CN114808944A - Grouting and expanding concrete-filled steel tubular column pile and its construction method - Google Patents

Grouting and expanding concrete-filled steel tubular column pile and its construction method Download PDF

Info

Publication number
CN114808944A
CN114808944A CN202210432181.XA CN202210432181A CN114808944A CN 114808944 A CN114808944 A CN 114808944A CN 202210432181 A CN202210432181 A CN 202210432181A CN 114808944 A CN114808944 A CN 114808944A
Authority
CN
China
Prior art keywords
grouting
concrete
pile
filled steel
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210432181.XA
Other languages
Chinese (zh)
Inventor
胡玉银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tongrenli Geotechnical Engineering Technology Co ltd
Original Assignee
Shanghai Tongrenli Geotechnical Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tongrenli Geotechnical Engineering Technology Co ltd filed Critical Shanghai Tongrenli Geotechnical Engineering Technology Co ltd
Priority to CN202210432181.XA priority Critical patent/CN114808944A/en
Publication of CN114808944A publication Critical patent/CN114808944A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明提供一种注浆挤扩钢管混凝土立柱桩及其施工方法,所述注浆挤扩钢管混凝土立柱桩包括钢管混凝土桩段和钢管混凝土立柱段;所述钢管混凝土桩段采用钻孔植入和注浆挤扩工艺施工,所述钢管混凝土桩段的外周壁之外形成桩侧区;钢管植入钻孔时外附泥浆置换注浆管,用于向所述桩侧区注浆。所述钢管混凝土桩段包括注浆挤扩装置,所述注浆挤扩装置位于所述钢管混凝土桩段的底部。如此配置,通过水泥浆置换桩侧泥浆和注浆挤扩,使得钢管混凝土桩段的侧阻力得到提高;同时,利用钢管代替了钢筋笼,减少了施工工序,节省了材料,降低了工程造价;此外,混凝土灌注与桩侧注浆能够同时进行,提高了施工效率。

Figure 202210432181

The invention provides a grouting extruded and expanded concrete-filled steel tubular column pile and a construction method thereof. The grouted extruded and expanded concrete-filled steel tubular column pile comprises a concrete-filled steel tubular pile section and a concrete-filled steel tubular column section; the concrete-filled steel tubular pile section is implanted by drilling and grouting extrusion and expansion process construction, the outer peripheral wall of the CFST pile section forms a pile side area; when the steel pipe is implanted in the borehole, a mud replacement grouting pipe is attached for grouting the pile side area. The CFST pile section includes a grouting and expansion device, and the grouting and expansion device is located at the bottom of the CFST pile section. With this configuration, the side resistance of the CFST pile section is improved by replacing the mud on the side of the pile with cement slurry and grouting expansion; at the same time, the steel cage is used instead of the steel cage, which reduces the construction process, saves materials, and reduces the project cost; In addition, concrete grouting and pile side grouting can be carried out at the same time, which improves the construction efficiency.

Figure 202210432181

Description

注浆挤扩钢管混凝土立柱桩及其施工方法Grouting and expanding concrete-filled steel tubular column pile and its construction method

技术领域technical field

本发明涉及土木工程施工技术领域,尤其是一种注浆挤扩钢管混凝土立柱桩及其施工方法。The invention relates to the technical field of civil engineering construction, in particular to a grouting squeeze-expanded concrete-filled steel tubular column pile and a construction method thereof.

