JPH03132532A - Construction method of precast reinforced concrete column and beam - Google Patents
Construction method of precast reinforced concrete column and beamInfo
- Publication number
- JPH03132532A JPH03132532A JP27024689A JP27024689A JPH03132532A JP H03132532 A JPH03132532 A JP H03132532A JP 27024689 A JP27024689 A JP 27024689A JP 27024689 A JP27024689 A JP 27024689A JP H03132532 A JPH03132532 A JP H03132532A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcements
- column
- reinforcement
- reinforced concrete
- beams
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 36
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 230000002787 reinforcement Effects 0.000 claims abstract description 112
- 239000004567 concrete Substances 0.000 claims abstract description 24
- 230000009191 jumping Effects 0.000 claims abstract description 10
- 230000003014 reinforcing effect Effects 0.000 claims description 20
- 229910000831 Steel Inorganic materials 0.000 claims description 16
- 239000010959 steel Substances 0.000 claims description 16
- 238000000034 method Methods 0.000 claims description 6
- 230000008878 coupling Effects 0.000 abstract 1
- 238000010168 coupling process Methods 0.000 abstract 1
- 238000005859 coupling reaction Methods 0.000 abstract 1
- 238000009415 formwork Methods 0.000 description 9
- 210000003205 muscle Anatomy 0.000 description 5
- 239000011210 fiber-reinforced concrete Substances 0.000 description 4
- 230000006378 damage Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011120 plywood Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、鉄筋(あるいはまた鉄骨)コンクリート造ラ
ーメン構造建物におけるプレキャスト式鉄筋コンクリー
ト柱・梁構築法に関するらのである。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method for constructing precast reinforced concrete columns and beams in reinforced concrete (or steel frame) rigid frame buildings.
(従来の技術)
従来、鉄筋(あるいはまた鉄骨)コンクリート造ラーメ
ン構造建物は、施工現場にて鉄筋(柱、梁等の主筋、剪
断補強筋等、あるいはまた鉄骨)を組み立て、組立鉄筋
(あるいはまた鉄筋)の周囲に型枠を組み立てて囲み、
同型枠内にコンクリ−トを打設して乾燥、固着後に同型
枠を解体して構築するのか一般的であるが、作業現場に
おける前記鉄筋(あるいはまた鉄骨)の組立、型枠の組
立、解体等は、危険な作業となり熟練とともに多くの手
数、時間を要し、また組立、配置のバラツキ等で施工精
度が十分に確保されず、熟練作業者の確保、工期の短縮
等が課題になっている。(Prior art) Conventionally, reinforced concrete (or steel frame) concrete rigid frame buildings are constructed by assembling reinforcing bars (main bars of columns, beams, etc., shear reinforcing bars, etc., or steel frames) at the construction site, and constructing assembled reinforcing bars (or steel frames). Assemble a formwork around the reinforcing steel and surround it.
It is common practice to pour concrete into the same formwork, dry it, solidify it, then dismantle the formwork and construct it, but it is also possible to assemble the reinforcing bars (or steel frames), assemble and dismantle the formwork at the work site. etc., is dangerous work and requires a lot of skill and labor and time, and construction accuracy cannot be ensured due to variations in assembly and layout, making it difficult to secure skilled workers and shorten the construction period. There is.
前記のような実情に鑑み、工場等で予め組み立てた組立
鉄筋(あるいはまた鉄骨)、組立型枠を施工現場に搬入
して設置する先組み工法か開発され、さらに最近では、
工場等で製造したプレキャスト鉄筋コンクリート梁(部
材)や中空形状のプレキャスト鉄筋コンクリート柱部材
を、施工現場に搬入、設置して型枠兼用とし、同部材を
梁、柱(一部)の構造材とするプレキャスト式鉄筋コン
クリート柱・梁構築法が提案され、型枠を節減し施工精
度を高め前記課題に対応されている。In view of the above-mentioned circumstances, a pre-assembly method has been developed in which assembled reinforcing bars (or steel frames) and assembled formwork that have been assembled in advance at a factory etc. are transported to the construction site and installed, and more recently,
Precast reinforced concrete beams (components) and hollow precast reinforced concrete column components manufactured in factories, etc. are delivered to the construction site, installed, and used as formwork, and the same components are used as structural materials for beams and columns (some of them). A method for constructing reinforced concrete columns and beams has been proposed to address the above-mentioned issues by reducing the need for formwork and improving construction accuracy.
