JPH0949264A - Constructing method for reinforced concrete framework and structure, and member therefor - Google Patents
Constructing method for reinforced concrete framework and structure, and member thereforInfo
- Publication number
- JPH0949264A JPH0949264A JP22956895A JP22956895A JPH0949264A JP H0949264 A JPH0949264 A JP H0949264A JP 22956895 A JP22956895 A JP 22956895A JP 22956895 A JP22956895 A JP 22956895A JP H0949264 A JPH0949264 A JP H0949264A
- Authority
- JP
- Japan
- Prior art keywords
- hpc
- girder
- concrete
- pillar
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、鉄筋コンクリート造の
架構のような、構造物の構築方法と、これの実施に必要
な物に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a structure, such as a reinforced concrete frame, and a material necessary for implementing the method.
【0002】[0002]
【従来の技術】従来、鉄筋コンクリート造軸組の構築方
法は、足場を掛け、仮枠支保工を建て、その上に仮枠を
設置し、仮枠内部に鉄筋を組立て、コンクリートを打設
し、コンクリートが所定の強度を発現した後、仮枠支保
工と仮枠を撤去する、という方法であった。この構築方
法は、工程が複雑で長期間の工期を要し、作業は高所で
の現場作業が多く、工場や地上の作業場の作業に比較し
て、作業環境が悪いため、安全と能率の面で改善が求め
られていた。足場、仮枠支保工と型枠の設置および撤
去、仮枠内部での鉄筋の組立は、煩雑で多大の労力と時
間を要することから、これらを軽減する方法が提案され
ている。例えば工場生産された鉄筋コンクリート製の中
空の柱部材を現場に設置し、これにコンクリ−トを打設
して柱の一部とする方法がある(特開昭64−8064
9号)。この方法は柱について仮枠支保工と仮枠の設置
および撤去を不要にしているが、鉄筋コンクリート造軸
組全体についての作業の単純化、省力化と工期の短縮の
観点から、なお不十分であった。2. Description of the Related Art Conventionally, a method of constructing a reinforced concrete frame is to hang a scaffold, build a temporary frame support, install a temporary frame on it, assemble a reinforcing bar inside the temporary frame, and place concrete. The method was to remove the temporary frame support work and the temporary frame after the concrete developed a predetermined strength. This construction method is complicated and requires a long construction period, and most of the work is on-site work at high places, and the work environment is poor compared to work at a factory or a work place on the ground, so safety and efficiency are improved. In terms of aspect, improvement was required. Since scaffolding, temporary frame support work, installation and removal of formwork, and rebar assembly inside the temporary frame are complicated and require a lot of labor and time, a method of reducing them has been proposed. For example, there is a method in which a hollow column member made of reinforced concrete produced in a factory is installed on the site, and a concrete is placed therein to form a part of the column (Japanese Patent Laid-Open No. 64-8064).
No. 9). This method eliminates the need for temporary frame support work and the installation and removal of temporary frames for columns, but it is still insufficient from the viewpoints of simplification of work on the entire reinforced concrete framework, labor saving, and shortening of the construction period. It was
【0003】[0003]
【発明が解決しようとする課題】本発明は、鉄筋コンク
リート造軸組の構築方法を改善して、足場、仮枠支保工
と仮枠を不要とし、従来高所の現場で行われていた仮枠
支保工、仮枠の組立作業と鉄筋の組立作業を工場または
現場作業場の作業に置き換え、また工場生産部材ユニッ
ト、現場作業場組立部材ユニット双方の重量を平準化し
て、資材の効率的な運搬を可能にし、工期を短縮し、工
事費を節減し、作業の安全性の確保し、同時に、在来の
鉄筋コンクリート造構造物の構築方法である、コンクリ
ートを現場で一体に打設して連続で不静定次数の高い優
れた構造物を作るという長所を有する、強靭な鉄筋コン
クリート造軸組の構築方法を提供し、次に前記構築方法
が一般的方法であることを利用し、地震時の地震力の構
造物への伝わり方を抑制する免震装置を有する免震構造
と、比較的長い梁間で必要となるPSコンクリートの大
梁を含む軸組構造と、二次部材の一例として、HPC床
版部材を含んだ鉄筋コンクリート構造物等にまで拡張し
た構築方法と、これに用いる部材を提供することにあ
る。DISCLOSURE OF THE INVENTION The present invention has improved the method of constructing a reinforced concrete frame to eliminate the need for scaffolding, temporary frame support and temporary frame, and the conventional temporary frame that has been carried out at high places. Support work, temporary frame assembly work and rebar assembly work have been replaced with factory or field work site work, and the weight of both the factory production material unit and field work site assembly material unit has been leveled to enable efficient transportation of materials. It shortens the construction period, saves the construction cost, secures the safety of work, and at the same time, it is the conventional method of constructing a reinforced concrete structure. Providing a method of constructing a strong reinforced concrete construction frame, which has the advantage of producing an excellent structure with a high constant order, and then utilizing the fact that the construction method is a general method, How to reach the structure For a seismic isolation structure having a seismic isolation device, a frame structure including a PS concrete large beam required for relatively long beams, and a reinforced concrete structure including an HPC floor slab member as an example of a secondary member. The purpose of the present invention is to provide a construction method expanded up to and a member used therefor.
【0004】[0004]
(構築方法の改善)先ず、従来の鉄筋コンクリート造軸
組の構築方法を、工場あるいは現場作業場で造られたH
PC柱部材、とHPC大梁部材をHPC軸組架構に組み
立て、工場あるいは現場作業場で、組み立てられた先組
み鉄筋篭を立て込み、コンクリートを打設するという構
築方法に改善する。この構築方法において、打設するコ
ンクリートと、鉄筋篭と、HPC部材を、架構のための
3要素と考えて、それぞれを次のように分割する。(Improvement of construction method) First, the construction method of the conventional reinforced concrete frame is the H
The construction method of assembling the PC pillar member and the HPC girder member into the HPC shaft frame structure, placing the assembled pre-assembled rebar cage and placing concrete in the factory or on-site workshop is improved. In this construction method, the concrete to be cast, the rebar cage, and the HPC member are considered as three elements for the frame, and each is divided as follows.
【0005】(コンクリートの打設区分)コンクリート
は、床面を打ち継ぎ部分とし、床面から直上階の床面ま
でを一体となるように打設して、連続で不静定次数の高
い優れた構造物を作るという、在来の鉄筋コンクリート
造構造物の架構方法の長所を生かす。(Concrete placement category) Concrete is a continuous joint having a high static constant order by placing the floor surface as a jointing portion and placing the floor surface and the floor surface immediately above the floor integrally. The advantage of the conventional method of framing reinforced concrete structures is to make use of these structures.
【0006】(HPC造軸組の分割)HPC造軸組は、
節点を接続部とし、柱にあっては、各階の床面から大梁
下面までを1部材とし、大梁にあっては、スパン毎に梁
端から梁端までを、1部材としたユニットに分割する。(Splitting of HPC Framework) HPC framework is
Divide into units with nodes as connecting parts, and for columns, from the floor surface of each floor to the bottom of the girder as one member, and for girders, from the beam end to the beam end as one member for each span. .
【0007】(鉄筋篭への分割)鉄筋篭は中央部と中間
部を接続部とし、柱は中央部、大梁は中間部で分割し、
柱筋は、下柱の上部分から上柱の下部分、大梁筋は、左
梁の右部分から右梁の左部分、後ろ梁の前部分から前梁
の後ろ部分の鉄筋を、節点毎に1つの鉄筋篭に組み立て
る。(Division into rebar cages) Rebar cages have a central portion and an intermediate portion as connecting portions, a pillar is divided into a central portion, and a girder is divided into an intermediate portion,
Column reinforcements are from the upper part of the lower column to the lower part of the upper column, and the girder reinforcements are the reinforcements from the right part of the left beam to the left part of the right beam, the front part of the back beam to the back part of the front beam, for each node. Assemble into one rebar basket.
【0008】(HPC柱部材の形と構造)次に、HPC
柱部材の形と構造は、頂部及び底部が開放で、内部が中
空な筒状で、出隅部分内側に配置したHPC柱部材主筋
と、HPC柱部材帯筋を互いに緊結して、HPC柱部材
主筋の周囲の被り部分と、HPC柱部材帯筋の外側の被
り部分は、法令に定められた以上の厚さのコンクリート
で被覆して、本体部分に内蔵し、HPC柱部材帯筋から
内側に向かっては、前記帯筋が隠れる程度にコンクリー
トに埋設している。また前記主筋は両端部で、頂部突出
主筋と底部突出主筋に連続している。(Shape and Structure of HPC Column Member) Next, HPC
The shape and structure of the pillar member is such that the top and bottom are open and the inside is hollow, and the HPC pillar member main bar and the HPC pillar member band bar arranged inside the projected corner are tightly connected to each other to form an HPC pillar member. The covering part around the main bar and the outer covering part of the HPC pillar member stirrup are covered with concrete having a thickness greater than that specified by law, and built into the main body part. On the other hand, it is buried in concrete to such an extent that the strips are hidden. The main bar is continuous at both ends with the top protruding main bar and the bottom protruding main bar.
