まれた
地盤を地上から掘削する。この場合、連続地中壁24の
鋼製内壁に垂直連続排土装置(トレリフタ)29及び自
動掘削機30を取り付けて無人施工することができる。 また、底盤28の水の処理に関しては、空間部25内に
排水ポンプ31を設置し、連続地中壁24の鋼製内壁に
設けたストレーナ32を通して吸い出す、さらに、連続
地中壁24の鋼製内壁には、エレベータ33や階段等を
設けることもできる。 上記の実施例では、リング状に連続した溝14を掘削し
た後、その中に、円筒形に連結した鋼製パネル1を順次
上に継ぎ足しながら沈設したが、溝を始めからリング状
に連続させないで円周分割して掘削し、その掘削した溝
に所定深度まで調製パネル1を沈設した後、次の溝の掘
削と鋼製パネルlの沈設を交互に繰り返して最終的に円
筒形に連続させる方法もある。 第8図及び第9図はその一例で、所要の幅員の溝34を
掘削した後、その溝34内にクレーンで吊持した第1番
目の鋼製パネルhを挿入し、これを泥水中に浮かせて例
えばガイドリング35で所要の深さに固定しておき、次
の第2番目の鋼製パネル1、を継手部2において左側ま
たは右側に継ぎ、同じ要領で第3番目の鋼製パネルl、
を継ぐ、このようにして連結された3枚の鋼製パネル1
.〜工、を1エレメントとして、その上に次のエレメン
トを順次継ぎ足す。所定深さまで沈設したら、両側の鋼
製パネル11.1sの継手部2付近にモルタルジャケッ
ト36を設置し、該モルタルジャケット36で囲まれた
間隙37の泥水を固化させる。これによって1区画分の
調製二重壁体がI威される。 モルタルジャケット36の遮蔽具38は、吊治具39、
吊ロー140、クレーンフック41を使用して泥水が固
化するまで吊持しておく、泥水固化後、次の隣接する溝
を掘削し、この溝内において上記と同様に鋼製パネルl
、〜l、を連結し、さらに上に継ぎ足す、この場合、既
に設置させている1区画分の鋼製二重壁体と継手部2で
連結する。以下、溝の掘削と調製パネル1+”−1sの
連結・継ぎ足しを交互に繰り返し、円筒形に連続した連
続地中壁を構築する。 第1O図及び第11図は同様に円周分割による方法であ
るが、第8図及び第9図に示した例とは継手部2の処理
が異なる。すなわち、両端の鋼製パネルII、Ijの継
手部2にグl↓−ス等を詰めてここでは泥水固化が生じ
ないようにしておき、1区画分の鋼製二重壁体をfJI
戒後、その全周の泥水42を固化させる。鋼製二重壁体
を固定した後、第11図のように両端の鋼製パネル11
,13の継手部2について、それをガイドとしてジ、S
7トクリーナ等の洗浄機43を取り付は移動させ、該継
手部2の周囲の泥水固化材を撤去する。 なお、溝の掘削時に何等かのトラブルで掘削部をそのま
まの状態で長期間維持する必要がある場合、または掘削
部が崩壊しやすい場合には、撹拌によりゲル状態を解放
する性質のゲル化剤(いわゆるケミカルゲル薬)を使用
して泥水をゲル化して安定させると良い。そのゲル化泥
水は適時に撹拌機で撹拌して元の泥水に戻す。この場合
、撹拌機は鋼製二重壁体に取り付けることができる。 また、本発明は全体円筒形の連続地中壁を横築する場合
に限らず、矩形や楕円形などの他の形状の連続地中壁を
構築する場合にも広く適用できるものである。
Embodiments of the present invention will be described in detail below with reference to the drawings. FIG. 2 is a perspective view of an example of a steel panel used in the construction method of the present invention. First, let me explain this steel panel 1. It has a form in which two steel sheet piles and a square steel pipe are integrated. That is, there are two vertically long rope plates (an inner and outer one) each having a U-shaped cross-sectional joint part 2 on the left and right side edges.
A steel sheet pile) 3゜4 and two left and right steel ribs 5 of the same vertical length are integrally molded into a cross-shaped structure, with a box-shaped part (square steel pipe) 6 in the center and recesses 7 on the left and right sides. The box-shaped portion 6 is filled with foamed concrete 8 for reinforcement and buoyancy. The width of the outer steel plate 4 is equal to the width of the inner steel plate 3 so that when the panels 1 made of A are added to the left and right, it becomes cylindrical.
It's bigger. In the steel panel 1 shown in the figure, a large number of openings 9 are provided on both left and right sides of the outer rope plate 4 at predetermined intervals vertically. This opening 9 is for letting the concrete filled in the left and right recesses 7 flow out to the outside, as will be described later. It is not necessary to provide this in all steel panels 1, and it is not necessary to provide this in all steel panels 1. There are also steel panels that are installed only on either the left or right side. Note that the foamed concrete 8 is concrete containing a large number of closed cells, and can be easily made by, for example, creating foam with a foaming agent, kneading the foam with cement straw, and hardening it within the box-shaped portion 6. . When ordinary concrete is used instead of foamed concrete 8, a hollow part 10 is formed in it to give it buoyancy. In addition, although the figure shows an example in which the box-shaped portion 6 is one, FIGS. 8 and 10
As shown in the figure, a plurality of them may be arranged side by side on the left and right. Steel panels 1 of any form are manufactured at a factory and brought to the site with appropriate lengths. FIG. 3 is an explanatory diagram showing the working procedure of an example of the construction method of the present invention;
