JPS6151089B2 - - Google Patents

Info

Publication number
JPS6151089B2
JPS6151089B2 JP58205964A JP20596483A JPS6151089B2 JP S6151089 B2 JPS6151089 B2 JP S6151089B2 JP 58205964 A JP58205964 A JP 58205964A JP 20596483 A JP20596483 A JP 20596483A JP S6151089 B2 JPS6151089 B2 JP S6151089B2
Authority
JP
Japan
Prior art keywords
invert
formwork
concrete
end plate
slide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP58205964A
Other languages
Japanese (ja)
Other versions
JPS6098004A (en
Inventor
Masabumi Saito
Kyoshi Matsumoto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP58205964A priority Critical patent/JPS6098004A/en
Publication of JPS6098004A publication Critical patent/JPS6098004A/en
Publication of JPS6151089B2 publication Critical patent/JPS6151089B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明はインバートスライド型枠装置に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an invert slide formwork apparatus.

トンネル工事において、地山の崩壊を防止する
ため、掘削後早急に力学的に土圧に対抗できる構
造の支保を構築する必要がある。
In tunnel construction, in order to prevent the ground from collapsing, it is necessary to construct a structural support that can mechanically resist earth pressure as soon as possible after excavation.

万一不安定な覆工状態で長期間放置すると底部
を最後に覆工する関係から底部の強度が発現する
以前に側壁土圧が作用して「盤ぶくれ現象」を発
生する場合もあるので早急に覆工を完了させる必
要がある。
If the lining is left in an unstable state for a long period of time, because the bottom is the last to be lined, side wall earth pressure may act before the bottom has developed its strength, causing a ``plate bulge'' phenomenon. It is necessary to complete the lining as soon as possible.

ところで、従来、インバートコンクリート(床
部分のコンクリート)用型枠(妻板)には次のよ
うな問題がある。
By the way, conventional forms (end plates) for invert concrete (floor concrete) have the following problems.

<イ> 従来のトンネルではまずインバートコン
クリートを約50cm程打設し、すべての仮設車両
等はその上面を走行させている。
<B> In conventional tunnels, approximately 50 cm of inverted concrete is first poured, and all temporary vehicles run on top of it.

そして最終的な仕上がりコンクリートは数ケ
月も以前に打設したインバートコンクリートの
上に打設するものである。
The final finished concrete is poured on top of the inverted concrete that was poured several months earlier.

<ロ> インバートコンクリートは単なる仕切板
で良いと言う事から従来軽視されていた。
<B> Inverted concrete has been neglected in the past because it can be used as a simple partition plate.

しかし、実際には正確な高さの維持、妻板の
断面に貫通する鉄筋の処理などの問題があつ
た。
However, in reality, there were problems such as maintaining accurate height and dealing with reinforcing bars that penetrated the cross section of the end plate.

しかもコンクリートを打設する度、妻板を新
しく加工していた。
What's more, every time concrete was poured, new gable boards were being processed.

そのため、型枠の枠組作業が煩雑であり、そ
のうえ枠組が低能率である。
Therefore, the work of assembling the formwork is complicated, and the efficiency of the framework is low.

<ハ> さらに、インバートの中央や側方に排水
溝を形成する場合には仕上げ高さや型枠組み立
ての容易さが要求される。
<C> Furthermore, when forming drainage grooves in the center or sides of the invert, the finished height and the ease of erecting the formwork are required.

本発明はこの様な点を改善するためになされた
もので型枠の操作性、作業性に優れ、高い打設精
度が得られるインバートスライド型枠装置を提供
する事を目的とする。
The present invention has been made to improve the above-mentioned problems, and an object of the present invention is to provide an invert slide formwork device that has excellent formwork operability and workability and can provide high pouring accuracy.

次に本発明の一実施例について説明するが、ま
ず本発明に係る装置の各部について説明する。
Next, an embodiment of the present invention will be described. First, each part of the apparatus according to the present invention will be described.

[イ] 全体の説明 本発明のインバートスライド型枠装置1は第
1図に示すように架台2と、この架台2の開削
側(以下「前方」と言う)に設けた妻板3と、
レール11上を走行する走行部、および既設イ
ンバート上に載置する制動部で構成する。
[B] Overall description As shown in FIG. 1, the invert slide formwork device 1 of the present invention includes a pedestal 2, a end plate 3 provided on the excavated side (hereinafter referred to as "front") of the pedestal 2,
It consists of a running section that runs on rails 11 and a braking section that is placed on the existing invert.

[ロ] 架台 架台2はトンネル縦断方向に並行に配置した
2本の縦断桁21と、この縦断桁21間ををト
ンネル断面方向に連絡する横断桁22で構成す
る。
[B] Frame The pedestal 2 is composed of two longitudinal girders 21 arranged in parallel in the longitudinal direction of the tunnel, and a transverse girder 22 that connects the longitudinal girders 21 in the cross-sectional direction of the tunnel.

