JPH058303B2 - - Google Patents

Info

Publication number
JPH058303B2
JPH058303B2 JP25959385A JP25959385A JPH058303B2 JP H058303 B2 JPH058303 B2 JP H058303B2 JP 25959385 A JP25959385 A JP 25959385A JP 25959385 A JP25959385 A JP 25959385A JP H058303 B2 JPH058303 B2 JP H058303B2
Authority
JP
Japan
Prior art keywords
formwork
column
reinforcing bars
main
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP25959385A
Other languages
Japanese (ja)
Other versions
JPS62121249A (en
Inventor
Fumitoshi Sakuramoto
Yasuhiro Kameda
Satoshi Betsusho
Hisao Tanaka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP25959385A priority Critical patent/JPS62121249A/en
Publication of JPS62121249A publication Critical patent/JPS62121249A/en
Publication of JPH058303B2 publication Critical patent/JPH058303B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は鉄骨鉄筋コンクリート造において柱
及び梁をプレフアブ化した、柱・梁の施工方法に
関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method of constructing columns and beams in a steel-framed reinforced concrete structure in which the columns and beams are prefabricated.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

近年鉄筋コンクリート造建物の骨組を、現場作
業の単純化及び省力化と、それによる工期の短縮
化等の要請を反映して予めプレフアイブ化された
柱と梁とから構築する方法が開発されている。
In recent years, methods have been developed for constructing the frames of reinforced concrete buildings from prefabricated columns and beams, reflecting the demand for simplification and labor-saving on-site work, and thereby shortening the construction period.

この発明はこうした傾向を踏まえ、作業の省力
化を図る一方法を提供する目的からなされたもの
で、より工期の短縮化を可能にする柱・梁の施工
方法を提案しようとするものである。
In view of these trends, this invention was made for the purpose of providing a method for labor-saving work, and is intended to propose a method of constructing columns and beams that makes it possible to further shorten the construction period.

〔問題点を解決するための手段〕[Means for solving problems]

この発明では柱型枠と梁型枠に主筋と帯筋やス
ターラツプを埋め込んでこれをプレキヤストコン
クリートで製作しておき、この柱型枠と梁型枠と
により構成することにより型枠の組立と解体、及
び支保工の設置を不要化し、現場作業の省力化、
そして工期の短縮化を図る。
In this invention, the main reinforcements, stirrups, and stirrups are embedded in the column formwork and beam formwork, and these are made of precast concrete, and by constructing the column formwork and beam formwork, it is possible to assemble the formwork. Eliminates the need for dismantling and installing shoring, saving labor on site.
We will also aim to shorten the construction period.

梁型枠は主筋及び帯筋が埋設されて箱形に製作
され、下階のスラブ上に設置され、内部に、接合
部を高さ方向に貫通する縦筋とその中間部に巻き
付けられる帯筋とからなる組立鉄筋が配筋されて
コンクリートが充填される。
The beam formwork is made into a box shape with main reinforcing bars and stirrups buried, and is installed on the slab on the lower floor. Inside, there are vertical bars that pass through the joint in the height direction and tie bars that are wrapped around the middle part. The prefabricated reinforcing bars consisting of are arranged and filled with concrete.

梁型枠は下端主筋及びスターラツプの下側が埋
設されてU形に製作され、端部が柱型枠上に載置
され、相対する複数の梁型枠間には接合部を貫通
して双方の下端主筋を連結する下端連結鉄筋と、
同じく接合部を貫通する上端主筋が配筋され、コ
ンクリートが充填される。
The beam formwork is made into a U-shape with the bottom main reinforcement and stirrup buried under the ground, and the end is placed on the column formwork. A lower end connecting reinforcing bar that connects the lower end main reinforcement,
The top main reinforcement that also passes through the joint is placed and filled with concrete.