従来の前記プレキャスト式構築法は、例えば断面U形状
コンクリート梁主体の内面に複数の肋筋を固着し、各肋
筋内の上、下部に複数の梁上、下部主筋を固着した構造
の断面U形状プレキャスト鉄筋コンクリート梁部材を用
い、同梁部材の端部をプレキャスト鉄筋コンクリート柱
部材の柱頭部に架設して、前記柱部材、梁部材にコンク
リートを打設するプレキャスト式鉄筋コンクリート柱・
梁構築法か提案されている(例えば特開昭63−400
29号)。In the conventional precast construction method, for example, a plurality of ribs are fixed to the inner surface of a main concrete beam with a U-shaped cross section, and a plurality of beam top and bottom main bars are fixed to the upper and lower parts of each rib. A precast type reinforced concrete column in which a precast reinforced concrete beam member is used, the end of the beam member is erected on the column head of a precast reinforced concrete column member, and concrete is poured into the column member and beam member.
Beam construction methods have been proposed (for example, Japanese Patent Application Laid-open No. 63-400
No. 29).
また、複数の梁下部、中間主筋および肋筋を埋設したコ
ンクリート中実形状のプレキャスト鉄筋コンクリート梁
の端部を柱頭部に架設して、同梁の端部から露出し相対
されている露出跳上部間に閉鎖型ループ筋を嵌合してそ
の周囲に補強帯筋を配筋し、柱頭部に鋼繊維補強コンク
リートを打設して柱頭部と両県間を一体に施工、構築す
るプレキャスト式鉄筋コンクリート柱・梁構築法が提案
されている(例えば特公昭62−32299号)。In addition, the end of a precast reinforced concrete beam with a solid concrete shape in which multiple lower beams, intermediate main reinforcements, and cost reinforcements are embedded is erected on the column head, and between the exposed jump parts that are exposed from the end of the beam and facing each other. A precast reinforced concrete column is constructed by fitting closed-loop reinforcement into the frame, arranging reinforcing bars around it, pouring steel fiber reinforced concrete into the column head, and constructing the column head and the area between the two prefectures as one unit. - Beam construction methods have been proposed (for example, Japanese Patent Publication No. 32299/1983).
(発明が解決しようとする課題)
従来の前記プレキャスト式鉄筋コンクリート柱・梁構築
法において、前記断面U形状プレキャスト鉄筋コンクリ
ート梁部材を用いる工法は、肋筋梁下部主筋が断面U形
状のコンクリート梁主体の内面に固着され、打設コンク
リート等の荷重で変形、破壊される恐れがあって梁部材
自体の補強か必要となり、また同梁部材に固着された梁
上、下部主筋の施工現場における通し配筋に、多くの手
数、時間を要する。(Problem to be Solved by the Invention) In the conventional precast type reinforced concrete column/beam construction method, the construction method using the precast reinforced concrete beam member with a U-shaped cross section is such that the lower main reinforcement of the cross-section beam is attached to the inner surface of the main concrete beam having a U-shaped cross section. There is a risk of deformation and destruction due to the load of poured concrete, etc., which requires reinforcement of the beam member itself. , which requires a lot of effort and time.
また、前記中実形状プレキャスト鉄筋コンクリート梁を
用いる工法では、同梁の変形等は防止されるが、露出跳
上部間の閉鎖型ループ筋の嵌合、その周囲の補強帯筋の
配筋、さらに鋼繊維補強コンクリートの打設を要し、特
に梁間の柱頭部内への局部的な前記コンリート打設は面
倒な作業となり、施工精度の低下の一因となり易いなど
の問題点がある。In addition, in the construction method using solid precast reinforced concrete beams, deformation of the beams is prevented, but there are also problems such as the fitting of closed-loop bars between the exposed jump parts, the arrangement of reinforcing bars around them, and the It is necessary to place fiber-reinforced concrete, and in particular, placing the concrete locally within the column head between the beams is a troublesome work, and there are problems in that it is likely to be one of the causes of a decrease in construction accuracy.