【0009】(HPC大梁部材の形と構造)HPC大梁
部材の形と構造は、両端部及び頂部が開放で、全体とし
て溝型で、梁長の全区間に亘り、下側の出隅部分内側
に、HPC大梁部材主筋を引き通し、さらに長期加重に
よる曲げモーメントに対し必要な場合は、主筋を梁長の
中間部の下側に追加配置し、前記主筋とU字型で上方開
放のHPC大梁部材肋筋を緊結し、HPC大梁部材肋筋
の外側の被り部分と、HPC大梁部材主筋の周囲の被り
部分は法令に定められた以上厚さのコンクリートで被覆
して、本体部分に内蔵し、HPC大梁部材肋筋から内側
に向かっては、前記肋筋が隠れる程度にコンクリーに埋
設している。(Shape and Structure of HPC Girder Member) The shape and structure of the HPC girder member is a groove type as a whole with both ends and apex open, and inside the lower projected corner portion over the entire length of the beam. In addition, if the main reinforcement of the HPC girder member is pulled through and the bending moment due to long-term loading is required, the main reinforcement is additionally arranged below the middle part of the beam length, and the main reinforcement and the UPC girder of U-shape open upward. The member ribs are tightly bound, and the outer covering portion of the HPC girder member ribs and the covering portion around the HPC girder member main muscles are covered with concrete having a thickness not less than that stipulated by law, and embedded in the main body. The HPC girder member is buried in concrete from the ribs toward the inside so that the ribs are hidden.
【0010】(PSのHPC大梁部材の構造)必要に応
じて、HPC大梁部材主筋については、鉄筋コンクリー
ト鋼棒に替えて、PC鋼線又はPC鋼棒を使用し、PS
のHPC大梁部材とすることができる。(Structure of HPC Girder Member of PS) If necessary, for the main bar of the HPC girder member, a PC steel wire or a PC steel bar is used instead of the reinforced concrete steel bar.
The HPC girder member can be used.
【0011】(軸組接合部の構造)柱と大梁の交差部で
ある軸組接合部の形と構造は、上下のHPC柱部材の底
部突出主筋と頂部突出主筋を接合する、スリーブジョイ
ントを配置し、鉄筋篭を挿入後、スリーブジョイントを
取り巻いて帯筋を配筋し、両者を緊結し、スリーブジョ
イント周辺に必要な補強配筋を行い、これらの鉄筋に法
令で定められた以上の厚さの被りを有するようにコンク
リートを打設する。柱を中心にして隣接する大梁の相互
の間は、HPC柱大梁部材で囲われていないので、この
部分は別途仮枠が必要であるが、仮枠の材料としてはコ
ンクリート打設後、鉄筋の被りの一部として機能し、取
り外す必要のない材料を用い、打ち込み仮枠とする。(Structure of framing joint) The shape and structure of the framing joint, which is the intersection of the pillar and the girder, has a sleeve joint for joining the bottom protruding main bar and the top protruding main bar of the upper and lower HPC pillar members. Then, after inserting the rebar cage, arranging the band joints around the sleeve joints, binding them together, and performing the necessary reinforcement bar arrangements around the sleeve joints. Pour the concrete so that it has a cover. Since the HPC column girder members are not enclosed between adjacent girders centering around the column, a separate temporary frame is required for this part. Use a material that functions as a part of the cover and does not need to be removed, and make a temporary frame for driving.
【0012】(免震基礎)免震要素を備えた免震基礎及
び地中梁を、所定の位置に所定の構造で構築し、その上
に前述の鉄筋コンクリート造軸組を構築し、全体として
免震性能を有する鉄筋コンクリート造構造物を構築す
る。(Seismic isolation foundation) A seismic isolation foundation and an underground girder having seismic isolation elements are constructed in a prescribed structure at a prescribed position, and the above-mentioned reinforced concrete frame is constructed on the seismic isolation foundation. Construct a reinforced concrete structure with seismic performance.
【0013】(HPC床版部材)軸組の節点部分で接続
して組立てたHPC軸組のHPC大梁部材の上に、HP
C床版部材または既成の床版部材や捨て仮枠を掛け渡
し、所定の床配筋を行った後、鉄筋コンクリート造構造
物を構築する。(HPC floor slab member) On the HPC girder member of the HPC shaft assembly assembled by connecting at the nodal points of the shaft assembly, HP
After the C floor slab member or the existing floor slab member and the temporary frame for discarding are laid over and predetermined floor reinforcement is performed, a reinforced concrete structure is constructed.
【0014】[0014]
(分割と組立)本発明による構築方法では、打設するコ
ンクリートと、先組みの鉄筋篭と、HPC部材を、架構
のための3要素と考え、それぞれを前述のように分割し
た結果、HPC部材の接合部は節点に、先組みの鉄筋篭
の継ぎ手は部材中央部と中間部に設けられ、両者は分離
するので、組立のための材料と作業の輻輳が避けられ
る。(Division and Assembly) In the construction method according to the present invention, the concrete to be cast, the pre-assembled rebar cage, and the HPC member are considered to be the three elements for the frame, and the HPC member is divided as described above. The joints are provided at the nodes, and the joints of the pre-assembled rebar cages are provided at the central portion and the intermediate portion of the member, and the two are separated from each other, so that the material for assembling and the work congestion can be avoided.
【0015】(鉄筋の継ぎ手)構造強度の点から水平加
重時の曲げモーメントは、一般に節点部分が大きく、部
材の中間部分、中央部分は小さくなるが、本発明による
先組みの鉄筋篭の鉄筋は、応力の大きくなる節点部分で
は、引き通し鉄筋となり、応力の小さい部材の中央部
分、中間部分で、鉄筋篭の主筋の継ぎ手を設けることと
なり、構造上非常に有利である。(Reinforcing bar joint) From the viewpoint of structural strength, the bending moment when horizontally loaded is generally large at the nodal points and small at the intermediate and central portions of the member, but the reinforcing bar of the pre-assembled rebar cage according to the present invention is The joints of the main bars of the rebar cage are provided at the central portion and the intermediate portion of the member having the small stress, which is very advantageous in terms of the structure.
【0016】(ユニット重量の平準化)また前述の分割
の結果、HPC柱部材、HPC大梁部材、鉄筋篭の各ユ
ニットの大きさは限定され、重量は軽減され、通常の中
型揚重機の平常時の揚重能力以内となり、且つ重量は平
準化される。(Leveling Unit Weight) As a result of the above-mentioned division, the size of each unit of the HPC column member, HPC girder member, and rebar cage is limited, and the weight is reduced. Within the lifting capacity of, and the weight is leveled.
【0017】(免震基礎の構築)免震要素を備えた免震
基礎及び地中梁を構築し、その上に前述の鉄筋コンクリ
ート軸組架構を構築し全体として、簡単に免震構造の鉄
筋コンクリート造構造物を構築する。(Construction of seismic isolation foundation) A seismic isolation foundation and an underground beam having seismic isolation elements are constructed, and the above-mentioned reinforced concrete frame structure is constructed on the seismic isolation structure to make it easy to construct a seismic isolation structure. Build a structure.
【0018】(HPC柱部材の立て込み)具体的な工程
は、先ずHPC柱部材を、揚重機を使って建て込むが、
施工階の床コンクリートの節点位置から、上方に突出し
ている鉄筋篭の上柱の下部分を、HPC柱部材の中空部
に内挿するように降ろし、さらにHPC柱部材の底部突
出主筋を、施工階の床コンクリートの節点位置に埋め込
まれているスリーブジョイントに挿入して、下階のHP
C柱部材の頂部突出主筋とを接合する。(Standing up of HPC pillar member) In the concrete process, first, the HPC pillar member is built using a hoist,
From the nodal position of the floor concrete on the construction floor, lower the lower part of the upper pillar of the reinforcing bar cage protruding upward so as to be inserted into the hollow part of the HPC pillar member, and further construct the bottom protruding main bar of the HPC pillar member. Insert it into the sleeve joint embedded in the node position of the floor concrete on the first floor, and
The top protruding main bar of the C pillar member is joined.
【0019】(仮説支持柱としてのHPC柱部材)この
ようにして建てられたHPC柱部材は、それ自身を仮枠
として、中空部に鉄筋を挿入しコンクリートを打設し、
HPC部分と合体して、鉄筋コンクリート造柱材を造
る。さらにそれ自身に出隅部内側にHPC柱部材主筋配
し、HPC柱部材帯筋と緊結し、主筋の周囲と帯筋の外
面は、法令に定められた以上の厚さのコンクリートで被
覆されて、不完全ながらも鉄筋コンクリート造の柱で、
鉛直荷重に耐える構造強度を有し、さらに柱脚は底部突
出主筋によって下階に固定されているので、大梁、床
版、コンクリートなどの工事荷重を裁荷出来る。(HPC Column Member as Hypothesis Supporting Column) The HPC column member thus constructed is used as a temporary frame by inserting a reinforcing bar into the hollow portion and placing concrete,
Combine with the HPC part to make a reinforced concrete pillar material. Furthermore, the HPC pillar member main reinforcement is arranged on the inside of the projected corner on itself, and it is tightly connected to the HPC pillar member reinforcement, and the periphery of the main reinforcement and the outer surface of the reinforcement are covered with concrete of a thickness greater than that required by law. Although it is incomplete, it is a reinforced concrete pillar,
It has the structural strength to withstand the vertical load, and since the column base is fixed to the lower floor by the bottom protruding main bar, it can handle the construction load such as large beams, floor slabs and concrete.