接合部の施工は下階のスラブ上に柱型枠を建て
込み、その上端に梁型枠の端部を載置し、相対す
る複数の梁型枠の下端主筋間に跨つて下端連結鉄
筋を配筋して下端主筋を連結した後、組立鉄筋を
柱型枠の内部に挿入して帯筋を梁型枠の端部間に
位置させ、更に梁型枠の上方へ突出するスターラ
ツプの下側に上端主筋を対向する梁型枠間に跨つ
て配筋し、柱型枠内部と梁型枠内部にコンクリー
トを充填する。
To construct the joint, a column formwork is built on the slab on the lower floor, the end of the beam formwork is placed on the upper end of the column formwork, and the lower end connecting reinforcing bars are installed across the lower end main bars of the opposing beam formworks. After arranging reinforcement and connecting the lower end main reinforcement, insert the prefabricated reinforcing bars inside the column formwork, position the stirrups between the ends of the beam formwork, and then place the stirrups on the lower side of the stirrups that protrude above the beam formwork. Place the upper main reinforcement across the opposing beam formwork, and fill the inside of the column formwork and beam formwork with concrete.

〔実施例〕〔Example〕

以下この説明を一実施例を示す図面に基づいて
説明する。
This description will be made below based on drawings showing one embodiment.

この発明はプレキヤストコンクリートで製作し
た柱型枠Aと梁型枠Bとを組み立て、その内部に
コンクリートを打設して柱・梁を構成する方法で
ある。
This invention is a method of constructing columns and beams by assembling column formwork A and beam formwork B made of precast concrete, and pouring concrete inside them.

柱型枠Aは主筋1a及び帯筋2aが埋設されて
第1図、第2図に示すように箱形の中空断面形状
に製作され、梁型枠Bは下端主筋1a及びスター
ラツプ2bが埋設されて第1図、第3図のように
U形断面形状に製作される。
The column formwork A has the main reinforcement 1a and the stirrups 2a buried therein, and is manufactured to have a box-shaped hollow cross-section as shown in Figs. It is manufactured to have a U-shaped cross section as shown in FIGS. 1 and 3.

スターラツプ2bはその下側が梁型枠B中に埋
設され、上側が梁型枠Bから突出し、その突出し
た部分に上端主筋3bが配筋される。
The stirrup 2b has its lower side buried in the beam form B, and its upper side protrudes from the beam form B, and the upper end main reinforcement 3b is arranged at the protruding part.

柱型枠Aの主筋1aと梁型枠Bの下端主筋1b
の長さは第1図〜第3図に示すように各型枠の端
部までであり、接合部を挟んで上下に隣接する柱
型枠A,Aの各主筋1a,1aは組立鉄筋Cによ
り、また対向する複数の梁型枠B,Bの下端主筋
1b,1bは下端連結鉄筋4−1により連結され
る。
Main reinforcement 1a of column formwork A and lower end main reinforcement 1b of beam formwork B
The length is up to the end of each formwork as shown in Figs. Accordingly, the lower end main reinforcements 1b, 1b of the plurality of opposing beam forms B, B are connected by the lower end connecting reinforcing bars 4-1.

組立鉄筋Cは第1図に示すように接合部を高さ
方向に貫通する長さを持つ縦筋1cと、その高さ
方向の中間部に巻き付けられる帯筋2cとから組
み立てられ、柱型枠Aの内部に最下部の帯筋2c
の下まで挿入され、帯筋2cは梁型枠B,B間、
すなわち柱・梁接合部に位置する。
As shown in Fig. 1, the assembled reinforcing bar C is assembled from a vertical bar 1c having a length that passes through the joint in the height direction, and a tie bar 2c wrapped around the intermediate part in the height direction, and is assembled into a column formwork. The lowest strap 2c inside A
The tie bars 2c are inserted between the beam forms B and B,
In other words, it is located at the column/beam joint.

下端連結鉄筋4−1は下端主筋1b,1bと重
ね継手により連結されるのに十分な長さを持ち、
対向する複数の梁型枠B,Bに跨り、その下端主
筋1b,1b上に重なる形で配筋される。
The lower end connecting reinforcing bars 4-1 have a length sufficient to be connected to the lower end main reinforcements 1b, 1b by lap joints,
The reinforcing bars are arranged so as to straddle the plurality of opposing beam forms B, B, and to overlap with the lower end main reinforcing bars 1b, 1b.