本発明は、前記のような課題に対処するために開発され
たものであって、梁の設計、施工計画等に対する自由度
が高く、省力化、施工能率の向上とともに、コスト節減
、品質向上等を可能としたプレキャスト式鉄筋コンクリ
ート柱・梁構築法を提供するにある。The present invention was developed to address the above-mentioned problems, and has a high degree of freedom in beam design, construction planning, etc., and can save labor, improve construction efficiency, reduce costs, improve quality, etc. To provide a method for constructing precast reinforced concrete columns and beams that enables
(課題を解決するための手段)
本発明は、梁下部上筋と肋筋を埋設した複数の断面U形
状プレキャスト鉄筋コンクリート梁部材の端部を柱頭部
に架設し、各梁部材の端部から露出し柱中心線の手前で
相対せしめた梁下部上筋の各露出跳上部間に補強副筋を
施して、相対し各梁部材の底部内面中央部に縦設されて
いる溝部内および梁間の柱頭部に中央部の梁下部上筋を
通し配筋し、各梁部材の肋筋の上部および梁間の柱頭部
に梁上部上筋を通し配筋することに特徴を有し、各露出
跳上筋(補強副筋)によるアンカーと梁上、下部主筋の
通し配筋にて、基本的に柱・梁接合部強度を確保すると
ともに、アンカーによる調整と中央部の梁下部上筋およ
び梁上部上筋の径、本数等の選択、設定により、所要の
柱・梁接合部強度への対応を容易、自在とし、局部的な
鋼繊維補強コンクリートの打設を不要にして、同様なコ
ンクリートの連続打設を可能にしている。(Means for Solving the Problems) The present invention involves erecting the ends of a plurality of precast reinforced concrete beam members with a U-shaped cross section in which lower beam upper reinforcements and cost reinforcements are buried in the column head, and exposing the ends of each beam member. A reinforcing sub-reinforcement is provided between each exposed jump part of the upper reinforcement at the bottom of the beam that faces each other in front of the column center line, and the column head is installed in the groove and between the beams that are vertically installed in the center of the bottom inner surface of each opposing beam member. The feature is that reinforcement is placed through the lower part of the beam at the center of the beam, and the upper reinforcement of the beam is placed through the top of the cost reinforcement of each beam member and the column head between the beams, and each exposed jump reinforcement Basically, the strength of the column-beam joint is ensured by anchors (reinforcing sub-reinforcements) and through-reinforcement on the beam top and bottom main reinforcements, and the strength of the column-beam joint is basically ensured, as well as adjustment using the anchors and the beam bottom top reinforcement and beam top top reinforcement in the center. By selecting and setting the diameter, number, etc., it is easy and flexible to accommodate the required strength of the column-beam joint, eliminating the need for localized steel fiber reinforced concrete pouring and allowing continuous pouring of similar concrete. is made possible.
また、相対した露出跳上部間にスパイラル筋と鋼管を嵌
装し補強副筋として施し、あるいは各梁下部主筋の露出
跳上筋を柱中心部を越えた配置とすることにより、アン
カー力の増加調整、露出跳上筋の短縮等を可能としコン
クリート打設を容易にして、所望の連結、固着力を確保
している。In addition, the anchor force can be increased by inserting spiral reinforcements and steel pipes between opposing exposed jump parts as reinforcement reinforcement, or by placing the exposed jump reinforcement of each beam lower main reinforcement beyond the center of the column. It enables adjustment, shortening of exposed jump bars, etc., making concrete placement easier and ensuring the desired connection and fixing force.
(作用)
梁下部主筋と肋筋を埋設した複数の断面U形状プレキャ
スト鉄筋コンクリート梁部材の端部を柱頭部に架設し、
各梁部材の端部を柱頭部で相対せしめかつ同端部から露
出しな各梁下部主筋の露出跳上筋を柱中心線の手前で相
対せしめ、同露出跳上筋間に補強副筋を施すとともに、
相対し各梁部材の底部内面中央部に縦設されている溝部
内および梁間の柱頭部に中央部の梁下部主筋を通し配筋
し、各梁部材の肋筋の上部および梁間の柱頭部に複数の
梁上部主筋を通し配筋して、同梁上、下部主筋の径、本
数等の選択、設定により所要の柱・梁接合部強度に対応
せしめ、柱部、柱頭部および梁部材に同様なコンクリー
トを連続して打設し、柱部分とともに複数の梁か一体に
連続施工、構築される。(Function) The ends of multiple U-shaped cross-sectional precast reinforced concrete beam members with embedded beam lower main reinforcement and cost reinforcement are erected on the column head,
The ends of each beam member are made to face each other at the column head, and the exposed jump reinforcements of the lower main reinforcement of each beam that are not exposed from the same end are made to face each other in front of the column center line, and reinforcing sub-reinforcements are placed between the exposed jump reinforcements. Along with giving
Reinforce the bottom main reinforcement of the central part of the beam in the groove vertically installed in the center of the bottom inner surface of each opposing beam member and through the column head between the beams. By placing reinforcement through multiple beam upper main reinforcements and selecting and setting the diameter, number, etc. of the upper and lower main reinforcements of the same beam, it corresponds to the required strength of the column-beam joint, and the same applies to column parts, column heads, and beam members. Concrete is poured continuously, and multiple beams or beams are continuously constructed and constructed together with the pillars.
