JPH102200A - Constructing method of underground structure and retaining wall - Google Patents
Constructing method of underground structure and retaining wallInfo
- Publication number
- JPH102200A JPH102200A JP8177351A JP17735196A JPH102200A JP H102200 A JPH102200 A JP H102200A JP 8177351 A JP8177351 A JP 8177351A JP 17735196 A JP17735196 A JP 17735196A JP H102200 A JPH102200 A JP H102200A
- Authority
- JP
- Japan
- Prior art keywords
- shields
- retaining wall
- ground
- shaft
- underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、大型地下ダム、大
型擁壁、先行地中梁などの地中構造物の構築方法に関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure such as a large underground dam, a large retaining wall, and a preceding underground beam.
【0002】[0002]
【発明が解決しようとする課題】従来、大型地下ダムや
擁壁等を構築する場合、地上から大型の機械を用いて施
工を行っていたため、地上の施工条件が制約されると施
工が困難であった。本発明は、地上の制約を受けないで
地中構造物の構築が可能な方法を提供する。Conventionally, when constructing a large underground dam or retaining wall, construction has been carried out using large machines from the ground. Therefore, if the construction conditions on the ground are restricted, the construction is difficult. there were. The present invention provides a method capable of constructing an underground structure without being restricted by the ground.
【0003】[0003]
【課題を解決するための手段】上記課題を解決するため
の手段として、本発明は、立坑から地中に複数のシ−ル
ドを間隔をおいて並列させて施工した後、これらのシ−
ルド間を一体に接続して行うことを特徴とした、地中構
造物の構築方法を提供する。As a means for solving the above-mentioned problems, the present invention relates to a method for constructing a plurality of shields in parallel from a shaft in the ground at intervals and then constructing these shields.
The present invention provides a method of constructing an underground structure, characterized in that the fields are connected to each other.
【0004】また、地山を押さえる土留壁体部と、この
土留壁体部の下部の地山側にほぼ水平方向に連続する支
持底部とよりなる擁壁の構築方法において、立坑から地
中の前記擁壁の構築予定場所に、ほぼ水平方向の複数の
シ−ルドを間隔をおいて並列させて施工し、これらのシ
−ルド間を一体に接続して擁壁を構築した後、擁壁の前
面を掘削して行うことを特徴とした、擁壁の構築方法を
提供する。Further, in a method for constructing a retaining wall comprising a retaining wall portion for holding a ground and a supporting bottom portion which is substantially horizontally continuous with a lower portion of the retaining wall in the ground side, a method for constructing the retaining wall from the shaft to the underground is provided. At the place where the retaining wall is to be constructed, a plurality of shields in a substantially horizontal direction are installed in parallel at intervals, and these shields are connected together to construct the retaining wall. A method for constructing a retaining wall, characterized by excavating the front surface, is provided.
【0005】さらに、地山を押さえる土留壁体部と、こ
の土留壁体部の下部の地山側にほぼ水平方向に連続する
支持底部とよりなる擁壁の構築方法において、立坑から
地中の前記擁壁の構築予定場所に、ほぼ水平方向の複数
のシ−ルドを、シ−ルド同士を接合しながら並列させて
擁壁を構築した後、擁壁の前面を掘削して行うことを特
徴とした、擁壁の構築方法を提供する。[0005] Further, in a method of constructing a retaining wall comprising a soil retaining wall portion for holding the ground and a supporting bottom portion which is substantially horizontally continuous with the lower ground side of the retaining wall portion, the above-mentioned method is used to construct the retaining wall from the shaft to the underground. At the location where the retaining wall is to be constructed, a plurality of shields in a substantially horizontal direction are arranged side by side while joining the shields to construct a retaining wall, and then excavating the front surface of the retaining wall. To provide a method for building retaining walls.
【0006】[0006]
【発明の実施の形態1】図1〜3は地下ダムの構築例を
示す。先ず、図1、2に示すように、地上の制約を受け
ない場所に立坑1を掘削する。First Embodiment FIGS. 1 to 3 show an example of construction of a subsurface dam. First, as shown in FIGS. 1 and 2, a shaft 1 is excavated in a place where there is no restriction on the ground.
【0007】次に、立坑1内から地下ダムの構築予定場
所に、ほぼ水平方向にシ−ルド機2を発進させてシ−ル
ド3を構築する。シ−ルド3は、上下方向に所定の間隔
をおいて複数層にわたって構築する。Next, a shield machine 2 is started in a substantially horizontal direction from a shaft 1 to a place where an underground dam is to be constructed, thereby constructing a shield 3. The shield 3 is constructed over a plurality of layers at predetermined intervals in the vertical direction.