上端主筋3bは後述するようにスターラツプ2
bに仮止めされた状態で梁型枠Bを設置した後に
対向する側へ移動することにより、もしくは第1
図に示すように予めスターラツプ2bに結束さ
れ、下端主筋1bの場合と同様に後から上端連結
鉄筋4−3が上端主筋3bに重なつて設置される
ことにより相対する複数の梁型枠B,B間に跨
り、接合部を貫通して配筋される。前者の場合、
上端主筋3bは梁型枠Bからスライドすることに
より接合部を貫通して配筋され、後者の場合相対
する複数の梁型枠B,Bの各上端主筋3b,3b
は第2図、第3図に示すように梁型枠Bの設置後
に相対する梁型枠B,B間に跨つて配筋される上
端連結鉄筋4−3により重ね継手より接合部で連
結する。
The upper end main reinforcement 3b is a stirrup 2 as described later.
By moving the beam formwork B to the opposite side after installing it with it temporarily fixed to b, or by moving it to the opposite side, or by
As shown in the figure, a plurality of beam formworks B are bound in advance to the stirrup 2b, and the upper end connecting reinforcing bars 4-3 are later installed so as to overlap the upper end main reinforcing bars 3b, as in the case of the lower end main reinforcing bars 1b. Reinforcement is placed across B and through the joint. In the former case,
The upper end main reinforcement 3b is inserted through the joint by sliding from the beam formwork B, and in the latter case, each upper end main reinforcement 3b, 3b of a plurality of opposing beam formworks B, 3b.
As shown in Figures 2 and 3, after the beam form B is installed, the upper end connecting reinforcing bars 4-3 are placed across the opposing beam forms B and B, and are connected at the joint by lap joints. .

柱・梁接合部は、柱型枠Aを下階のスラブ上に
建て込んだ後、第1図に示すようにその上端に相
対する複数の梁型枠B,Bの端部を載置し、相対
する複数の梁型枠B,Bの下端主筋1b,1b間
に跨つて下端連結鉄筋4−1を配筋して下端主筋
1b,1bを互いに連結した後、組立鉄筋Cを柱
型枠Aの内部に挿入してその帯筋2cを相対する
複数の梁型枠B,Bの端部間に位置させ、更に梁
型枠Bの上方へ突出するスターラツプ2bの下側
に上記いずれかの要領で接合部を貫通して上端主
筋3bを配筋し、柱型枠Aの内部と梁型枠Bの内
部にコンクリートを充填する、という手順で施工
される。
For the column-beam joint, after the column formwork A is erected on the slab on the lower floor, the ends of the multiple beam formworks B and B are placed on top of it, as shown in Figure 1. , After connecting the lower end main reinforcements 1b, 1b with each other by arranging the lower end connecting reinforcing bars 4-1 across the lower end main reinforcements 1b, 1b of the plurality of opposing beam forms B, B, the assembled reinforcing bars C are attached to the column formwork. The stirrup 2c is inserted into the inside of the beam formwork A and placed between the ends of a plurality of opposing beam formworks B, B, and one of the above-mentioned stirrups is placed below the stirrup 2b that protrudes above the beam formwork B. Construction is carried out in the following steps: the upper end main reinforcement 3b is placed through the joint, and the inside of the column formwork A and the beam formwork B are filled with concrete.

次に第4図により1層分の架構の施工手順を具
体的に説明する。
Next, the construction procedure for one layer of the frame will be specifically explained with reference to FIG.

