JPS607119B2 - Tunnel construction method using mobile center - Google Patents

Tunnel construction method using mobile center

Info

Publication number
JPS607119B2
JPS607119B2 JP55019379A JP1937980A JPS607119B2 JP S607119 B2 JPS607119 B2 JP S607119B2 JP 55019379 A JP55019379 A JP 55019379A JP 1937980 A JP1937980 A JP 1937980A JP S607119 B2 JPS607119 B2 JP S607119B2
Authority
JP
Japan
Prior art keywords
center
lower center
construction method
side wall
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP55019379A
Other languages
Japanese (ja)
Other versions
JPS56115500A (en
Inventor
治助 清水
正男 伊藤
吉男 鷹巣
真 壷井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP55019379A priority Critical patent/JPS607119B2/en
Publication of JPS56115500A publication Critical patent/JPS56115500A/en
Publication of JPS607119B2 publication Critical patent/JPS607119B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明は、地下鉄一般線路部、下水道などの単純断面構
造をなす地下トンネルの側壁および上床を盛替切梁工法
によって構築する施工方法であって、移動可能で内盛替
切梁の機能をそなえた下部セントル2基と、この下部セ
ントル上を滑動させる上床型枠用の上部セントル1基を
もって側壁上部および上床コンクリートを打設する移動
式セントルの施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention is a construction method for constructing the side walls and upper floors of underground tunnels having a simple cross-sectional structure such as subway general track sections and sewerage lines using the reversing beam construction method. This relates to a construction method for a mobile center in which the upper part of the side walls and upper floor concrete is poured using two lower center centers that have the function of switching beams and one upper center center for the upper floor formwork that slides on these lower center centers. .

従来、地下鉄一般線路部等の地下トンネルの構築には、
盛替切梁工法が採用されている。
Conventionally, when constructing underground tunnels such as subway general track sections,
The shorikae cut beam construction method has been adopted.

盛替切梁工法は、土庄、山蟹工法、杭間隔および切梁の
位置、あるいは安全性、工事の速さおよび経済性等によ
ってその施工方法に相違があるが、若材令の躯体コンク
リートに悪影響を与えない一般的方法としては、既にコ
ンクリート打設が完了した躯体の内外に切梁を設置し、
直上段の切梁を解体する方法がある。第1図はこの従来
工法によって地下鉄一般線路部の地下トンネルを構築す
る施工順序を示したものである。
There are differences in the construction methods of the Morigae Kiribe construction method, such as the Tonosho method, the Yamagani construction method, the pile spacing, the position of the cut beams, safety, speed of construction, economical efficiency, etc., but it is A general method that does not cause any negative impact is to install struts inside and outside of the concrete structure that has already been poured.
There is a way to dismantle the strut directly above. Figure 1 shows the construction sequence for constructing an underground tunnel for a subway general track section using this conventional construction method.

すなわち、■ 下床コンクリート打設(防水を含む。In other words, ■ Subfloor concrete placement (including waterproofing).

)■ 下床ハンチコンクリート打設、側部防水■ 捨切
梁■ 捨切梁■の直上切梁解体 霊}集および側壁コンクリ−ト打設、側部防鯵}内盛替
切梁架設および捨切梁■ 捨切梁■の直上切梁解体 ■ 側壁上部および上床コンクリート打設、防水がその
従来工法の施工順序である。
) ■ Placing subfloor corbel concrete, side waterproofing ■ Supposed beams ■ Demolition of the directly above stump beams and pouring of side wall concrete, erection of replacement stump beams inside the side corbels, and dumping The conventional construction method includes dismantling the cut beam directly above the cut beam■, pouring concrete for the upper part of the side wall and the upper floor, and waterproofing.

ところで、盛替籾梁の設置には次のような作業および問
題点が付髄する。
By the way, the following work and problems are involved in the installation of the replacement paddy beams.