【0008】なお、本実施の形態は、縦長の矩形シ−ル
ド機を用い、その後方に予め長方形に製作したセグメン
トユニットを連結してシ−ルドを構築する場合である
が、円形シ−ルド機でも構わない。また、立坑1の掘削
は、シ−ルド3を上層から順に発進させるのに伴って、
次第に下方に掘削していくとよい。In this embodiment, a vertically long rectangular shield machine is used, and a shield is constructed by connecting segment units made in advance in a rectangular shape to the rear thereof. It can be a machine. The excavation of the shaft 1 is performed by starting the shield 3 in order from the upper layer.
It is good to dig down gradually.
【0009】シ−ルド3をすべて構築した後は、図3に
示すように、シ−ルド3間に接続部31を構築する。接
続部31の構造は、鉄筋コンクリ−ト構造、PC構造、
無筋コンクリ−ト構造、SRC構造、鉄骨構造等を適宜
選択する。After all the shields 3 have been constructed, as shown in FIG. 3, a connecting portion 31 is constructed between the shields 3. The structure of the connecting portion 31 is a reinforced concrete structure, a PC structure,
A plain concrete structure, an SRC structure, a steel structure and the like are appropriately selected.
【0010】そして、シ−ルド3間のすべての接続部3
1を構築した後、シ−ルド3内にコンクリ−トを打設し
て、地下ダム4の構築を完了する。Then, all the connecting portions 3 between the shields 3
After constructing the concrete, a concrete is cast in the shield 3 to complete the construction of the underground dam 4.
【0011】[0011]
【実施の形態2】図4は、地山を押さえる土留壁体部5
1と、この土留壁体部51の下部の地山側にほぼ水平方
向に連続する支持底部52とよりなる擁壁5の構築方法
を示す。上記実施の形態1と同様に、立坑から擁壁5の
構築予定場所に、ほぼ水平方向の複数のシ−ルド3を間
隔をおいて並列させて施工し、これらのシ−ルド3間を
一体に接続して(接続部31)擁壁5を構築する。擁壁
5の構築後は、擁壁5の前面地山の掘削を行い施工を終
了する。[Embodiment 2] FIG. 4 shows a retaining wall portion 5 for holding down the ground.
1 and a method of constructing a retaining wall 5 composed of a support bottom portion 52 which is substantially horizontally continuous with a bottom of the retaining wall body portion 51 on the ground side. In the same manner as in the first embodiment, a plurality of shields 3 in a substantially horizontal direction are arranged in parallel at intervals from the shaft to the location where the retaining wall 5 is to be constructed, and these shields 3 are integrated. (Connecting portion 31) to construct the retaining wall 5. After the construction of the retaining wall 5, excavation of the ground in front of the retaining wall 5 is performed to complete the construction.
【0012】[0012]
【実施の形態3】図5、6は、特開平3−187500
に記載のシ−ルド機6であり、このシ−ルド機6は、テ
−ルプレ−ト61の一部にスリット62を設け、その両
側に突出プレ−ト63を形成し、それらの間に把持空間
64を形成したことを特徴とする。このシ−ルド機6を
推進させる場合は、図6に示すように既設のシ−ルド7
を把持空間64内に把持し、既設シ−ルド7をガイドと
して推進させる。Embodiment 3 FIGS. 5 and 6 show Japanese Patent Application Laid-Open No. 3-187500.
The shield machine 6 is provided with a slit 62 in a part of a tail plate 61, and a protruding plate 63 formed on both sides thereof, between them. It is characterized in that a holding space 64 is formed. When propelling the shield machine 6, as shown in FIG.
Is held in the holding space 64, and the existing shield 7 is propelled as a guide.
【0013】そして、シ−ルド機6の推進に追従して、
既設シ−ルド7と新規シ−ルド71とをボルト等で連結
することができる。従って、本発明の施工において上記
シ−ルド機6を用いれば、シ−ルド構築後のシ−ルド間
の接続工程が不要となるため、施工能率の向上を図るこ
とができる。Then, following the propulsion of the shield machine 6,
The existing shield 7 and the new shield 71 can be connected by bolts or the like. Therefore, if the above-mentioned shield machine 6 is used in the construction of the present invention, the connection step between the shields after the construction of the shield is not required, so that the construction efficiency can be improved.
【0014】[0014]
【発明の効果】以上のように本発明は、立坑からシ−ル
ド機を発進させ、複数のシ−ルドを並列させて施工する
ことにより、地上の制約を受けないで地中構造物の構築
が可能である。そのため、地上の施工条件が悪い場合で
も影響されずに施工が行える。As described above, according to the present invention, by starting a shield machine from a shaft and constructing a plurality of shields in parallel, an underground structure can be constructed without being restricted by the ground. Is possible. Therefore, even when the construction conditions on the ground are bad, construction can be performed without being affected.
【図1】 シ−ルド施工工程の説明図FIG. 1 is an explanatory view of a shield construction process.
【図2】 シ−ルド施工工程の説明図FIG. 2 is an explanatory view of a shield construction process.
【図3】 シ−ルドの接続工程の説明図FIG. 3 is an explanatory view of a shield connection process.