この第4図は上端主筋3b,3bをスターラツ
プ2bに結束して配筋しておき、梁型枠Bの設置
後に相対する複数の梁型枠B,Bの上端主筋3
b,3bに跨り、柱・梁接合部を貫通して配筋さ
れる上端連結鉄筋4−3により連結する場合の実
施例である。この場合、下端連結鉄筋4−1、上
端連結鉄筋4−3共、各下端主筋1b、上端主筋
3bとの継手の効果が得られるに十分な定着長さ
が与えられる。また第3図に示すように交差する
方向の下端主筋1b,1b、上端主筋3b,3b
には、下端連結鉄筋4−1と上端連結鉄筋4−3
の配筋時の干渉を回避するために段差が付けられ
る。
In Fig. 4, the upper end main reinforcements 3b, 3b are tied to the stirrup 2b and reinforced, and after the beam formwork B is installed, the upper end main reinforcements 3 of the opposing beam formworks B, B are arranged.
This is an example in which the upper end connecting reinforcing bars 4-3 are arranged across the columns b and 3b and are reinforced through the column-beam joint. In this case, both the lower end connecting reinforcing bars 4-1 and the upper end connecting reinforcing bars 4-3 are given a sufficient anchoring length to achieve the joint effect with the respective lower end main reinforcements 1b and upper end main reinforcing bars 3b. In addition, as shown in Fig. 3, the lower end main reinforcements 1b, 1b and the upper end main reinforcements 3b, 3b in the intersecting directions.
, lower end connecting reinforcing bar 4-1 and upper end connecting reinforcing bar 4-3.
Steps are added to avoid interference during reinforcing.

まず下階のスラブの上面から突出した、または
スラブ上に組み立てられた柱主筋上に柱型枠Aを
建て込み()、その上端に一方向の相対する複
数の梁型枠B,Bを建て込んで、隣接する柱型枠
A,A間に跨設し()、引き続き、この梁型枠
Bに直交する方向の梁型枠Bを同じく柱型枠A,
A上に跨設する()。柱型枠Aの建て込み時、
柱主筋はその内側に納まる。
First, column formwork A is erected on the main column reinforcement that protrudes from the top surface of the slab on the lower floor or is assembled on the slab (), and multiple beam formworks B and B are erected on its upper end facing each other in one direction. Then, the beam form B in the direction orthogonal to this beam form B is installed in the same manner as the column form A,
Straddle over A (). When building column formwork A,
The main column reinforcement will fit inside it.

続いて梁型枠B上にスラブPC版5を載置し
()、下端連結鉄筋4−1を梁型枠B,B間に配
筋し()、柱型枠A内へ組立鉄筋Cを挿入する
()。
Next, place the slab PC plate 5 on the beam formwork B (), place the lower end connecting reinforcing bars 4-1 between the beam formworks B and B (), and install the assembly reinforcing bars C into the column formwork A. insert().

次に上端連結鉄筋4−3を上端主筋3b,3b
に跨つて配筋し、()、スラブPC版5上にスラ
ブメツシユ筋6を配筋した後()、柱型枠Aと
梁型枠B内及びスラブPC版5上へコンクリート
を打設して柱・梁接合部の施工が終了する。以
下、()から()までの手順を繰り返して架
構が構築される。
Next, connect the upper end connecting reinforcing bars 4-3 to the upper end main bars 3b, 3b.
(), and after placing slab mesh reinforcement 6 on the slab PC plate 5 (), concrete is poured inside the column formwork A and beam form B and on the slab PC plate 5. Construction of the column/beam joint is completed. Thereafter, the frame is constructed by repeating the steps from () to ().

次に第5図に示す実施例の施工手順を説明す
る。
Next, the construction procedure of the embodiment shown in FIG. 5 will be explained.

この実施例は上端主筋3bをスターラツプ2b
に仮止めしておき、組立鉄筋Cの建て込み後に梁
型枠B側へ移動させることにより相対する両梁型
枠B,Bに跨り、接合部を貫通させて配筋する方
法である。この場合、上端主筋3b,3bは一方
の梁型枠Bに二段重ねで仮止めされ、相対する複
数の梁型枠B,Bを柱型枠A上に載置した後に、
他方の梁型枠Bへスライドさせられてその側の上
端主筋3bと連結される。継手はガス圧接、重ね
継手、カプラー等による。
In this embodiment, the upper main reinforcement 3b is stirrup 2b.
This is a method of temporarily fixing the reinforcing bars C, and then moving them to the beam form B side after the erection of the assembled reinforcing bars C, thereby straddling both opposing beam forms B, B, and penetrating the joint. In this case, the upper end main reinforcements 3b, 3b are temporarily fixed to one beam formwork B in two stages, and after placing the opposing beam formworks B, B on the column formwork A,
It is slid to the other beam form B and connected to the upper end main reinforcement 3b on that side. Joints are gas pressure welding, lap joints, couplers, etc.

