JPS5853152B2 - Joining method in prefabricated construction method - Google Patents

Joining method in prefabricated construction method

Info

Publication number
JPS5853152B2
JPS5853152B2 JP17721380A JP17721380A JPS5853152B2 JP S5853152 B2 JPS5853152 B2 JP S5853152B2 JP 17721380 A JP17721380 A JP 17721380A JP 17721380 A JP17721380 A JP 17721380A JP S5853152 B2 JPS5853152 B2 JP S5853152B2
Authority
JP
Japan
Prior art keywords
wall
walls
floor
erected
prefabricated construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP17721380A
Other languages
Japanese (ja)
Other versions
JPS57104743A (en
Inventor
福秀 飽津
秀世 本橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haseko Corp
Original Assignee
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hasegawa Komuten Co Ltd filed Critical Hasegawa Komuten Co Ltd
Priority to JP17721380A priority Critical patent/JPS5853152B2/en
Publication of JPS57104743A publication Critical patent/JPS57104743A/en
Publication of JPS5853152B2 publication Critical patent/JPS5853152B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 本発明はプレハブ工法における接合方法に関するもので
ある。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a joining method in a prefabricated construction method.

本発明の目的は壁と壁とを簡単かつ強固に接合すること
にある。
An object of the present invention is to simply and firmly join walls.

以下本発明の一実施例を図面に基づいて説明する。An embodiment of the present invention will be described below based on the drawings.

まずPC壁1を建込み、PC壁上部に設けである梁2の
一端を定着金具3を介して柱鉄骨4に定着させて、PC
壁を柱鉄骨に支持させる。
First, the PC wall 1 is erected, and one end of the beam 2 provided at the top of the PC wall is fixed to the column steel frame 4 via the fixing fitting 3.
Support the wall on the steel columns.

このPC壁1の上下両端部にはコツクー5・・・および
コツクーロ・・・を突設してあり、コツクー5・・・と
下側のコツクーロとはそれぞれピッチを異にしている。
At both the upper and lower ends of this PC wall 1, there are protruding tips 5 and 5, and the pitches of the tips 5 and the lower tips are different from each other.

そしてPC壁1の上下両端部外方には、このPC壁内に
配筋しである鉄筋7の両端部が突出しており、各端部は
ループ状に屈曲した連絡筋であるダボ筋8・・・および
9・・・となっている。
Both ends of reinforcing bars 7, which are reinforced inside the PC wall, protrude outside both the upper and lower ends of the PC wall 1, and each end is connected to a dowel bar 8, which is a connecting bar bent in a loop shape. ...and 9...

ついでPC壁1の梁2上面にPC床版10・・・を架設
支持する。
Next, PC floor slabs 10 are erected and supported on the upper surface of the beam 2 of the PC wall 1.

そしてPC壁1の上方に、このPC壁と同一構成のPC
Cr2O建込む。
Then, above PC wall 1, there is a PC with the same configuration as this PC wall.
Cr2O is built.

この際、PC壁1の上側のダボ筋8に上階のPCCr2
O下側のダボ筋9aを重合対応させる。
At this time, the PCCr2 on the upper floor is attached to the dowel strip 8 on the upper side of the PC wall 1.
The dowel strips 9a on the lower side of O are made to overlap.

その後、スラブコンクリート11をPC床版10上に打
設する。
Thereafter, slab concrete 11 is placed on the PC floor slab 10.

この結果、PC壁1と1aとの接合部分12(第2図)
に現場打コンクIJ −ト11が充填され、接合部分が
固定され、上下のPC壁1,1aおよび床、さらには柱
までが一体化され、特にPC壁の接合部分12はコツク
ー5および6aとダボ筋8.9aとの存在によって強固
となる。
As a result, the joint portion 12 between the PC walls 1 and 1a (Fig. 2)
is filled with cast-in-place concrete IJ-te 11, the joints are fixed, and the upper and lower PC walls 1, 1a, the floor, and even the pillars are integrated. In particular, the joints 12 of the PC walls are connected to the PC walls 5 and 6a. It becomes strong due to the presence of the dowel muscle 8.9a.

またPCCr2Oその上階のPC壁1bとの接合も、上
記の接合方法と同様であり、梁2a上にPC床版10a
・・・を架設してから、上階のPC壁1bを建込み、ダ
ボ筋8aおよび9bを重合させて、コンクリート11a
を打設する。
Also, the connection of PCCr2O with the PC wall 1b on the upper floor is the same as the above-mentioned joining method, and the PC floor slab 10a is placed on the beam 2a.
..., then erect the PC wall 1b on the upper floor, polymerize the dowel reinforcements 8a and 9b, and form the concrete 11a.
to be poured.

こうすると、接合部%12a(第2図)が固定され、P
C壁la、ibは床、柱とともに一体化される。
In this way, the joint %12a (Fig. 2) is fixed and P
C walls la and ib are integrated with the floor and columns.