FIG. 1 is a perspective view showing the process in detail. In FIG. 3, as shown in (a), preliminary excavation for the guide wall described later is performed using a power shovel 11, etc., and as shown in (b) and (C), holes are repeatedly excavated using an excavator 12.
A ring-shaped groove 14 of a predetermined depth filled with muddy water 13 is dug like dl. As shown in (d), with the steel panels 1 suspended by the crane 15, the joints 2 between the steel panels 1 are welded to watertightly connect the steel panels 1 to the left and right, and the bottom cylinder 16. form. And this is crane 1
The steel panels 1 that are adjacent to each other in the circumferential direction are suspended in muddy water 13 while being suspended by 5, and their recesses 7 are continuous to form a vertically elongated cavity. Since a certain steel panel 1 is used in combination with a steel panel L without it or with only one side, a cavity 1 with an opening 9 is created.
7 and a cavity 18 without it are formed. ! ! Only in the lower cylindrical double mesh elmmen 6, the lower end of the cavity 17 without the opening 9 is sealed. Next, as shown in (e), weld the lower end of the second tier steel panel 1 to the upper end of the steel panel 1 of the lowest cylindrical double-shelled Niremen H6+, and then do the same with the crane on the second tier. 15, the steel panel 1 is suspended and connected to the left and right sides at the joint 2, and a second stage cylindrical double-barrel element 16. 16. , 16□
constitutes a double shell 16 which is a continuous cylindrical steel double wall body. In this case, the seams between the upper and lower steel panels 1 should be arranged in a staggered manner to ensure strength, and the cavities 17 with openings 9 and the cavities 18 without them should be vertically continuous, respectively. . Water is poured into the cavity 18 that does not have an opening 9, and the double shell 16 is
is guided by the guide ring 19 (Fig. 1) to the required depth as shown in (f) and allowed to settle. In this state, the third stage (7) circular LJ-shaped double-barrel element 163 is added, and the same operation is carried out thereafter. By repeating the steps (5), the double shell 16 made up of the designed number of cylindrical double shell elements is sunk to a predetermined depth. If the weight of the double shell 16 is such that it will naturally settle into the muddy water 13 due to its own weight, buoyancy may be applied from the outside using an air packer or the like, or it may be supported by the guide ring 19. and keep it floating in the muddy water 13, and perform the replenishment work. Further, for a steel panel provided with a hollow part 10 as shown in FIG. 2, water can be poured into the hollow part 10 to cause it to settle. In this case, the cavity 18 without the opening 9 is not necessarily required. After completing the sinking to the predetermined depth as described above, the opening 9
Water in the cavity 18 where there is no water is drained, and if necessary, concrete 20 is placed in the cavity 18 as shown in FIG. 4 to strengthen the rigidity. Note that 21 is a guide wall. Also, concrete is injected from the tremie pipe 22 into the cavity I7 with the opening 9, and the concrete flows out through the opening 9, and the fifth As shown in the figure, concrete 23 is poured or muddy water therein is solidified to fix the double shell 16 underground. As a result, a continuous underground wall 24 having a double wall structure made of steel and having an overall cylindrical shape is constructed. Next, as shown in FIG. 6, a horizontal poling device 26 for soil improvement and piping 27 to the ground are installed from the spaces (cavities) 25 left at required locations on this continuous underground wall 24, The ground of the bottom bed 28 surrounded by the continuous underground wall 24 is improved. Thereafter, as shown in FIG. 7, the ground surrounded by continuous underground walls 24 is excavated from the ground. In