【0020】(仮設支持梁としてのHPC大梁部材)H
PC大梁部材を揚重機を使って、HPC柱部材の上に掛
け渡す。このようにして掛け渡されたHPC大梁部材
は、それ自身を仮枠として、中空部に鉄筋を挿入し、コ
ンクリートを打設し、HPC部分と合体して、鉄筋コン
クリート造大梁材を造るが、さらにそれ自身の中に、H
PC大梁部材主筋とHPC大梁部材肋筋を緊結し、主筋
の周囲と肋筋の外側は、法令に定められた以上の厚さの
コンクリートで被覆されているので、不完全ながらも鉄
筋コンクリート造の大梁で、単純梁として鉛直荷重に耐
える構造強度を有しているので、この上に床版、コンク
リートなどの工事荷重を裁荷出来る。(HPC large beam member as a temporary support beam) H
Using a hoist, hang the PC girder member over the HPC pillar member. The HPC girder member thus bridged is used as a temporary frame to insert a reinforcing bar into the hollow part, cast concrete, and combine with the HPC part to make a reinforced concrete structure girder material. H in itself
The main beam of PC girder member and the rib of HPC girder member are tightly bound, and the periphery of the main bar and the outer side of the rib are covered with concrete having a thickness greater than that specified by law. Since it has a structural strength as a simple beam that can withstand the vertical load, the work load of floor slab, concrete, etc. can be handled on it.
【0021】(PS材による代替)HPC大梁部材の主
筋を鉄筋コンクリート鋼棒に替えて、PC鋼線またはP
C鋼棒としPSのHPC大梁部材とすることができる。
このPSのHPC大梁部材の上に、HPCの小梁、床版
を設置する。(Replacement with PS material) The main bar of the HPC girder member is replaced with a reinforced concrete steel rod, and a PC steel wire or P steel wire is used.
An HPC girder member of PS can be used as the C steel rod.
The HPC beam and floor slab are installed on the PS HPC beam member.
【0022】(床材の裁置)足場仮枠支保工仮枠を用い
ないと言う課題に沿って前述のHPC大梁部材の上にH
PC床版部材を裁置する。HPC床版部材に替えてフル
PC床版、或いは打ち込みデッキプレート等も用いるこ
ともできる。(Placement of floor material) Scaffolding temporary frame In order to solve the problem of not using a temporary supporting frame, H is placed on the above-mentioned HPC girder member.
Place the PC floor slab member. Instead of the HPC floor slab member, a full PC floor slab or a driven deck plate can also be used.
【0023】(鉄筋篭の構造)鉄筋については、1つの
節点に集まる鉄筋毎に分割して、柱筋は、下柱の上半分
から上柱の下半分の主筋を、それぞれ帯筋で緊結し、柱
大梁の接合部分では、HPC柱部材の底部突出主筋と頂
部突出主筋を接を繋ぐスリーブジョイントを、外側から
囲む帯筋を接合部に組み込んでおく。大梁筋は左梁の右
半分から右梁の左半分、後ろ梁の前半分から前梁の後ろ
半分の主筋を、それぞれ肋筋で緊結し、一つの節点に集
まる鉄筋ごとに、1つのユニットまとめ、工場と作業場
で先組み鉄筋篭として組み立てる。(Structure of Reinforcing Bar Basket) Reinforcing bars are divided into reinforcing bars gathering at one node, and the reinforcing bars are connected to the upper half of the lower pillar to the lower half of the upper pillar with the cords. In the joint portion of the column girder, a sleeve joint that connects the bottom projecting main bar and the top projecting main bar of the HPC column member to each other is incorporated into the joint part. The main girders are the right half of the left girder to the left half of the right girder, and the main bars of the front half of the back girder to the back half of the front girder are tied together with ribs, and one unit is put together for each rebar gathering at one node, Assemble as a pre-assembled rebar cage at the factory and workshop.
【0024】(鉄筋篭の設置)この鉄筋篭を揚重機を使
って吊り降ろし、下柱上部の鉄筋をHPC柱部材の中空
部に内挿するよう、左梁の右半分と右梁の左半分、後ろ
梁の前半分と前梁の後ろ半分の鉄筋をそれぞれHPC軸
組架構の接点の左梁、右梁、後ろ梁、前梁、のU字溝内
部に収まるよう、且つ接合部の帯筋がHPC柱部材の出
隅の内側に埋め込まれた主筋を繋ぐスリーブジョイント
を、外側から囲む様に設置する。(Installation of rebar cage) This rebar cage is hung with a hoist and the rebar above the lower column is inserted into the hollow part of the HPC column member so that the right half of the left beam and the left half of the right beam are inserted. , Reinforcing bars of the front half of the back beam and the back half of the front beam are placed in the U-shaped groove of the left beam, right beam, back beam, and front beam of the HPC frame structure, respectively, and the joint bar Installs a sleeve joint that connects the main bars embedded inside the projected corner of the HPC pillar member from the outside.
【0025】(軸組接合部の帯筋)接合部を囲む帯筋
を、この様な吊り降ろす設置作業が困難な場合は、鉄筋
篭に組み込まないで、鉄筋篭が吊り降ろし設置された
後、いくつかの部分に分割した帯筋を、接合部の所定の
場所に差し込み、相互に緊結して組み立ててもよい。(Braces of framing joints) If it is difficult to suspend and install the braces surrounding the joints, do not install them in the rebar cage and after the rebar cage is suspended and installed, The stirrup, which is divided into several parts, may be inserted into place of the joint and tightly connected to each other to be assembled.
【0026】(隅部の仮枠)この主筋の接合と、帯筋の
この主筋への緊結は、接合部の柱を中心にして隣接する
大梁の間は仮枠が取り付けらる以前に、この部分から作
業する。コンクリート打設後には、そのコンクリートと
一体になり、それ自身鉄筋の被覆となる材料で作られ
た、打ち込み仮枠をHPC柱部材に外面に沿って取り付
ける。(Temporary Frame at Corner) The joining of this main bar and the tight binding of the stirrup to this main bar are performed before the temporary frame is attached between the adjacent girders centering on the column of the joint. Work from the part. After the concrete has been cast, a temporary casting frame, which is made of a material which is integral with the concrete and which itself serves as a coating for the reinforcing bars, is attached to the HPC pillar member along the outer surface.
【0027】(鉄筋篭の接合)鉄筋篭相互の接合は、柱
鉄筋については上部の柱筋篭と下部の柱筋篭の内部に継
ぎ手用鉄筋篭を掛け渡し添え継ぎ手を作る方法と上部の
柱筋篭と下部の柱筋篭のいずれかの断面を絞り込みもう
一方の鉄筋篭の内部に挿入添え継ぎ手を作る方法があ
る。大梁主筋については隣接する鉄筋篭の間を継ぎ手用
鉄筋篭を掛け渡して添え継ぎ手を作る。継ぎ手用鉄筋の
掛け渡し区間は大梁の端部を含まず、長期加重時に必要
な下端鉄筋はHPC大梁部材に内蔵しているので、通常
の場合下端鉄筋は不要であり上端鉄筋だけを掛け渡せば
足りる。(Joining Reinforcing Bar Baskets) Reinforcing bar baskets are connected to each other by using a method of making a connecting rebar cage by connecting a reinforcing bar basket to the inside of an upper pillar bar cage and a lower bar bar cage, and an upper pillar. There is a method of narrowing down the cross section of either the squirrel cage or the lower sill cage and inserting it into the inside of the other reinforced cage to make a splice. For the main beam of Ohashi, a reinforcing bar cage for joints is hung between adjacent rebar cages to make a splice joint. The span of the rebar for the joint does not include the end of the girder, and the bottom rebar required for long-term loading is built into the HPC girder member, so the bottom rebar is usually unnecessary and only the top rebar can be bridged. Is enough.
【0028】(コンクリートの打設)柱、大梁以外の鉄
筋、例えばHPC床版の上端鉄筋等、所定の配筋を完了
した後コンクリートを打設するが、HPC柱、大梁部材
の端部は開放であり内部は連通しているので、この場合
コンクリートを連続に打設し、作業能率の向上とコンク
リートの一体性を確保する事が出来る。この時、普通コ
ンクリートに替えて、再生骨材を使用したコンクリート
を打設することが出来る。(Concrete Casting) Concrete reinforcement is laid after completion of predetermined rebar arrangement such as reinforcing bars other than columns and girders, for example, upper end reinforcing bars of HPC floor slabs, but the ends of HPC columns and girder members are open. Since the interior is in communication with each other, in this case, it is possible to place concrete continuously to improve the work efficiency and ensure the integrity of the concrete. At this time, concrete using recycled aggregate can be placed in place of normal concrete.
【0029】(HPC柱部材主筋の接合)次に上階のH
PC柱部材を、揚重機を使って建て込むが、この時建て
込み位置の節点から、上方に突出している組立鉄筋の柱
筋を、HPC柱部材の中空部に内挿するように降ろし、
さらにHPC柱部材の底部突出主筋を、スリーブジョイ
ントによって、下階のHPC柱部材の頂部突出主筋と接
合する。(Joining the main bars of HPC pillar members) Next, H on the upper floor
The PC pillar member is built using a hoist, but at this time, the pillar bar of the assembled reinforcing bar projecting upward from the node at the built-up position is lowered so as to be inserted into the hollow portion of the HPC pillar member.