断面U形状プレキャスト鉄筋コンクリート梁部材に、梁
下部主筋と肋筋を埋設することにより同梁部材の耐荷重
強度を高め、各露出跳上筋(補強副筋)によるアンカー
と中央部の梁下部主筋の通し配筋−および複数の梁上部
主筋の通し配筋により、基本的に柱・梁接合部の所要強
度が確保され、さらに各露出跳上笠間へのスパイラル筋
、鋼管の嵌装、または露出跳上筋を柱中心部を越えた配
置として各梁下部主筋の露出長さ増大と露出跳上筋を短
縮可能とする調整と、中央部の梁下部主筋および梁上部
主筋の径、本数等の選択、設定により、階層ことに異な
る所要の柱・梁接合部強度への対応を容易、自在となし
、中央部の前記梁下部主筋は溝部で埋設筋に対し容易に
整合され、梁上、下部主筋の配筋が容易、迅速に遂行さ
れる。The load-bearing strength of the beam member is increased by embedding the lower beam main reinforcement and cost reinforcement in a precast reinforced concrete beam member with a U-shaped cross section. The required strength of the column-beam joint is basically ensured by through-reinforcement arrangement and the through-reinforcement arrangement of multiple main reinforcements at the top of the beam, and furthermore, the required strength of the column-beam joint is ensured. Adjustment to increase the exposed length of the lower main reinforcement of each beam and shorten the exposed jump reinforcement by placing the upper reinforcement beyond the center of the column, and selection of the diameter, number, etc. of the lower main reinforcement of the beam and the upper main reinforcement of the beam in the center By setting, it is possible to easily and freely respond to the required strength of the column-beam joint, which differs depending on the hierarchy. Reinforcement can be easily and quickly performed.
また柱頭部内のみに鋼繊維補強コンクリートを打設する
必要がなくなり、柱部、柱頭部とともに梁部材内に同様
なコンクリートを連続して打設でき一施工か容易、迅速
に遂行され優れた施工精度が得られる。In addition, it is no longer necessary to pour steel fiber reinforced concrete only inside the column head, and the same concrete can be poured continuously inside the beam member as well as the column head, making it easy and quick to perform one construction job, resulting in excellent construction accuracy. is obtained.
(実施例)
第1図ないし第6図に本発明の第1実施例を示し、図中
1は柱部、10は断面U形状のプレキャスト鉄筋コンク
リート梁部材であって、柱部1は、施工現場で複数の柱
主筋2、柱帯筋3、柱側帯筋4を図示のように組み立て
配筋し、その組立鉄筋の周囲に合板型枠5を支持部材6
で配置して組立型枠とし、同組立型枠内にコンクリート
Cを打設して鉄筋コンクリート柱に構築する。(Embodiment) A first embodiment of the present invention is shown in FIGS. 1 to 6, in which 1 is a column, 10 is a precast reinforced concrete beam member with a U-shaped cross section, and the column 1 is a construction site. A plurality of column main reinforcements 2, column tie reinforcements 3, and column side tie reinforcements 4 are assembled and reinforced as shown in the figure, and a plywood formwork 5 is placed around the assembled reinforcement members 6.
The concrete C is then placed in the assembled form to form a reinforced concrete column.
プレキャスト鉄筋コンクリート梁部材10は、工場等で
予め製造され、断面U形状のコンクリート梁主体11、
同梁主体11内に埋設された複数の梁下部主筋12、埋
設された複数の肋筋13からなり、各梁下部主筋12は
、前記梁部材10の端部から突出して露出し先端部を上
方へ折り曲げ形成した露出跳上筋12aを有し、肋筋1
3は、その上部に露出部13aを有し、前記梁主体11
の底部内面中央部に溝部14を縦設し、さらに内面に多
数の凹部18を配設した構造になっている0図中15は
中央部に配筋される梁下部主筋、16は各肋筋13の上
部に配筋される梁上部主筋、17は露出跳上筋12a、
12a間に嵌装して補強副筋とするスパイラル筋、30
は上面に多数の係止筋(カイザー筋)31が突出、配設
されたプレキャスト鉄筋コンクリート打設版である。The precast reinforced concrete beam member 10 is manufactured in advance in a factory or the like, and has a U-shaped cross-sectional concrete beam main body 11,
Consisting of a plurality of beam lower main reinforcements 12 buried in the beam main body 11 and a plurality of buried cost reinforcements 13, each beam lower main reinforcement 12 protrudes from the end of the beam member 10 and is exposed, with the tip end facing upward. It has an exposed jumping muscle 12a that is bent to form a rib muscle 1.
3 has an exposed portion 13a on its upper part, and the beam main body 11
It has a structure in which a groove 14 is installed vertically in the center of the inner surface of the bottom, and a number of recesses 18 are further arranged in the inner surface.In the figure, 15 is the main reinforcement at the bottom of the beam, which is reinforced in the center, and 16 is each sub-reinforcement. 13 is the beam upper main reinforcement placed on the upper part, 17 is the exposed jumping reinforcement 12a,
Spiral reinforcement inserted between 12a and used as reinforcing sub-reinforcement, 30
This is a precast reinforced concrete plate with a large number of locking bars (Kaiser bars) 31 protruding from the upper surface.