背景技术Background technique

目前基坑工程立柱桩主要有两种形式:钻孔灌注桩+格构柱、钻孔灌注桩+钢管桩。这两种立柱桩采用坑底以下为钻孔灌注桩,坑底以上为格构柱或钢管桩。格构柱或钢管桩植入钻孔灌注桩中,因此钻孔灌注桩直径要求比较大,一般不小于800mm。为节约桩基成本,往往采用扩径技术将坑底以下5m范围的桩径扩大至800mm,施工工序复杂、材料消耗量大,工程造价高。At present, there are two main types of column piles in foundation pit engineering: bored cast-in-place piles + lattice columns, bored cast-in-place piles + steel pipe piles. These two types of column piles use bored piles below the pit bottom, and lattice columns or steel pipe piles above the pit bottom. Lattice columns or steel pipe piles are implanted in bored piles, so the diameter of bored piles is required to be relatively large, generally not less than 800mm. In order to save the cost of the pile foundation, the diameter expansion technology is often used to expand the diameter of the pile within 5m below the pit bottom to 800mm. The construction process is complicated, the material consumption is large, and the project cost is high.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种注浆挤扩钢管混凝土立柱桩及其施工方法,以解决现有基坑工程立柱桩施工工序复杂、材料消耗量大、工程造价高的问题。The purpose of the present invention is to provide a grouting extruding and expanding concrete-filled steel tubular column pile and a construction method thereof, so as to solve the problems of complicated construction procedures, large material consumption and high engineering cost of the existing foundation pit engineering column pile.

为了达到上述目的,本发明提供了一种注浆挤扩钢管混凝土立柱桩,其包括:立柱桩本体和泥浆置换注浆管;In order to achieve the above object, the present invention provides a grouting extrusion-expanded concrete-filled steel tubular column pile, which comprises: a column pile body and a mud replacement grouting pipe;

所述立柱桩本体包括钢管混凝土桩段,所述钢管混凝土桩段用于容置于钻孔中,所述钢管混凝土桩段的外周壁之外形成桩侧区;The column pile body comprises a concrete-filled steel tubular pile section, the concrete-filled steel tubular pile section is used for being accommodated in a borehole, and a pile side area is formed outside the outer peripheral wall of the concrete-filled steel tubular pile section;

所述泥浆置换注浆管附设于所述钢管混凝土桩段的外周壁之外,并用于向所述桩侧区注浆。The mud replacement grouting pipe is attached outside the outer peripheral wall of the concrete-filled steel pipe pile section, and is used for grouting to the pile side area.

可选的,所述钢管混凝土桩段包括注浆挤扩装置,所述注浆挤扩装置位于所述钢管混凝土桩段的底部。Optionally, the concrete-filled steel tube pile section includes a grouting and expansion device, and the grouting and expansion device is located at the bottom of the concrete-filled steel tube pile section.

可选的,所述注浆挤扩装置包括束浆袋,所述束浆袋贴附于所述钢管混凝土桩段的外周壁的外侧。Optionally, the grouting and expansion device includes a grouting bag, and the grouting bag is attached to the outer side of the outer peripheral wall of the concrete-filled steel pipe pile section.

可选的,所述注浆挤扩装置还包括注浆管,所述注浆管附设于所述钢管混凝土桩段的外周壁之外并与所述束浆袋连接,用于向所述束浆袋注浆以形成水泥浆挤扩段。Optionally, the grouting and expansion device further includes a grouting pipe, the grouting pipe is attached outside the outer peripheral wall of the concrete-filled steel pipe pile section and is connected with the grouting bag, and is used for injecting the grouting into the bundle. The slurry bag is grouted to form the cement slurry extrusion section.

可选的,所述立柱桩本体还包括钢管混凝土立柱段,所述钢管混凝土立柱段用于与基坑的多个支撑装置连接。Optionally, the column pile body further includes a CFST column section, and the CFST column section is used to connect with a plurality of supporting devices of the foundation pit.

可选的,所述钢管混凝土立柱段与所述钢管混凝土桩段一体设置。Optionally, the CFST column section and the CFST pile section are integrally provided.

为解决上述技术问题,本发明还提供了一种注浆挤扩钢管混凝土立柱桩施工方法,应用于如上所述的注浆挤扩钢管混凝土立柱桩;所述注浆挤扩钢管混凝土立柱桩施工方法包括:In order to solve the above technical problems, the present invention also provides a construction method for grouting and expanding concrete-filled steel tubular column piles, which is applied to the above-mentioned grouting and expanding concrete-filled steel tubular column piles; Methods include:

在地面钻进以形成钻孔,对所述钻孔进行清孔;Drilling in the ground to form a borehole, clearing the borehole;

将注浆挤扩装置安装在所述钢管混凝土桩段的钢管的底部;installing the grouting extrusion and expansion device on the bottom of the steel pipe of the concrete-filled steel pipe pile section;