Further, the bottom protruding main bar of the HPC pillar member is joined to the top protruding main bar of the HPC pillar member on the lower floor by a sleeve joint.
【0030】[0030]
(概要)実施例について図面を参照し説明すると、図1
は本発明の構築方法を示す説明図、図2は鉄筋コンクリ
ート造構造物の概要を示す立面図、図3は平面図であ
り、図中、1は基礎フーチング、2は地中梁、3は免震
装置、4は軸組の柱、5は軸組の大梁、6は構造物の床
版、55は軸組接合部、14は軸組の柱の中央部、16
は軸組の大梁の中間部、17は軸組の大梁の中央部を示
す。(Outline) Referring to the drawings, an embodiment will be described with reference to FIG.
Is an explanatory view showing a construction method of the present invention, FIG. 2 is an elevation view showing an outline of a reinforced concrete structure, FIG. 3 is a plan view, in the figure, 1 is a foundation footing, 2 is an underground beam, 3 is Seismic Isolation Device, 4 is a column of the frame, 5 is a large beam of the frame, 6 is a floor slab of the structure, 55 is a joint of the frame, 14 is a central part of the column of the frame, 16
Is the middle part of the girder of the frame, and 17 is the central part of the girder of the frame.
【0031】(HPC部材の分割)この鉄筋コンクリー
ト造構造物を構築するため、本発明による構築方法に従
って、打設するコンクリートと、鉄筋篭と、HPC造軸
組を、鉄筋コンクリート造軸組の3要素と考え、そのう
ちHPC造軸組を、図4のHPC軸組の分割と配置を示
す立面図、図5の同平面図に示すごとく分割する。図
中、18はHPC柱部材で、19はHPC大梁部材であ
り、HPC造軸組の節点部分接点11と、隣接する節点
部分11の間が一部材を構成するように分割されてい
る。(Splitting of HPC member) In order to construct this reinforced concrete structure, according to the construction method of the present invention, the concrete to be placed, the reinforced basket, the HPC framing, and the three elements of the reinforced concrete framing are used. Considering that, the HPC frame set is divided as shown in the elevation view showing the division and arrangement of the HPC frame set in FIG. 4 and the plan view in FIG. In the figure, 18 is an HPC pillar member, and 19 is an HPC girder member, and the HPC frame joints are divided so that the joints 11 and the adjacent joints 11 form one member.
【0032】(鉄筋篭の分割)鉄筋篭については、図6
の鉄筋篭の分割と配置を示す立面図、図7の同平面図に
示すごとく各節点について、軸組の接合部55を中心
に、柱鉄筋が上下、大梁鉄筋が左右前後に引き通し交差
し、軸組の柱の中央部14、軸組の大梁の中間部16、
で分割する。(Division of Reinforcing Bar Basket) For the reinforcing bar cage, see FIG.
As shown in the plan view of FIG. 7 showing the division and arrangement of the rebar cages in FIG. 7, for each node, the column rebars are pulled up and down, and the girder rebars are pulled back and forth around the joint 55 of the frame. Then, the central portion 14 of the column of the frame, the intermediate portion 16 of the girder of the frame,
Divide by.
【0033】(HPC柱部材の制作)分割されたHPC
柱部材18を、図8のHPC柱部材の平面図、図9の同
立面図、10図の同横断面図、図11の同縦断面図に示
す様に、工場または現場作業場で制作する。図中、21
は筒状の本体部分であり、22はHPC柱部材の中空部
であり、23はHPC柱部材主筋であり、24は頂部突
出主筋であり、25は底部突出主筋である。HPC柱部
材主筋23はHPC柱部材帯筋26と緊結されており、
共にHPC柱部材のコンクリート部分27に埋め込まれ
ており、28はHPC柱部材帯筋の外側の被り部分、2
9はHPC柱部材主筋の周囲の被り部分であり、共に法
令で定められた以上の厚さを有している。(Production of HPC pillar member) Divided HPC
The pillar member 18 is produced in a factory or on-site workshop as shown in the plan view of the HPC pillar member of FIG. 8, the elevation view of FIG. 9, the transverse sectional view of FIG. 10, and the longitudinal sectional view of FIG. . In the figure, 21
Is a cylindrical main body portion, 22 is a hollow portion of the HPC column member, 23 is an HPC column member main bar, 24 is a top protruding main bar, and 25 is a bottom protruding main bar. The HPC pillar member main bar 23 is tightly connected to the HPC pillar member stirrup 26,
Both are embedded in the concrete part 27 of the HPC pillar member, and 28 is the outer covering part of the HPC pillar member strip.
Reference numeral 9 denotes a covering portion around the main bars of the HPC column member, both of which have a thickness equal to or more than the legally required value.
【0034】(HPC大梁部材の制作)分割されHPC
大梁部材19を、図12のHPC大梁部材の立面図、図
13の同側面図、図14の同立面方向からの断面図、図
15の同側面方向からの断面図に示すように、工場また
は現場作業場で制作する。図中、31は樋状の本体部
分、32はHPC大梁部材中空部であり、33はHPC
大梁部材主筋である。HPC大梁部材主筋33はHPC
大梁部材肋筋36に緊結されており、共にHPC大梁部
材のコンクリート部分37に埋め込まれており、38は
HPC大梁部材肋筋の外側被りの部分、39はHPC大
梁部材主筋の周囲の被り部分であり、共に法令で定めら
れた以上の厚さを有している。(Production of HPC Large Beam Member) Divided HPC
As shown in the elevation view of the HPC girder member of FIG. 12, the same side view of FIG. 13, the cross-sectional view from the same elevation direction of FIG. 14, and the cross-sectional view of the same side direction of FIG. Produce in a factory or on-site workshop. In the figure, 31 is a gutter-shaped main body portion, 32 is a hollow portion of the HPC girder member, and 33 is an HPC.
This is the main bar for the large beam members. HPC girder member main bar 33 is HPC
They are tightly connected to the girder member ribs 36, and both are embedded in the concrete portion 37 of the HPC girder member, 38 is an outer covering portion of the HPC girder member ribs, and 39 is a covering portion around the HPC girder member main bar. Yes, both have a thickness greater than that required by law.
【0035】(鉄筋篭の制作)分割された鉄筋篭を、図
16の鉄筋篭の配筋詳細を示す立面図、図17の同平面
図に示すように、工場または現場作業場で制作する。図
中、42は鉄筋篭の上柱の下部分、43は同下柱の上部
分、44は同右大梁の左部分、45は同左大梁の右部
分、46は同手前の大梁の後ろの部分、47は同後ろの
大梁の手前部分である。また40は鉄筋篭の柱帯筋、5
0は鉄筋篭の大梁肋筋、48は鉄筋篭の柱主筋、49は
鉄筋篭の大梁主筋である。(Production of Reinforcing Bar Basket) The divided rebar baskets are produced in a factory or on-site workshop as shown in the elevation view showing the details of the reinforcing bar cage arrangement in FIG. 16 and the plan view in FIG. In the figure, 42 is the lower part of the upper pillar of the rebar cage, 43 is the upper part of the lower pillar, 44 is the left part of the right girder, 45 is the right part of the left girder, 46 is the part behind the front girder, 47 is the front part of the large beam behind the same. In addition, 40 is a bar girder of the rebar cage, 5
Reference numeral 0 is a rebar cage girder rib, 48 is a rebar cage pillar main bar, and 49 is a rebar cage main beam main bar.
【0036】(HPC柱部材の建て込み)組立作業は、
先ずHPC柱部材18を、揚重機(図示せず)を使って
建て込むが、この時建て込み位置の軸組節点から、上方
に突出している鉄筋篭の上柱の下部分42を、HPC柱
部材18の中空部22に内挿するように降ろし、さらに
HPC柱部材の底部突出主筋25をHPC柱部材主筋の
スリーブジョイント53によって、下階のHPC柱部材
の頂部突出主筋24とを接合する。(Installation of HPC pillar member)
First, the HPC pillar member 18 is built using a lifting machine (not shown). At this time, the lower part 42 of the upper pillar of the reinforcing bar cage projecting upward from the frame assembly node at the built-up position is replaced with the HPC pillar. It is lowered so as to be inserted into the hollow portion 22 of the member 18, and the bottom protruding main bar 25 of the HPC pillar member is joined to the top protruding main bar 24 of the HPC pillar member on the lower floor by the sleeve joint 53 of the HPC pillar member main bar.
【0037】(HPC大梁部材の掛け渡し)HPC大梁
部材19を揚重機を使って、予めHPC柱部材18に取
り付けられたHPC大梁部材仮受け部材(図示せず)の
上に掛け渡し仮固定する。仮受け部材の形構造は工事現
場の実状により設計される。(Hanging of HPC girder member) The HPC girder member 19 is hung and temporarily fixed on the HPC girder member temporary receiving member (not shown) previously attached to the HPC column member 18 by using a hoist. . The shape of the temporary receiving member is designed according to the actual conditions at the construction site.