縦断桁21の全長は架台2を開削方向にスラ
イドする関係から少なくとも、インバートコン
クリートの1スパン分の打設距離よりやや長く
形成する。
The total length of the longitudinal girder 21 is made to be at least slightly longer than the casting distance for one span of inverted concrete, since the pedestal 2 slides in the excavation direction.

[ハ] 走行部 縦断桁21の前端には伸縮自在な走行ジヤツ
キ5を床面に向けて取付け、この走行ジヤツキ
5の先端には床地盤に敷設したレール11上を
走行するサポートローラ51を設ける。
[C] Running part A telescopic running jack 5 is attached to the front end of the longitudinal girder 21 so as to face the floor, and a support roller 51 that runs on the rail 11 laid on the floor ground is provided at the tip of the running jack 5. .

縦断桁21の後端には回動腕6の回動自在に
軸支し、回動腕6の先端にはガイドローラ61
を設ける。
A rotating arm 6 is rotatably supported at the rear end of the longitudinal girder 21, and a guide roller 61 is provided at the tip of the rotating arm 6.
will be established.

すなわち、回動腕6および走行ジヤツキ5で
インバートスライド型枠装置1を支承した状態
で走行できるよう構成する。
That is, the invert slide formwork device 1 is configured to be able to travel with the rotating arm 6 and the traveling jack 5 supporting the invert slide formwork device 1.

[ニ] 制動部 縦断桁21の回動腕6側(以下「後方」と言
う)には床面に向けてストツパー4を突設す
る。
[D] Braking section A stopper 4 is provided on the rotary arm 6 side (hereinafter referred to as "rear") of the longitudinal girder 21 so as to protrude toward the floor surface.

ストツパー4の全長は回動腕6より短く形成
し、後述するようにインバートコンクリートを
打設する際、ストツパー4が回動腕6に代わつ
てインバートスライド型枠装置1を支承できる
よう構成する。ストツパー4でインバートスラ
イド型枠装置1を支持するとストツパー4の下
面が既設インバート面に係止してインバートス
ライド型枠装置1の移動を阻止する事ができ
る。
The entire length of the stopper 4 is formed to be shorter than that of the rotating arm 6, so that the stopper 4 can support the invert slide formwork device 1 in place of the rotating arm 6 when pouring invert concrete as described later. When the invert slide formwork device 1 is supported by the stopper 4, the lower surface of the stopper 4 is engaged with the existing invert surface, and movement of the invert slide formwork device 1 can be prevented.

なお、ストツパー4を伸縮自在に構成する事
も可能である。
Note that it is also possible to configure the stopper 4 to be extendable and retractable.

この場合、架台2のレベルが求め易くなる。 In this case, the level of the pedestal 2 can be easily determined.

[ホ] 妻板 インバートスライド型枠装置1の前方にはト
ンネル横断方向に妻板3を配置する。
[E] End plate A end plate 3 is arranged in front of the invert slide formwork device 1 in the tunnel crossing direction.

妻板3は縦断桁21を横断する方向に連絡す
る横断桁22に取り付けた垂直の板体である。
The end plate 3 is a vertical plate attached to the transverse girder 22 that communicates with the longitudinal girder 21 in the transverse direction.

従つて架台2をスライドしたときには架台2
と一体に移動する事になる。
Therefore, when the pedestal 2 is slid, the pedestal 2
It will move together with the.

インバートコンクリートを打設する際、鉄筋
82を妻板3から開削方向に露出させておく必
要がある。
When placing inverted concrete, it is necessary to expose the reinforcing bars 82 from the end plate 3 in the excavation direction.

そのため、例えば第4図に示すように妻板3
下面から鉄筋82が突出できる寸法に妻板3を
形成し、さらに、妻板3前方外面には横断材3
1を多少の間隔を介して取付け、妻板3と横断
材31との間を縦方向の小区分に分割する。
Therefore, for example, as shown in FIG.
The end plate 3 is formed to a size that allows the reinforcing bars 82 to protrude from the lower surface, and furthermore, a cross member 3 is provided on the front outer surface of the end plate 3.
1 are attached at some intervals, and the space between the end plate 3 and the cross member 31 is divided into small sections in the vertical direction.

妻板3下方の開放空間は、これらの小区分内
に細幅の板体32を鉄筋82と衝突しない位置
に差込み、キヤンバ33で固定して遮断する事
ができる。
The open space below the end plate 3 can be blocked by inserting the narrow plate body 32 into these small sections at a position where it does not collide with the reinforcing bars 82 and fixing it with a camber 33.

[ヘ] 溝型枠 溝型枠7は、インバート面に例えば集水溝や
排水溝を成形する際に使用する。
[F] Groove formwork The groove formwork 7 is used when forming, for example, a water collection groove or a drainage groove on the invert surface.

