JPS6054461B2 - Connection structure method between the head of cast-in-place concrete pile and foundation footing - Google Patents

Connection structure method between the head of cast-in-place concrete pile and foundation footing

Info

Publication number
JPS6054461B2
JPS6054461B2 JP14871481A JP14871481A JPS6054461B2 JP S6054461 B2 JPS6054461 B2 JP S6054461B2 JP 14871481 A JP14871481 A JP 14871481A JP 14871481 A JP14871481 A JP 14871481A JP S6054461 B2 JPS6054461 B2 JP S6054461B2
Authority
JP
Japan
Prior art keywords
concrete
pile
footing
head
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14871481A
Other languages
Japanese (ja)
Other versions
JPS5850218A (en
Inventor
明正 宮内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP14871481A priority Critical patent/JPS6054461B2/en
Publication of JPS5850218A publication Critical patent/JPS5850218A/en
Publication of JPS6054461B2 publication Critical patent/JPS6054461B2/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 本発明は場所打ちコンクリート杭の頭部と基礎フーチン
グとの連結構造方式に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a structure for connecting the head of a cast-in-place concrete pile to a foundation footing.

場所打ちコンクリート杭は騒音、振動が比較的少なく、
1本当りの支持力が大きく、荷重に合わせて径を選べる
ことなど利点が多く広く用いられているが、枕頭の処理
に種々の問題点があつた。
Cast-in-place concrete piles have relatively little noise and vibration;
Although it is widely used because of its many advantages, such as the large supporting capacity per rod and the ability to choose the diameter according to the load, it has had various problems in the treatment of the head of the bed.

そこで従来方式について説明すると、予めオーガ機によ
つて基礎杭孔を掘削し、この孔内に鉄筋かごを挿入し、
トリミー管でコンクリートを打設する。そして掘削用の
ケーシングを除去し、埋±して、根切りした後、上端部
の全盛不良コンクリートをはつり(研)り除き、敷砂利
、捨てコンクリートの敷設の後、フーチングの配筋をし
て型枠を組み、この型枠内にフーチングコンクリートを
打設するものである。ところでこの従来方式の欠点には
、次のようなものである。
Therefore, to explain the conventional method, a foundation pile hole is excavated in advance with an auger machine, a reinforcing bar cage is inserted into this hole,
Concrete is poured using a trimmer pipe. Then, after removing the excavation casing, burying the ground, and cutting the roots, scraping off (grinding) the poor concrete at the top end, laying gravel and waste concrete, and then reinforcing the footing. A formwork is constructed and footing concrete is placed within this formwork. By the way, the drawbacks of this conventional method are as follows.

1 枕頭部で全盛不良コンクリート (500〜100
0wf!ft)のはつり工事のための工期が必要であり
、更にこの工事に伴う騒音、振動が公害問題となり近隣
から苦情が寄せられることがある。
1 Poor concrete at the head of the pillow (500-100
0wf! ft) is required, and the noise and vibrations associated with this construction may become a pollution problem and may result in complaints from neighbors.

2 場所打ちコンクリート杭施工中の孔壁崩壊やコンク
リートの共上り等のトラブルが生じた場合の対策が難し
く、従来はその対処法として増打杭とならざるを得ない
2. Countermeasures against problems such as hole wall collapse and concrete upheaval during construction of cast-in-place concrete piles are difficult to deal with, and conventionally, the only way to deal with these problems has been to use additional driven piles.

3 支持地盤の傾斜、不陸により鉄筋かごの長さに過不
足が生じ易い。
3. Due to the slope or unevenness of the supporting ground, the length of the reinforcing bar cage is likely to be too long or too short.

4 枕頭部の鉄筋が変形する。4 The reinforcing bars at the head of the pillow are deformed.

5 杭径は支持地盤条件により決定されるために基礎フ
ーチングの形状も大きくなる。
5. Since the pile diameter is determined by the supporting ground conditions, the shape of the foundation footing will also be large.

6 杭天端が検尺ミスにより所定より不足(深い)した
場合の対策が難しい。
6. It is difficult to take countermeasures when the top of the pile is shorter (deeper) than specified due to a measurement error.

7 杭と基礎フーチングの接合をヒンジと固定に使い分
けることが難しい。
7. It is difficult to use the joint between the pile and foundation footing as a hinge or as a fixation.

そこで本発明は上記従来技術の欠点を除去するもので、
図面に基づいて本発明の実施例を説明する。
Therefore, the present invention eliminates the drawbacks of the above-mentioned prior art.
Embodiments of the present invention will be described based on the drawings.

第1図において、基礎杭を構築する所定の位置Gにアー
スドリルを使用して杭孔1を掘削する。
In FIG. 1, a pile hole 1 is drilled using an earth drill at a predetermined position G where a foundation pile is to be constructed.