‘ィー 腹起しを受けるブラケット等の取付けおよび撤
去‘o} 盛替切梁用継村の中間杭への取付けおよび撤
去し一 用済後解体した材料の駄目穴からの搬出9 盛
替切梁の架設および撤去時の安全上の問題などがあり、
その作業は煩雑であるうえ、危険を伴うものである。
Attachment and removal of brackets, etc. that receive uprights. Attachment to and removal of intermediate piles for replacement beams. 1. Carrying out dismantled materials from dead holes after use. 9. There are safety issues when constructing and removing beams.
The work is not only complicated but also dangerous.

本発明は、従来工法における問題点の解消を図ることを
目的とするものであって、盛替切梁工法における作業の
簡素化と作業上の安全を確保することができる移動式セ
ントルを用いるトンネルの施工方法を提供するものであ
る。
The present invention aims to solve the problems in conventional construction methods, and is a tunnel using a mobile center that can simplify the work and ensure work safety in the replacement cut beam construction method. This provides a construction method.

次に本発明の施工方法を地下鉄一般線路部の施工例につ
いて具体的に説明する。
Next, the construction method of the present invention will be specifically explained with reference to a construction example of a subway general track section.

第2図ないし第5図において〜 重!ま下床、2は下床
ハンチ部、3は側壁下部、4は上り線トンネルと下り線
トンネル間の柱であって、これらは開削溝内にト第1図
に示した従来工法の施工順序■〜■でコンクリートの打
設によって構築されるものである。
In Figures 2 to 5 ~ Heavy! The lower floor, 2 is the lower floor haunch, 3 is the lower part of the side wall, and 4 is the pillar between the up and down tunnels. ■~■It is constructed by pouring concrete.

なお、5は上り線トンネルと下り糠トンネル間に設けら
れた中間杭であって、柱4を避けるため上り線トンネル
側寄りに位置している。第1図においても5は同機の中
間杭を示している。本発明の施工法に用いる移動式セン
トルのうち下部セントル6は第2,3図に示すすように
6,6′の2種類ある。その一方のものは、側壁下部3
の高さよりやや低い高さに上下の桁材をもって直方体状
に組立てたセントル本体7の上部両側にそれぞれ横方向
に挿縮するジャッキ8を取付けてなるものであって、セ
ントル7は下床翼面上に並べたコロ9上に設置される。
下部セントル6のセントル本体7の両側の桁上面は前後
方向に延びる溝型状レールをなしている。他の下部セン
トル6′は、上記下部セントル6のセントル本体7より
横幅をせまく形成したセントル本体7デの一側上部に横
方向に伸縮するジャッキ8′を取付け、その他側上部に
はヒンジ構造により水平状態から下方へ垂直状態に折た
たみ可能に取付けた切梁9′の先端にジャッキ8′を取
付けた構造のものである。このように、ジャッキ8′を
取付けた切梁9′を折たたみ可能にしたのは、移動の際
に中間杭5を避けるためである。また、上部セントル1
0も第4,5図に示すようにIQ,10′の2種類あり
、その一方のものは、下部セントル6のセ、ントル本体
7上を滑動させるセントル本体11の上部に上床型枠1
2を取付けてなるものであって「 セントル本体11の
下面には、下部セントル6のセントル本体7上面のレー
ルを滑動するソリ量3が取付けられている。
Note that 5 is an intermediate pile provided between the up-line tunnel and the down-line tunnel, and is located closer to the up-line tunnel side in order to avoid the pillar 4. In Figure 1, 5 also indicates the intermediate pile of the aircraft. Among the movable centers used in the construction method of the present invention, there are two types of lower centers 6, 6 and 6', as shown in FIGS. One of them is the lower part of the side wall 3
The center body 7 is assembled into a rectangular parallelepiped shape with upper and lower spars at a height slightly lower than the height of It is installed on the rollers 9 arranged above.
The girder upper surfaces on both sides of the center body 7 of the lower center center 6 form groove-shaped rails extending in the front-rear direction. The other lower center 6' has a horizontally expandable jack 8' attached to the upper part of one side of the center main body 7, which is narrower in width than the center main body 7 of the lower center 6, and has a hinge structure at the upper part of the other side. It has a structure in which a jack 8' is attached to the tip of a strut 9' which is foldable from a horizontal position downward to a vertical position. The reason why the strut 9' to which the jack 8' is attached is made foldable is to avoid the intermediate pile 5 during movement. Also, upper center 1
0 also has two types, IQ and 10', as shown in FIGS.
2 is attached to the lower surface of the center body 11, and a sled 3 is attached to the lower surface of the center body 11 to slide on a rail on the upper surface of the center body 7 of the lower center center 6.