溝型枠7は第1図に示すように断面U字形の
連続型枠であり、この型枠7をインバートスラ
イド型枠装置1の中央に縦断桁21と平行に設
置する。
The groove formwork 7 is a continuous formwork with a U-shaped cross section as shown in FIG.

次に施工方法について説明する [イ] 引き出し準備(第2図) 公知の開削方法でトンネルを掘削し、掘削土
を坑外に運搬する。
Next, the construction method will be explained [a] Preparation for extraction (Figure 2) A tunnel is excavated using a known excavation method, and the excavated soil is transported outside the tunnel.

1スパンの掘削を完了したら新インバートA
の打設範囲の床面にレール11を敷設して前記
インバートスライド型枠装置1を引き出す。
After completing one span of excavation, a new invert A
A rail 11 is laid on the floor surface in the casting range, and the invert slide formwork device 1 is pulled out.

すなわちインバートスライド型枠装置1の回
動腕6を開いて既設インバーートBに支承さ
せ、同時に走行ジヤツキ5を伸長してインバー
トスライド型枠装置1を浮上させて、開削方向
に1スパンの距離だけ移動する。
That is, the rotating arm 6 of the invert slide formwork device 1 is opened and supported on the existing invert B, and at the same time, the traveling jack 5 is extended to levitate the invert slide formwork device 1 and move it by a distance of one span in the excavation direction. do.

レール11は埋殺しにしないでインバートス
ライド型枠装置1を移動したらレール11を開
削方向に移動して再使用する。
The rail 11 is not buried, but when the invert slide formwork device 1 is moved, the rail 11 is moved in the excavation direction and reused.

そして地山全域にアンカーボルトや吹付けコ
ンンクリートを施しアーチ状の一次覆工を形成
する。
Anchor bolts and sprayed concrete are then applied to the entire area of the ground to form an arch-shaped primary lining.

[ロ] 型枠の設置(第3図) インバートを打設するために、インバートス
ライド型枠装置1の回動腕6を畳み、ストツパ
ー4を既設インバートBに着地させる。
[B] Installation of the formwork (Fig. 3) To cast the invert, the rotating arm 6 of the invert slide formwork device 1 is folded, and the stopper 4 is landed on the existing invert B.

さらに妻板3の両側には第1図のように細幅
状の補強板からなる補助型枠9を縦断桁21と
並行に配置する。
Further, on both sides of the end plate 3, as shown in FIG. 1, auxiliary formwork 9 made of narrow reinforcing plates is arranged in parallel with the longitudinal girder 21.

この補助型枠9は打設するインバートの隅部
を傾斜面に形成して、側壁との打継部の滑りを
防止するためである。
The purpose of this auxiliary formwork 9 is to form the corner of the invert to be cast into an inclined surface to prevent the joint part from slipping with the side wall.

[ハ] インバート打設 インバートスライド型枠装置1の設置を完了
したらコンクリートを打設する。
[C] Invert pouring After completing the installation of the invert slide formwork device 1, pour concrete.

このとき、打設コンクリートの仕上がり面を
妻板3の上縁、および溝型枠7の上縁などに一
致させる事によつて容易に正確な仕上げ面を得
ることができる。
At this time, by aligning the finished surface of the poured concrete with the upper edge of the end plate 3 and the upper edge of the groove formwork 7, an accurate finished surface can be easily obtained.

その結果、床面には中央に溝81を開設した
軌道スラブ8が形成される。
As a result, a track slab 8 having a groove 81 in the center is formed on the floor surface.

[ニ] 脱型、移動 養生期間経過後、回動腕6を広げ、同時に走
行ジヤツキ5を伸長して軌道スラブ8からすべ
ての型枠を剥離する。
[D] Demoulding and movement After the curing period has elapsed, the rotating arms 6 are expanded, and at the same time the traveling jacks 5 are extended to peel off all the formwork from the track slab 8.

剥離作業はインバートスライド型枠装置1を
浮上するだけの簡単な操作で完了できるので手
数が掛からない。
The peeling work can be completed with a simple operation of floating the invert slide formwork device 1, so it does not require much effort.

浮上した状態のインバートスライド型枠装置
1を開削方向に移動して順次インバートコンク
リートを打設していく。
The floating invert slide formwork device 1 is moved in the excavation direction to successively place invert concrete.

本発明は以上説明したようになるから次のよう
に効果を期待することができる。
Since the present invention is as explained above, the following effects can be expected.

<イ> 従来のように仮設のインバートコンクリ
ートを打設せず、一回で仕上げ面まで施工して
しまうので運搬車等はその上を走行でき、トラ
フイカビリテイーが良好になる。
<B> Unlike conventional methods, temporary invert concrete is not poured, and the finished surface is constructed in one step, allowing transport vehicles to run on top of it, resulting in better troughability.