将所述钢管混凝土桩段的钢管、所述注浆挤扩装置以及泥浆置换注浆管植入所述钻孔中;implanting the steel pipe of the CFST pile section, the grouting extrusion device and the mud replacement grouting pipe into the borehole;

在所述钢管混凝土桩段的钢管的内部安装混凝土灌注导管,并进行二次清孔;Install a concrete pouring conduit inside the steel pipe of the concrete-filled steel pipe pile section, and carry out secondary hole cleaning;

通过所述混凝土灌注导管向所述钢管混凝土桩段的钢管的内部灌注混凝土,同时,通过所述泥浆置换注浆管向桩侧区注浆;Concrete is poured into the inside of the steel pipe of the concrete-filled steel tube pile section through the concrete pouring conduit, and at the same time, the pile side area is poured through the mud replacement pouring tube;

待所述桩侧区的水泥浆养护完成后,通过注浆管向束浆袋注浆以在所述钢管混凝土桩段的底部形成水泥浆挤扩段。After the curing of the cement slurry in the pile side area is completed, grouting is carried out into the bundled slurry bag through a grouting pipe to form a squeezed and expanded section of the cement slurry at the bottom of the CFST pile section.

可选的,所述注浆挤扩钢管混凝土立柱桩施工方法还包括:Optionally, the construction method of the concrete-filled steel tubular column pile by grouting extrusion and expansion further includes:

将所述基坑的多个支撑装置架设于钢管混凝土立柱段。A plurality of supporting devices of the foundation pit are erected on the concrete-filled steel tubular column section.

可选的,所述桩侧区的水泥浆的养护时间为不小于48h。Optionally, the curing time of the cement slurry in the pile side area is not less than 48h.

可选的,利用注浆泵通过所述注浆管向所述束浆袋注浆。Optionally, a grouting pump is used for grouting into the grouting bag through the grouting pipe.

综上所述,在本发明提供的注浆挤扩钢管混凝土立柱桩及其施工方法中,所述注浆挤扩钢管混凝土立柱桩包括立柱桩本体和泥浆置换注浆管;所述立柱桩本体包括钢管混凝土桩段,所述钢管混凝土桩段用于容置于钻孔中,所述钢管混凝土桩段的外周壁之外形成桩侧区;所述泥浆置换管附设于所述钢管混凝土桩段的外周壁之外,并用于向所述桩侧区注浆。所述钢管混凝土桩段包括注浆挤扩装置,所述注浆挤扩装置位于所述钢管混凝土桩段的底部。To sum up, in the grouting extrusion-expanded concrete-filled steel tubular column pile and its construction method provided by the present invention, the grouting extrusion-expanded concrete-filled steel tubular column pile comprises a column pile body and a mud replacement grouting pipe; the column pile body It includes a concrete-filled steel tube pile section, the concrete-filled steel tube pile section is used to be accommodated in a borehole, and a pile side area is formed outside the outer peripheral wall of the concrete-filled steel tube pile section; the mud replacement pipe is attached to the concrete-filled steel tube pile section outside the outer peripheral wall of the pile and is used for grouting the pile side area. The CFST pile section includes a grouting and expansion device, and the grouting and expansion device is located at the bottom of the CFST pile section.

如此配置,通过泥浆置换注浆管向桩侧区注浆,增加了钢管混凝土桩段的侧阻力;同时,通过注浆挤扩装置进行注浆挤扩,使得钢管混凝土桩段的侧阻力进一步提高;另一方面,利用钢管代替了钢筋笼,减少了制作钢筋笼这一工序,节省了材料,降低了工程造价;此外,混凝土灌注与桩侧注浆能够同时进行,提高了施工效率。In this configuration, the grouting pipe is used to replace the grouting pipe to the side area of the pile, which increases the side resistance of the CFST pile section; at the same time, the grouting and expansion device is used for grouting and expansion, so that the side resistance of the CFST pile section is further improved. On the other hand, the use of steel pipes instead of steel cages reduces the process of making steel cages, saves materials, and reduces engineering costs; in addition, concrete pouring and pile side grouting can be carried out at the same time, which improves construction efficiency.