本発明は、中層さらに高層の鉄筋(あるいはまた鉄骨)
コンクリート造ラーメン構造建物の構築に好適なプレキ
ャスト式鉄筋コンクリート柱・梁W4築法であり、柱部
1に鉄筋2〜4、型枠5.6を図示のように組み立て、
間隔をおき複数の梁下部主筋12と肋筋13を埋設した
複数のプレキャスト鉄筋コンクリート梁部材10の端部
を柱頭部1aに架設し、前記端部を柱頭部1aで相対せ
しめ各露出跳上筋12aを柱中心部の手前に配置し相対
せしめ、相対した各露出跳上筋12a、12a間に補強
副筋、即ちスパイラル筋17を嵌装して施し、相対し前
記各梁部材10の底部内面中央部に縦設されている溝部
14内および梁間の柱頭部1aに中央部の梁下部主筋1
5を通し配筋し、前記各梁部材10の肋筋13の上部お
よび梁間の柱頭部1aに複数の梁上部主筋16を通し配
筋して、同梁上、下部主筋12.15.16を所0
要の柱・梁接合部強度に対応せしめ、柱部1、柱頭部1
aおよび前記梁部材10に同様なコンクリ−1−〇を連
続的に打設し、その乾燥、固着により柱と梁が一体に連
結施工、構築される。The present invention is a method for reinforcing bars (or steel frames) in middle and high-rise buildings.
It is a precast reinforced concrete column/beam W4 construction method suitable for constructing a concrete rigid frame structure building, and the column part 1 is assembled with reinforcing bars 2 to 4 and formwork 5.6 as shown in the diagram.
The ends of a plurality of precast reinforced concrete beam members 10, in which a plurality of beam lower main reinforcements 12 and cost reinforcements 13 are buried at intervals, are erected on the column head 1a, and the ends are made to face each other at the column head 1a, and each exposed jump reinforcement 12a is constructed. are arranged in front of the center of the column so that they face each other, and a reinforcing sub-reinforcement, that is, a spiral reinforcement 17 is fitted between the opposing exposed jumping reinforcements 12a, 12a, and the center of the inner surface of the bottom of each beam member 10 is placed opposite to each other. Main reinforcement 1 at the bottom of the beam in the center of the column head 1a between the beams and in the groove 14 vertically installed in the section.
5, and a plurality of beam upper main reinforcements 16 are passed through the upper part of the cost reinforcement 13 of each beam member 10 and the column head 1a between the beams, and the upper and lower main reinforcements 12, 15, and 16 of the beams are reinforced. Required 0 Corresponding to the required strength of the column-beam joint, column part 1, column head 1
A and the beam member 10 are continuously poured with similar concrete 1-0, and by drying and fixing, the column and the beam are connected and constructed as one.
前記構築に際し、、梁上部に床を同時に施工、構築する
。即ち前記各梁部材10の前記業主体11の上部に係止
筋31付き床下板30が図示のように配置され、第1.
5図のように床下板30.30間に多数の連結筋32を
、床下板30上の全面に多数の床主筋33を係止筋31
で配筋して、前記コンクリートCを梁部材10内に続き
梁上部、さらに床下板30の上面にわたり打設し、梁上
部に露出部13a、連結筋32、床主筋33等を埋設し
た床連結部を一体に施工、構築する。During the above construction, the floor is constructed and constructed on the top of the beam at the same time. That is, a floorboard 30 with locking bars 31 is disposed above the business body 11 of each beam member 10 as shown in the figure, and the first.
As shown in FIG.
The concrete C is placed inside the beam member 10, over the top of the beam, and then over the top surface of the subfloor board 30, and the exposed part 13a, connecting bars 32, main floor bars 33, etc. are buried in the top of the beam to connect the floor. Construction and construction of the parts as one.
第7図ないし第10図に本発明の第2実施例を示し、第
1実施例と比べると、前記スパイラル筋17とともに各
露出跳上筋12a 、12a間の折り曲げ基部に鋼管1
9を嵌装し補強副筋として施し、柱タイヤフープ筋8を
中間の柱主筋2に角部の嵌合により配筋した構成に特徴
を有し、その池の構成は1
第1実施例と同様になっており、柱・梁接続部強度が高
められ比較的大きい柱・梁接合部強度か要求される階層
の梁に好適となる。A second embodiment of the present invention is shown in FIGS. 7 to 10, and in comparison with the first embodiment, a steel pipe is attached to the bent base between each exposed jumping reinforcement 12a, 12a together with the spiral reinforcement 17.
9 is fitted as a reinforcing sub-reinforcement, and the column tire hoop reinforcement 8 is arranged by fitting the corner of the main column reinforcement 2 in the middle, and the configuration of the pond is 1. Similarly, the strength of the column-beam joint is increased, making it suitable for beams on floors that require relatively large strength of the column-beam joint.