【0038】(HPC床材の取り付け)HPC大梁部材
19の上にHPC床版54を取り付ける。(Attachment of HPC Floor Material) The HPC floor slab 54 is attached on the HPC girder member 19.
【0039】(鉄筋篭の建て込み)鉄筋篭41を揚重機
を使って吊り降ろし、鉄筋篭の下柱の上部分43を、H
PC柱部材の中空部22に内挿するよう、鉄筋篭の左大
梁の右部分45と右大梁の左部分44、後ろ大梁の手前
部分47と手前大梁の後ろ部分46を、それぞれHPC
軸組の接点の左梁、右梁、後ろ梁、前梁、のHPC大梁
部材中空部32内に収まるよう、且つ接合部の帯筋がH
PC柱部材主筋のスリーブジョイント53を、外側から
囲む様に設置する。(Built-in Reinforcing Bar Basket) Reinforcing bar cage 41 is hung using a lifting machine, and the upper portion 43 of the lower pillar of the rebar cage is set to H
The right part 45 of the left girder of the rebar cage and the left part 44 of the right girder, the front part 47 of the rear girder and the rear part 46 of the front girder are respectively inserted into the hollow part 22 of the PC pillar member by HPC.
The left stirrup, the right stirrup, the rear stirrup, and the front stirrup of the contact points of the frame fit within the hollow portion 32 of the HPC girder member, and the stirrup of the joint is H.
The sleeve joint 53 of the PC column member main reinforcement is installed so as to surround it from the outside.
【0040】(鉄筋篭の接合)柱については、柱鉄筋篭
に内挿する継ぎ手用鉄筋篭51を、上下の鉄筋篭の柱の
中に重ね継ぎ手を作る様に、下柱の鉄筋篭に取り付けて
おき、上階の鉄筋篭を揚重機で吊り下げ、継ぎ手鉄筋篭
の上部が鉄筋篭下柱内部に納められるように取り付け
る。大梁については大梁の上端鉄筋についてのみ隣り合
う大梁の中間部分を継手鉄筋52で掛け渡し隣り合う鉄
筋篭を接続する。(Joining rebar cages) For columns, attach rebar cages 51 for joints that are inserted in the column rebar cages to the rebar cages of the lower columns so that a joint is made in the columns of the upper and lower rebar cages. Set aside the rebar cage on the upper floor with a lifting machine, and attach it so that the upper part of the joint rebar cage is housed inside the rebar cage lower pillar. Regarding the girders, only the upper end reinforcing bars of the girders are bridged with the joint reinforcing bars 52 at the intermediate portions of the adjacent girders to connect the adjacent reinforcing bar cages.
【0041】(コンクリートの打設)柱大梁の接合部の
補強配筋及びその他所定の配筋を完了した後コンクリー
トを打設するが、HPC柱頂部、HPC大梁部材端部は
開放であり内部は連通しているのでコンクリートを連続
して1回で打設して、作業効率の向上とコンクリートの
一体性を確保することが出来る。(Placement of concrete) Concrete is placed after completion of reinforcing reinforcements and other predetermined reinforcements at the joints of column girders, but the HPC column tops and HPC girder member ends are open and the inside is Since they are in communication, it is possible to place concrete continuously at one time to improve work efficiency and ensure concrete integrity.
【0042】(柱断面についての工程)柱断面について
の前述の各工程を、図18の鉄筋篭の柱部分の配筋を示
す横断面図、図19の鉄筋篭がHPC柱部材内部に設置
された時の、柱部分の横断面図、図20のコンクリート
が打設された時の、柱部分の横断面図の順序で示す。(Step for Column Section) The above-described steps for column section are shown in FIG. 18, which is a transverse sectional view showing the bar arrangement of the column portion of the rebar cage, and the rebar cage of FIG. 19 is installed inside the HPC column member. The cross-sectional view of the pillar portion when the concrete is placed, and the cross-sectional view of the pillar portion when the concrete in FIG.
【0043】(大梁断面についての工程)大梁断面につ
いての前述の各工程を、図21の鉄筋篭の大梁部分の配
筋を示す側向方向からの断面図、図22の鉄筋篭がHP
C大梁部材内部に設置された時の、大梁部分の側面方向
からの断面図、図23のコンクリートが打設された時
の、大梁部分の側面方向からの断面図の順序で示す。図
中54はHPC床版でありコンクリート打設により、大
梁と一体化している。(Steps for cross-section of girder) The above-described steps for cross-section of girder are cross-sectional views from the lateral direction showing the reinforcement of the girder portion of the reinforcing bar cage in FIG. 21, and the reinforcing bar cage in FIG. 22 is HP.
The cross-sectional view from the side direction of the girder part when installed inside the C girder member, and the cross-sectional view from the side direction of the girder part when concrete of FIG. In the figure, 54 is an HPC floor slab, which is integrated with the girder by concrete pouring.
【0044】[0044]
【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果を秦する。Since the present invention is configured as described above, it brings about the following effects.
【0045】(仮設不要)HPC柱部材は、それ自身に
鉛直荷重に耐える性能を有し、HPC大梁部材は、それ
自身に単純梁として鉛直荷重に耐える性能を有しおり、
これらで組み立てられたHPC造軸組は、この上に床
版、コンクリートなどの工事荷重を裁荷することが出来
る。またHPC柱部材、HPC大梁部材はそれ自身仮枠
を兼ねているので仮枠及び仮枠支保工は不要となる。(Temporarily unnecessary) The HPC column member itself has the ability to withstand a vertical load, and the HPC girder member itself has the ability to withstand a vertical load as a simple beam.
The HPC framework assembled by these can handle the work load of floor slab, concrete, etc. on this. Further, since the HPC column member and the HPC girder member also serve as a temporary frame, the temporary frame and the temporary frame support work are unnecessary.
【0046】(現場作業の大幅な減少)現場での仮枠支
保工と仮枠の設置作業は、HPC製造工場の作業の中に
吸収され、撤去作業も不要となる。また現場の鉄筋組立
作業は、工場での柱大梁鉄筋の部分組立と、現場作業場
での鉄筋篭の大組立に置き換えられる。作業が工場又は
現場作業場に移されるので、高所での作業環境の悪い現
場作業は大幅に減少し、作業環境を改善し、安全性を確
保し、作業能率を増進することが出来る。(Significant reduction of on-site work) Temporary frame support work and temporary frame installation work on site are absorbed in the work of the HPC manufacturing plant, and removal work is unnecessary. In addition, the on-site rebar assembly work will be replaced by the partial reassembly of pillar girder rebars at the factory and the large rebar cage assembly at the work site. Since the work is transferred to the factory or the site work site, the work site where the work environment at a high place is bad can be greatly reduced, the work environment can be improved, the safety can be secured, and the work efficiency can be improved.
【0047】(効率的な資材の運搬)足場、仮枠支保
工、仮枠を殆ど使用しないので、資材は搬入だけで搬出
は殆どなくなり、無駄な運搬作業を無くすことが出来
る。HPC柱部材、HPC大梁部材、HPC床版部材、
鉄筋篭各ユニットの最大重量は、通常2頓以内で、大型
の揚重機は不必要であり、中小型の揚重機で揚重運搬す
ることが出来る。同時に、前記各ユニットの重量は平準
化されているので揚重機を効率的に運用することが出来
る。次に前記各ユニットは、揚重機で直接所定の位置に
直接吊り込まれるので、横持ち運搬作業が省くことが出
来る。コンクリート打設は各階毎に1回で完了するの
で、効率的な打設作業を行うことが出来る。全体として
無駄な運搬がなくなり、効率的な資材運搬が可能とな
る。(Efficient Transport of Materials) Since the scaffold, the temporary frame support work, and the temporary frame are scarcely used, the materials are hardly brought in and out, and wasteful transportation work can be eliminated. HPC pillar members, HPC girder members, HPC floor slab members,
The maximum weight of each unit of the rebar cage is usually within 2 tons, a large lifting machine is not necessary, and it can be lifted and transported by small and medium-sized lifting machines. At the same time, since the weight of each unit is leveled, the lifting machine can be operated efficiently. Next, since each unit is directly suspended by a lifting machine at a predetermined position, the lateral carrying work can be omitted. Since concrete pouring is completed once for each floor, efficient pouring work can be performed. As a whole, wasteful transportation is eliminated and efficient material transportation becomes possible.
【0048】(工期の短縮)HPC部材の設計制作に若
干の準備期間が必要となるが、現場作業はHPC各部材
と鉄筋篭を搬入し組み立て、配筋とコンクリート打設で
完了し大幅に減少するので、躯体工事の工期の短縮が可
能となる。コンクリートを打設し強度が発現した床面
は、上階の架構構築作業に殆ど使用しないので、この床
面で直ちに、次の工程である仕上工事の作業を開始出来
るので、全体工期の短縮が可能となる。(Reduction of construction period) Although some preparation period is required for designing and producing HPC members, on-site work is completed by carrying in and assembling HPC members and rebar cages, and arranging and placing concrete. As a result, it is possible to shorten the construction period of the frame work. Since the floor surface where concrete is poured and strength is developed is rarely used for the construction work of the frame on the upper floor, the work of finishing work, which is the next process, can be immediately started on this floor surface, which shortens the overall construction period. It will be possible.
