JPS63312417A - Water construction of continuous wall using steel caisson - Google Patents
Water construction of continuous wall using steel caissonInfo
- Publication number
- JPS63312417A JPS63312417A JP14632387A JP14632387A JPS63312417A JP S63312417 A JPS63312417 A JP S63312417A JP 14632387 A JP14632387 A JP 14632387A JP 14632387 A JP14632387 A JP 14632387A JP S63312417 A JPS63312417 A JP S63312417A
- Authority
- JP
- Japan
- Prior art keywords
- steel caisson
- continuous wall
- caisson
- concrete
- walls
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 28
- 239000010959 steel Substances 0.000 title claims abstract description 28
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 16
- 238000010276 construction Methods 0.000 title claims description 11
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims abstract description 6
- 238000005192 partition Methods 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 description 6
- 238000009408 flooring Methods 0.000 description 3
- 238000009423 ventilation Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
この発明は、鋼製ケーソンを用いて水中に連続壁を施工
し、基礎又は剛性の高い躯体な構築するための工法に関
するものである。DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a construction method for constructing a foundation or a highly rigid frame by constructing a continuous wall underwater using a steel caisson.
「従来の技術、発明か解決せんとする問題点」従来、水
上で連続壁を構築する場合、埋め立てにより人工地盤を
造成する方法、或いは一つのエレメント毎に壁板体を設
置する方法か実施されていた。``Prior art, problems to be solved by invention'' Conventionally, when constructing a continuous wall over water, the methods used were to create an artificial ground by reclaiming land, or to install a wall plate for each element. was.
しかしながら、埋立てによる方法ては大規模な設備と多
大の工期を要すると共に、埋立層の崩落などの欠点かあ
る。However, the landfill method requires large-scale equipment and a long construction period, and has drawbacks such as the collapse of the reclaimed layer.
また、一つのエレメント毎に壁板体を設置する方法ては
、壁板体の建込み用のガイドを有する基準杭の打設を要
するため、その施工か容易てないと共に、施工精度か低
いなどの欠点かあった。In addition, the method of installing a wall plate for each element requires the driving of reference piles with guides for installing the wall plate, which is not easy to do, and the accuracy of construction is low. There were some drawbacks.
「問題点を解決するための手段」
この発明は前記従来の課題を解決するために、内外二重
の躯体壁からなる鋼製ケーソンを水底下に設置し、その
水底下付近を根固めして安定させた後、このケーソン上
においてその内外の躯体壁間の下方の水底地盤を掘削し
、その掘削部分及び内外の躯体壁間の間隙に鉄筋篭を配
置した後、一体にコンクリートを打設することにより、
鋼製ケーソンを大規模な掘削を要せずに簡単に根固めす
るたけて設置し、エレメント毎に壁板体を設置すること
なく鋼製ケーソンと一体的に連続地中壁を施工てき、地
盤に強固に支持された水中構造物を構築することを可能
とした工法を提案するものである。"Means for Solving the Problems" In order to solve the above-mentioned conventional problems, the present invention installs a steel caisson with double inner and outer frame walls under the water bottom, and hardens the area near the bottom of the water. After stabilization, excavate the underwater ground between the inner and outer frame walls on this caisson, place reinforcing bar cages in the excavated area and the gap between the inner and outer frame walls, and then pour concrete all together. By this,
The steel caisson can be easily installed in a pile without requiring large-scale excavation, and a continuous underground wall can be constructed integrally with the steel caisson without installing wall plates for each element. This paper proposes a construction method that makes it possible to construct underwater structures that are firmly supported.
「実施例」
以下この発明を図面に示す実施例について説明すると、
第1図に示すように水底地盤な床堀掘削し、この床材部
1に鋼製ケーソン2を沈設し、床付部lに水中コンクリ
ート3等を打設して鋼製ケーソン2の水底下付近を根固
めして安定させる。"Embodiments" Below, embodiments of the present invention shown in the drawings will be described.
As shown in Fig. 1, a trench is excavated on the underwater ground, a steel caisson 2 is sunk in the flooring part 1, and underwater concrete 3 is placed in the flooring part 1, so that the steel caisson 2 is placed under the water. Stabilize the area by solidifying the roots.
鋼製ケーソン2は、所定間隙を保持して対設した内外二
重の躯体壁2a、2bを有する上下か開口した中空体て
、適宜個所に躯体壁2a。The steel caisson 2 is a hollow body that is open at the top and bottom and has double inner and outer frame walls 2a and 2b facing each other with a predetermined gap, and has frame walls 2a at appropriate locations.