他の上部セントル10′は、上床型枠12′の一側張出
部分をヒンジ構造により上下に折たたみ可能にしたもの
であり〜そのセントル本体13′の下面には下部セント
ル6′のセントル本体7′上面のレールを滑動するソリ
13′が取付けられている。上床型枠12′を折たたみ
可能にしたのは移動の際に中間杭5を避けるためである
。叙上の如き下部セントル6,6′、上部セントルー0
,10′は、第2図に鎖線で示す側壁上部14および上
床15のコンクリート打設に使用されるが〜下部セント
ル6と上部セントル竃Q‘ま中間杭5のない下り線トン
ネル側の施工に、下部セントル6′と上部セントルIQ
′は中間杭5のある上り線トンネル側の施工にそれぞれ
用いられる。
The other upper center 10' has a side projecting part of the upper floor formwork 12' that can be folded up and down by a hinge structure. A sled 13' is attached that slides on a rail on the upper surface of 7'. The reason why the upper floor formwork 12' is made foldable is to avoid the intermediate piles 5 during movement. Lower center 6, 6' as described above, upper center 0
, 10' are used for concreting the upper part of the side wall 14 and the upper floor 15, which are shown by chain lines in Fig. 2.The lower center 6 and the upper center Q' are used for construction on the down-line tunnel side where there is no intermediate pile 5. , lower center 6′ and upper center IQ
' is used for construction on the up-line tunnel side where the intermediate pile 5 is located.