第11図に本発明の第3実施例を示しており、第1大施
例と比べると、各梁下部上筋12の露出跳上筋12aを
柱中心線を越えた配置にした構成に特徴を有し、その他
の構成は基本的に第1実施例と同様になっており、梁下
部上筋の露出長さを増大してアンカー力を確保し、露出
跳上筋の短縮を可能としコンクリートの打設を容易にし
て、比較的に下部階層の梁に好適となる。FIG. 11 shows a third embodiment of the present invention, which, compared to the first large embodiment, is characterized by a structure in which the exposed jump reinforcements 12a of each beam lower upper reinforcement 12 are arranged beyond the column center line. The rest of the structure is basically the same as the first embodiment, and the exposed length of the upper reinforcement at the bottom of the beam is increased to ensure anchoring force, and the exposed jump reinforcement can be shortened. This makes it easier to place the concrete, making it relatively suitable for beams on lower floors.
前記補強副筋としては、スパイラル筋17のみ、鋼管1
9の併設、あるいは柱中心部を越えた露出跳上筋12a
の適用により、所要の柱・梁接合部強度に対応される。As the reinforcing sub-reinforcements, only the spiral reinforcement 17 and the steel pipe 1 are used.
9 or exposed jumping muscle 12a beyond the center of the column.
By applying this, the required strength of the column-beam joint can be achieved.
また該補強副筋は、図示のように相対した複数木組こと
に配置され柱中心部の周囲にコンパクトに配置されて、
コンクリート打設を容易とし効果的に機能する。In addition, the reinforcing sub-reinforcements are arranged in a plurality of opposing wooden frames as shown in the figure, and arranged compactly around the center of the column.
It facilitates concrete placement and functions effectively.
中央部の梁下部上筋15は、溝部14内に容易に配置さ
れ自動的に埋設筋に対し整合されるとともに、2
その径、本数等の選択、設定により、所要の柱・梁接合
部強度に対応され、その通し配筋により優れた連結強度
が確保される。また梁上部主筋16についても同様な選
択、設定と通し配筋により、同様な効果かを得ることが
できる。また第5図に示すように複数の梁中間主筋34
も配筋される。The beam lower upper reinforcement 15 in the central part is easily placed in the groove 14 and automatically aligned with the buried reinforcement. The through reinforcement arrangement ensures excellent connection strength. Moreover, the same effect can be obtained with the beam upper main reinforcement 16 by similar selection, setting, and through-reinforcement arrangement. In addition, as shown in FIG. 5, a plurality of beam intermediate main reinforcements 34
Reinforcement will also be provided.
プレキャスト鉄筋コンクリート梁部材10は、複数の梁
下部上筋12、肋筋13か埋設され強化されて変形、破
壊か防止され、露出跳上筋12a −12a(補強副筋
)によるアンカー、梁上、下部主筋15.16の通し配
筋により、同様なコンクリートで連続して打設でき、施
工能率、精度が格段に向上される。また梁部材10の内
面に設けた多数の凹部18により打設コンクリートと一
体化される。The precast reinforced concrete beam member 10 has a plurality of lower beam upper reinforcements 12 and cost reinforcements 13 embedded and strengthened to prevent deformation and destruction, and is anchored by exposed jump reinforcements 12a-12a (sub-reinforcement reinforcements), upper and lower parts of the beam. Through-through arrangement of main reinforcements 15 and 16 allows continuous pouring of similar concrete, greatly improving construction efficiency and accuracy. Furthermore, the beam member 10 is integrated with the poured concrete by a large number of recesses 18 provided on the inner surface thereof.
前記実施例において、プレキャスト鉄筋コンクリート柱
部材の適用、また鉄骨の一部併用も可能である。In the embodiments described above, it is possible to use precast reinforced concrete column members, or to partially use a steel frame.
(発明の効果)
本発明は、前述のように断面U形状プレキャスト鉄筋コ
ンクリート梁部材に、梁下部上筋、肋筋3
を埋設して変形、破壊を防止して施工を容易とし、各梁
下部上筋の露出跳上筋間のアンカーと、梁上、下部主筋
の通し配筋とともに、それらの自在な調整により、所要
の柱・梁接合部強度への対応・注を有り1梁設計−施工
計画等の自由度か高く、施工が容易、迅速に遂行されて
、省力化とともに施工能率か格段に向上され優れた施工
精度か得られる。(Effects of the Invention) As described above, the present invention embeds the beam lower upper reinforcement and cost reinforcement 3 in a precast reinforced concrete beam member with a U-shaped cross section to prevent deformation and destruction and facilitate construction. Exposure of reinforcement In addition to anchors between jump reinforcements and through-reinforcement of main reinforcements on the top and bottom of the beam, by freely adjusting them, the required strength of the column-beam joint can be accommodated and noted. 1 beam design - construction plan The degree of freedom is high, construction is easy and quick, labor-saving, construction efficiency is greatly improved, and excellent construction accuracy is achieved.