2b間を仕切る仕切板4か設けられている。A partition plate 4 is provided to partition the space 2b.
そして、この鋼製ケーソン2の−L端にその製造時又は
水底に設置した後に設置した作業ヤード5上において、
掘削機械により躯体壁2a。Then, on the working yard 5 installed at the -L end of this steel caisson 2 during its manufacture or after it was installed on the bottom of the water,
The skeleton wall 2a is excavated by an excavation machine.
2b間の下方の水底地盤を掘削し、その掘削部分6と躯
体壁2a、2b間の間隙内に鉄筋篭7を配置した上て一
体にコンクリート8を打設し、掘削部分6の連続地中壁
と一体化した一連の連続壁に囲まれた水中構造躯体を構
築する。2b is excavated, and a reinforcing bar cage 7 is placed in the gap between the excavated portion 6 and the frame walls 2a and 2b, and then concrete 8 is cast in one piece, and the excavated portion 6 is continuously underground. Build an underwater structural framework surrounded by a series of continuous walls that are integrated into the walls.
この連続壁の施工は、第7図に示すように仕切板4て仕
切られた多数のエレメントA、Bの内、最初に一つ置き
のエレメントAの部分を施工し、その施工完了後に残り
の一つ置きのエレメントBの部分を施工する。To construct this continuous wall, as shown in Figure 7, among the many elements A and B separated by the partition plate 4, every other element A is first constructed, and after that construction is completed, the remaining elements A and B are constructed. Construct every other element B part.
仕切板4には、その両面に予めジベル筋等のジヨイント
部材9を突設しておき、第7図に示すように隣接エレメ
ントA、B間のコンクリート8を一体化する。Joint members 9 such as dowel reinforcements are provided in advance on both sides of the partition plate 4 so as to protrude, and the concrete 8 between adjacent elements A and B is integrated as shown in FIG.
このようにして構築された構造躯体を、例えば橋脚基礎
などケーソン内部空間を利用しない一体構造物として使
用する場合には、第5図に示すように鋼製ケーソン2の
内底部を掘削し、内部空間にコンクリートlOを打設し
て連続壁と一体化する。When the structural frame constructed in this way is used as an integral structure that does not utilize the internal space of the caisson, for example, as a pier foundation, the inner bottom of the steel caisson 2 is excavated as shown in Fig. Concrete lO is placed in the space and integrated with the continuous wall.
次に、この構造躯体を第6図に示すように海底トンネル
の換気塔などケーソン内部空間を利用する構造物として
使用する場合には、内部に連続壁と一体の床版施工を行
う。Next, as shown in Fig. 6, when this structural frame is used as a structure that utilizes the internal space of the caisson, such as a ventilation tower for an undersea tunnel, a floor slab integrated with a continuous wall is constructed inside.
この床版施工に際しては、第8.9図に示すように、鋼
製ケーソン2の内側躯体壁2bの床版接合部分の内外面
にジベル筋などのジヨイント部材11を突設しておき、
これに配筋した鉄筋12をラップさせて床版コンクリー
ト13を打設し、連続壁と一体化する。When constructing this floor slab, as shown in Fig. 8.9, joint members 11 such as dowel bars are provided protrudingly on the inner and outer surfaces of the floor slab joining portion of the inner frame wall 2b of the steel caisson 2.
A floor slab concrete 13 is placed by wrapping the reinforced reinforcing bars 12 on this, and is integrated with the continuous wall.
この場合、躯体壁2a、2b間の下方の水底地盤を掘削
する際に、掘削パケット等の掘削機がジヨイント部材1
1に当らないように、ジヨイント部材11の前方に仕切
板4に設けたガイド溝14に沿ってスライド自在な遮蔽
板15を設け、掘削完了後遮蔽板15を引上げてコンク
リート8を打設する。In this case, when excavating the underwater ground below between the frame walls 2a and 2b, an excavator such as an excavation packet
A slidable shielding plate 15 is provided in front of the joint member 11 along a guide groove 14 provided in a partition plate 4 so as not to hit the joint member 1, and after completion of excavation, the shielding plate 15 is pulled up and concrete 8 is poured.
