JPS6340024A - Pile-type caisson work - Google Patents
Pile-type caisson workInfo
- Publication number
- JPS6340024A JPS6340024A JP18322586A JP18322586A JPS6340024A JP S6340024 A JPS6340024 A JP S6340024A JP 18322586 A JP18322586 A JP 18322586A JP 18322586 A JP18322586 A JP 18322586A JP S6340024 A JPS6340024 A JP S6340024A
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- piles
- double
- ground
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 claims abstract description 14
- 238000007667 floating Methods 0.000 claims description 3
- 230000002093 peripheral effect Effects 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 239000013535 sea water Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000010802 sludge Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
Landscapes
- Revetment (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
防波堤、岸壁、護岸、防潮堤、離岸堤、ヨツト・・−パ
ー等の外郭施設をケーソン工法で急速施工することがで
きるようにした杭式ケーソン二
抗法に関する発明である。[Detailed description of the invention] [Industrial application field] Piles that enable rapid construction of outer facilities such as breakwaters, quay walls, seawalls, sea walls, off-shore breakwaters, yachts, etc. using the caisson construction method. This is an invention related to the two-way caisson method.
従来のケーソン工法は、剛体の安定により、防波を行な
うため海中に所定の強度を持つ基礎を築造し、その上に
ケーソン等を据付ていた。In the conventional caisson construction method, a foundation with a certain strength was built underwater to provide wave protection through the stability of a rigid body, and a caisson etc. was installed on top of the foundation.
このためヘドロ等の堆積している地域では、海底の軟弱
層の置換あるいは地盤改良工法等によシ、基礎地盤を造
らねばならず、施工性、工期、工費等の面で制約が多い
欠点を有していたものである。For this reason, in areas where sludge and other deposits have accumulated, it is necessary to replace the soft seabed layer or create a foundation using soil improvement methods, which has the disadvantage of having many restrictions in terms of construction efficiency, construction period, construction cost, etc. This is what I had.
ケーソンを据付けるについてヘドロ等の堆積している地
域の海底の軟弱層の置換あるいは地盤改良をしなければ
ならないという問題点を解決しようとするものである。This is an attempt to solve the problem of having to replace the soft seabed layer or improve the ground in areas where sludge and other deposits have accumulated when installing caissons.
ドライド、り、70−ティングドック内で周側壁を二重
壁で形成したケーソンを曳航し軟弱地盤にソフトランデ
インクし、ケーソンの周側壁の二重壁をガイドとして杭
を支持地盤まで打設した後、二重壁にコンクリートを打
設して杭とケーソンとを剛結することにより、ケーソン
の据付けに先立って軟弱地盤の置換あるいは地盤改良工
法による基礎地盤を造る等の処置の必要なくケーソンを
据付けることができるようにして問題点を解決したもの
である。A caisson with a double circumferential wall was towed into the soft ground in a dry dock, and piles were driven to the supporting ground using the double wall of the caisson's circumferential wall as a guide. After that, by pouring concrete into the double wall and rigidly connecting the piles and caisson, it is possible to install the caisson without having to take any measures such as replacing the soft ground or creating a foundation using soil improvement methods prior to the installation of the caisson. This problem was solved by making it possible to install it.
ドライドツク、フローティングドック内で周側壁を二重
壁で形成したケーソンの二重壁の下底部を鉄板等で閉塞
し水上に浮べ、該ケーソンを目的地まで曳航し、公知の
方法にて軟弱地盤持地盤まで打設する。二重壁の底部の
鉄板は杭の打設に先立ち撤去する。ソフトランデインク
した状態を保つためケーソン周側に海水を注水し沈下さ
せるかフロートをケーソンの周側に取り付は浮遊した状
態にする。Inside a dry dock or floating dock, the lower bottom of the double-walled caisson is closed off with an iron plate, etc., and the caisson is floated on the water.The caisson is towed to the destination and the soft ground is secured using a known method. Concrete down to the ground. The steel plate at the bottom of the double wall will be removed prior to driving the piles. In order to keep the caisson in a state of soft landing, seawater is injected around the caisson to make it sink, or a float is installed around the caisson to make it float.