【0049】(強靭な各部分)柱は、HPC柱部材と、
その中空部の鉄筋コンクリート材との合成材であり、二
重の帯筋によりコンクリートを緊結している。大梁はH
PC大梁材とその中空部の鉄筋コンクリート材との合成
材であり一部分は二重の肋筋によってコンクリートを緊
結しており共に高い靭性が期待できる。また接合部の鉄
筋は上下柱の主筋、左右、前後の大梁の主筋はそれぞれ
引き通されて工場又は作業場で鉄筋篭に組み立てられる
ので、鉄筋が輻輳することなく、精度良く配置し組み立
ることが出来る。より多くの鉄筋を整然と配置してコン
クリートを密実に打設しより強固で信頼性の高い構造体
を建造することが出来る。HPC柱部材の内蔵主筋を繋
ぐスリーブジョイントの外側を取り巻く帯筋と、鉄筋篭
の柱部分を緊結する帯筋により、接合部のコンクリート
は二重に拘束されているので、この部分の靭性は高い。
又この部分の断面は、柱断面より少しく大きくなってい
るので接合部は大きな強度が期待できる。The (strong parts) columns are composed of HPC column members,
It is a synthetic material with the reinforced concrete material in the hollow part, and the concrete is tightly bound by double stirrups. Large beam is H
It is a composite material of PC girder material and reinforced concrete material in its hollow part, and in part, concrete is bound by double ribs, and high toughness can be expected together. Also, the reinforcing bars of the joints are the main bars of the upper and lower columns, the left and right, and the main bars of the front and rear girders are pulled through and assembled in the rebar cage at the factory or workshop, so that the rebars can be placed and assembled accurately without congestion. I can. It is possible to construct a stronger and more reliable structure by arranging more reinforcing bars in an orderly manner and pouring concrete in a solid manner. Since the concrete at the joint is doubly restrained by the stirrups surrounding the outside of the sleeve joint that connects the internal main bars of the HPC pillar member and the stirrups that tightly connect the pillars of the rebar cage, the toughness of this part is high. .
Further, since the cross section of this portion is slightly larger than the cross section of the column, a large strength can be expected at the joint.
【0050】(鉄筋篭の接合)鉄筋篭相互の接合は、柱
については、ほぼ中央部で接合されるが、この部分は水
平力による曲げモーメントが殆どなく、又既にHPC柱
部材の出隅の内部に内蔵されている主筋が引き通されて
いるので、鉄筋篭の主筋については、全強度を伝える接
合は不必要になり、簡単な接合方法例えば添え鉄筋によ
る接合方法が使用できる。 大梁では、中間部付近で接
合されるが、この部分は水平力による曲げモーメントは
充分減少しており、又長期の曲げモーメントに対しては
既にHPC大梁部材の下部出隅内部に引き通され、さら
に必要に応じて追加された主筋が内蔵されているので下
端主筋は不必要であり、上端主筋については、中央部に
肋筋によって緊結された鉄筋篭繋ぎ筋を掛け渡し配筋す
れば充分である。(Joining of rebar cages) Reinforcing bar cages are joined to each other at almost the center of the column. However, this portion has almost no bending moment due to horizontal force, and the corners of the HPC column member have already been joined. Since the main bar contained inside is pulled through, the main bar of the rebar cage does not need to be joined to transmit the entire strength, and a simple joining method, for example, a joining method using a reinforcing bar can be used. In the girder, it is joined near the middle part, but the bending moment due to horizontal force is sufficiently reduced in this part, and for a long-term bending moment, it has already been drawn into the lower corner of the HPC girder member. Furthermore, since the main reinforcement added as needed is built-in, the lower main reinforcement is unnecessary.For the upper main reinforcement, it is sufficient to arrange the reinforcing bar cage connecting muscles tied to the center by the ribs. is there.
【0051】(技術の一般性)本発明による鉄筋コンク
リート造軸組の構築方法は、一般的技術の組み合わせ工
法であり、特殊な機械材料技能者を必要としない。構造
設計の方法も、おおむね従来の鉄筋コンクリート構造設
計基準に準拠できるので、次のような組み合わせ工法が
可能である。(Generality of Technology) The method for constructing a reinforced concrete frame according to the present invention is a combination method of general technologies and does not require a special machine material technician. Since the structural design method can also be based on the conventional reinforced concrete structural design standard, the following combination method is possible.
【0052】(免震性能を有する構造物)免震要素を備
えた免震基礎を構築しその上に前記の鉄筋コンクリート
造軸組の構築方法による軸組を構築し全体として免震性
能を有する鉄筋コンクリート造構造物を構築することが
出来る。免震構造は地震時に上部架構に伝わる地震力を
減少させて、建物内部の人、物を保護するので非常に優
れた構造体であるが、設計と準備に日時を要するため、
工期が長くなり工事費が増加するという欠点があった。
免震基礎の上に前記鉄筋コンクリート造軸組を構築すれ
ば、工期の長期化と工事費の増大を抑制し、且つ免震性
能を有する構造物の構築が可能となる。(Structure having seismic isolation performance) A seismic isolation foundation having seismic isolation elements is constructed, and a skeleton structure is constructed on the reinforced concrete frame construction method, and reinforced concrete having seismic isolation performance as a whole. Build structures can be built. The seismic isolation structure is an excellent structure because it reduces the seismic force transmitted to the upper frame during an earthquake and protects people and objects inside the building, but it takes time to design and prepare, so
There was a drawback that the construction period was long and the construction cost increased.
By constructing the reinforced concrete framework on the seismic isolation foundation, it becomes possible to construct a structure having seismic isolation performance while suppressing the extension of construction period and increase in construction cost.
【0053】(PSコンクリート構造)本発明は、主筋
に通常の構造用鉄筋を使用する、HPC大梁部材を用い
る構築方法に加えて、主筋にPC鋼線またはPC鋼棒を
使用しプレストレスを加えたHPC大梁部材を用いた構
築方法があるPSを加えたHPC大梁部材は大きな曲げ
モーメントに耐えることが出来変形量も小さくすること
が出来るが、製造工程も複雑で、制作費も高い。 前記
HPC大梁は本発明による軸組の中で、構造用鉄筋を主
筋とするHPC大梁部材と全く同様に取り扱えるので、
比較的梁間の長い構造物や、一つの構造体の中で、比較
的梁間の長い箇所に部分的に混用し比較的梁間の長い構
造物にも使用できる。(PS concrete structure) In the present invention, in addition to a construction method using an HPC girder member in which ordinary structural reinforcing bars are used for main bars, PC steel wire or PC steel bar is used for main bars and prestress is applied. There is a construction method using the HPC girder member. The HPC girder member with PS added can withstand a large bending moment and can reduce the amount of deformation, but the manufacturing process is complicated and the production cost is high. Since the HPC girder can be handled in the frame according to the present invention in exactly the same manner as the HPC girder member having the structural reinforcing bar as the main bar,
It can also be used for a structure having a relatively long beam, or a structure having a relatively long beam, which is partially mixed in a relatively long space between beams in one structure.
【0054】(床版の構造)本発明は、柱にHPC柱部
材、大梁にHPC大梁部材を用いるに加えて、床版にも
HPC床版部材を用い、工場あるいは現場作業場で制作
し、所定の場所に組み立てて、別に工場あるいは現場作
業場で、組み立てられた先組み鉄筋篭を立て込み、必要
な配筋をおこない、コンクリートを打設するという構築
方法であるので、柱から床版に至るまで、足場、型枠支
保工、型枠等の仮設資材を用いる必要がない。従って仮
枠支保工と仮枠の設置および撤去に要する、労力、時
間、資材等の節約と、鉄筋の配筋組立作業を工場または
地上の作業場で行うことにより、架構構築の作業の省力
化と単純化と工期の短縮がより広範囲に可能となる。(Structure of floor slab) In the present invention, in addition to using an HPC pillar member for a pillar and an HPC girder member for a girder, an HPC floor slab member is also used for a floor slab, which is produced at a factory or a site workshop, It is a construction method in which it is assembled in the place of, and the pre-assembled rebar cage is set up at the factory or the site workshop separately, the necessary reinforcement is done, and the concrete is placed, so from the pillar to the floor slab There is no need to use temporary materials such as scaffolding, formwork support, and formwork. Therefore, the labor, time, materials, etc. required for temporary frame support work and the installation and removal of temporary frames can be saved, and the work for constructing the frame can be saved by performing the reinforcing bar reinforcement assembly work in the factory or on the ground. A wider range of simplification and shortening of construction period is possible.
【0055】HPC柱、大梁部材は仮枠として密実で、
保水性能も良く良好なコンクリートの養生環境を作り出
しているので、工事現場で発生した廃材のコンクリート
から製造した再生骨材を使用したコンクリートを省資源
の目的で使用出来る。HPC columns and girder members are solid as a temporary frame,
Since it has good water retention performance and creates a good concrete curing environment, concrete using recycled aggregate produced from waste concrete generated at the construction site can be used for resource saving purposes.
【図1】本発明の構築方法を示す説明図である。FIG. 1 is an explanatory diagram showing a construction method of the present invention.
【図2】鉄筋コンクリート造構造物の概要を示す立面図
である。FIG. 2 is an elevational view showing an outline of a reinforced concrete structure.
【図3】鉄筋コンクリート造構造物の概要を示す平面図
である。FIG. 3 is a plan view showing an outline of a reinforced concrete structure.