this case, unmanned construction can be performed by attaching a vertical continuous earth removal device (trelifter) 29 and an automatic excavator 30 to the steel inner wall of the continuous underground wall 24. Regarding the treatment of water in the bottom panel 28, a drainage pump 31 is installed in the space 25, and the water is sucked out through a strainer 32 provided on the steel inner wall of the continuous underground wall 24. An elevator 33, stairs, etc. can also be provided on the inner wall. In the above example, after excavating a continuous ring-shaped groove 14, the steel panels 1 connected in a cylindrical shape were sunk into the groove while being successively added to the top, but the groove was not made continuous in a ring-shape from the beginning. Divided into circumferential sections, the prepared panels 1 are deposited in the excavated trenches to a predetermined depth, and then the next trench is excavated and the steel panels 1 are deposited alternately to form a continuous cylindrical shape. There is a way. Figures 8 and 9 are examples of this. After excavating a groove 34 of the required width, the first steel panel h suspended by a crane is inserted into the groove 34, and then submerged in muddy water. Float it and fix it at a required depth using, for example, a guide ring 35, then connect the next second steel panel 1 to the left or right side at the joint 2, and then connect the third steel panel l in the same way. ,
Three steel panels 1 connected in this way
.. ~Work is taken as one element, and the following elements are successively added on top of it. After sinking to a predetermined depth, a mortar jacket 36 is installed near the joint 2 of the steel panels 11.1s on both sides, and the muddy water in the gap 37 surrounded by the mortar jacket 36 is solidified. As a result, one compartment of the prepared double-walled body is destroyed. The shielding tool 38 of the mortar jacket 36 includes a hanging jig 39,
Suspend the muddy water using a hanging row 140 and a crane hook 41 until it solidifies. After the muddy water solidifies, excavate the next adjacent trench, and install steel panels in this trench in the same manner as above.
, ~l, and then add it to the top. In this case, it is connected to the steel double wall of one section that has already been installed at the joint part 2. Thereafter, a continuous cylindrical underground wall is constructed by alternately repeating the excavation of trenches and the connection and addition of prepared panels 1+''-1s. However, the processing of the joint part 2 is different from the examples shown in Figs. To prevent muddy water from solidifying, one section of the steel double-walled body was
After the precept, the muddy water 42 around the entire circumference is solidified. After fixing the steel double wall, as shown in Fig. 11, the steel panels 11 at both ends are fixed.
, 13, using it as a guide, di, S
7. The washer 43 such as a toner cleaner is installed and moved, and the muddy water solidifying material around the joint portion 2 is removed. In addition, if there is a problem when excavating a trench and it is necessary to maintain the excavated part as it is for a long period of time, or if the excavated part is likely to collapse, use a gelling agent that releases the gel state by stirring. It is best to use a so-called chemical gel to turn the muddy water into a gel and stabilize it. The gelled mud water is stirred with an agitator at appropriate times to return it to its original state. In this case, the stirrer can be mounted on a steel double wall. Further, the present invention is widely applicable not only to the horizontal construction of continuous underground walls having a cylindrical shape as a whole, but also to the construction of continuous underground walls of other shapes such as rectangular or elliptical shapes.