「発明の効果」
以上の通りこの発明によれば、内外二重の躯体壁からな
る鋼製ケーソンを水底下に設置し、その水底下付近を根
固めして安定させた後、このケーソン上においてその内
外の躯体壁間の下方の水底地盤を掘削し、その掘削部分
及び内外の躯体壁間の間隙に鉄筋篭を配置した後、一体
にコンクリートを打設することにより、水底地盤の大規
模な掘削を要せずに鋼製ケーソンな簡中に根固めするた
けて設置し、しかもエレメント毎に壁板体を設置するこ
となく鋼製ケーソンの内外の躯体壁間に打設したコンク
リートと、その下方の水底地盤に設けた連続地中壁と一
体化した剛性並ひに精度の高い連続壁を施工てき、これ
によってさほど工期、工費を要せずに鋼製ケーソン上に
おいて地盤に強固に支持された連続壁による水中構造物
を構築することか可能となる。"Effects of the Invention" As described above, according to the present invention, a steel caisson consisting of double internal and external frame walls is installed below the water bottom, and after the area under the water bottom is stabilized by hardening, the steel caisson is placed on top of the caisson. By excavating the underwater ground below between the inner and outer building walls, placing reinforcing bar cages in the excavated area and the gap between the inner and outer building walls, and then pouring concrete all together, the large-scale underwater ground can be removed. Concrete is placed between the inner and outer walls of the steel caisson without the need for excavation, and without installing wall plates for each element. We have constructed a continuous wall with high rigidity and precision that is integrated with a continuous underground wall installed in the underwater ground below.This allows us to firmly support the steel caisson on the ground without requiring much construction time or cost. It becomes possible to construct underwater structures with continuous walls.
:51〜4図はこの発明による施工工程を順に示す縦断
面図、第5図はこの発明により橋脚基礎を構築した態様
の縦断面図、第6図はこの発明により水中換気塔を構築
した態様の縦断面図、第7図はこの発明に係る構成ケー
ソンの平面図、第8図はこの発明における床版コンクリ
ートとの接合部の構成を示す縦断面図、第9図は同横断
面と各エレメントの結合部の構成を示す横断面の図であ
る。
1・・床材部、2・・鋼製ケーソン、
2a、2b・・躯体壁、3・・水中コンクリート、4・
・仕切板、5・・作業ヤード、6・・掘削部分、7・・
鉄筋篭、8・・コンクリート、9・・ジヨイント部材、
IO・・コンクリート、11・・ジヨイント部材、12
・・鉄筋、13・・床版コンクリート、14・・ガイド
溝、15・・遮蔽板。: Figures 51 to 4 are vertical cross-sectional views showing the construction process according to the present invention in order; Figure 5 is a vertical cross-sectional view of an embodiment of a pier foundation constructed according to the present invention; and Figure 6 is a vertical cross-sectional view of an embodiment of an underwater ventilation tower constructed according to the present invention. FIG. 7 is a plan view of the caisson according to the present invention, FIG. 8 is a longitudinal cross-sectional view showing the structure of the joint with the concrete floor slab in the present invention, and FIG. 9 is a cross-sectional view of the caisson according to the invention. FIG. 3 is a cross-sectional view showing the configuration of a connecting portion of an element. 1.Flooring section, 2.Steel caisson, 2a, 2b..Structure wall, 3..Underwater concrete, 4.
・Partition plate, 5. Working yard, 6. Excavation part, 7.
Reinforced cage, 8. Concrete, 9. Joint member,
IO...Concrete, 11...Joint member, 12
...Reinforcing bars, 13.. Floor slab concrete, 14.. Guide grooves, 15.. Shielding plates.