<ロ> 型枠を架台と一体に形成し、かつ、この
架台を走行自在に構成したので、型枠の移動お
よび設置が迅速となり作業の効率化を図る事が
できる。
<B> Since the formwork is formed integrally with the pedestal and the pedestal is configured to be movable, the formwork can be moved and installed quickly, and work efficiency can be improved.

<ハ> 複数箇所(妻板、溝型枠の上縁等)から
レベルを求めるのでインバートコンクリート
(軌道スラブ上面)の仕上げ面を正確に形成で
きる。
<C> Since the level is determined from multiple locations (end plate, upper edge of groove formwork, etc.), the finished surface of invert concrete (top surface of track slab) can be formed accurately.

<ニ> 妻板の製作や配筋作業、および地山掘削
面とのすり合せをコンクリート打設の都度行う
必要がなくなつた。
<d> There is no longer a need to manufacture gable boards, place reinforcements, and align them with the ground excavation surface each time concrete is poured.

<ホ> インバートの隅部の正確な傾斜面に成形
できるので側壁の覆工の為の型枠のセツトが容
易となる。
<E> Since the invert corner can be formed on a precise slope surface, it becomes easy to set the formwork for lining the side wall.

<ヘ> 溝型枠を使用した場合、集水溝および排
水溝を同時に施工できる。
<F> When using trench formwork, water collection trenches and drainage trenches can be constructed at the same time.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図:本発明の一実施例の説明図、第2、3
図:施工方法の説明図、第4図:妻板先端部分の
拡大図、第5図:インバートコンクリート打設状
態の設明図。 1:インバートスライド型枠装置、2:架台、
3:妻板、4:ストツパー、5:走行ジヤツキ、
6:回動腕。
Figure 1: Explanatory diagram of one embodiment of the present invention, 2nd and 3rd
Figure: Explanatory drawing of the construction method, Figure 4: Enlarged view of the end of the end plate, Figure 5: Construction drawing of the invert concrete placement state. 1: Invert slide formwork device, 2: Frame,
3: Wife board, 4: Stopper, 5: Running jack,
6: Rotating arm.

Claims (1)

【特許請求の範囲】 1 複数の縦断桁に、 横断方向に1枚の妻板を、 縦方向に溝型枠を各々一体に取り付け、 縦断桁の両端は走行可能に構成した事を特徴と
する、 インバートスライド型枠装置。
[Claims] 1. A plurality of longitudinal girders are integrally attached with one end plate in the transverse direction and a groove formwork in the longitudinal direction, and both ends of the longitudinal girders are configured to be movable. Invert slide formwork equipment.
JP58205964A 1983-11-04 1983-11-04 Invert slide type frame apparatus Granted JPS6098004A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58205964A JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58205964A JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Publications (2)

Publication Number Publication Date
JPS6098004A JPS6098004A (en) 1985-06-01
JPS6151089B2 true JPS6151089B2 (en) 1986-11-07

Family

ID=16515622

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58205964A Granted JPS6098004A (en) 1983-11-04 1983-11-04 Invert slide type frame apparatus

Country Status (1)

Country Link
JP (1) JPS6098004A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2327845A2 (en) * 2008-09-09 2011-06-01 Ju Tae Kim Floor construction apparatus

Also Published As

Publication number Publication date
JPS6098004A (en) 1985-06-01

Similar Documents

Publication Publication Date Title
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
CH615236A5 (en)
KR101917813B1 (en) Railroad lower part no dig excavation construction sructure and construction method using it
JP3318533B2 (en) Arch rib construction equipment for concrete arch bridges
JPS6349011B2 (en)
CN112323627A (en) Frame type construction system and construction method in existing railway temporary bridge construction
JPS6151089B2 (en)
JPS61216997A (en) Inverted slide mold frame apparatus
JPS62288269A (en) Method for extending underground stair of building
JP2845060B2 (en) Construction method of underground construction by fully automatic building construction system
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
JP4037004B2 (en) Construction method of underground structure
JPS6114300B2 (en)
JPH0584773B2 (en)
JPS6329064B2 (en)
US3442088A (en) Method and machine for building tunnels
CN212388598U (en) Pipe jacking pipe piece and parking steel structure combined prefabricated underground mechanical stereo garage structure
CN212375729U (en) Frame type construction system in existing railway temporary bridge construction
US3527553A (en) Apparatus for the construction of elevated ways
US2128284A (en) Method of constructing subways and like underground structures
JPH0633640B2 (en) Foundation slab structure
JP4083335B2 (en) Structure of retaining wall for construction of underground structure
JPS607119B2 (en) Tunnel construction method using mobile center
JPS61186623A (en) Method of building foundation of building
JP2003193405A (en) Grade separation and its constructing method