まず「中間杭5のない下り線トンネル側においてはし下
部セントル6を2基と上部セントルIQを1基用意して
、第6図1〜6に示すように1基の下部セントル6を既
に側壁上部貴4および上床富5のコンクリート打設が完
了した位置の下床1面上に、他の1基の下部セントル6
をその前方に接続状にそれぞれ設置し÷上部セントルー
0を後方の下部セントル6上に戦暦する。また、中間杭
5のある上り線側においても、同様に下部セントル6′
を2基と上部セントル10′を1基配設する。そしてト
次に側壁上部14および上床15を構築する位置すなわ
ち前方の下部セントル6,6′の位置で第1図に示す■
〜■の工程を終えた後「従来工の■の工程にかえて前方
の下部セントル6,6′の上部両側のジャッキ8,8′
を伸長させて側壁下部3の上部を内側から互いに突張る
状態に内盛替を行い、かつ側壁下部3の裏側に捨切梁■
を入れる。そして「捨切梁■の直上の功梁■を解体し「
上床型枠12,富2′を下げて上部セントル10,10
′を前方の下部セントル6,6′上に移動させ「側壁上
部14および上床15のコンクリートを打設し養生する
。次いで所定の時間が経過したならば、上床型枠12,
12′を下げ、上部セントル10,10′を一旦後方の
下部セントル6,6′上に引戻し、前方の下部セントル
6,6′を次に側壁上部14、上床15のコンクリート
を打設する位置まで移動させ、その位置に捨切梁■を入
れ、前方の下部セントル6,6′のジャッキ8を伸長さ
せて側壁下部3の上部を内盛替した後、上部セントル1
0,10′を載せた後方の下部セントル6,6′を前方
の下部セントル6,6′に連接する位置まで移動させて
、前記同様に側壁上部14および上床15のコンクリー
ト打設を行う。以下同様の工程を繰返して上り線および
下り線トンネルの構築も進行させる。なお、上り線トン
ネル側には中間杭5があるので、下部セントル6′の移
動に際しては切梁9′を下方に倒し「また上部セントル
10′の移動に際しても上床型枠12′の一側を下方へ
倒した状態にし、中間杭5を避ける。そして、それらが
所定の位置に移動されたならば、切梁9fおよび上床型
枠12′の一側を上方へはね上げてその状態に保持して
おけばよい。本発明に係る移動式セントルの施工方法は
、以上説明したように、地下トンネルの側壁および上床
を盛替切梁工法によって構築する施工方法であって、土
蟹坑内の下床面上を移動可能で内盛替切梁の機能をそな
えた下部セントル2基と「 この下部セントル上を滑動
させる上床型枠用の上部セントル1基を設け、側壁上部
および上床コンクリート打設位置とその後方にそれぞれ
下部セントルを連接状態に設置すると共に「上部セント
ルを後方の下部セントル上に設置して、側壁裏捨切梁施
工と側壁上部および上床コンクリート打談位置の切梁を
解体し、上部セントルを前方の下部セントル上に移動さ
せて側壁上部および上床コンクリートを打設した後、上
部セントルを一旦後方の下部セントル上に引戻し、次い
で前方の下部セントルを次の施工位置まで移動させ、上
部セントルを載せた後方の下部セントルを前方の下部セ
ントルに連接する位層まで移動させて、以後前記工程を
繰返すものであるから、側壁上部および上床コンクリー
トの打設にあたり、内盛替作業を下部セントルの移動に
よって、また上床型枠の設置も上部セントルの移動によ
って簡易迅速に、しかも安全に行うことができ、従来工
法における種々の問題点の一挙解決を図り、併せて作業
能率の大幅な向上を図ることができる効果が得られる。
First, prepare two lower center centers 6 and one upper center center IQ on the down-line tunnel side where there is no intermediate pile 5, and one lower center center 6 is already attached to the side wall as shown in FIGS. One other lower center 6 is installed on the first floor of the lower floor at the location where the concrete pouring of the upper center 4 and upper floor 5 has been completed.
are installed in a connected manner in front of them, and the upper center 0 is placed on the lower center 6 at the rear. Similarly, on the up line side where the intermediate stake 5 is located, the lower center 6'
Two units and one upper center 10' are installed. Then, at the position where the upper part of the side wall 14 and the upper floor 15 are to be constructed, that is, the position of the front lower center 6, 6', as shown in FIG.
After completing the steps ~■, instead of doing the conventional process ■, install the jacks 8, 8' on both sides of the upper part of the front lower center 6, 6'.
Extend the upper part of the lower part of the side wall 3 and replace it internally so that it extends from the inside, and install a cut beam on the back side of the lower part of the side wall 3.
Put in. Then, ``the gong beam■ directly above the stub beam■ was dismantled and''
Upper floor formwork 12, lower the wealth 2' and upper center 10, 10
' is moved onto the front lower center 6, 6', and the concrete for the upper part of the side wall 14 and the upper floor 15 is poured and cured.Next, when a predetermined period of time has elapsed, the upper floor formwork 12,
12', pull the upper center centers 10, 10' back onto the rear lower center centers 6, 6', and then move the front lower center centers 6, 6' to the position where the concrete for the upper part of the side wall 14 and upper floor 15 will be poured. After moving it and inserting the cut-off beam ■ in that position, extending the jacks 8 of the front lower center centers 6 and 6' and replacing the upper part of the lower part of the side wall 3, the upper center center 1
