JPS6016698A - Pipe parallelly arranging method - Google Patents
Pipe parallelly arranging methodInfo
- Publication number
- JPS6016698A JPS6016698A JP58122233A JP12223383A JPS6016698A JP S6016698 A JPS6016698 A JP S6016698A JP 58122233 A JP58122233 A JP 58122233A JP 12223383 A JP12223383 A JP 12223383A JP S6016698 A JPS6016698 A JP S6016698A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- support
- piles
- traffic road
- underground structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明は交通路を横断して地下構造物を施工する際のパ
イプ並列工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a pipe parallel construction method when constructing an underground structure across a traffic route.
従来のパイプ並列工法(バイブルーフ工法若しくはアー
マ−工法)では施工すべき地下構造物(例えば、トンネ
ル)の断面輪郭に沿ってパイプを並設しており、地下構
造物の断面が方形の場合には、側壁部にパイプを上下方
向に重なる状態で打設しているが、パイプ打設機の位置
を上下方向に移し替える作業は仲々面倒である。In the conventional pipe parallel construction method (by roof construction method or armor construction method), pipes are installed in parallel along the cross-sectional contour of the underground structure (for example, a tunnel) to be constructed. In this method, the pipes are installed on the side wall in a vertically overlapping manner, but the work of relocating the pipe driving machine in the vertical direction is rather troublesome.
本発明は頂壁部のパイプ列を側方へ延長することによシ
側壁部のパイプ列の省略を図ったものであって、以下、
図示の一実施態様に基いてその詳細を説明する。The present invention aims to omit the pipe row on the side wall by extending the pipe row on the top wall laterally.
The details will be explained based on one illustrated embodiment.
図中、1は鉄道、道路のような交通路、2は交通路1を
横断して施工される地下構造物である。In the figure, 1 is a traffic route such as a railway or road, and 2 is an underground structure constructed across the traffic route 1.
本発明工法では、先ず、交通路1の両側に沿ってそれぞ
れ少くとも4本(図の場合は4本)の支持杭を打設する
が、この支持杭31 + 32+ 33+ 34(41
r 42 + 43 + 44 )は既製又は現場打ち
の何れでも良い。In the construction method of the present invention, first, at least four (four in the figure) support piles are driven along both sides of the traffic road 1, but the support piles 31 + 32 + 33 + 34 (41
r 42 + 43 + 44) may be either ready-made or cast in place.
支持杭32133(42143)の間隔は、交通路1に
対する地下構造物2の投影長(地下構造物2が交通路1
に直交する場合にはその幅員)に略々等しくし、また、
支持杭31132(41142)及び33 、34(4
3+44)の間隔は、地下構造物2の底面両端から引い
た土のすベシ線Sと地下構造物2の頂壁のレベルとの交
点を支持杭31(41)及び34 (44)の軸ノし・
が通ることを一応の目安として定める。The interval between the supporting piles 32133 (42143) is the projected length of the underground structure 2 with respect to the traffic route 1 (the distance between the underground structure 2 and the traffic route 1 is
(if the width is perpendicular to the width), and
Support piles 31132 (41142) and 33, 34 (4
3+44) is the distance between the intersection of the soil slope line S drawn from both ends of the bottom of the underground structure 2 and the level of the top wall of the underground structure 2 to the axis of the support piles 31 (41) and 34 (44). death·
As a tentative guideline, it is determined that the
次に、支持杭31132+ 33134 (41142
143144)上に受梁5(6)を載置し、各支持杭と
鉄筋等で剛結した後、両側の受梁5,6間に多数のパイ
プ7.7・・・を並設するが、各パイプ7は一側の受梁
5から他側の受梁6に向って直角に土中を前進させて両
端部を受梁5.6上に支承させる。Next, support piles 31132 + 33134 (41142
143144) After placing the support beams 5 (6) on top and rigidly connecting each support pile with reinforcing bars, etc., a large number of pipes 7, 7... are installed in parallel between the support beams 5 and 6 on both sides. , each pipe 7 is advanced through the soil at right angles from the support beam 5 on one side toward the support beam 6 on the other side, and both ends are supported on the support beam 5.6.
