JPS5850218A - Connecting structure system for head of cast-in-place concrete pile and footing - Google Patents
Connecting structure system for head of cast-in-place concrete pile and footingInfo
- Publication number
- JPS5850218A JPS5850218A JP14871481A JP14871481A JPS5850218A JP S5850218 A JPS5850218 A JP S5850218A JP 14871481 A JP14871481 A JP 14871481A JP 14871481 A JP14871481 A JP 14871481A JP S5850218 A JPS5850218 A JP S5850218A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- pile
- footing
- cast
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は場所打ちコンクリート杭の頭部と基礎フーチン
グとの連結構造方式に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a structure for connecting the head of a cast-in-place concrete pile to a foundation footing.
場所打ちコンクリート杭は騒音、振動が比較的少なく、
1本当りの支持力が大きく、荷重に合わせて径を選べる
ことなど利点が多く広く用いられているが、杭頭の処理
に種々の間粗点があった。Cast-in-place concrete piles have relatively little noise and vibration;
Although it is widely used and has many advantages such as a large bearing capacity per pile and the ability to choose the diameter according to the load, there have been various problems with the processing of the pile cap.
そこで従来方式について説明するi、予めオーガ機によ
って基礎杭孔を掘削し、この孔内に鉄筋かとを挿入し、
トレミー管でコンクリ、−トを打設する。、そして掘削
用のケーシングを除去し、埋土して、根切シした後、上
端部の余盛不良コンクリ−、トをはつシ(研)り除き、
敷砂利、捨てコンクリートめ敷設の後、フーチングの配
筋をして型枠を組み、トの型枠内にフーチングコンフリ
ートラ打設するものである。Therefore, I will explain the conventional method. First, a foundation pile hole is excavated using an auger machine, and reinforcing bars are inserted into this hole.
Concrete is poured using tremie pipes. Then, after removing the excavation casing, filling the soil, and cutting the roots, the defective excess concrete at the top end was removed by grinding.
After laying gravel and sacrificial concrete, the footings are reinforced, the formwork is constructed, and the footings are poured into the formwork.
ところでこの従来方式の欠点には、次のようなものがあ
る。By the way, the drawbacks of this conventional method include the following.
■ 杭頭部で余盛不良コンクIJ −ト(500〜10
00 m )のはつり工事のだめの工期が8俊であり、
更にこの工事に伴う馳音、振動が公害問題となシ近隣か
ら苦情が寄せられることがある。■ Defective concrete IJ-to (500~10
00 m), the construction period for the chisel work is 8 shun,
Furthermore, the noise and vibrations associated with this construction work are a pollution problem, and complaints may be received from nearby residents.
■ 場所打ちコンクリート杭施工中の孔壁崩壊やコンク
リートの弁上シ等のトラブルが生じた場合の対策が峻し
く、従来はその対処法として増打杭とならざるを得ない
。■ Countermeasures against problems such as hole wall collapse or concrete overhang during construction of cast-in-place concrete piles are difficult to deal with, and conventionally, the only way to deal with these problems has been to increase the number of piles.
■ 支持地盤の傾斜、不陸によりibかどの長さに過不
足が生じ易い。■ The length of the ib corner is likely to be too long or too short due to the slope or unevenness of the supporting ground.
■ 杭頭部の鉄筋が変形する・
■ 杭径は支持地盤条件によシ決定されるために基礎フ
ーチングの形状も大きくなる。■ The reinforcing bars at the pile head are deformed. ■ Since the pile diameter is determined by the supporting ground conditions, the shape of the foundation footing also becomes larger.
■ 杭天端が検尺ミスによシ所定よシネ足(深い)した
場合の対策が難しい。■ It is difficult to take countermeasures when the top of the pile is deeper than the specified depth due to a measurement error.