ケーソン周側の杭の打設が完了したならば二重壁内にコ
ンクリートを打設し、杭とケーソンとを剛結する。ケー
ソン設置後、上部工を打設する。上部工を打設後フロー
トが取シ付けられているときはフロートを取シはずして
施工を完了させる。When the driving of the piles around the caisson is completed, concrete is placed inside the double wall to rigidly connect the piles and the caisson. After installing the caisson, the superstructure will be poured. After pouring the superstructure, if a float is attached, remove the float and complete the construction.
〔実施例〕
ドライドツク、フローティングドック内でケ底部を開放
するため適当箇所において数箇所縦方向にコンクリート
壁で連結し、曳航に当って二重壁の底部を鉄板等の薄板
で閉塞して海水が入らないようにする。[Example] In order to open the bottom of a dry dock or floating dock, concrete walls are connected vertically at several appropriate locations, and when towing the bottom of the double wall is closed with a thin plate such as a steel plate to prevent seawater from leaking out. Avoid entering.
該ケーソン(1)を目的地ま−で曳航し軟弱地盤(3)
上にソフトランデインクさせる。軟弱地盤にソフトラン
デインクした状態で杭打ちをするため、必要に応じて海
水を注入又はフロート(4)をケー支持地盤(6)まで
打設しケーソン(1)の周壁全ての杭(5)の打設が完
了したならば二重壁(2a)(2b)間にコンクリート
(7)を打設して杭(5)とケーソン(1)とを剛結す
る。ケーソン設置後、上部工(8)を打設し、フロート
(4)がある場合はフロート(4)を取シはすすもので
ある。The caisson (1) is towed to the destination and the soft ground (3) is
Apply soft land ink on top. In order to drive piles into soft ground with a soft land incline, inject seawater or drive floats (4) up to the support ground (6) as necessary, and then drive all the piles (5) on the surrounding wall of the caisson (1). When the pouring is completed, concrete (7) is poured between the double walls (2a) and (2b) to rigidly connect the pile (5) and the caisson (1). After installing the caisson, the superstructure (8) is poured, and if there is a float (4), the float (4) is removed.
杭(5)の打設に際し二重壁(2a) (2b)の底部
に水が入らないように薄い鉄板をバンドのようなもので
ケーソン(1)に締付けておくことによシ簡単に取シは
ずすことができるので、杭(5)の打設には支障がない
ものである。To prevent water from entering the bottom of the double walls (2a) and (2b) when driving the piles (5), a thin iron plate is fastened to the caisson (1) with something like a band, making it easy to install. Since it can be removed, there is no problem in driving the pile (5).
本願は前記のように施工することによシ急速施工ができ
、且つ通常ケーソンのスパンが10〜15mに対し、こ
の工法ではioo m単位のスパンが可能で、更に軟弱
地盤の改良が不用であシ経済的である等の特徴を有する
ものである。This construction method enables rapid construction by carrying out the construction as described above, and while the span of a typical caisson is 10 to 15 m, this construction method allows spans of IOOm, and furthermore, does not require improvement of soft ground. It has characteristics such as being economical.
図は本願の施工時の断面図である。 The figure is a sectional view during construction of the present application.
