JPS6098004A - Invert slide type frame apparatus - Google Patents

Invert slide type frame apparatus

Info

Publication number
JPS6098004A
JPS6098004A JP58205964A JP20596483A JPS6098004A JP S6098004 A JPS6098004 A JP S6098004A JP 58205964 A JP58205964 A JP 58205964A JP 20596483 A JP20596483 A JP 20596483A JP S6098004 A JPS6098004 A JP S6098004A
Authority
JP
Japan
Prior art keywords
invert
formwork
concrete
slide
end plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP58205964A
Other languages
Japanese (ja)
Other versions
JPS6151089B2 (en
Inventor
斉藤 正文
清 松本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP58205964A priority Critical patent/JPS6098004A/en
Publication of JPS6098004A publication Critical patent/JPS6098004A/en
Publication of JPS6151089B2 publication Critical patent/JPS6151089B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明はインバートスライド型枠装置に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an invert slide formwork apparatus.

]−ンネルエ事において、地山の崩壊を防止するため、
掘削後早急に力学的に土圧に対抗できる構造の支保を構
築する必要がある。
】-In order to prevent the collapse of the ground during the construction work,
Immediately after excavation, it is necessary to construct a structural support that can mechanically resist earth pressure.

万一不安定な覆工状態で長期間放置すると底部を最後に
覆工する関係から底部の強度が発現する以前に側壁土圧
が作用して「盤ふくれ現象」を発生する場合もあるので
早急に覆工を完了させる必要がある。
If the lining is left in an unstable state for a long period of time, since the bottom is the last to be lined, side wall earth pressure may act before the bottom has developed its strength, causing a ``plate bulging phenomenon.'' It is necessary to complete the lining.

ところで、従来、インバートコンクリート(床部弁のコ
ンクリート)用型枠(妻板)には次のような問題がある
By the way, conventional forms (end plates) for invert concrete (concrete for floor valves) have the following problems.

〈イ〉従来のトンネルではまずインバートコンクリート
を約5Qcm程打設し、すべての仮設車両等はその上面
を走行させている。
<B> In conventional tunnels, inverted concrete is first poured to a depth of about 5 Qcm, and all temporary vehicles run on top of it.

そして最終的な仕上がりコンクリートは数ケ月も以前に
打設したインバートコンクリートの上に打設するもので
ある。
The final finished concrete is poured on top of the inverted concrete that was poured several months earlier.

〈口〉インバートコンクリートは単なる仕切板で良いと
言う事から従来軽視されていた。
〈Mouth〉Inverted concrete has been neglected in the past because it can be used as a simple partition plate.

しかし、実際には正確な高さの維持、妻板の断面に貫通
ずる鉄筋の処理などの問題があった。
However, in reality, there were problems such as maintaining accurate height and dealing with reinforcing bars that penetrated the cross section of the end plate.

しかもコンクリートを打設する度、妻板を新しく加工し
ていた。
What's more, every time concrete was poured, new gable boards were being processed.

そのため、型枠の枠組作業が煩雑であり、そのうえ枠組
み作業が低能率である。
Therefore, the work of constructing the formwork is complicated, and furthermore, the efficiency of the work of constructing the formwork is low.

くハ〉さらに、インバートの中央や側方に排水溝を形成
する場合には仕上げ高さや型枠組み立ての容易さが要求
される。
Furthermore, when forming drainage grooves in the center or sides of the invert, the finished height and the ease of erecting the formwork are required.

本発明はこの様な点を改善するためになされたもので型
枠の操作性、作業性に優れ、高い打設精度が得られるイ
ンバートスライド型枠装置を提供する事を目的とJる。
The present invention has been made to improve the above-mentioned problems, and an object of the present invention is to provide an invert slide formwork device that has excellent formwork operability and workability and can provide high pouring accuracy.