【発明の効果】【Effect of the invention】

本発明の効果を以下に列記する。 ■ 重量のある鉄筋カゴの代わりに中空二重壁構造の鋼
製パネルを使用し、これを泥水中に浮かせて継ぎ足して
いくので、従来は150 tクラスのクレーンが必要で
あったところ、50tクラスのクレーンでも作業が可能
であり、大深度の連続地中壁を能率的に施工でき、かつ
作業スペースも小さくて済む。 ■ 鋼製パネルは工場で製作でき、しかも泥水中への沈
降に伴い順次継ぎ足すことができるので、鉄筋カゴの現
場組立のような大きな作業スペースは不要で、その分だ
けでも作業スペースを2〜3割程度縮小できる。 ■ 構築された壁の中空部を利用して排水設備や底盤改
良用水平ポーリング設備を設置できる。 ■ 鋼製パネルは工場で製作するので、均一な品質の壁
体ができる。 ■ 継手部は完全溶接できるので、連壁として完全な止
水性が確保できる。 ■ 鋼製パネルの製作は現場作業とは別工程でできるの
で、工事現場での工程を約2分の1に短縮できる。 ■ 階段やエレベータ等の昇降設備を、連続地中壁の鋼
製内壁を利用して正確かつ確実に取り付けることができ
る。 ■ 壁・躯体継手がある場合、所定の位置に配置できる
。 ■ 壁にかかる応力を鋼製連壁の円周方向にも伝達させ
、構造物全体で応力を受ける形とし、切梁・腹起しを使
用しないで、短期間で掘削ができる。
The effects of the present invention are listed below. ■ Hollow double-walled steel panels are used instead of heavy reinforcing cages, which are floated in muddy water and added to the structure. The work can be done even with a crane, allowing efficient construction of continuous underground walls at great depths, and requiring only a small work space. ■ Steel panels can be manufactured in a factory and can be added to as they settle in muddy water, so there is no need for a large work space like that required for on-site assembly of reinforcing cages, and the work space can be saved by 2~ It can be reduced by about 30%. ■ The hollow part of the constructed wall can be used to install drainage equipment and horizontal polling equipment for improving the base. ■ Since the steel panels are manufactured in a factory, the walls can be of uniform quality. ■ Since the joints can be completely welded, complete water-tightness can be ensured as a continuous wall. ■ Manufacturing of steel panels can be done in a separate process from on-site work, so the process at the construction site can be shortened by about half. ■ Lifting equipment such as stairs and elevators can be installed accurately and reliably using the steel inner wall of the continuous underground wall. ■ If there is a wall/frame joint, it can be placed in the specified position. ■ The stress applied to the wall is also transmitted in the circumferential direction of the steel continuous wall, so that the entire structure receives the stress, allowing excavation to be carried out in a short period of time without using struts or uprights.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の工法の一例の斜視図、第2図は本発明
による鋼製パネルの一例の斜視図、第3図(al〜(ロ
)は本発明の工法の一例の作業手順を示す説明図、第4
図はそれにおけるコンクリート打設状態の断面図、第5
図はコンクリート打設及び泥水固化後の状態を示す平面
図、第6図は連続地中壁構築後の底盤の地盤改良状態を
示す断面図、第7図は立坑掘削状態を示す断面図、第8
図及び第9図は本発明の工法の他の例の平面図及び断面
図、第1O図及び第11図はさらに別の例の平面図であ
る。 1・・・・・・鋼製パネル、2・・・・・・継手部、3
.4・・・・・・内外の鋼板、5・・・・・・鋼リブ、
6・・・・・・箱形部、8・・・・・・発泡コンクリー
ト、9・・・・・・開口部、1o・・・・・・中空部、
13・・・・・・泥水、14.34・・・・・・溝。
Fig. 1 is a perspective view of an example of the construction method of the present invention, Fig. 2 is a perspective view of an example of a steel panel according to the invention, and Figs. Explanatory diagram showing, No. 4
The figure is a cross-sectional view of the state of concrete pouring.
Figure 6 is a plan view showing the state after concrete placement and mud solidification, Figure 6 is a sectional view showing the state of soil improvement of the bottom bed after construction of a continuous underground wall, Figure 7 is a sectional view showing the state of shaft excavation, 8
9 and 9 are a plan view and a sectional view of another example of the construction method of the present invention, and FIGS. 10 and 11 are plan views of still another example. 1...Steel panel, 2...Joint part, 3
.. 4... Inner and outer steel plates, 5... Steel ribs,
6... Box-shaped part, 8... Foamed concrete, 9... Opening, 1o... Hollow part,
13...Muddy water, 14.34...Ditch.

Claims (1)