Claims (1)
を二重壁で形成したケーソンを曳航し軟弱地盤にソフト
ランデインクしケーソンの周側壁の二重壁をガイドとし
て杭を支持地盤まで打設した後、二重壁にコンクリート
を打設して杭とケーソンとを剛結することを特徴とする
杭式ケーソン工法。(1) Inside a dry dock or floating dock, a caisson with double peripheral walls is towed into soft ground, and piles are driven to the supporting ground using the double walls of the caisson as a guide. , a pile-type caisson construction method characterized by pouring concrete into a double wall and rigidly connecting the piles and caisson.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18322586A JPS6340024A (en) | 1986-08-04 | 1986-08-04 | Pile-type caisson work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18322586A JPS6340024A (en) | 1986-08-04 | 1986-08-04 | Pile-type caisson work |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6340024A true JPS6340024A (en) | 1988-02-20 |
Family
ID=16131979
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18322586A Pending JPS6340024A (en) | 1986-08-04 | 1986-08-04 | Pile-type caisson work |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6340024A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0369709A (en) * | 1989-08-07 | 1991-03-26 | Kajima Corp | Method of constructing shore protection structure |
JPH0424308A (en) * | 1990-05-17 | 1992-01-28 | Oomotogumi:Kk | Construction method for underwater structure by use of bottoming of floating frame |
ES2375883A1 (en) * | 2011-12-30 | 2012-03-07 | Universidad Politécnica de Madrid | Sub-pressure reduction system in vertical drawers of drawers through tablestacas. (Machine-translation by Google Translate, not legally binding) |
JP2013217091A (en) * | 2012-04-09 | 2013-10-24 | Geostr Corp | Precast block to be foundation of tide embankment |
JP2018204365A (en) * | 2017-06-07 | 2018-12-27 | ワールドエンジニアリング株式会社 | Revetment construction method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5016887A (en) * | 1973-06-14 | 1975-02-21 | ||
JPS5042612A (en) * | 1973-04-26 | 1975-04-17 |
-
1986
- 1986-08-04 JP JP18322586A patent/JPS6340024A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5042612A (en) * | 1973-04-26 | 1975-04-17 | ||
JPS5016887A (en) * | 1973-06-14 | 1975-02-21 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0369709A (en) * | 1989-08-07 | 1991-03-26 | Kajima Corp | Method of constructing shore protection structure |
JPH0424308A (en) * | 1990-05-17 | 1992-01-28 | Oomotogumi:Kk | Construction method for underwater structure by use of bottoming of floating frame |
ES2375883A1 (en) * | 2011-12-30 | 2012-03-07 | Universidad Politécnica de Madrid | Sub-pressure reduction system in vertical drawers of drawers through tablestacas. (Machine-translation by Google Translate, not legally binding) |
JP2013217091A (en) * | 2012-04-09 | 2013-10-24 | Geostr Corp | Precast block to be foundation of tide embankment |
JP2018204365A (en) * | 2017-06-07 | 2018-12-27 | ワールドエンジニアリング株式会社 | Revetment construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4618286A (en) | Composite platform for petroleum workings in polar seas | |
GB1574784A (en) | Method and apparatus for casting tanks in water | |
JPS6340024A (en) | Pile-type caisson work | |
JPH09268562A (en) | Dry working method and working case employed therefor | |
JPS58143023A (en) | Caisson for pile supporting type breakwater | |
JPH0921141A (en) | Construction of undersea or under-river tunnel | |
JP2000290936A (en) | Method and caisson for constructing bridge pier footing | |
JP2815492B2 (en) | How to build an underwater foundation | |
JP2000265450A (en) | Artificial ground consisting of porous housing and construction method therefor | |
JPH05311627A (en) | Foundation structure for large-scale artificial island | |
JPS60215924A (en) | Settlement of steel skeleton for underwater foundation structure | |
CN100360377C (en) | Semi submersible type under water construction flow blocking device | |
JPH09242081A (en) | Dry work method and work box or vessel used therefor | |
JP2953823B2 (en) | Construction method of offshore substructure | |
CN207749530U (en) | Self installation combines the settling type basic platform of anchoring pile and consolidated subsoil | |
JP2608824B2 (en) | Structures such as aquaculture equipment that can be installed on the silt layer and their installation methods | |
JPS6178924A (en) | Temporary coffering work for dry dock | |
JPH053542Y2 (en) | ||
EP2189576A1 (en) | Foundation system for marine structures in deep water | |
JPH0213098B2 (en) | ||
JP2953818B2 (en) | Construction method for deep water structures | |
JPS6335766B2 (en) | ||
JPS58207410A (en) | Assembler for prefabricated steel sheet pile cell | |
JPH06257163A (en) | Droughty pontoon for constructing shallow foundation | |
JPS5820331B2 (en) | Artificial island for oil drilling in frozen waters |