次に本発明の一実施例について説明するが、まず本発明
に係る装置の各部についてび1明する。
Next, an embodiment of the present invention will be described, but first, each part of the device according to the present invention will be explained.

[イ]全体の説明 本発明のインバートスライド型枠装置1は第1図に示す
ように架台2と、この架台2の開削側(以下「前方」と
言う)に設けた妻板3と、レール11上を走行する走行
部、および既設インバー1−上に載置する制動部で構成
する。
[B] Overall description As shown in FIG. 1, the invert slide formwork device 1 of the present invention includes a pedestal 2, a end plate 3 provided on the excavated side (hereinafter referred to as "front") of this pedestal 2, and a rail 11. It consists of a running section that runs on top of the inverter, and a braking section that is placed on top of the existing invar.

r口1架台 架台2はトンネル縦断方向に並行に配置した2本の縦断
桁21と、この縦断桁21間をトンネル断面方向に連1
8りる横断桁22で構成する。
The r-entrance 1 frame frame 2 has two longitudinal girders 21 arranged in parallel in the longitudinal direction of the tunnel, and a continuous line between the longitudinal girders 21 in the cross-sectional direction of the tunnel.
It consists of eight cross girders 22.

縦断桁21の全長は架台2を開削方面にスライドづる関
係から少なくとも、インバートコンク1ノートの1スパ
ン分の打設距離よりやや長く形成する。
The total length of the longitudinal girder 21 is formed to be at least slightly longer than the casting distance for one span of one inverted concrete notebook in order to allow the pedestal 2 to slide in the excavation direction.

[ハコ走行部 縦断桁21の前端には伸縮自在な走行ジヤツキ5を床面
に向(プて取付け、この走行ジヤツキ5の先端には床地
盤に敷設したレール11上を走行するサポートに1−ラ
51を設ける。
[At the front end of the vertical girder 21 of the box traveling section, a telescopic traveling jack 5 is attached so as to face the floor. 51 is provided.

縦断桁21の後端には回動腕6を回動自在に軸支し、回
動腕6の先端にはガイドローラ61を設ける。
A rotary arm 6 is rotatably supported at the rear end of the longitudinal girder 21, and a guide roller 61 is provided at the tip of the rotary arm 6.

すなわち、回動腕6および走行ジA1ツキ5でインバー
トスライド型枠装置1を支承し/j状態で走行できるよ
う構成する。
That is, the structure is such that the invert slide formwork device 1 is supported by the rotating arm 6 and the traveling arm 5 and can travel in the /j state.

[二]制動部 縦断桁21の回動腕6側(以下「後方」と言う)には床
面に向(プてストッパー4を突設する。
[2] A stopper 4 is provided on the rotary arm 6 side (hereinafter referred to as "rear") of the braking section longitudinal girder 21 so as to protrude toward the floor surface.

ストッパー4の全長は回動腕6より短く形成し、後述り
゛るようにインバートコンクリートを打設する際、スi
・ツバ−4が回動腕6に代わってインバートスライド型
枠装置1を支承できるよう構成する。 ストッパー4で
インバートスライド型枠装置1を支持するとストッパー
4の下面が既設インバー1〜面に係止してインバートス
ライド型枠装置1の移動を剛化する事ができる。
The total length of the stopper 4 is formed to be shorter than the rotating arm 6, so that when pouring invert concrete as described later,
- Constructed so that the collar 4 can support the invert slide formwork device 1 instead of the rotating arm 6. When the invert slide formwork device 1 is supported by the stopper 4, the lower surface of the stopper 4 is engaged with the existing invert 1~ surface, and the movement of the invert slide formwork device 1 can be made rigid.

なお、ストッパー4を伸縮自在に構成する事も可能であ
る。
Note that it is also possible to configure the stopper 4 to be expandable and retractable.

この場合、架台2のレベルがめ易くなる。In this case, it becomes easier to determine the level of the pedestal 2.