まず第4図の場合と同じく、スラブ上に柱型枠
Aを建て込み()、一方向に梁型枠Bを柱型枠
A上に載置し()、更にこれに直交する梁型枠
Bを載置する()。
First, as in the case of Fig. 4, column formwork A is built on the slab (), beam formwork B is placed on column formwork A in one direction (), and beam formwork perpendicular to this is placed (). Place B ().

次にスラブPC版5を梁型枠B上に設置し
()、下端連結鉄筋4−1の配筋()に続いて
組立鉄筋Cを設置する()。
Next, the slab PC version 5 is installed on the beam formwork B (), and the assembly reinforcing bars C are installed following the reinforcement of the lower end connecting reinforcing bars 4-1 ().

引き続き、二段に仮止めされた上端主筋3b,
3bを相対する複数の梁型枠B,Bへスライドさ
せてその側の上端主筋3b,3bと相互に継ぎ
()、更にスラブメツシユ筋6を配筋して()
コンクリートを打設し()、柱・梁が構成され
る。
Subsequently, the upper end main reinforcement 3b temporarily fixed in two stages,
3b to the opposing beam forms B, B, and connect them to the upper end main reinforcements 3b, 3b on that side (), and then place the slab mesh reinforcements 6 ().
Concrete is poured () and columns and beams are constructed.

〔発明の効果〕〔Effect of the invention〕

この発明は以上の通りであり、主筋と帯筋やス
ターラツプを埋め込んでプレキヤストコンクリー
トで製作された柱型枠と相対する複数の梁型枠と
により接合部を構成するものであるため、接合部
用の型枠の組立と解体、及び支保工の設置が不要
となり、現場では下端連結鉄筋や上端連結鉄筋と
組立鉄筋の配筋と、コンクリートの打設のみで
柱・梁が施工されるため現場作業の省力化、そし
て工期の短縮化を図ることができる。
This invention is as described above, and since the joint is configured by a column formwork made of precast concrete with main reinforcement, stirrups and stirrups embedded, and a plurality of opposing beam formworks, the joint part is There is no need to assemble and dismantle formwork and install supports, and columns and beams can be constructed on site by simply arranging lower end connecting reinforcing bars, upper end connecting reinforcing bars, assembly reinforcing bars, and pouring concrete. It is possible to save labor and shorten the construction period.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は柱型枠上に梁型枠と組立鉄筋を設置し
た様子を示した斜視図であり、第2図はその平面
図、第3図は縦断面図である。第4図、第5図は
1層分の架構の施工手順を示した立面図である。 A……柱型枠、1a……主筋、2a……帯筋、
B……梁型枠、1b……下端主筋、2b……スタ
ーラツプ、3b……上端主筋、4−1……下端連
結鉄筋、4−3……上端連結鉄筋、C……組立鉄
筋、1c……縦筋、2c……帯筋、5……スラブ
PC版、6……スラブメツシユ筋。
FIG. 1 is a perspective view showing the beam formwork and assembly reinforcing bars installed on the column formwork, FIG. 2 is a plan view thereof, and FIG. 3 is a vertical sectional view thereof. FIGS. 4 and 5 are elevational views showing the construction procedure for one layer of the frame. A... Column formwork, 1a... Main bar, 2a... Stir bar,
B...beam formwork, 1b...lower end main reinforcement, 2b...stirrup, 3b...upper end main reinforcement, 4-1...lower end connecting reinforcing bar, 4-3...upper end connecting reinforcing bar, C...assembly reinforcing bar, 1c... ...Vertical bar, 2c...Stir bar, 5...Slab
PC version, 6...Slab mesh muscle.