The rear lower center centers 6, 6' on which 0, 10' are placed are moved to a position where they are connected to the front lower center centers 6, 6', and concrete is poured for the side wall upper part 14 and the upper floor 15 in the same manner as described above. Thereafter, the same process is repeated to proceed with the construction of uplink and downlink tunnels. In addition, since there is an intermediate pile 5 on the up-line tunnel side, when moving the lower center 6', the strait 9' must be pushed down.Also, when moving the upper center 10', one side of the upper floor formwork 12' must be It is brought down to avoid the intermediate pile 5. Then, once they have been moved to a predetermined position, the strut 9f and one side of the upper floor formwork 12' are flipped upward and held in that state. As explained above, the construction method of the mobile center according to the present invention is a construction method in which the side walls and upper floor of an underground tunnel are constructed by the replacement beam construction method, and the lower floor surface in the earth crab tunnel is There are two lower centers that can be moved on the top and have the function of internal replacement cut beams, and one upper center for the upper floor formwork that slides on these lower centers. At the same time, install the lower center in a connected state on each side, install the upper center on the lower center at the rear, dismantle the side wall back cut beam construction and the top of the side wall and the upper floor concrete pouring position, and then install the upper center on the upper center. After moving the front lower center onto the front lower center and pouring the upper part of the side wall and upper floor concrete, the upper center is once pulled back onto the rear lower center, then the front lower center is moved to the next construction position, and the upper center is placed. The placed rear lower center is moved to the level where it connects to the front lower center, and the above process is then repeated. Therefore, when pouring concrete for the upper part of the side walls and upper floor, the inner refilling work is carried out by moving the lower center. In addition, by moving the upper center, the upper floor formwork can be installed easily, quickly, and safely, which solves all the problems of conventional construction methods and greatly improves work efficiency. The effect that can be obtained is obtained.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明に係る施工方法を地下鉄一般線路部の施工
例について実施した態様を示すものであって、第1図は
従来工法の施工順序を示した縦断正面図、第2図は本発
明による下部セントルの正面図、第3図は同上側面図「
第4図は同じく上部セントルの正面図、第5図は同上側
面図、第6図は本発明による施工法の説明図である。 1…・・・下床、2……下床ハンチ、3…・・・側壁下
部、4・…・・柱、5・…・・中間杭、6,6′…・・
。 下部セントル、10,10′……上部セントル、12,
12′・・・…上床型枠、14・・・…側壁上部、15
…・・・上床。第1図 第2図 第3図 第4図 第5図 第6図
The drawings show an embodiment in which the construction method according to the present invention was implemented for a construction example of a subway general track section, and FIG. 1 is a vertical cross-sectional front view showing the construction order of the conventional construction method, and FIG. 2 is a construction method according to the present invention. The front view of the lower center, Figure 3 is the side view of the same as above.
FIG. 4 is a front view of the upper center, FIG. 5 is a side view of the same, and FIG. 6 is an explanatory diagram of the construction method according to the present invention. 1...Subfloor, 2...Subfloor haunch, 3...Bottom part of side wall, 4...Column, 5...Intermediate pile, 6,6'...
. Lower center, 10, 10'... Upper center, 12,
12'...Top floor formwork, 14...Top of side wall, 15
...Upper floor. Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6