【特許請求の範囲】 1、内外の鋼板とその間の複数枚の鋼リブとで箱形をな
す縦長の鋼製パネルの箱形内部に軽量充填材を充填、ま
たは空洞部を形成して浮力を持たせ、該鋼製パネルを掘
削溝の泥水中に浮かせた状態で、鋼製パネル相互の鋼板
の左右両端及び上下両端を溶接等で連結することにより
、鋼製パネルを左右及び上下に順次継ぎ足しながら沈降
させ、所望の形体の鋼製二重壁体にして所定深度まで沈
設した後、該鋼製二重壁体の外周と上記掘削溝の内壁と
の間に、コンクリートを打設またはその間の泥水を固化
することを特徴とする連続地中壁の構築工法。 2、前記鋼製パネルを千鳥状に継ぎ足しながら沈降させ
ることを特徴とする請求項1記載の連続地中壁の構築工
法。 3、前記鋼製二重壁体にして所定深度まで沈設した後、
鋼製パネルの内外の鋼板の間にコンクリートを打設する
ことを特徴とする請求項1または2に記載の連続地中壁
の構築工法。 4、前記鋼製パネルの外側の鋼板に開口部を設け、鋼製
パネルの内外の鋼板の間に打設されたコンクリートを、
該開口部からさらに前記鋼製二重壁体の外周と前記掘削
溝の内壁との間に打設することを特徴とする請求項3記
載の連続地中壁の構築工法。 5、縦長の内外二枚の鋼板を複数枚の鋼リブで連結して
箱状部を形成し、該箱状部内に軽量充填材を充填しまた
は空洞部を形成して浮力を持たせ、上記内外の鋼板の左
右両側縁に継手部を設け、さらに外側の鋼板にコンクリ
ート流出用の開口部を設けたことを特徴とする連続地中
壁構築用鋼製パネル。
[Scope of Claims] 1. Buoyancy is achieved by filling the box-shaped interior of a vertically elongated steel panel with inner and outer steel plates and a plurality of steel ribs therebetween, or by forming a cavity. With the steel panels floating in the muddy water of the excavation trench, the left and right ends and the top and bottom ends of the steel plates of each steel panel are connected by welding, etc., and the steel panels are successively added left and right and up and down. After settling the steel double wall to a predetermined depth, concrete is poured between the outer periphery of the steel double wall and the inner wall of the excavation trench. A continuous underground wall construction method characterized by solidifying muddy water. 2. The method for constructing a continuous underground wall according to claim 1, characterized in that the steel panels are submerged while being added in a staggered manner. 3. After making the steel double-walled body and sinking it to a predetermined depth,
3. The method for constructing a continuous underground wall according to claim 1, wherein concrete is placed between the inner and outer steel plates of the steel panel. 4. An opening is provided in the outer steel plate of the steel panel, and concrete is placed between the inner and outer steel plates of the steel panel.
4. The method for constructing a continuous underground wall according to claim 3, further comprising pouring from the opening between the outer periphery of the steel double wall and the inner wall of the excavated trench. 5. Connect two vertically long inner and outer steel plates with a plurality of steel ribs to form a box-shaped part, fill the box-shaped part with a lightweight filler or form a cavity to give it buoyancy, and A steel panel for constructing a continuous underground wall, characterized in that joints are provided on the left and right edges of the inner and outer steel plates, and openings for concrete to flow out are provided in the outer steel plates.
JP20970189A 1989-08-15 1989-08-15 Construction method of continuous underground wall and steel panel for continuous underground wall construction Expired - Fee Related JPH0647821B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20970189A JPH0647821B2 (en) 1989-08-15 1989-08-15 Construction method of continuous underground wall and steel panel for continuous underground wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20970189A JPH0647821B2 (en) 1989-08-15 1989-08-15 Construction method of continuous underground wall and steel panel for continuous underground wall construction

Publications (2)

Publication Number Publication Date
JPH0376922A true JPH0376922A (en) 1991-04-02
JPH0647821B2 JPH0647821B2 (en) 1994-06-22

Family

ID=16577205

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20970189A Expired - Fee Related JPH0647821B2 (en) 1989-08-15 1989-08-15 Construction method of continuous underground wall and steel panel for continuous underground wall construction

Country Status (1)

Country Link
JP (1) JPH0647821B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0649524U (en) * 1992-12-02 1994-07-08 房夫 坂野 Connecting wall built on the near line

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013163906A (en) * 2012-02-10 2013-08-22 Giken Seisakusho Co Ltd Steel pipe pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0649524U (en) * 1992-12-02 1994-07-08 房夫 坂野 Connecting wall built on the near line

Also Published As

Publication number Publication date
JPH0647821B2 (en) 1994-06-22

Similar Documents

Publication Publication Date Title
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN105649094B (en) A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
CN211873023U (en) Foundation pit supporting device
JPH0376922A (en) Construction of continuous underground wall and steel panel therefor
CN111119200A (en) Foundation pit supporting device
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JP4159148B2 (en) Construction method of shaft
JP7096469B1 (en) Small cross-section underground continuous wall
JP4146250B2 (en) Open caisson bottom plate construction method
CN115467321B (en) Two-wall-in-one multi-cavity type steel reinforced concrete composite structure and construction method thereof
JP7398609B2 (en) Concrete frame construction method and underground structure
JPH01315520A (en) Underground outer wall constructing method for superstructure
JPH07216903A (en) Bulkhead caisson and construction method of bulkhead
JP2002061204A (en) Construction method of underground structural body
JPH10152852A (en) Method of building underground structure and structural member used therein
JPH10152853A (en) Method of building underground structure and structure member used therein
CN113373936A (en) Assembly type structure and construction method thereof
JP3248010B2 (en) Method of manufacturing concrete frame
CN111827267A (en) Underground continuous wall construction method
JPH06108459A (en) Construction of underground continuous wall
JPS62111028A (en) Construction of underground structure
JP2021143554A (en) Construction method of underground structure
JPH06194485A (en) Construction of nuclear power plant building
CN112942312A (en) T-shaped underground diaphragm wall construction process

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees