JPH0469252B2 - - Google Patents
Info
- Publication number
- JPH0469252B2 JPH0469252B2 JP60243677A JP24367785A JPH0469252B2 JP H0469252 B2 JPH0469252 B2 JP H0469252B2 JP 60243677 A JP60243677 A JP 60243677A JP 24367785 A JP24367785 A JP 24367785A JP H0469252 B2 JPH0469252 B2 JP H0469252B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- slit
- box
- construction
- underwater
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 claims description 21
- 238000005192 partition Methods 0.000 claims description 8
- 239000004567 concrete Substances 0.000 claims description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 239000007788 liquid Substances 0.000 description 3
- 239000011150 reinforced concrete Substances 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000000087 stabilizing effect Effects 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- -1 earth Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、水中構造物の施工方法に関する。[Detailed description of the invention] [Industrial application field] The present invention relates to a construction method for an underwater structure.
一般に、海の中や河川内に橋脚等の構造物を鉄
筋コンクリートによつて構築する場合、その多く
は築島上および築島下部で行なわれる。このため
本工事の前に大規模な築島を構築する必要があつ
た。
Generally, when constructing structures such as bridge piers in the sea or in rivers using reinforced concrete, most of the construction is done on or below Tsukishima. For this reason, it was necessary to construct a large-scale rocky island before starting the main construction work.
このため築島の構築と水中構造物の施工後築島
部分の撤去に相当の工期と工事費がかかり、工期
の長期化と工事費の肥大化が避けられないという
欠点があつた。
For this reason, it took a considerable amount of time and construction cost to construct the Tsukishima and remove the part of the Tsukishima after constructing the underwater structure, which had the drawback of unavoidably prolonging the construction period and increasing the construction cost.
この発明は、前記従来の問題点を解消するため
に提案されたもので、工期の大幅な短縮化および
工事費の大幅な低減化が図れる水中構造物の施工
方法を提供することを目的とする。 This invention was proposed in order to solve the above-mentioned conventional problems, and aims to provide a construction method for underwater structures that can significantly shorten the construction period and significantly reduce construction costs. .
この発明の水中構造物の施工方法は外壁と内壁
とから二重壁を形成し、函体の周縁部に上下方向
に連続するスリツトを有しかつ所要位置に外壁と
内壁とを補強する隔壁を設けた函体を海底に据付
け固定し、続いて前記スリツトをガイドとする掘
削機によつて函体のスリツト直下の海底地盤中に
所定深さの削孔を形成し、この削孔およびスリツ
ト内に鉄筋を配筋し、続いてコンクリートを打設
してスリツトおよびその下方地盤中に連続壁を造
成し、所定規模の水中構造物を構築しようとする
ものである。
The method for constructing an underwater structure of the present invention is to form a double wall with an outer wall and an inner wall, and to have a vertically continuous slit on the periphery of the box, and a partition wall to reinforce the outer wall and the inner wall at a predetermined position. The provided box is installed and fixed on the seabed, and then a hole of a predetermined depth is formed in the seabed ground directly below the slit of the box using an excavator using the slit as a guide. The idea is to construct an underwater structure of a predetermined size by placing reinforcing bars in the slit and then pouring concrete to create a continuous wall in the slit and the ground below it.
以下、この発明の施工方法を順を追つて説明す
る。
Hereinafter, the construction method of the present invention will be explained step by step.
ドツグ等において、所定規模の函体1を鋼材
または鉄筋コンクリートによつて形成する。 In a dog or the like, a box 1 of a predetermined size is formed of steel or reinforced concrete.
函体1は構築される水中構造物の規模により
所定径を有する矩形断面の筒状に形成するとと
もに外壁2と内壁3とから二重壁に形成する。
外壁2と内壁3間には所定幅のスリツト4を函
体1の周縁部上下方向に連続して形成し、スリ
ツト4の下端部には底5を形成する。なお、底
5を形成しない場合もある。 The box 1 is formed into a cylindrical shape with a rectangular cross section having a predetermined diameter depending on the scale of the underwater structure to be constructed, and is also formed into a double wall with an outer wall 2 and an inner wall 3.
A slit 4 of a predetermined width is formed continuously between the outer wall 2 and the inner wall 3 in the vertical direction at the peripheral edge of the box 1, and a bottom 5 is formed at the lower end of the slit 4. Note that the bottom 5 may not be formed in some cases.
また、スリツト4には隔壁6を上下方向に連
続して形成することにより外壁2および内壁3
を補強する。隔壁6は外壁2および内壁3と一
体若しくは取外し自在に取付ける。隔壁6を取
外し自在に取付けるにはたとえば外壁2および
内壁3の内側にこれらの上下方向に連続するリ
ツプ溝を設け、このリツプ溝にH形断面の隔壁
6をスライド式に取付ける。 In addition, by forming partition walls 6 continuously in the vertical direction in the slit 4, the outer wall 2 and the inner wall 3
Reinforce. The partition wall 6 is attached to the outer wall 2 and the inner wall 3 integrally or detachably. To removably attach the partition wall 6, for example, a lip groove is provided inside the outer wall 2 and the inner wall 3, which are continuous in the vertical direction, and the partition wall 6 having an H-shaped cross section is slidably attached to this lip groove.