Claims (1)

【特許請求の範囲】[Claims] 1 地下トンネルの側壁および上床を盛替切梁工法によ
つて構築する施工方法であつて、土留坑内の下床面上を
移動可能で内盛替切梁の機能をそなえた下部セントル2
基と、この下部セントル上を滑動させる上床型枠用の上
部セントル1基を用い、側壁上部および上床コンクリー
ト打設位置とその後方にそれぞれ下部セントルを連続状
態に設置すると共に、上部セントルを後方の下部セント
ル上に設置して、打設位置の下部セントルで内盛替及び
側壁裏捨切梁施工をすると共に、側壁上部及び上床コン
クリート打設位置の切梁を解体し、上部セントルを打設
位置の下部セントル上に移動させて側壁上部及び上床コ
ンクリートを打設した後、上部セントルを一旦後方の下
部セントル上に引戻し、次いで打設位置の下部セントル
を次の施工位置まで移動させ、上部セントルを載せた後
方の下部セントルを打設位置の下部セントルに連接する
位置まで移動させて、以後前記工程を繰返すことを特徴
とする移動式セントルを用いるトンネルの施工方法。
1. A construction method in which the side walls and upper floor of an underground tunnel are constructed using the refill beam construction method, in which a lower center is movable on the lower floor surface of the earth retaining shaft and has the function of an internal refill beam.
Using a base and an upper center for the upper floor formwork that slides on this lower center, the lower centers are installed continuously at and behind the upper part of the side walls and the upper floor concrete pouring position, and the upper center is installed at the rear. Installed on the lower center, internal replacement and construction of side wall back cut beams are carried out at the lower center at the pouring position, and the cut beams at the upper part of the side wall and upper floor concrete pouring position are dismantled, and the upper center is placed at the pouring position. After placing the upper part of the side wall and upper floor concrete, the upper center is once pulled back onto the lower center at the rear, and then the lower center at the pouring position is moved to the next construction position, and the upper center is moved to the next construction position. A method for constructing a tunnel using a movable center, characterized in that the lower center placed at the rear is moved to a position where it connects to the lower center at the pouring position, and the above steps are repeated thereafter.
JP55019379A 1980-02-19 1980-02-19 Tunnel construction method using mobile center Expired JPS607119B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP55019379A JPS607119B2 (en) 1980-02-19 1980-02-19 Tunnel construction method using mobile center

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP55019379A JPS607119B2 (en) 1980-02-19 1980-02-19 Tunnel construction method using mobile center

Publications (2)

Publication Number Publication Date
JPS56115500A JPS56115500A (en) 1981-09-10
JPS607119B2 true JPS607119B2 (en) 1985-02-22

Family

ID=11997676

Family Applications (1)

Application Number Title Priority Date Filing Date
JP55019379A Expired JPS607119B2 (en) 1980-02-19 1980-02-19 Tunnel construction method using mobile center

Country Status (1)

Country Link
JP (1) JPS607119B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS579998A (en) * 1980-06-18 1982-01-19 Okabe Kk Execution of culvert
JP6664699B2 (en) * 2016-02-03 2020-03-13 清水建設株式会社 Mountain retaining method and support system

Also Published As

Publication number Publication date
JPS56115500A (en) 1981-09-10

Similar Documents

Publication Publication Date Title
CN207160062U (en) A kind of underground is without post overlapping wall station
CN112962459B (en) Integrated bridge girder erection machine for piling, pier mounting and girder erection and bridge construction method
CN104594204A (en) Construction supporting system for hill type U beam of viaduct of urban light rail and construction method
CN102268858B (en) Cradle for suspension pouring of arch-type bridge
CN109057321A (en) Integral steel platform mould bases super large bearing capacity attached wall system and construction method
CN109736593B (en) Underground engineering group pit mid-partition wall chiseling method
CN112323627A (en) Frame type construction system and construction method in existing railway temporary bridge construction
RU2692518C1 (en) Method for constructing a three-span subway station of an open method of performing works with a lateral arrangement of passenger platforms and a double-track still tunnel
JPS607119B2 (en) Tunnel construction method using mobile center
KR20130042721A (en) Concrete filling apparatus using temporary bridge
JPH09125318A (en) Construction device of bridge girder
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
JP2829363B2 (en) Formwork equipment for pillar construction
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
CN218147885U (en) Movable rainwater box culvert outer template mounting and dismounting trolley
CN218953323U (en) Tunnel vault formwork construction trolley
AU597836B2 (en) Wall casting system
JPH11140892A (en) Method for excavating ground and method for constructing underground structure using the same
KR20190092676A (en) Method for constructing level tunnel connecting part of vertical structure and apparatus thereof
JPS6114300B2 (en)
CN220704323U (en) Integrated bridging equipment
US3392496A (en) Building skeleton of precast modular units with assembly adjunct
CN217536634U (en) Stride and prop landing stage
JP3234442B2 (en) Building and scrap type building method
CN112609701B (en) Method for dismantling inner support of deep foundation pit