さらに大幅なコスト節減がされるなとの利点がある。There is also the advantage of significant cost savings.
第1図は本発明の第1実施例を示す全体の斜視図、第2
図Aは第17の柱部横断面図、第2図Bは梁部材の正面
図、第3図は柱・梁接合部分の側視図、第4図は同じく
平面図、第5図は梁部の縦断面図、第6図は露出跳上筋
の側視図、第7図は第2実施例を示す全体の斜視図、第
8図は第7図の柱・梁接合部分の側視図、第9図は同じ
く平面図、第10図は露出跳上筋の側視図、第11図は
第3実施例を示す全体の斜視図である。
1a:柱頭部 10:鉄筋コンクリート梁部材4
12.
15:
梁下部主筋
12a・露出跳上筋
3
肋筋
4
溝部
6
梁上部主筋
7
スパイラル筋
19:
鋼管
代理、(FIG. 1 is an overall perspective view showing the first embodiment of the present invention, and FIG.
Figure A is a cross-sectional view of the 17th column, Figure 2B is a front view of the beam member, Figure 3 is a side view of the column-beam joint, Figure 4 is the same plan view, and Figure 5 is the beam member. FIG. 6 is a side view of the exposed jump muscle, FIG. 7 is a perspective view of the entire structure showing the second embodiment, and FIG. 8 is a side view of the column-beam joint in FIG. FIG. 9 is a plan view, FIG. 10 is a side view of the exposed jumping muscle, and FIG. 11 is an overall perspective view showing the third embodiment. 1a: Column head 10: Reinforced concrete beam member 4 12. 15: Beam lower main reinforcement 12a/exposed jump reinforcement 3 Cost reinforcement 4 Groove 6 Beam upper main reinforcement 7 Spiral reinforcement 19: Steel pipe substitute, (
Claims (3)
レキャスト鉄筋コンクリート梁部材の端部を柱頭部に架
設し、前記各梁部材の端部から露出し柱中心線の手前側
で相対せしめた梁下部主筋の各露出跳上筋間に補強副筋
を施して、相対し前記各梁部材の底部内面中央部に縦設
されている溝部内および梁間の柱頭部に中央部の梁下部
主筋を通し配筋し、前記各梁部材の肋筋の上部および梁
間の柱頭部に複数の梁上部主筋を通し配筋して、同梁上
、下部主筋を所要の柱・梁接合部強度に対応せしめ、前
記柱頭部および前記梁部材にコンクリートを打設するこ
とを特徴とするプレキャスト式鉄筋コンクリート柱・梁
構築法。(1) The ends of a plurality of precast reinforced concrete beam members with a U-shaped cross section, in which the lower beam main reinforcement and reinforcing bars are buried, are erected on the column head, and the ends of each beam member are exposed from the end and are faced to each other on the near side of the column center line. A reinforcing sub-reinforcement is provided between each exposed jump reinforcement of the lower main reinforcement of the beam, and the lower main reinforcement of the beam at the center is installed in the column head between the beams and in the groove vertically installed in the center of the bottom inner surface of each of the opposing beam members. By placing reinforcement through the upper part of each beam member and through the column head between the beams, multiple beam upper main reinforcements are installed, and the upper and lower main reinforcements of the beam correspond to the required strength of the column-beam joint. A method for constructing a precast reinforced concrete column and beam, characterized by pouring concrete into the column head and the beam member.
柱・梁構築法において、相対した露出跳上筋間にスパイ
ラル筋と鋼管を嵌装して補強副筋とすることを特徴とす
るプレキャスト式鉄筋コンクリート柱・梁構築法。(2) In the precast reinforced concrete column/beam construction method according to claim 1, the precast reinforced concrete column/beam is characterized in that spiral reinforcements and steel pipes are fitted between the exposed jumping reinforcements to serve as secondary reinforcing reinforcements. Beam construction method.