Claims (1)
設置し、その水底下付近を根固めして安定させた後、前
記ケーソン上においてその内外の躯体壁間の下方の水底
地盤を掘削し、その掘削部分及び内外の躯体壁間の間隙
内に鉄筋篭を配置した後、一体にコンクリートを打設す
ることを特徴とする鋼製ケーソンを用いた連続壁の水上
施工法。 2)連続壁構築後、各エレメントを仕切る仕切板の両面
に突設したジョイント部材により連続壁を一体化するこ
とを特徴とする特許請求の範囲第1項記載の鋼製ケーソ
ンンを用いた連続壁の水上施工法 3)連続壁の構築後、鋼製ケーソンの内部の水底地盤を
掘削し、鋼製ケーソン内部にコンクリートを打設するこ
とを特徴とする特許請求の範囲第1項記載の鋼製ケーソ
ンを用いた連続壁の水上施工法。 4)連続壁構築後、鋼製ケーソン内部に床版コンクリー
トを打設し、この床版を鋼製ケーソン内側の躯体壁の内
外面に突設したジョイント部材により連続壁に一体化す
ることを特徴とする特許請求の範囲第1項記載の鋼製ケ
ーソンを用いた連続壁の水上施工法。[Scope of Claims] 1) A steel caisson consisting of double inner and outer frame walls is installed below the water bed, and after the area under the water bed is stabilized by foot-roofing, a steel caisson is installed between the inner and outer frame walls on the caisson. A continuous wall using a steel caisson characterized by excavating the underwater ground below, placing a reinforcing bar cage in the excavated part and the gap between the inner and outer building walls, and then pouring concrete in one piece. Floating construction method. 2) A continuous wall using a steel caisson according to claim 1, wherein after construction of the continuous wall, the continuous wall is integrated by joint members protruding from both sides of a partition plate that partitions each element. 3) After constructing the continuous wall, the underwater ground inside the steel caisson is excavated and concrete is poured inside the steel caisson. Floating construction method for continuous walls using caissons. 4) After constructing the continuous wall, a concrete floor slab is poured inside the steel caisson, and this floor slab is integrated into the continuous wall using joint members protruding from the inner and outer surfaces of the frame wall inside the steel caisson. A method for constructing a continuous wall over water using a steel caisson according to claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14632387A JPH0826542B2 (en) | 1987-06-12 | 1987-06-12 | Overwater construction method of continuous wall using steel casing. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14632387A JPH0826542B2 (en) | 1987-06-12 | 1987-06-12 | Overwater construction method of continuous wall using steel casing. |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63312417A true JPS63312417A (en) | 1988-12-20 |
JPH0826542B2 JPH0826542B2 (en) | 1996-03-13 |
Family
ID=15405072
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14632387A Expired - Lifetime JPH0826542B2 (en) | 1987-06-12 | 1987-06-12 | Overwater construction method of continuous wall using steel casing. |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0826542B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107130624A (en) * | 2017-06-30 | 2017-09-05 | 中交第航务工程局有限公司 | A kind of round caisson wall steel reinforcement cage overall binding lift-on/lift-off system |
-
1987
- 1987-06-12 JP JP14632387A patent/JPH0826542B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107130624A (en) * | 2017-06-30 | 2017-09-05 | 中交第航务工程局有限公司 | A kind of round caisson wall steel reinforcement cage overall binding lift-on/lift-off system |
Also Published As
Publication number | Publication date |
---|---|
JPH0826542B2 (en) | 1996-03-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6678487B2 (en) | How to build an underground structure | |
KR20120126573A (en) | Soil cement wall structure and method for constructing thereof | |
JP3829319B2 (en) | Construction method of underground hollow structure and its underground hollow structure | |
JP2005002671A (en) | Underpinning method and viaduct | |
JPS63312417A (en) | Water construction of continuous wall using steel caisson | |
JP4146250B2 (en) | Open caisson bottom plate construction method | |
JPS5851092B2 (en) | Earth retaining installation method using advance shoring frame | |
JPH0721196B2 (en) | Reverse construction method of underground structure | |
JPH041811B2 (en) | ||
JP2558414B2 (en) | Construction method of the main retaining wall and the retaining wall | |
JPH084033A (en) | Structure method of building underground outer periphery pressure bulkhead | |
JPH10299003A (en) | Foundation work using precast concrete member | |
KR20120032368A (en) | Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same | |
JPH07216903A (en) | Bulkhead caisson and construction method of bulkhead | |
JPS5853321Y2 (en) | Element for mountain retainer | |
JPH11158891A (en) | Construction of basement for residence | |
JPS62111028A (en) | Construction of underground structure | |
JPH0748848A (en) | Construction method for underground skeleton by inverted construction method | |
JPH0430021A (en) | Constructing method of guide for underground continuous wall | |
JPS6013086B2 (en) | Construction method of underground continuous wall | |
JPH07119160A (en) | Method of constructing concrete footing, casing for footing section form of concrete footing and panel for underground girder section form | |
JPS5972319A (en) | Underground continuous wall work utilizing soil pillar-row wall | |
JPH06194485A (en) | Construction of nuclear power plant building | |
JPS6019369B2 (en) | How to build a diaphragm wall | |
JP2001323485A (en) | Method of constructing underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080313 Year of fee payment: 12 |