パイプ7の断面形状は任意であり、また、パイプ7とし
て両側に継手を設けたものを用い、図示のように隣接の
パイプ7.7間に連結部8を設けると、パイプ列を一体
化させることができる。The cross-sectional shape of the pipe 7 is arbitrary, and if the pipe 7 is provided with joints on both sides and a connecting part 8 is provided between adjacent pipes 7 and 7 as shown in the figure, the pipe rows can be integrated. be able to.
前述のパイプ列をtif成した後は、交通路1の活荷重
をパイプ列で受けさせることができるから、この状態で
支持杭32 r 33 (42r 43)間に地下構造
物2を施工する。After forming the above-mentioned pipe rows, the live load of the traffic road 1 can be received by the pipe rows, so the underground structure 2 is constructed between the support piles 32 r 33 (42 r 43) in this state.
地下構造物2は現場打ちコンクリートを既製コンクリー
ト体の何れで構成しても構わない。The underground structure 2 may be constructed of cast-in-place concrete or ready-made concrete.
現場打ちコンクリートで構成する場合は、支持杭32
+ 42間及び3a + 43間に土留を施しながら支
持杭32133(42143)間を機械掘削するが、前
記土留は側方土圧に耐えるだけの■ij易なもので良い
。When constructed with cast-in-place concrete, support piles 32
The space between the support piles 32133 (42143) is mechanically excavated while providing earth retaining between +42 and 3a +43, but the earth retaining may be of a simple type that can withstand lateral earth pressure.
パイプ列を永久構造物として残すときは、側壁部のコン
クリートの厚さを薄くすることができ、また頂壁部はパ
イプ列で構成されるのでその下ff1l+を化粧仕上げ
するだけで良い。When the pipe row is left as a permanent structure, the thickness of the concrete on the side wall can be made thinner, and since the top wall is composed of the pipe row, it is only necessary to apply a decorative finish to the bottom ff1l+.
既製コンクリート体を用いる場合は、索引若しくは推進
工法で前進させて所定位置にセットするが、パイプ列を
残すときのコンクリート体はU型に形成する。If a ready-made concrete body is used, it is advanced by an indexing or propulsion method and set in a predetermined position, but the concrete body is formed into a U-shape when leaving a row of pipes.
前述の説明から明らかなように、本発明工法は、パイプ
列で交通路の活荷重を完全に支持した状態で交通路を横
断する地下構造物の施工を行うので、容易かつ安全に工
事を行うことができ、しかも、パイプ列は横にだけ延び
ているので、パイプ列形成時の機械の盛シ替えが容易で
あシ、全体的に工期が短縮されコスト的にも有利である
。As is clear from the above explanation, the construction method of the present invention performs construction of an underground structure that crosses a traffic route while fully supporting the live load of the traffic route with pipe rows, so construction can be carried out easily and safely. Moreover, since the pipe rows extend only horizontally, it is easy to change the machine when forming the pipe rows, and the overall construction period is shortened, which is advantageous in terms of cost.