[ホ]妻板 インバートスライド型枠装置1の前方にはトンネル横断
方向に妻板3を配置する。
[E] In front of the end plate invert slide formwork device 1, the end plate 3 is arranged in the tunnel crossing direction.

妻板3は縦断桁21を横断する方向に連絡する横断桁2
2に取り付けた垂直の板体である。
The end plate 3 connects the transverse girder 2 in the direction of crossing the longitudinal girder 21
It is a vertical plate attached to 2.

従って架台2をスライドしたときには架台2と一体に移
動する事になる。
Therefore, when the pedestal 2 is slid, it moves together with the pedestal 2.

インバートコンクリートを打設する際、鉄筋82を妻板
3から開削方向に露出させておく必要がそのため、例え
ば第4図に示すように妻板3下面から鉄筋82が突出で
きる寸法に妻板3を形成し、さらに、妻板3前方外面に
は横断材31を多少の間隔を介して取付け、妻板3と横
断材31との間を縦方向の小区分に分割する。
When pouring inverted concrete, it is necessary to expose the reinforcing bars 82 from the end plate 3 in the excavation direction, so for example, as shown in FIG. Further, a cross member 31 is attached to the front outer surface of the end plate 3 with some spacing therebetween, and the space between the end plate 3 and the cross member 31 is divided into small sections in the vertical direction.

妻板3下方の開放空間は、これらの小区分内に細幅の板
体32を鉄WJ82と衝突しない位置に差込み、キャン
バ33で固定して遮断する事ができる。
The open space below the end plate 3 can be blocked by inserting the narrow plate body 32 into these small sections at a position where it will not collide with the iron WJ82 and fixing it with the camber 33.

[へ]溝型枠 溝型枠7は、インバート面に例えば集水溝や排水溝を成
形する際に使用する。
[F] Groove formwork The groove formwork 7 is used when forming, for example, a water collection groove or a drainage groove on the invert surface.

溝型枠7は第1図に示づ゛ように断面U字形の連続型枠
であり、この型枠7をインバートスライド型枠装置1の
中央に縦断桁21と平行に設置する。
The groove formwork 7 is a continuous formwork having a U-shaped cross section as shown in FIG.

次に施工方法について説明する。Next, the construction method will be explained.

[イ]引き出し準備(第2図) 公知の開削方法でトンネルを掘削し、掘削土を坑外に運
搬する。
[B] Preparation for extraction (Figure 2) Excavate a tunnel using a known excavation method and transport the excavated soil outside the mine.

1スパンの掘削を完了したら新インバートAの打設範囲
の床面にレール11を敷設して前記インバートスライド
型枠装置1を引ぎ出す。
When one span of excavation is completed, rails 11 are laid on the floor in the area where the new invert A is to be placed, and the invert slide formwork device 1 is pulled out.

すなわちインバートスライド型枠装置1の回動腕6を開
いて既設インバートBに支承させ、同時に走行ジヤツキ
5を伸長してインバートスライド型枠装置1を浮上させ
て、開削方向に1スパンの距離だけ移動する。
That is, the rotating arm 6 of the invert slide formwork device 1 is opened and supported on the existing invert B, and at the same time, the traveling jack 5 is extended to levitate the invert slide formwork device 1 and move it by a distance of one span in the excavation direction. do.

レール11は埋殺しにしないでインバートスライド型枠
装置1を移動したらレール11を開削方向に移動して再
使用する。
The rail 11 is not buried, but when the invert slide formwork device 1 is moved, the rail 11 is moved in the excavation direction and reused.

そして地山全域にアンカーボルトや吹付はコンクリート
を施しアーチ状の一次覆■を形成する。
Anchor bolts and spray concrete are then applied to the entire area of the ground to form an arch-shaped primary cover.