柱・梁構築法において、各梁下部主筋の露出跳上筋を柱
中心部を越えた配置とし、柱頭部における各梁下部主筋
の露出部長さを増大することを特徴とするプレキャスト
式鉄筋コンクリート柱・梁構築法。(3) In the precast reinforced concrete column/beam construction method according to claim 1, the exposed jump reinforcement of each beam lower main reinforcement is arranged beyond the center of the column, increasing the length of the exposed length of each beam lower main reinforcement at the column head. A precast reinforced concrete column and beam construction method that is characterized by:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27024689A JPH0742721B2 (en) | 1989-10-19 | 1989-10-19 | Reinforced concrete column / beam construction method using precast beam members |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27024689A JPH0742721B2 (en) | 1989-10-19 | 1989-10-19 | Reinforced concrete column / beam construction method using precast beam members |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03132532A true JPH03132532A (en) | 1991-06-05 |
JPH0742721B2 JPH0742721B2 (en) | 1995-05-10 |
Family
ID=17483585
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP27024689A Expired - Lifetime JPH0742721B2 (en) | 1989-10-19 | 1989-10-19 | Reinforced concrete column / beam construction method using precast beam members |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0742721B2 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100806821B1 (en) * | 2006-12-19 | 2008-02-22 | 삼성중공업 주식회사 | Hollow core beam using the u-type precast concrete box, construction method and connection thereof |
JP2008127941A (en) * | 2006-11-24 | 2008-06-05 | Kurosawa Construction Co Ltd | Structure and method for joining column and beam together |
JP2008127940A (en) * | 2006-11-24 | 2008-06-05 | Kurosawa Construction Co Ltd | Structure and method for joining column and beam together |
US20080302057A1 (en) * | 2005-07-28 | 2008-12-11 | Michael Muller | Method for Producing a Wall-Ceiling Reinforced Concrete Construction |
JP2019082006A (en) * | 2017-10-27 | 2019-05-30 | 三井住友建設株式会社 | Beam-to-column connection structure and construction method thereof |
CN110093978A (en) * | 2019-05-28 | 2019-08-06 | 广东联城住工装备信息科技有限公司 | Connecting joint structure, the construction method of connecting joint structure and assembled architecture |
CN115573597A (en) * | 2022-11-02 | 2023-01-06 | 中铁建工集团有限公司 | Fully-assembled concrete canopy and construction method thereof |
-
1989
- 1989-10-19 JP JP27024689A patent/JPH0742721B2/en not_active Expired - Lifetime
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080302057A1 (en) * | 2005-07-28 | 2008-12-11 | Michael Muller | Method for Producing a Wall-Ceiling Reinforced Concrete Construction |
US8484928B2 (en) * | 2005-07-28 | 2013-07-16 | Vst Verbundschalungstechnik Ag | Method for producing a wall-ceiling reinforced concrete construction |
JP2008127941A (en) * | 2006-11-24 | 2008-06-05 | Kurosawa Construction Co Ltd | Structure and method for joining column and beam together |
JP2008127940A (en) * | 2006-11-24 | 2008-06-05 | Kurosawa Construction Co Ltd | Structure and method for joining column and beam together |
KR100806821B1 (en) * | 2006-12-19 | 2008-02-22 | 삼성중공업 주식회사 | Hollow core beam using the u-type precast concrete box, construction method and connection thereof |
JP2019082006A (en) * | 2017-10-27 | 2019-05-30 | 三井住友建設株式会社 | Beam-to-column connection structure and construction method thereof |
CN110093978A (en) * | 2019-05-28 | 2019-08-06 | 广东联城住工装备信息科技有限公司 | Connecting joint structure, the construction method of connecting joint structure and assembled architecture |
CN115573597A (en) * | 2022-11-02 | 2023-01-06 | 中铁建工集团有限公司 | Fully-assembled concrete canopy and construction method thereof |
CN115573597B (en) * | 2022-11-02 | 2023-08-15 | 中铁建工集团有限公司 | Fully-assembled concrete canopy and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH0742721B2 (en) | 1995-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH03132532A (en) | Construction method of precast reinforced concrete column and beam | |
JP2926149B2 (en) | Column and beam joining method and its structure | |
JPH0762731A (en) | Joining method of pillar and beam | |
JPS6314937A (en) | Reinforcing bar composite pillar | |
JPH02300439A (en) | Prefabricating method | |
JPH0434161A (en) | Centrifugally molded hollow pc concrete column and column construction method | |
JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
JPS63268834A (en) | Method for constructing body of multi-storied building and reinforcing bar connected cylinder used therein | |
JP2006328798A (en) | Composite structure frame | |
JPH0732706Y2 (en) | Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams | |
JPH01214641A (en) | Construction of steel-pipe precast concrete pole | |
JPH07103620B2 (en) | Construction method for steel structure | |
JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
JPH0447737B2 (en) | ||
JPH06306931A (en) | Construction of steel frame reinforced concrete structure | |
JPH0745783B2 (en) | Construction method of precast column beam and precast earthquake resistant wall. | |
JPH01203537A (en) | Src precast beam and junction structure of column and beam | |
JP2893406B2 (en) | Precast concrete beam-column joining method | |
JPS5830459B2 (en) | Construction method of precast reinforced concrete structure | |
JPS6134468Y2 (en) | ||
JPS6334926B2 (en) | ||
JPS62182329A (en) | Construction of concrete structure | |
JPH0949264A (en) | Constructing method for reinforced concrete framework and structure, and member therefor | |
JPH10231559A (en) | Center pillar provided with beam steel frame, and construction method for mixed structure using same | |
JP2002097716A (en) | Short support slab supporting structure |