【図4】HPC造軸組の分割と配置を示す立面図であ
る。FIG. 4 is an elevational view showing division and placement of an HPC framework.
【図5】HPC造軸組の分割と配置を示す平面図であ
る。FIG. 5 is a plan view showing division and arrangement of an HPC framework.
【図6】鉄筋篭の分割と配置を示す立面図である。FIG. 6 is an elevational view showing division and arrangement of a reinforcing bar basket.
【図7】鉄筋篭の分割と配置を示す平面図である。FIG. 7 is a plan view showing division and arrangement of a rebar cage.
【図8】HPC柱部材の平面図である。FIG. 8 is a plan view of an HPC column member.
【図9】HPC柱部材の立面図である。FIG. 9 is an elevational view of an HPC column member.
【図10】HPC柱部材の横断面図である。FIG. 10 is a cross-sectional view of an HPC column member.
【図11】HPC柱部材の縦断面図である。FIG. 11 is a vertical cross-sectional view of an HPC column member.
【図12】HPC大梁部材の立面図である。FIG. 12 is an elevational view of an HPC girder member.
【図13】HPC大梁部材の側面図である。FIG. 13 is a side view of the HPC girder member.
【図14】HPC大梁部材の立面方向からの断面図であ
る。FIG. 14 is a cross-sectional view of the HPC girder member from the vertical direction.
【図15】HPC大梁材の側面方向からの断面図であ
る。FIG. 15 is a cross-sectional view of the HPC girder material from the side direction.
【図16】鉄筋篭の配筋詳細を示す立面図である。FIG. 16 is an elevational view showing the details of bar arrangement of a reinforcing bar cage.
【図17】鉄筋篭の配筋詳細を示す平面図である。FIG. 17 is a plan view showing details of the reinforcing bar cage arrangement.
【図18】鉄筋篭の柱部分の配筋を示す横断面図であ
る。FIG. 18 is a transverse cross-sectional view showing the reinforcement of the pillar portion of the reinforcing bar cage.
【図19】鉄筋篭がHPC柱部材内部に設置された時
の、柱部分の横断面図である。FIG. 19 is a transverse cross-sectional view of a pillar portion when the rebar cage is installed inside the HPC pillar member.
【図20】コンクリートが打設された時の、柱部分の横
断面図である。FIG. 20 is a cross-sectional view of a pillar portion when concrete is poured.
【図21】鉄筋篭の大梁部分の配筋を示す側面方向から
の、断面図である。FIG. 21 is a cross-sectional view from the side direction showing the reinforcement of the large beam portion of the reinforcing bar cage.
【図22】鉄筋篭がHPC大梁部材内部に設置された時
の、大梁部分の側面方向からの断面図である。FIG. 22 is a cross-sectional view of the girder portion viewed from the side when the reinforcing bar cage is installed inside the HPC girder member.
【図23】コンクリートが打設された時の、大梁部分の
側面方向からの横断面図である。FIG. 23 is a lateral cross-sectional view from the side direction of the girder portion when concrete is poured.
1 基礎フーチング 2 地中梁 3 免震装置 4 軸組の柱 5 軸組の大梁 6 構造物の床版 11 HPC造軸組の節点部分 12 軸組の柱の上端 13 軸組の柱の下端 14 軸組の柱の中央部 15 軸組の大梁の端部 16 軸組の大梁の中間部 17 軸組の大梁の中央部 18 HPC柱部材 19 HPC大梁部材 21 筒状の本体部分 22 HPC柱部材の中空部 23 HPC柱部材主筋 24 頂部突出主筋 25 底部突出主筋 26 HPC柱部材帯筋 27 HPC柱部材のコンクリート部分 28 HPC柱部材帯筋の外側の被り部分 29 HPC柱部材主筋の周囲の被り部分 31 樋状の本体部分 32 HPC大梁部材中空部 33 HPC大梁部材主筋 36 HPC大梁部材肋筋 37 HPC大梁部材のコンクリート部分 38 HPC大梁部材の肋筋の外側の被り部分 39 HPC大梁部主筋の周囲の被り部分 40 鉄筋篭の柱帯筋 41 鉄筋篭 42 鉄筋篭の上柱の下部分 43 鉄筋篭の下柱の上部分 44 鉄筋篭の右大梁の左部分 45 鉄筋篭の左大梁の右部分 46 鉄筋篭の手前大梁の後ろ部分 47 鉄筋篭の後ろ大梁の手前部分 48 鉄筋篭の柱主筋 49 鉄筋篭の大梁主筋 50 鉄筋篭の大梁の肋筋 51 鉄筋篭の柱主筋の継ぎ手鉄筋 52 鉄筋篭の大梁主筋の継ぎ手鉄筋 53 HPC柱部材主筋のスリーブジョイント 54 HPC床版 55 軸組接合部 1 Foundation footing 2 Underground beam 3 Seismic isolation device 4 Column of frame 5 Beam of frame 5 Floor deck of structure 11 Node part of HPC frame 12 Upper end of column of frame 13 Lower end of column of frame 14 The center of the pillar of the framework 15 The end of the girder of the framework 16 The middle part of the girder of the framework 17 The center of the girder of the framework 18 HPC pillar members 19 HPC girder members 21 Cylindrical main body 22 HPC pillar members Hollow part 23 HPC pillar member main bar 24 Top protruding main bar 25 Bottom protruding main bar 26 HPC column member band bar 27 Concrete part of HPC column member 28 Overburden part of HPC column member bar bar 29 Overburden part around HPC column member bar bar 31 Trough-shaped main body part 32 HPC girder member hollow part 33 HPC girder member main bar 36 HPC girder member ribs 37 Concrete part of HPC girder member 38 Cover of outside ribs of HPC girder member Part 39 HPC Large beam part Covered part around the main bar 40 Reinforcing bar girder girder 41 41 Reinforcing bar cage Lower part of upper column of reinforcing bar cage 43 Upper part of lower column of reinforcing bar cage 44 Left part of right girder of reinforcing bar cage 45 Reinforcing bar Left part of girder left part of girder 46 Rear part of girder in front of rebar basket 47 Rear part of girder behind girder 48 Part of girder main bar of rebar basket 49 Main girder bar of girder bar 50 Bar girder rib of girder basket 51 Reinforcing bar girder pillar Main reinforcement joint reinforcement 52 Reinforcement cage girder main reinforcement joint reinforcement 53 HPC column member Main reinforcement sleeve joint 54 HPC floor slab 55 Frame joint
Claims (8)
部材(18)とハーフプレキャスト(HPCという)大
梁部材(19)を制作し、これらをHPC造軸組の節点
部分(11)で接続してHPC造軸組に組立て、これと
は別に、柱の主筋は、節点を中心に上下に柱材の中央部
まで引き通し帯筋と緊結し、大梁の主筋は、節点を中心
に前後左右に大梁材の中間部分まで引き通し肋筋と緊結
し、地上で一体の鉄筋篭(41)に先組みし、この先組
みされた鉄筋篭を、先に組み立てたHPC造軸組のHP
C柱部材中空部(22)、HPC大梁部材中空部(3
2)に設置し、隣接した鉄筋篭相互を鉄筋篭の柱主筋の
継ぎ手鉄筋(51)と鉄筋篭の大梁主筋の継ぎ手鉄筋
(52)で接続した後、HPC造軸組のHPC柱部材中
空部(22)、HPC大梁部材中空部(32)内にコン
クリートを打設する、鉄筋コンクリート造軸組の構築方
法。1. A half-precast pillar member (18) and a half-precast (referred to as HPC) girder member (19) are produced in a factory or a work place, and these are connected at a node portion (11) of an HPC frame structure to produce an HPC structure. Assembled to the frame, apart from this, the main bar of the column is pulled up and down around the node up and down to the center of the column material and tied up with the tie bar, and the main bar of the girder is the girder material of the girder material around the node. The HPC of the HPC framework assembled by pulling it up to the middle part and tightly connecting it to the ribs, and pre-assembling it to the integrated rebar cage (41) on the ground.
C pillar member hollow part (22), HPC girder member hollow part (3
Installed in 2) and connecting adjacent rebar cages with each other by connecting the rebar cage pillar main bar joint rebar (51) and the rebar cage main beam main bar joint rebar (52), then the HPC column member hollow part of the HPC framework (22), A method for constructing a reinforced concrete framework, in which concrete is placed in the hollow portion (32) of the HPC girder member.
装置(3)からなる基礎及び地中梁を、所定の位置に所
定の構造で構築し、この上に請求項1の方法により鉄筋
コンクリート造軸組を構築する、免震性能を有する鉄筋
コンクリート造構造物の構築方法。2. A foundation footing (1) an underground girder (2) and a foundation consisting of a seismic isolation device (3) and an underground girder are constructed at a predetermined position with a predetermined structure, and the method according to claim 1 is further formed thereon. A method of constructing a reinforced concrete structure having seismic isolation performance by constructing a reinforced concrete frame by.