[口]型枠の設置(第3図) インバートを打設するために、インバートスライド型枠
装置1の回動腕6を畳み、ストッパー4を既設インバー
トBに着地させる。
[Opening] Formwork installation (Fig. 3) To cast an invert, the rotating arm 6 of the invert slide formwork device 1 is folded, and the stopper 4 is landed on the existing invert B.

さらに髪板3の両側には第1図のように細幅状の補強板
からなる補助型枠9を縦断桁21と並行に配置する。
Further, on both sides of the hair plate 3, as shown in FIG. 1, auxiliary forms 9 made of narrow reinforcing plates are arranged in parallel with the longitudinal beams 21.

この補助型枠9は打設するインバートの隅部を傾斜面に
形成して、側壁との打継部の滑りを防止するためである
The purpose of this auxiliary formwork 9 is to form the corner of the invert to be cast into an inclined surface to prevent the joint part from slipping with the side wall.

[ハ]インバート打設 インバートスライド型枠装置1の設置を完了したらコン
クリートを打設する。
[C] Invert pouring After the installation of the invert slide formwork device 1 is completed, concrete is poured.

このとき、打設コンクリートの仕上がり面を妻板3の上
縁、および溝型枠7の上縁などに一致させる事によって
容易に正確な仕上げ面を得ることができる。
At this time, by aligning the finished surface of the poured concrete with the upper edge of the end plate 3 and the upper edge of the groove formwork 7, an accurate finished surface can be easily obtained.

その結果、床面には中央に溝81を開設した軌道スラブ
8が形成される。
As a result, a track slab 8 having a groove 81 in the center is formed on the floor surface.

[二]脱型、移動 養生期間経過後、回動腕6を広げ、同時に走行ジヤツキ
5を伸長して軌道スラブ8からすべての型枠を剥離する
[2] After the demolding and movement curing period has elapsed, the rotating arms 6 are expanded, and at the same time the traveling jacks 5 are extended to peel off all the formwork from the track slab 8.

剥離作業はインバートスライド型枠装置1を浮上するだ
【ノの簡単な操作で完了できるので手数が掛からない。
The peeling work can be completed with a simple operation of floating the invert slide formwork device 1, so it does not take much effort.

浮上した状態のインバートスライド型枠装置1を開削方
向に移動して順次インバートコンクリートを打設してい
く。
The floating invert slide formwork device 1 is moved in the excavation direction to successively place invert concrete.

本発明は以上説明したようになるから次のような効果を
期待することができる。
Since the present invention is as explained above, the following effects can be expected.

〈イ〉従来のように仮設のインバ・−トコンクリ−1〜
を打設せず、−回で仕上げ面までNILでしまうので運
搬車等はその上を走行でき、トラフイカビリティ−が良
好になる。
<B> Temporary invert concrete 1 as in the past
Since the finished surface is covered with NIL without being poured, transport vehicles etc. can run on it and the troughability is improved.

〈口〉型枠を架台と一体に形成し、かつ、この架台を走
行自在に構成したので、型枠の移動および設置が迅速と
なり作業の効率化を図る事ができる。
<Entrance> Since the formwork is formed integrally with the pedestal, and the pedestal is configured to be movable, the formwork can be moved and installed quickly, making work more efficient.

くハ〉複数箇所(妻板、溝型枠の上縁等)からレベルを
められるのでインバー1−コンクリート(軌道スラブ上
面)の仕上げ面を正確に形成できる。
Kuha> Since the level can be determined from multiple locations (end plate, upper edge of groove formwork, etc.), the finished surface of Invar 1 concrete (top surface of track slab) can be accurately formed.

〈二〉妻板の製作や配筋作業、および地山掘削面とのす
り合せをコンクリート打設の都度行う必要がなくなった
(2) It is no longer necessary to manufacture gable boards, arrange reinforcement work, and align them with the ground excavation surface every time concrete is poured.

〈ホ〉インバートの隅部を正確な傾斜面に成形できるの
で側壁の覆工の為の型枠のセットが容易となる。
<E> Since the corners of the invert can be formed into accurate sloped surfaces, it is easy to set the formwork for lining the side walls.