附图说明Description of drawings

图1是传统立柱桩的示意图;Fig. 1 is the schematic diagram of traditional column pile;

图2是本发明实施例的钢管混凝土桩段注浆前的示意图;Fig. 2 is the schematic diagram of the concrete-filled steel tubular pile section before grouting according to the embodiment of the present invention;

图3是本发明实施例的钢管混凝土桩段注浆后的示意图;3 is a schematic diagram of the concrete-filled steel tubular pile section after grouting according to the embodiment of the present invention;

图4是本发明实施例的立柱桩本体注浆后的示意图;4 is a schematic diagram of the column pile body after grouting according to the embodiment of the present invention;

图5是本发明实施例的施工方法中的步骤S1的示意图;Fig. 5 is the schematic diagram of step S1 in the construction method of the embodiment of the present invention;

图6是本发明实施例的施工方法中的步骤S2的示意图;Fig. 6 is the schematic diagram of step S2 in the construction method of the embodiment of the present invention;

图7是本发明实施例的施工方法中的步骤S3的示意图;Fig. 7 is the schematic diagram of step S3 in the construction method of the embodiment of the present invention;

图8是本发明实施例的施工方法中的步骤S4的示意图;Fig. 8 is the schematic diagram of step S4 in the construction method of the embodiment of the present invention;

图9是本发明实施例的施工方法中的步骤S5的示意图;Fig. 9 is the schematic diagram of step S5 in the construction method of the embodiment of the present invention;

图10是本发明实施例的施工方法中的步骤S6的示意图。FIG. 10 is a schematic diagram of step S6 in the construction method of the embodiment of the present invention.

其中,附图标记为:Among them, the reference numerals are:

1-立柱桩本体;2-泥浆置换注浆管;3-钻孔;4-桩侧区;5-支撑装置;6-钢管立柱;7-钻孔灌注桩;10-钢管混凝土桩段;20-钢管混凝土立柱段;100-注浆挤扩装置;1001-束浆袋;1002-注浆管;1003-水泥浆挤扩段。1- Column pile body; 2- Mud replacement grouting pipe; 3- Drilling hole; 4- Pile side area; 5- Support device; 6- Steel pipe column; - CFST column section; 100 - grouting expansion device; 1001 - grouting bag; 1002 - grouting pipe; 1003 - cement slurry extrusion and expansion section.

具体实施方式Detailed ways

为使本发明的目的、优点和特征更加清楚,以下结合附图和具体实施例对本发明作进一步详细说明。需说明的是,附图均采用非常简化的形式且未按比例绘制,仅用以方便、明晰地辅助说明本发明实施例的目的。此外,附图所展示的结构往往是实际结构的一部分。特别的,各附图需要展示的侧重点不同,有时会采用不同的比例。In order to make the objects, advantages and features of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that the accompanying drawings are all in a very simplified form and are not drawn to scale, and are only used to facilitate and clearly assist the purpose of explaining the embodiments of the present invention. Furthermore, the structures shown in the drawings are often part of the actual structure. In particular, the emphasis needs to be shown in different drawings, and sometimes different scales are used.