造軸組を構築する過程で、コンクリートの打設に先だっ
て、前記HPC軸組のHPC大梁部材(19)の上に、
HPC床版部材(54)または既成の床版部材や捨て型
枠を掛け渡し、床版に必要な鉄筋を配筋した後、HPC
床版部材(54)の上面とHPC造軸組のHPC柱部材
中空部(22)、HPC大梁部材中空部(32)にコン
クリートを打設する、鉄筋コンクリート造構造物の構築
方法。3. In the process of constructing a reinforced concrete frame by the method of claim 1, prior to placing concrete, on the HPC girder member (19) of the HPC frame,
HPC floor slab member (54) or existing floor slab member and abandoned formwork are laid over, and after reinforcing bars necessary for the floor slab are arranged, HPC
A method for constructing a reinforced concrete structure, comprising placing concrete on the upper surface of the floor slab member (54), the HPC column member hollow part (22) and the HPC girder member hollow part (32) of the HPC framework.
材を使用したコンクリートを打設することを含む、請求
項1、2、3に記載の方法。4. The method according to claim 1, 2, or 3, wherein the concrete pouring includes pouring concrete using recycled aggregate.
部が開放で、内部に中空部(22)を有し、出隅部分内
側に配置したHPC柱部材主筋(23)と、HPC柱部
材帯筋(26)を互いに緊結して、HPC柱部材主筋
(23)の周囲の被り部分(29)と、HPC柱部材帯
筋(26)の外側の被り部分(28)は法令に定められ
た以上の厚さのコンクリートで被覆して本体部分(2
1)に内蔵し、前記主筋は両端部で頂部突出主筋(2
4)、底部突出主筋(25)に連続しており、全体とし
て筒状の本体部分(21)を有する、HPC柱部材(1
8)。5. The HPC pillar member main bar (23), which has an open top and a bottom, has a hollow portion (22) inside, and is arranged inside a projecting corner portion, as used in claim 1, 2, and 3. The column member stirrup (26) is tightly connected to each other, and the covering portion (29) around the HPC pillar member main bar (23) and the outer covering portion (28) of the HPC pillar member stirrup (26) are stipulated by law. The body part (2
Built in 1), the main bars at both ends are top projecting main bars (2
4), an HPC pillar member (1) which is continuous with the bottom protruding main bar (25) and has a tubular main body part (21) as a whole.
8).
頂部が開放で、内部に中空部(32)を有し、梁長の全
区間の下側の出隅部分内側にHPC大梁部材主筋(3
3)を引き通し、長期加重による曲げモーメントに対し
必要な場合は、主筋を梁長の中間部の下側に追加配置
し、前記主筋とU字型で上方開放のHPC大梁肋筋(3
6)を緊結し、HPC大梁肋筋の外側被り部分(38)
とHPC大梁主筋の周囲被り部分(39)は法令に定め
られた以上厚さのコンクリートで被覆して本体部分(3
1)に内蔵し、全体として樋状の本体(31)を有す
る、HPC大梁部材(19)。6. The HPC girder for use in claim 1, 2, 3 having both ends and a top open, a hollow part (32) inside, and an inner corner of the lower part of the entire beam length section. Member main bar (3
3), and if necessary for bending moment due to long-term load, a main bar is additionally arranged below the middle part of the beam length, and the main bar and U-shaped HPC girder rib (3
6) Tighten, and the outer covering part of the HPC girder ribs (38)
The HPC girder main bar surroundings (39) is covered with concrete having a thickness greater than that specified by law, and the main body (3)
An HPC girder member (19) built in 1) and having a gutter-shaped main body (31) as a whole.
る鉄筋コンクリート用鋼棒に替えて、PC鋼線又はPC
鋼棒を使用する、両端部及び頂部が開放で、内部に中空
部を有し、梁長の全区間の下側の出隅部分内側にPC鋼
線またはPC鋼棒を引き通し、前記PC鋼線またはPC
鋼棒とU字型で上方開放のHPC大梁部材肋筋を緊結
し、HPC大梁肋筋の外側被り部分とPC鋼線またはP
C鋼棒の周囲被り部分は法令に定められた以上の厚さの
コンクリートで被覆して、本体部分に内蔵し、全体とし
て樋状の本体を有する、プレストレスド(PSという)
のHPC大梁部材。7. A PC steel wire or PC in place of the steel rod for reinforced concrete used for the main bar of the HPC girder member of claim 6.
Using a steel rod, both ends and the top are open, there is a hollow inside, and a PC steel wire or a PC steel rod is drawn through inside the projected corner portion on the lower side of the entire section of the beam length. Line or PC
The steel rod and U-shaped HPC girder member, which is open upwards, are tightly connected to each other, and the outer covering portion of the HPC girder rib and PC steel wire or P
Pre-stressed (called PS), which has a gutter-shaped body as a whole, with the surrounding covering part of the C steel rod covered with concrete having a thickness greater than that required by law and built into the body part.
HPC girder member.
C柱部材の底部突出主筋(25)と、施工階のHPC柱
部材の頂部突出主筋(24)を接合するための、外側が
円柱状で内側にテーパーのある円筒状の柱状スリーブ内
に異形鉄筋の端部を挿入し高強度グラウト材を充填して
鉄筋を接合する鉄筋継手(スリーブジョイントという)
(53)を所定の位置に配置し、鉄筋篭(41)を挿入
後スリーブジョイント(53)を取り巻いて帯筋を配筋
し、両者を緊結し、スリーブジョイント周辺に必要な補
強配筋を行い、これらの鉄筋に法令で定められた以上厚
さのコンクリート被覆した構造を有するようにコンクリ
ートを打設する、軸組の柱(4)と軸組の大梁(5)と
の輔組接合部(55)。8. The HP on the upper floor used in claim 1, 2, or 3.
Deformed bar in a cylindrical columnar sleeve with a cylindrical outer side and a tapered inner side for joining the bottom protruding main bar (25) of the C column member and the top protruding main bar (24) of the HPC column member on the construction floor Reinforcing bar joint (referred to as sleeve joint) that inserts the end of the and inserts high-strength grout material to join rebar
Place (53) at a predetermined position, insert the rebar cage (41), surround the sleeve joint (53) and arrange the stirrup, tightly connect both, and perform necessary reinforcement reinforcement around the sleeve joint. , Placing concrete so that these reinforcing bars have a concrete-covered structure with a thickness greater than that specified by law, and a joint between a pillar (4) of a frame and a girder (5) of a frame ( 55).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22956895A JPH0949264A (en) | 1995-08-04 | 1995-08-04 | Constructing method for reinforced concrete framework and structure, and member therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22956895A JPH0949264A (en) | 1995-08-04 | 1995-08-04 | Constructing method for reinforced concrete framework and structure, and member therefor |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0949264A true JPH0949264A (en) | 1997-02-18 |
Family
ID=16894220
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22956895A Pending JPH0949264A (en) | 1995-08-04 | 1995-08-04 | Constructing method for reinforced concrete framework and structure, and member therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0949264A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003013495A (en) * | 2001-07-02 | 2003-01-15 | Nishimatsu Constr Co Ltd | Design-build order system of concrete skeleton |
KR101458435B1 (en) * | 2013-03-08 | 2014-11-05 | 삼성물산 주식회사 | Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same |
KR101458434B1 (en) * | 2013-03-08 | 2014-11-05 | 삼성물산 주식회사 | Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same |
-
1995
- 1995-08-04 JP JP22956895A patent/JPH0949264A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003013495A (en) * | 2001-07-02 | 2003-01-15 | Nishimatsu Constr Co Ltd | Design-build order system of concrete skeleton |
KR101458435B1 (en) * | 2013-03-08 | 2014-11-05 | 삼성물산 주식회사 | Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same |
KR101458434B1 (en) * | 2013-03-08 | 2014-11-05 | 삼성물산 주식회사 | Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101903628B1 (en) | Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof | |
JP3333788B2 (en) | Prefabricated bridge pier | |
JP2002089043A (en) | Reinforced concrete structure and construction method for steel framed reinforced concrete, structure | |
JP2586224B2 (en) | Building method using precast concrete formwork | |
JPH09268648A (en) | Steel frame reinforced concrete structure column plus girder and its construction method plus framework | |
JPH0949264A (en) | Constructing method for reinforced concrete framework and structure, and member therefor | |
JPH11247288A (en) | Column-beam main bar pre-assembled hollow precast concrete column unit and column constructing method using this column unit | |
JPH03132532A (en) | Construction method of precast reinforced concrete column and beam | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
CN113403936A (en) | Bracket-free rapid construction method for hollow pier partition plate of bridge | |
JPH09111721A (en) | Execution method and structure of bridge pier | |
JP3116767B2 (en) | Existing building seismic isolation structuring method | |
JPH07324376A (en) | Method for constructing reinforced concrete structure | |
JPH01214641A (en) | Construction of steel-pipe precast concrete pole | |
JP3338240B2 (en) | Construction method for reinforced concrete structures | |
JPH0893137A (en) | Precast post serving as form and construction method therefor | |
JP3187618B2 (en) | How to assemble beam reinforcement | |
CN110821040B (en) | Steel ladle beam supporting structure | |
JP2763488B2 (en) | Prefabricated pillar and inverted ramen prefabricated construction method | |
JP3830062B2 (en) | Seismic reinforcement method for reinforced concrete buildings | |
JP2643641B2 (en) | Building method using PC members | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
JPH0988348A (en) | Foundation beam construction method | |
JPH09256549A (en) | Frame unit for building frame of concrete building structure and method of construction using frame unit thereof |