一方、海中構造物の構築現場では従来工法に
よつて水底地盤Aを所定深さに掘削するととも
にその掘削底面を可能な限り水平にする。 On the other hand, at a construction site for an underwater structure, the underwater ground A is excavated to a predetermined depth using conventional construction methods, and the bottom surface of the excavation is made as horizontal as possible.
続いて、完成ずみの函体1を構築現場まで洩
航する。この場合、函体1のスリツト4および
中央部の中央部を封することにより函体1に浮
力を付けることもできる。 Next, the completed box 1 is sailed to the construction site. In this case, buoyancy can be imparted to the box 1 by sealing the slit 4 and the central portion of the box 1.
また、底なしの函体1は台船に乗せて移送
し、クレーン船によつて沈設する。 Further, the bottomless box 1 is transported on a barge and is sunk by a crane ship.
続いて、函体1を沈め前記海底地盤Aに据付
けるとともに函体1の周辺部を埋めもどすこと
により函体1を海底に固定する。 Subsequently, the box 1 is sunk and installed on the seabed ground A, and the peripheral portion of the box 1 is buried back to fix the box 1 to the seabed.
続いて、スリツト4をガイドする掘削機(図
省略)によつてスリツト4直下の下方海底地盤
A中に所定深さの削孔7を形成する。底5を有
する構造では削孔7の掘削に際し、スリツト4
の底5は掘削機によつて突き破り、かつ隔壁6
直下の海底地盤も併せて掘削するものとする。
最終的に削孔7はスリツト4の形状に対応して
四角形等の連続した溝状に掘削する。また、削
孔7の側面を可能な限り傷めないように安定液
(泥水)を使用するものとする。 Subsequently, an excavator (not shown) that guides the slit 4 forms a hole 7 of a predetermined depth in the lower seabed ground A directly below the slit 4. In the structure with the bottom 5, when drilling the hole 7, the slit 4
The bottom 5 is pierced by an excavator and the bulkhead 6
The seabed ground immediately below will also be excavated.
Finally, the hole 7 is drilled in a continuous groove shape, such as a rectangular shape, corresponding to the shape of the slit 4. In addition, a stabilizing liquid (muddy water) shall be used so as not to damage the side surface of the drilled hole 7 as much as possible.
続いてスリツト4および削孔7内に必要量の
鉄筋かご(図省略)を配筋し、続いてコンクリ
ート8を打設してスリツトおよびその下方地盤
中に地中連続壁を造成する。 Next, a required amount of reinforcing steel cages (not shown) are arranged in the slit 4 and the drilled hole 7, and then concrete 8 is poured to create an underground continuous wall in the slit and the ground below it.
また、構造物の用途により函体1の中空部9
を砕石や土砂あるいはコンクリートを充てんす
ることにより完全に埋める。 Also, depending on the purpose of the structure, the hollow part 9 of the box 1 may be
Completely fill with crushed stone, earth, or concrete.
以上の施工順序によつて所定規模の水中構造
物を構築することができる。 By the above construction order, an underwater structure of a predetermined scale can be constructed.
なお、函体1は矩形断面に限られるものでは
なく円形や多角形断面でもよい。また、構築現
場は海洋に限られるものではなく湖や河川でも
可能である。施工時に隔壁6を順次撤去し−
断面でも相隣りあうスリツト4をつなぐこと
もできる。 Note that the box 1 is not limited to a rectangular cross section, but may have a circular or polygonal cross section. Furthermore, the construction site is not limited to the ocean, but can also be a lake or river. During construction, partition walls 6 were removed one by one.
It is also possible to connect adjacent slits 4 in cross section.
この発明は、以上の構成からなるので、以下の
効果を奏する。
Since the present invention has the above configuration, it has the following effects.
仮設構造物である築島の構築および水中構造
物の施工後築島の撤去作業が全くないので、工
期の大幅な短縮化および工事費の大幅な低減化
が図れる。しかも水上作業が短期間ですむの
で、暴風雨にさらされることも少なく作業の安
全性が図れる。 Since there is no work to construct the temporary structure of the Tsukishima and to remove the Tsukishima after construction of the underwater structure, the construction period can be significantly shortened and the construction cost can be significantly reduced. Moreover, since the work on the water can be completed in a short period of time, there is less exposure to storms and work safety can be ensured.
水底地盤の掘削のため安全液を使用しても外
壁と内壁からなる二重壁のスリツト内で掘削す
るので外部に安定液および掘削土砂が流出する
心配がなく環境汚染対策の向上が図れる。 Even if a safety liquid is used to excavate underwater ground, since the excavation is carried out within a double-walled slit consisting of an outer wall and an inner wall, there is no fear that the stabilizing liquid and excavated soil will flow out to the outside, and environmental pollution countermeasures can be improved.