如在本说明书中所使用的,单数形式“一”、“一个”以及“该”包括复数对象,术语“或”通常是以包括“和/或”的含义而进行使用的,术语“若干”通常是以包括“至少一个”的含义而进行使用的,术语“至少两个”通常是以包括“两个或两个以上”的含义而进行使用的,此外,术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”、“第三”的特征可以明示或者隐含地包括一个或者至少两个该特征,“一端”与“另一端”以及“近端”与“远端”通常是指相对应的两部分,其不仅包括端点,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。此外,如在本说明书中所使用的,一元件设置于另一元件,通常仅表示两元件之间存在连接、耦合、配合或传动关系,且两元件之间可以是直接的或通过中间元件间接的连接、耦合、配合或传动,而不能理解为指示或暗示两元件之间的空间位置关系,即一元件可以在另一元件的内部、外部、上方、下方或一侧等任意方位,除非内容另外明确指出外。术语“上”、“下”、“顶”、“底”通常是按重力方向进行排布的相对位置关系;术语“竖向、竖直方向”通常是指沿重力方向,其一般垂直于地面,“水平向、水平面方向”通常是沿平行于地面的方向;对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本说明书中的具体含义。As used in this specification, the singular forms "a," "an," and "the" include plural referents, the term "or" is generally employed in its sense including "and/or", and the term "a number" It is usually used in the sense including "at least one", the term "at least two" is usually used in the sense including "two or more", in addition, the terms "first", "the second" "Second" and "Third" are for descriptive purposes only, and cannot be understood as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first", "second", "third" may expressly or implicitly include one or at least two of those features, "one end" and "the other end" and "proximal end" and "Distal" usually refers to two corresponding parts, which not only include end points, and the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection, or It can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication between two elements or the interaction relationship between the two elements. Furthermore, as used in this specification, the disposition of one element on another element generally only means that there is a connection, coupling, cooperation or transmission relationship between the two elements, and the two elements may be directly or indirectly through intermediate elements. connection, coupling, cooperation or transmission, and should not be construed as indicating or implying the spatial positional relationship between two elements, that is, one element can be in any position inside, outside, above, below or on one side of the other element, unless the content Also clearly stated. The terms "upper", "lower", "top" and "bottom" usually refer to the relative positional relationship arranged in the direction of gravity; the terms "vertical and vertical" usually refer to the direction of gravity, which is generally perpendicular to the ground , "horizontal direction, horizontal plane direction" is usually along the direction parallel to the ground; for those of ordinary skill in the art, the specific meanings of the above terms in this specification can be understood according to specific situations.

本发明的目的在于提供一种注浆挤扩钢管混凝土立柱桩及其施工方法,以解决现有基坑工程立柱桩施工工序复杂、材料消耗量大、工程造价高的问题。The purpose of the present invention is to provide a grouting extruding and expanding concrete-filled steel tubular column pile and a construction method thereof, so as to solve the problems of complicated construction procedures, large material consumption and high engineering cost of the existing foundation pit engineering column pile.

以下参考附图进行描述。The following description is made with reference to the accompanying drawings.

发明人发现,如图1所示,在现有的传统立柱桩中,采用的是上柱下桩两段式,基坑底以上为格构柱或钢管立柱6,基坑底以下为钻孔灌注桩7,在施工过程中,需要将钢管立柱6内置于钻孔灌注桩7中,增加了搭接材料的消耗量,同时,钢筋笼和格构柱的加工工作量大,现场施工环节增多,造成工程造价的提高。The inventor found that, as shown in FIG. 1, in the existing traditional column pile, the upper column and the lower pile are two-stage type, above the bottom of the foundation pit are lattice columns or steel pipe columns 6, and below the bottom of the foundation pit are drilled holes. For the cast-in-place pile 7, during the construction process, the steel pipe column 6 needs to be built into the bored cast-in-place pile 7, which increases the consumption of lap joint materials. At the same time, the processing workload of the reinforcement cage and the lattice column is large, and the number of on-site construction links is increased. , resulting in an increase in project cost.