くへ〉溝型枠を使用した場合、集水溝および排水溝を同
時に施工できる。
When using gutter formwork, the water collection gutter and drainage gutter can be constructed at the same time.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明の一実施例の説明同 第2.3図:施工方法の説明図 第4図:妻板先端部分の拡大図 第5図:インバートコンクリート打設状態の説明図 1=インバートスライド型枠装置 2:架台 3:妻板 4:ストッパー 5:走行ジt1ツキ 6:回動腕 Figure 1: Description of one embodiment of the present invention Figure 2.3: Illustration of construction method Figure 4: Enlarged view of the tip of the end plate Figure 5: Explanatory diagram of invert concrete placement state 1 = Invert slide formwork device 2: Frame 3: Gable board 4: Stopper 5: Running jitter t1 luck 6: Rotating arm

Claims (1)

【特許請求の範囲】 複数の縦断桁に、 横断方向に1枚の妻板を、 縦方向に溝型枠を各々一体に取り付け、縦断桁の両端は
走行可能に構成した事を特徴とする、 インバートスライド型枠装置。
[Scope of Claims] An invert device characterized in that a plurality of longitudinal girders are integrally attached with one end plate in the transverse direction and a groove formwork in the longitudinal direction, and both ends of the longitudinal girders are configured to be movable. Slide formwork equipment.
JP58205964A 1983-11-04 1983-11-04 Invert slide type frame apparatus Granted JPS6098004A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58205964A JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58205964A JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Publications (2)

Publication Number Publication Date
JPS6098004A true JPS6098004A (en) 1985-06-01
JPS6151089B2 JPS6151089B2 (en) 1986-11-07

Family

ID=16515622

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58205964A Granted JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Country Status (1)

Country Link
JP (1) JPS6098004A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012502204A (en) * 2008-09-09 2012-01-26 ジュ・テ・キム Floor construction equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012502204A (en) * 2008-09-09 2012-01-26 ジュ・テ・キム Floor construction equipment

Also Published As

Publication number Publication date
JPS6151089B2 (en) 1986-11-07

Similar Documents

Publication Publication Date Title
CH615236A5 (en)
CN110184950A (en) The construction method of bridge former address reorganization and expansion new bridge under a kind of guarantor&#39;s gating condition
KR101917813B1 (en) Railroad lower part no dig excavation construction sructure and construction method using it
CN110499779A (en) A kind of air channel structure construction method sharing side wall with subway station
CN105781570A (en) Metro internal-bracing-free track panel shaft and construction method thereof
CN112323627A (en) Frame type construction system and construction method in existing railway temporary bridge construction
CN115324104B (en) Permanent-face combined assembled station and construction method thereof
JPS6098004A (en) Invert slide type frame apparatus
JPS62288269A (en) Method for extending underground stair of building
JPS61216997A (en) Inverted slide mold frame apparatus
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
JPS5918860A (en) Working platform
US902973A (en) Method of tunneling under streets, roads, squares, tracks, and the like.
JP4037004B2 (en) Construction method of underground structure
CN212375729U (en) Frame type construction system in existing railway temporary bridge construction
DE579544C (en) Process for the construction of tunnels, especially under urban roads
JP4083335B2 (en) Structure of retaining wall for construction of underground structure
RU1794193C (en) Method of construction of line of subway of shallow depth
US2128284A (en) Method of constructing subways and like underground structures
JPS5842510Y2 (en) Earth retention shoring device for excavated trenches
SU1481417A1 (en) Method of constructing a tunnel under railway
JPS59195996A (en) Tunnel constructing method
JPS607119B2 (en) Tunnel construction method using mobile center
JP2587029B2 (en) Viaduct construction method
SU981495A1 (en) Road passage through embankment of acting railway and method of constructing same