図面は本発明の一実施態様の説明図であって、第1図は
側面図、第2図は第1図のX−X線断面図である。
図中、l・・・交通路、2・・・地下M9造物、31,
3□。
33134 + 4+ + 42 + 43 + 44
・・・支掲杭、5,6・・・受梁、7・・・パイプ、・
・・・・・
特許出願人 日本国有鉄道
同 不動建設株式会社
代理人弁理士 染 谷 廣 司The drawings are explanatory diagrams of one embodiment of the present invention, in which FIG. 1 is a side view and FIG. 2 is a sectional view taken along the line X--X in FIG. 1. In the diagram, l... Traffic route, 2... Underground M9 structure, 31,
3□. 33134 + 4+ + 42 + 43 + 44
... Support pile, 5, 6... Support beam, 7... Pipe,
...Patent applicant Hiroshi Sometani, patent attorney for Fudo Construction Co., Ltd., Japan National Railways
Claims (1)
も各4本の支持杭を打設し、両側の支持杭列上にそれぞ
れ受梁を架設するとともに、−側の受梁から他側の受梁
に向って多数のパイプを渡して、交通路面下に受梁の全
長に亘るパイプ列を構成し、該パイプ列で交通路の活荷
重を支持しつつ、最外側の一支持杭に隣接する支持杭間
に、交通路を横断する地下構造物を施工することを特徴
゛とするパイプ並列工法。At least four support piles are driven at specified intervals on both sides of the traffic road parallel to the traffic road, and support beams are erected on each row of support piles on both sides. A large number of pipes are passed toward the support beam to form a pipe row that spans the entire length of the support beam under the traffic road surface, and while supporting the live load of the traffic road with this pipe row, it is placed adjacent to one of the outermost support piles. A pipe parallel construction method characterized by constructing an underground structure that crosses the traffic route between the supporting piles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58122233A JPS6016698A (en) | 1983-07-05 | 1983-07-05 | Pipe parallelly arranging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58122233A JPS6016698A (en) | 1983-07-05 | 1983-07-05 | Pipe parallelly arranging method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6016698A true JPS6016698A (en) | 1985-01-28 |
Family
ID=14830863
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP58122233A Pending JPS6016698A (en) | 1983-07-05 | 1983-07-05 | Pipe parallelly arranging method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6016698A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04198593A (en) * | 1990-11-28 | 1992-07-17 | Fujii Kiso Sekkei Jimusho:Kk | Construction of half tunnel and construction method thereof |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57143091A (en) * | 1981-02-28 | 1982-09-04 | Sumitomo Metal Ind | Construction of tunnel using horizontal steel pipe sheet pipe support |
JPS5813897A (en) * | 1981-07-17 | 1983-01-26 | 株式会社奥村組 | Drilling of horizontal hole under track |
-
1983
- 1983-07-05 JP JP58122233A patent/JPS6016698A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57143091A (en) * | 1981-02-28 | 1982-09-04 | Sumitomo Metal Ind | Construction of tunnel using horizontal steel pipe sheet pipe support |
JPS5813897A (en) * | 1981-07-17 | 1983-01-26 | 株式会社奥村組 | Drilling of horizontal hole under track |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04198593A (en) * | 1990-11-28 | 1992-07-17 | Fujii Kiso Sekkei Jimusho:Kk | Construction of half tunnel and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207144538U (en) | A kind of underground structure top board reserving hole temporary plugging structure | |
JPS62133209A (en) | Construction method for steel sheet pile retaining wall, and steel sheet pile for retaining wall | |
JPS6016698A (en) | Pipe parallelly arranging method | |
JP2000179299A (en) | Large-section tunnel construction method | |
JPS584094A (en) | Method of constructing low road cross | |
JP2017020176A (en) | Abutment reinforcement structure and reinforcing method | |
JP2860751B2 (en) | Construction method of underpass introduction section | |
JPH041811B2 (en) | ||
JP3045907B2 (en) | Construction method of continuous wall support pile | |
JP3049347B2 (en) | Earth retaining wall | |
JPS5841227Y2 (en) | Element for mountain retainer | |
JPS5853321Y2 (en) | Element for mountain retainer | |
JPS59195996A (en) | Tunnel constructing method | |
JP3471435B2 (en) | Tunnel wall | |
JPH0553888B2 (en) | ||
JPS5947776B2 (en) | Method for creating a cut slope using a lattice retaining wall | |
JPS5853322Y2 (en) | Vertical joints in underground walls | |
JPH07102507A (en) | Method for constructing earth retaining wall | |
JPS6237497A (en) | Pipe beam structure | |
JPS6131593A (en) | Construction of crossing structure under traffic road | |
JPH102200A (en) | Constructing method of underground structure and retaining wall | |
JPH0370050B2 (en) | ||
JPS59109606A (en) | Self-supporting type reinforced steel jacket revetment | |
JPS60133117A (en) | Method of constructing joint part of continuous underground wall | |
JPH05230842A (en) | Construction method of underground structure |