5aはコツター、7aは鉄筋である。5a is a cotter, and 7a is a reinforcing bar.

こうしてPC壁を順次接合して行く。In this way, the PC walls are successively joined.

以上のとおり本発明によれば、上下階PC壁を建込んで
コンクリートを打設するだけで上下のPC壁が床ととも
に一体化されるので、壁の接合が簡単かつ容易であり、
またその接合が強固に行え、壁、スラブが地震時に応力
に対して協働して耐震効果が高められる。
As described above, according to the present invention, the upper and lower PC walls are integrated with the floor by simply building the upper and lower PC walls and pouring concrete, so joining the walls is simple and easy.
In addition, the joints are strong, and the walls and slabs work together against stress during earthquakes, increasing earthquake resistance.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の一実施例を示すもので、第1図はPC壁
の接合状態を示す一部切欠正面図、第2図は第1図■−
■線拡大断面図である。 1、la、1b・・・・・・PC壁、5,5a・・・・
・・コツター、8,9,8a、9a、9b・・・・・・
ダボ筋、10.10a・・・・・・PC床版、11,1
1a・・・・・・現場打コンクリート、12,12a・
・・・・・PCiの接合部分。
The drawings show one embodiment of the present invention, and FIG. 1 is a partially cutaway front view showing the state of connection of PC walls, and FIG.
■It is a line enlarged sectional view. 1, la, 1b... PC wall, 5, 5a...
... Kotter, 8, 9, 8a, 9a, 9b...
Dowel strip, 10.10a...PC floor slab, 11,1
1a... Cast-in-place concrete, 12, 12a.
...Connection part of PCi.

Claims (1)

【特許請求の範囲】 1 上下端部にコツクーを突設しであるとともに連絡筋
が外方に突出しているPC壁を建込み、ついでこのPC
壁の上端部でPC床版を架設支持し、 その後上階にPC壁を建込み、このPC壁下端部の連絡
筋を階下のPC壁の連絡筋と重合させ、さらに上記PC
床版上に後打コンクリートを打設し台底スラブとする ことを特徴とするプレハブ工法における接合方法。
[Scope of Claims] 1. A PC wall is built in which the top and bottom ends are protruded and communication bars protrude outward, and then this PC wall is installed.
A PC floor slab is erected and supported at the upper end of the wall, then a PC wall is erected on the upper floor, the connecting bars at the bottom end of this PC wall are overlapped with the connecting bars on the PC wall downstairs, and then the above PC wall is erected and supported.
A joining method in the prefabricated construction method characterized by pouring post-cast concrete onto the floor slab to form a base slab.
JP17721380A 1980-12-17 1980-12-17 Joining method in prefabricated construction method Expired JPS5853152B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17721380A JPS5853152B2 (en) 1980-12-17 1980-12-17 Joining method in prefabricated construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17721380A JPS5853152B2 (en) 1980-12-17 1980-12-17 Joining method in prefabricated construction method

Publications (2)

Publication Number Publication Date
JPS57104743A JPS57104743A (en) 1982-06-29
JPS5853152B2 true JPS5853152B2 (en) 1983-11-28

Family

ID=16027135

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17721380A Expired JPS5853152B2 (en) 1980-12-17 1980-12-17 Joining method in prefabricated construction method

Country Status (1)

Country Link
JP (1) JPS5853152B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63131138U (en) * 1987-02-19 1988-08-26

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4672847B2 (en) * 2000-10-16 2011-04-20 鹿島建設株式会社 Structure of PCa wall slab joint

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63131138U (en) * 1987-02-19 1988-08-26

Also Published As

Publication number Publication date
JPS57104743A (en) 1982-06-29

Similar Documents

Publication Publication Date Title
JPS5853152B2 (en) Joining method in prefabricated construction method
JPH03132532A (en) Construction method of precast reinforced concrete column and beam
JPH02300439A (en) Prefabricating method
JP2769937B2 (en) Steel tube concrete column in underground reverse driving method
JPS6312987B2 (en)
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPS6134468Y2 (en)
JPH0448136B2 (en)
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH0447737B2 (en)
JPS6226481Y2 (en)
JPS5855819B2 (en) Reinforcement method for wall-type reinforced concrete structures
JPH0375704B2 (en)
JPS5830459B2 (en) Construction method of precast reinforced concrete structure
JPS6335773B2 (en)
JPH0546561Y2 (en)
JP2893406B2 (en) Precast concrete beam-column joining method
JPS62182329A (en) Construction of concrete structure
JPH0781355B2 (en) Construction method of joist slab using precast concrete girder
JPH0949264A (en) Constructing method for reinforced concrete framework and structure, and member therefor
JP2814873B2 (en) How to build a reinforced concrete building
JPH0544494B2 (en)
JPH058303B2 (en)
JPH02229337A (en) Constructing technique for concrete column