■ 杭と基礎フーチングの接合をヒンジと固定に使い分
けることが難しい。 ゛
そこで本発明・は上記従来技術の欠点を除去するもので
、図面に基ついて本発明の詳細な説明する。■ It is difficult to use the joint between the pile and foundation footing as a hinge or as a fixation. Therefore, the present invention is intended to eliminate the drawbacks of the above-mentioned prior art, and will be described in detail with reference to the drawings.
第1図において、基礎杭を構築する所定の位置Gにアー
スドリルを使用して杭孔1を掘削する。In FIG. 1, a pile hole 1 is drilled using an earth drill at a predetermined position G where a foundation pile is to be constructed.
そこで孔1内に鉄筋かと2を挿置し、トレミー管によっ
て、コンクリート3をフーチング底に対応するレベルL
まで打設し、そこで掘削用ケーシング4を引き上は取シ
外す。Therefore, reinforcing bars 2 are inserted into hole 1, and concrete 3 is raised to level L corresponding to the bottom of the footing using a tremie pipe.
Then, the excavation casing 4 is pulled up and removed.
次に第2図に示すように連結用既製杭5を孔1中央部に
垂直に挿入しセットする。この既製杭5は鋼管コンクリ
ートパイル又は鋼管パイルを使用し、その外周には必要
によシジベ・ル5aを突設しである。既製杭5の上端に
は吊支ロープ6を設ける支持バー7に係止することによ
って、コンクリート3が硬°イヒするまでこの既製杭を
コンクリートの所定位置に保持する。そして埋土、根切
り作業を柱て、第3図示のように泥土を除去し、天竺8
゜9を水平に小はクシする。Next, as shown in FIG. 2, a ready-made connecting stake 5 is vertically inserted into the center of the hole 1 and set. This ready-made pile 5 is made of a steel pipe concrete pile or a steel pipe pile, and a sill bevel 5a is protruded from the outer periphery thereof as necessary. A suspension rope 6 is provided at the upper end of the ready-made pile 5 and is engaged with a support bar 7, thereby holding the ready-made pile in a predetermined position on the concrete until the concrete 3 hardens. Then, by filling in the soil and cutting the roots, the mud was removed as shown in Figure 3, and the Tenjiku 8
゜9゜Comb horizontally.
その後フーチングの配筋をした後型枠を組む。After that, the footing is reinforced and the formwork is assembled.
そして型枠内にフーチングコンクリート10を打設し、
このコンクリート−131硬化すると、第4図示の状態
となる。その後は第5図示のように土11KGlを埋め
戻しすべての工程は完了する。Then, footing concrete 10 is poured into the formwork,
When this concrete 131 hardens, it will be in the state shown in Figure 4. After that, as shown in Figure 5, all the steps are completed by backfilling with 11KGl of soil.
そして本発明によって完成した基礎フーチングPにおい
て土部荷重は連結用既製杭5で全てを負担させておシ、
第5図に示す余盛不良ランクリートCは設計で荷重負担
させないが、安全サイドとして又防錆、受働土圧、座屈
防止において有効である。In the foundation footing P completed according to the present invention, the soil load is entirely borne by the ready-made connecting piles 5.
Although the rank concrete C with poor reinforcement shown in FIG. 5 is not designed to bear any load, it is effective on the safety side and in preventing rust, passive earth pressure, and buckling.
次に本発明の施工中のトラブルに対する処理について説
明する。−
第6図はコンクリート内に挿置した鉄筋かと2が深く入
シ過ぎ短くなった場合であるが、連結用既製杭5をその
分長くしたものである。1!は柱である。Next, processing for troubles during construction according to the present invention will be explained. - Figure 6 shows a case where the reinforcing bars 2 inserted into the concrete are too deep and become short, but the ready-made connecting piles 5 are lengthened accordingly. 1! is a pillar.
第7図は孔l壁にトラブルが生じた場合であるが、空隙
12.13が生じても連結用既製杭5を以て孔壁の崩壊
を防止し、応力を十分に支持できるようにすることがで
きる。Fig. 7 shows a case where trouble occurs in the hole l wall, but even if a gap 12.13 occurs, it is possible to prevent the hole wall from collapsing using the connecting prefabricated piles 5 and to be able to sufficiently support the stress. can.