【図4】 擁壁の構築方法の説明図FIG. 4 is an explanatory diagram of a method of constructing a retaining wall.
【図5】 シ−ルド機の説明図FIG. 5 is an explanatory view of a shield machine.
【図6】 シ−ルド機の説明図FIG. 6 is an explanatory view of a shield machine.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 水野 克彦 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Katsuhiko Mizuno Taisei Construction Co., Ltd. 1-25-1, Nishishinjuku, Shinjuku-ku, Tokyo
Claims (3)
おいて並列させて施工した後、 これらのシ−ルド間を一体に接続して行うことを特徴と
した、 地中構造物の構築方法。An underground structure wherein a plurality of shields are installed in parallel from a shaft in the ground at an interval, and the shields are integrally connected to each other. How to build.
壁体部の下部の地山側にほぼ水平方向に連続する支持底
部とよりなる擁壁の構築方法において、 立坑から地中の前記擁壁の構築予定場所に、ほぼ水平方
向の複数のシ−ルドを間隔をおいて並列させて施工し、 これらのシ−ルド間を一体に接続して擁壁を構築した
後、 擁壁の前面を掘削して行うことを特徴とした、 擁壁の構築方法。2. A method for constructing a retaining wall comprising a retaining wall body for holding a ground and a support bottom substantially horizontally continuous on the ground side below the retaining wall, comprising: At the place where the retaining wall is to be constructed, a plurality of shields in a substantially horizontal direction are installed in parallel at intervals, and these shields are connected together to construct a retaining wall. A method of constructing a retaining wall, characterized by excavating the front.
壁体部の下部の地山側にほぼ水平方向に連続する支持底
部とよりなる擁壁の構築方法において、 立坑から地中の前記擁壁の構築予定場所に、ほぼ水平方
向の複数のシ−ルドを、シ−ルド同士を接合しながら並
列させて擁壁を構築した後、 擁壁の前面を掘削して行うことを特徴とした、 擁壁の構築方法。3. A method for constructing a retaining wall comprising: a retaining wall body for holding a ground; and a support bottom which is substantially horizontally continuous with a lower ground side of the retaining wall in the ground. At the location where the retaining wall is to be constructed, a plurality of shields in a substantially horizontal direction are connected side by side while joining the shields to construct a retaining wall, and then excavating the front of the retaining wall. How to build a retaining wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8177351A JPH102200A (en) | 1996-06-18 | 1996-06-18 | Constructing method of underground structure and retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8177351A JPH102200A (en) | 1996-06-18 | 1996-06-18 | Constructing method of underground structure and retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH102200A true JPH102200A (en) | 1998-01-06 |
Family
ID=16029458
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8177351A Pending JPH102200A (en) | 1996-06-18 | 1996-06-18 | Constructing method of underground structure and retaining wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH102200A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060845A (en) * | 2017-05-04 | 2017-08-18 | 湖南城市学院 | Underground space structure builds construction method and application |
-
1996
- 1996-06-18 JP JP8177351A patent/JPH102200A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060845A (en) * | 2017-05-04 | 2017-08-18 | 湖南城市学院 | Underground space structure builds construction method and application |
CN107060845B (en) * | 2017-05-04 | 2019-01-15 | 湖南城市学院 | Underground space structure builds construction method and application |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH035600A (en) | Method and device for constructing branch and connection part of shield tunnel and its segment | |
JPH102200A (en) | Constructing method of underground structure and retaining wall | |
JP2816741B2 (en) | How to build a large cavity | |
JP4303511B2 (en) | Construction method of large section tunnel | |
JP2004316126A (en) | Work execution method for large section tunnel and deformed section shield boring machine | |
JP2554507B2 (en) | Underground space construction method | |
JPH11217824A (en) | Execution method of underground impervious wall | |
JP3511145B2 (en) | How to build underground structures | |
JPH0819824B2 (en) | Construction method of underground space | |
JP3045907B2 (en) | Construction method of continuous wall support pile | |
JPH09221744A (en) | Construction method of earth retaining wall using deep soil mixing consolidation pile and earth retaining wall structure | |
JP2673940B2 (en) | How to build a horizontal plate-like structure in the ground | |
JP3302661B2 (en) | Open shield machine and construction method of underground structure using it | |
JPH02248521A (en) | Open shield method | |
JPH0726877A (en) | Construction method of underground structure | |
JPH03137320A (en) | Open shield construction method | |
JP4079297B2 (en) | Shield tunnel connection method | |
JP2799343B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
JPH01210598A (en) | Construction work of underground space | |
JPH1030226A (en) | Generating method for liquefaction-resistant ground | |
JPH10140556A (en) | Execution method of underground continuous wall and device thereof | |
JPH03137319A (en) | Open shield construction method | |
JPH0641953A (en) | Execution method for earth retaining wall combinedly used for regular prepared wall | |
JPH03137318A (en) | Open shield construction method | |
JPH06235298A (en) | Segment |