スリツトおよび下方地盤中に鉄筋コンクリー
トの連続壁が一体的に造成され、水中構造物と
なるので所定規模の水中構造が確実に施工で
き、しかも施工中の占有面積が小さいので作業
性がよい。 A continuous wall of reinforced concrete is integrally constructed in the slit and the lower ground, making it an underwater structure, so an underwater structure of a predetermined scale can be reliably constructed, and the area occupied during construction is small, making it easy to work.
第1図〜第3図はこの発明の一実施例を示した
もので、第1図は函体の設置状態を示す縦断面
図、第2図および第3図は第1図における−
線、−線断面図である。
1……函体、2……外壁、3……内壁、4……
スリツト、5……底、6……隔壁、7……削孔、
8……コンクリート、9……中空部。
1 to 3 show an embodiment of the present invention. FIG. 1 is a vertical sectional view showing the installation state of the box, and FIGS. 2 and 3 are - in FIG. 1.
It is a line, - line sectional view. 1...Box, 2...Outer wall, 3...Inner wall, 4...
Slit, 5...Bottom, 6...Partition wall, 7...Drilling,
8...Concrete, 9...Hollow part.
Claims (1)
縁部に上下方向に連続するスリツトを有し、かつ
所要位置に外壁と内壁とを補強する隔壁を設けた
れ函体を水底に据付け、固定し、続いて前記スリ
ツトをガイドとする掘削機によつて函体のスリツ
ト直下の水底地盤中に所定深さの削孔を形成し、
この削孔およびスリツト内に鉄筋を配筋し、続い
てコンクリートを打設してスリツトおよびその下
方地盤中に連続壁を造成することを特徴とする水
中構造物の施工方法。1 A double wall is formed by an outer wall and an inner wall, a vertically continuous slit is provided at the periphery of the box, and partition walls are provided at required positions to reinforce the outer wall and inner wall, and the box is installed on the bottom of the water. , and then using an excavator using the slit as a guide to form a hole to a predetermined depth in the underwater ground directly below the slit of the box,
A construction method for an underwater structure characterized by placing reinforcing bars in the drilled holes and slits, and then pouring concrete to create a continuous wall in the slits and the ground below them.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24367785A JPS62107114A (en) | 1985-10-30 | 1985-10-30 | Construction work of underwater structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24367785A JPS62107114A (en) | 1985-10-30 | 1985-10-30 | Construction work of underwater structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62107114A JPS62107114A (en) | 1987-05-18 |
JPH0469252B2 true JPH0469252B2 (en) | 1992-11-05 |
Family
ID=17107344
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24367785A Granted JPS62107114A (en) | 1985-10-30 | 1985-10-30 | Construction work of underwater structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62107114A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111441376B (en) * | 2020-04-03 | 2022-03-18 | 中交第四航务工程勘察设计院有限公司 | Round caisson with balance mechanism and use method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5016887A (en) * | 1973-06-14 | 1975-02-21 | ||
JPS58146619A (en) * | 1982-02-24 | 1983-09-01 | Ohbayashigumi Ltd | Construction of continuous wall under water |
-
1985
- 1985-10-30 JP JP24367785A patent/JPS62107114A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5016887A (en) * | 1973-06-14 | 1975-02-21 | ||
JPS58146619A (en) * | 1982-02-24 | 1983-09-01 | Ohbayashigumi Ltd | Construction of continuous wall under water |
Also Published As
Publication number | Publication date |
---|---|
JPS62107114A (en) | 1987-05-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102561371B (en) | Steel caisson enclosure structure at island-tunnel combination part and construction method thereof | |
JP2005330718A (en) | Construction method of underwater foundation | |
JPH06146305A (en) | Underwater foundation and installation method thereof | |
JPS58143023A (en) | Caisson for pile supporting type breakwater | |
JP2000290936A (en) | Method and caisson for constructing bridge pier footing | |
JPH0469252B2 (en) | ||
KR20140092217A (en) | Construction method of the pier with the working bardge | |
JPH03275812A (en) | Foundation construction method for soft sea bottom ground | |
JP4132320B2 (en) | Foundation construction method | |
JPS6340024A (en) | Pile-type caisson work | |
EP1793047B1 (en) | Method for building a shallow tunnel at a water area bottom and a system for temporally dewatering a bottom area | |
JP2815492B2 (en) | How to build an underwater foundation | |
JPS5991228A (en) | Pit excavation work using caisson | |
JPH0323689B2 (en) | ||
JP3704613B2 (en) | Construction method for underground structures | |
JPH07216903A (en) | Bulkhead caisson and construction method of bulkhead | |
JPH09273382A (en) | Jacking machine for underwater tunnel | |
JP2556380B2 (en) | Construction method of revetment structure | |
JP3254546B2 (en) | How to construct a waterway crossing tunnel | |
KR100560847B1 (en) | Method for constructing a light beacon by excavating tube-type flute | |
JPH05156607A (en) | Construction method for temporary cutoff | |
SU633982A1 (en) | Method of constructing low pilework on terrain covered with water | |
JPS63236823A (en) | Earthquake-proof reinforcing work for existing caisson | |
JP2002129588A (en) | Undersea tunnel connecting method | |
JPS60233213A (en) | Lower structure of bridge beam and its construction |