第8図は敷地−境界線N近くに柱11を設ける時、柱と
既製杭5との軸心が一致しない場合が発生するが、この
時は既製杭の挿入位置を孔1の中心よシ柱の軸心に一致
するよう偏心させるもので、このため柱11と杭5の偏
心距離を短かくすることにより円滑に応力伝達が可能と
なる。Figure 8 shows that when a pillar 11 is installed near the site boundary line N, the axes of the pillar and the ready-made pile 5 may not match, but in this case, the inserting position of the ready-made pile is shifted from the center of the hole 1. The eccentricity is made to coincide with the axis of the column, and by shortening the eccentric distance between the column 11 and the pile 5, stress can be transmitted smoothly.
本発明は上記構成であるため、先ずはつり工事が激減し
騒音、振動による公害を防止でき、工事も短縮でき、孔
壁崩壊等のトラブルが発生した場合でも連結用既製杭を
長く作るなどしてその対応が容易であり、鉄筋かどの長
さの過不足の心配がなく、さらに従来に比して基礎フー
チングが小さくなりかつ捨てコンクリ、−ト、敷砂利が
不要となり、場所打ちコンクリート杭のコンクリート、
鉄筋の使用量も減シ、余盛不良コン表リート部分は安全
サイドに効果があシ、連結用既製杭は工場で量産が可能
である。又、杭頭部の荷重、応力の変化に応じて、連結
用既製杭の部材を自由に選択することも、杭頭をヒンジ
に近づけることも従来より容易である。Since the present invention has the above-mentioned configuration, first of all, the lifting work can be drastically reduced, pollution caused by noise and vibration can be prevented, the construction work can be shortened, and even if troubles such as hole wall collapse occur, it is possible to make long ready-made piles for connection. It is easy to handle, there is no need to worry about the length of reinforcing bars being too long or too short, and the foundation footing is smaller than before, and there is no need for waste concrete, concrete, or gravel, and concrete for cast-in-place concrete piles can be easily handled. ,
It also reduces the amount of reinforcing bars used, improves safety in concrete areas with poor reinforcement, and allows for mass production of ready-made piles for connections in factories. Furthermore, it is easier than before to freely select the members of the ready-made pile for connection and to move the pile head closer to the hinge according to changes in the load and stress on the pile head.
第1図乃至第5図はそれぞれ本発明の工法を段階的に示
す断面図、第6図乃至第8図は施工罠トラブルが生じた
場合の例を示す断面図である。
l・・・孔、2・・・鉄筋かご、3・・・コンクリート
、5・・・連結用既製杭、6・・・吊支ロープ、7・・
・支持バー、10・・・フーチングコンクリート、L・
・・フーチング底に和尚するレベル。
以上
第3図 第4図FIGS. 1 to 5 are cross-sectional views showing the construction method of the present invention step by step, and FIGS. 6 to 8 are cross-sectional views showing examples of cases where construction trap troubles occur. l...hole, 2...reinforced cage, 3...concrete, 5...ready-made pile for connection, 6...hanging rope, 7...