そこで孔1内に鉄筋かご2を挿置し、トレミー管によつ
て、コンクリート3をフーチング底に対応するレベルL
まで打設し、そこで掘削用ケーシング4を引き上け取り
外す。次に第2図に示すように連結用既製抗5を孔1中
央部に垂直に挿入しセットする。
Therefore, reinforcing bar cage 2 is inserted into hole 1, and concrete 3 is placed at level L corresponding to the bottom of the footing using a tremie pipe.
The excavation casing 4 is then lifted up and removed. Next, as shown in FIG. 2, a ready-made connecting resistor 5 is vertically inserted into the center of the hole 1 and set.

この既製杭5は鋼管コンクリートパイル又は鋼管パイル
を使用し、その外周には必要によりジベル5aを突設し
てある。既製杭5の上端には吊支ローブ6を設けてあり
、このローブを、地面に水平に架設してある支持バー7
に係止することによつて、コンクリート3が硬化するま
でこの既製杭をコンクリートの所定位置に保持する。そ
して埋土、根切り作業を経て、第3図示のように泥土を
除去し、天端8,9を水平に小はつりする。その後フー
チングの配筋をした後型枠を組む。
This ready-made pile 5 is made of a steel pipe concrete pile or a steel pipe pile, and has a dowel 5a protruding from its outer periphery if necessary. A suspension lobe 6 is provided at the upper end of the ready-made pile 5, and this lobe is attached to a support bar 7 installed horizontally on the ground.
By locking this prefabricated pile is held in place in the concrete until the concrete 3 hardens. After filling the soil and cutting the roots, the mud is removed as shown in the third figure, and the tops 8 and 9 are horizontally suspended. After that, the footing is reinforced and the formwork is assembled.

そして型枠内にフーチングコンクリート10を打設し、
このコンクリートが硬化すると、第4図示の状態となる
。その後は第5図示のように土壌G1を埋め戻しすべて
の工程は完了する。そして本発明によつて完成した基礎
フーチングPにおいて上部荷重は連結用既製杭5で全て
を負担させており、第5図に示す余盛不良コンクリート
Cは設計で荷重負担させないが、安全サイドとして又防
錆、受働土圧、座屈防止において有効である。
Then, footing concrete 10 is poured into the formwork,
When this concrete hardens, it will be in the state shown in the fourth diagram. After that, all the steps of backfilling with soil G1 are completed as shown in Figure 5. In the foundation footing P completed according to the present invention, the upper load is entirely borne by the prefabricated connecting piles 5, and although the poor reinforcement concrete C shown in Fig. 5 is not borne by the design, it is also Effective in preventing rust, passive earth pressure, and buckling.

次に本発明の施工中のトラブルに対する処理に5ついて
説明する。
Next, the fifth method of handling troubles during construction according to the present invention will be explained.

第6図はコンクリート内に挿置した鉄筋かご2が深く入
り過ぎ短くなつた場合であるが、連結用既製抗5をその
分長くしたものである。
FIG. 6 shows a case where the reinforcing bar cage 2 inserted into the concrete is too deep and has become short, but the ready-made connecting column 5 is lengthened accordingly.

11は柱である。11 is a pillar.

第7図は孔1壁にトラブルが生じた場合であるが、空隙
12,13が生じても連結用既製杭5を以て孔壁の崩壊
を防止し、応力が十分に支持できるようにすることがで
きる。
Fig. 7 shows a case where trouble occurs in the wall of the hole 1, but even if voids 12 and 13 occur, it is possible to prevent the hole wall from collapsing using the connecting prefabricated piles 5 and to ensure that the stress can be sufficiently supported. can.

第8図は敷地境界線N近くに柱11を設ける時、柱と既
製杭5との軸心が一致しない場合が発生するが、この時
は既製杭の挿入位置を孔1の中心より柱の軸心に一致す
るよう偏心させるもので、このため柱11と杭5の偏心
距離が短くすることにより円滑に応用伝達が可能となる
Figure 8 shows that when a pillar 11 is installed near the site boundary line N, the axes of the pillar and the ready-made pile 5 may not match. The shaft is eccentrically aligned with the axis, and by shortening the eccentric distance between the pillar 11 and the pile 5, smooth applied transmission becomes possible.

本発明は上記構成てあるため、先ずはつり工事が激減し
騒音、振動により公害を防止でき、工事も短縮でき、孔
壁崩壊等のトラブルが発生した場合でも連結用既製抗を
長く作るなどしてその対応が容易であり、鉄筋かごの長
さの過不足の心配がなく、さらに従来に比して基礎フー
チングが小さくなりかつ捨てコンクリート、敷砂利が不
要となり、場所打ちコンクリート杭のコンクリート、鉄
筋の使用量も減り、余盛不良コンクリート部分は安全サ
イドに効果があり、連結用既製杭は工場で量産が可能で
ある。
Since the present invention has the above-mentioned structure, first of all, the lifting work can be drastically reduced, pollution caused by noise and vibration can be prevented, the construction work can be shortened, and even if troubles such as hole wall collapse occur, it is possible to make long pre-made shafts for connection. This is easy to deal with, and there is no need to worry about the length of the rebar cage being too long or too short.Furthermore, the foundation footing is smaller than before, and there is no need for waste concrete or gravel. The amount of concrete used is reduced, the concrete parts with poor backfilling are safer, and ready-made piles for connection can be mass-produced in factories.