Claims (1)

【特許請求の範囲】[Claims] 1 主筋及び帯筋が埋設されて製作されたプレキ
ヤストコンクリート製の柱型枠を下階のスラブ上
に建て込み、下端主筋及びスターラツプが埋設さ
れてU形に製作されたプレキヤストコンクリート
製の梁型枠の端部を柱型枠上に載置し、相対する
複数の梁型枠間に跨つて各梁型枠の下端主筋と連
結される下端連結鉄筋を下端主筋近傍に配筋した
後、柱・梁接合部を高さ方向に貫通する長さを持
つ縦筋と、その長さ方向の中間部に巻き付けられ
る帯筋とからなる組立鉄筋を柱型枠の内部に挿入
して帯筋を梁型枠の端部間に位置させ、更に各梁
型枠のスターラツプの下側に上端主筋を、梁型枠
間に跨り、柱・梁接合部を貫通させて配筋し、柱
型枠と梁型枠内にコンクリートを打設して接合部
を構成する柱・梁の施工方法。
1 A precast concrete column formwork with the main reinforcing bars and ties buried is built on the slab on the lower floor, and a U-shaped precast concrete beam with the bottom main reinforcing bars and stirrups buried. After placing the end of the formwork on the column formwork and placing the lower end connecting reinforcing bars near the lower end main reinforcements that span between the opposing beam formworks and connect to the lower end main reinforcements of each beam formwork, An assembly reinforcing bar consisting of a vertical bar with a length that penetrates the column-beam joint in the height direction and a tie bar wrapped around the middle part of the longitudinal bar is inserted into the column formwork to create a tie bar. The top main reinforcement is placed between the ends of the beam formwork, and the top main reinforcement is placed below the stirrup of each beam formwork, spanning between the beam formworks and passing through the column-beam joint. A method of constructing columns and beams in which concrete is poured into beam formwork to form joints.
JP25959385A 1985-11-19 1985-11-19 Construction of pillar/beam connection part Granted JPS62121249A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25959385A JPS62121249A (en) 1985-11-19 1985-11-19 Construction of pillar/beam connection part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25959385A JPS62121249A (en) 1985-11-19 1985-11-19 Construction of pillar/beam connection part

Publications (2)

Publication Number Publication Date
JPS62121249A JPS62121249A (en) 1987-06-02
JPH058303B2 true JPH058303B2 (en) 1993-02-01

Family

ID=17336263

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25959385A Granted JPS62121249A (en) 1985-11-19 1985-11-19 Construction of pillar/beam connection part

Country Status (1)

Country Link
JP (1) JPS62121249A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2600194B2 (en) * 1987-09-21 1997-04-16 株式会社大林組 Lap joint of column main bar
JP2602362B2 (en) * 1990-11-27 1997-04-23 大成建設株式会社 Thick wall and beam or floor slab joining method

Also Published As

Publication number Publication date
JPS62121249A (en) 1987-06-02

Similar Documents

Publication Publication Date Title
JP4428721B2 (en) Construction method of ramen railway viaduct
JPH058303B2 (en)
JP3116767B2 (en) Existing building seismic isolation structuring method
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPS6039401Y2 (en) joint reinforcing bars
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH0332586Y2 (en)
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPH11181807A (en) Construction method for underground story
JP2003013493A (en) Beam-column connection joint and beam-column connection method
JP2978011B2 (en) U-shaped beam formwork and method of constructing beam and beam joint using the same
JPH1144092A (en) Constituting method of building frame
JPH0642037A (en) Construction method of wall type rigid frame construction
JPH0460183B2 (en)
JP2673235B2 (en) Parallel string reinforcement truss frame structure of building
JP2651506B2 (en) How to apply underground beams
JP3312945B2 (en) Construction method of concrete structure
JPS60510B2 (en) construction method
JP2001020297A (en) Sc-structured footing beam method for building
JPH0588331B2 (en)
JPH07197566A (en) Joining method for precast concrete wall column member
JPH08218390A (en) Method for constructing underground beam
JPH10131353A (en) Precast reinforced concrete made continuous layer earthquake resisting wall
JPS5938497A (en) Tunnel lining body