・Support bar, 10...Footing concrete, L・
...At the level of worshiping at the bottom of the footing. Above Figure 3 Figure 4
Claims (1)
に相当するレベルまで打設し、連結用既製杭を上記杭孔
内に垂直に挿入して、コンクリートが硬化するまでこの
既製杭を支持し、コンクリートが硬化した後上記杭孔の
上端開口部周辺の泥土を除去し、フーチングの配筋をし
て型枠を組み、 この型枠内にフーチングコンクリートを打設する工程を
含むことを特徴とする場所打ちコンクリート杭の頭部と
基礎フーチングとの連結構造方式。[Scope of Claims] Concrete is poured into the pile hole using a reinforcing bar cage device to a level corresponding to the bottom of the footing, and ready-made piles for connection are inserted vertically into the pile hole, and this is continued until the concrete hardens. The process of supporting the prefabricated piles, removing the mud around the upper opening of the pile hole after the concrete has hardened, arranging footing reinforcement, constructing a formwork, and pouring footing concrete into this formwork. A connection structure method between the head of a cast-in-place concrete pile and a foundation footing, characterized by comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14871481A JPS6054461B2 (en) | 1981-09-22 | 1981-09-22 | Connection structure method between the head of cast-in-place concrete pile and foundation footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14871481A JPS6054461B2 (en) | 1981-09-22 | 1981-09-22 | Connection structure method between the head of cast-in-place concrete pile and foundation footing |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5850218A true JPS5850218A (en) | 1983-03-24 |
JPS6054461B2 JPS6054461B2 (en) | 1985-11-30 |
Family
ID=15458949
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14871481A Expired JPS6054461B2 (en) | 1981-09-22 | 1981-09-22 | Connection structure method between the head of cast-in-place concrete pile and foundation footing |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6054461B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7308988B2 (en) | 2002-12-02 | 2007-12-18 | Kao Corporation | Cap |
CN112962586A (en) * | 2021-02-03 | 2021-06-15 | 上海兴庚基础工程有限公司 | Cast-in-situ bored pile construction process suitable for rock stratum area |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0460045U (en) * | 1990-09-27 | 1992-05-22 |
-
1981
- 1981-09-22 JP JP14871481A patent/JPS6054461B2/en not_active Expired
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7308988B2 (en) | 2002-12-02 | 2007-12-18 | Kao Corporation | Cap |
US8348075B2 (en) | 2002-12-02 | 2013-01-08 | Kao Corporation | Cap |
CN112962586A (en) * | 2021-02-03 | 2021-06-15 | 上海兴庚基础工程有限公司 | Cast-in-situ bored pile construction process suitable for rock stratum area |
Also Published As
Publication number | Publication date |
---|---|
JPS6054461B2 (en) | 1985-11-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100849226B1 (en) | C.i.p temporary wall and method for constructing thereof | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
JPS5850218A (en) | Connecting structure system for head of cast-in-place concrete pile and footing | |
KR20000058238A (en) | Underground construction method using permanent reinforced concrete girders as temporary struts | |
JP7275844B2 (en) | WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE | |
AU2019101512B4 (en) | A method of constructing a column, a subterranean structure, and a structure made from the method. | |
JPS6354093B2 (en) | ||
KR101077242B1 (en) | Construction method of basement structure using retaining wall and steel column | |
JP4159148B2 (en) | Construction method of shaft | |
CN220377275U (en) | Pile side reserved steel bar stab-preventing protection device for steel pipe column construction | |
JP3179243B2 (en) | Concrete placement method for deep foundation work | |
JP4479099B2 (en) | Building foundation construction method | |
JPH0610339A (en) | Landslide protection wall made of reinforced concrete and construction thereof | |
KR102644085B1 (en) | Steel outer casing molding jig coated with lining for drilling clearance | |
JP4178273B2 (en) | Construction method of structural pillars using ready-made piles | |
JPS6128774B2 (en) | ||
JP2001011874A (en) | Construction method for structural stud using precast pile | |
JPH073781A (en) | Method for constructing foundation footing on cast-in-place concrete pile head | |
JP2022137952A (en) | Construction method of eccentric substructural column | |
KR20030051477A (en) | The method of constructing diaphragm wall making use of support wall | |
JPS6062328A (en) | Treatment of head of cast-in-place pile | |
JPS6294688A (en) | Method of constructing large-depth shaft | |
JP2544614B2 (en) | Vertical shaft construction method | |
GB2434172A (en) | A retaining wall for an excavation | |
JPH0672419B2 (en) | Foundation / Underground Beam Construction Method |