又、杭頭部の荷重、応力の変化に応じて、連結用既製杭
の部材を自由に選択することも、杭頭をヒンヂに近づけ
ることも従来より容易である。
Furthermore, it is easier than ever to freely select the members of the ready-made pile for connection and to move the pile head closer to the hinge according to changes in the load and stress on the pile head.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第5図はそれぞれ本発明の工法を段階的に示
す断面図、第6図乃至第8図は施工にトラブルが生じた
場合の例を示す断面図である。 1・・・・・・孔、2・・・・・・鉄筋かご、3・・・
・・コンクリート、5・・・・・・連結用既製杭、6・
・・・・・吊支ローブ、7・・・・支持バー、10・・
・・・・フーチングコンクリート、L・・・・・・フー
チング底に相当するレベル。
FIGS. 1 to 5 are cross-sectional views showing the construction method of the present invention step by step, and FIGS. 6 to 8 are cross-sectional views showing examples when troubles occur during construction. 1... Hole, 2... Rebar cage, 3...
... Concrete, 5 ... Ready-made piles for connection, 6.
...Suspension rope, 7...Support bar, 10...
...Footing concrete, L...Level equivalent to the bottom of the footing.

Claims (1)

【特許請求の範囲】[Claims] 1 杭孔に鉄筋かごを挿置してコンクリートをフーチン
グ底に相当するレベルまで打設し、連結用既製杭を上記
杭孔内に垂直に挿入して、コンクリートが硬化するまで
この既製杭を支持し、コンクリートを硬化して後上記杭
孔の上端開口部周辺の泥土を除去し、フーチングの配筋
をして型枠を組み、この型枠内にフーチングコンクリー
トを打設する工程を含むことを特徴とする場所打ちコン
クリート杭の頭部と基礎フーチングとの連結構造方式。
1. Insert a reinforcing bar cage into the pile hole and drive concrete to a level equivalent to the bottom of the footing, insert a ready-made pile for connection vertically into the above-mentioned pile hole, and support this ready-made pile until the concrete hardens. After curing the concrete, removing the mud around the opening at the top of the pile hole, arranging footing reinforcement, constructing a formwork, and pouring footing concrete into this formwork. A unique structure that connects the head of a cast-in-place concrete pile to the foundation footing.
JP14871481A 1981-09-22 1981-09-22 Connection structure method between the head of cast-in-place concrete pile and foundation footing Expired JPS6054461B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14871481A JPS6054461B2 (en) 1981-09-22 1981-09-22 Connection structure method between the head of cast-in-place concrete pile and foundation footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14871481A JPS6054461B2 (en) 1981-09-22 1981-09-22 Connection structure method between the head of cast-in-place concrete pile and foundation footing

Publications (2)

Publication Number Publication Date
JPS5850218A JPS5850218A (en) 1983-03-24
JPS6054461B2 true JPS6054461B2 (en) 1985-11-30

Family

ID=15458949

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14871481A Expired JPS6054461B2 (en) 1981-09-22 1981-09-22 Connection structure method between the head of cast-in-place concrete pile and foundation footing

Country Status (1)

Country Link
JP (1) JPS6054461B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0460045U (en) * 1990-09-27 1992-05-22

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7308988B2 (en) 2002-12-02 2007-12-18 Kao Corporation Cap
CN112962586A (en) * 2021-02-03 2021-06-15 上海兴庚基础工程有限公司 Cast-in-situ bored pile construction process suitable for rock stratum area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0460045U (en) * 1990-09-27 1992-05-22

Also Published As

Publication number Publication date
JPS5850218A (en) 1983-03-24

Similar Documents

Publication Publication Date Title
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
JP6702128B2 (en) Foundation structure, pile head structure of steel pipe pile, and construction method of foundation structure
JP3756385B2 (en) Composite pile and its construction method
JPS6054461B2 (en) Connection structure method between the head of cast-in-place concrete pile and foundation footing
CN114808944A (en) Grouting squeezing expansion steel pipe concrete upright pile and construction method thereof
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JP4159148B2 (en) Construction method of shaft
JP3179243B2 (en) Concrete placement method for deep foundation work
JP4479099B2 (en) Building foundation construction method
JP2996113B2 (en) How to build a shaft
JP2000192472A (en) Method for immersing immersing body, and its immersing body
JPH0610339A (en) Landslide protection wall made of reinforced concrete and construction thereof
JPS6128774B2 (en)
JPH0351365Y2 (en)
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JPH0337603B2 (en)
JPS6142044B2 (en)
JPS6363690B2 (en)
JP2567990B2 (en) Reverse construction method for underground construction
JPH073781A (en) Method for constructing foundation footing on cast-in-place concrete pile head
JP2001011874A (en) Construction method for structural stud using precast pile
JPH0473491B2 (en)
JPS5842336B2 (en) Construction method of underwater foundation using reverse piles
JPS6062328A (en) Treatment of head of cast-in-place pile