基于上述研究,请参考图2至图4,本实施例提供一种注浆挤扩钢管混凝土立柱桩,其包括:立柱桩本体1和泥浆置换注浆管2;所述立柱桩本体1包括钢管混凝土桩段10,所述钢管混凝土桩段10用于容置于钻孔3中,所述钢管混凝土桩段10的外周壁之外形成桩侧区4;所述泥浆置换注浆管2附设于所述钢管混凝土桩段10的外周壁之外,并用于向所述桩侧区4注浆。需要说明的,钢管混凝土桩段10采用钻孔植入和注浆挤扩工艺施工,在图2至图4示出的示范例中,桩侧区4是指钢管混凝土桩段10的钢管的外周壁与钻孔3的孔壁之间形成的间隙,在另一些示范例中,钢管混凝土段10的施工工艺也可以是其他行之有效的方式,桩侧区4的位置范围也可以包括桩侧土体,本发明对此不限。本领域技术人员可以理解的,钻孔3开设在地面,其直径大于钢管混凝土桩段10的钢管外径,以便于钢管混凝土桩段10的钢管、注浆挤扩装置100和泥浆置换注浆管2的顺利下放。Based on the above research, please refer to FIG. 2 to FIG. 4 , this embodiment provides a grouting extruded and expanded concrete-filled steel tubular column pile, which includes: a column pile body 1 and a mud replacement grouting pipe 2; the column pile body 1 includes a steel pipe The concrete pile section 10, the concrete-filled steel tube pile section 10 is used to be accommodated in the borehole 3, the outer peripheral wall of the concrete-filled steel tube pile section 10 forms the pile side area 4; the mud replacement grouting pipe 2 is attached to the Outside the outer peripheral wall of the CFST pile section 10 , it is used for grouting to the pile side area 4 . It should be noted that the CFST pile section 10 is constructed by drilling implantation and grouting extrusion process. In the exemplary examples shown in FIGS. 2 to 4 , the pile side area 4 refers to the outer circumference of the steel pipe of the CFST pile section 10 . The gap formed between the wall and the hole wall of the borehole 3. In other examples, the construction process of the CFST section 10 can also be other effective ways, and the position range of the pile side area 4 can also include the pile side Soil, the present invention is not limited to this. Those skilled in the art can understand that the borehole 3 is opened on the ground, and its diameter is larger than the outer diameter of the steel pipe of the CFST pile section 10, so as to facilitate the steel pipe, the grouting extrusion and expansion device 100 and the mud replacement grouting pipe of the CFST pile section 10 2's smooth devolution.

如此配置,通过泥浆置换注浆管2向桩侧区4注浆,增加了钢管混凝土桩段10的侧阻力;同时,利用钢管代替钢筋笼,减少了现场制作钢筋笼这一工序,优化了施工工序,节省了材料,降低了工程造价;此外,在施工过程中,混凝土灌注与桩侧注浆能够同时进行,提高了施工效率。In this configuration, the grouting pipe 2 is used to replace the grouting pipe 2 to the pile side area 4, which increases the lateral resistance of the CFST pile section 10; at the same time, the use of steel pipes instead of steel cages reduces the process of making steel cages on site and optimizes the construction. In addition, in the construction process, concrete pouring and pile side grouting can be carried out at the same time, which improves the construction efficiency.

作为一种优选的实施方式,所述钢管混凝土桩段10包括注浆挤扩装置100,所述注浆挤扩装置100位于所述钢管混凝土桩段10的底部。如此配置,注浆挤扩装置100在注浆挤扩后形成水泥浆挤扩段1003,以增加钢管混凝土桩段10的侧阻力。当然在一些其他的实施例中,注浆挤扩装置100也可以位于钢管混凝土桩段的中部,本领域技术人员可根据实际情况对注浆挤扩装置100的位置进行配置,本发明对此不限。As a preferred embodiment, the CFST pile section 10 includes a grouting and expansion device 100 , and the grouting and expansion device 100 is located at the bottom of the CFST pile section 10 . In this configuration, the grouting and expansion device 100 forms the cement slurry extrusion and expansion section 1003 after the grouting and expansion, so as to increase the lateral resistance of the CFST pile section 10 . Of course, in some other embodiments, the grouting, squeezing and expanding device 100 may also be located in the middle of the concrete-filled steel tubular pile section, and those skilled in the art can configure the position of the grouting and squeezing and expanding device 100 according to the actual situation. limit.

进一步的,所述注浆挤扩装置100包括束浆袋1001,所述束浆袋1001贴附于所述钢管混凝土桩段10的外周壁的外侧。需要说明的,在图2至图4示出的示范例中,束浆袋1001的数量为一个,在一些其他的实施例中,束浆袋1001的数量也可以是两个或者更多,其可以沿钢管混凝土桩段10的周向均匀布置,相邻的两个束浆袋1001之间也可以相互连通,本领域技术人员可根据实际情况对束浆袋1001的数量以及排布方式进行配置,本发明对此不限。Further, the grouting and expansion device 100 includes a slurry bag 1001 , and the slurry bag 1001 is attached to the outer side of the outer peripheral wall of the concrete-filled steel tube pile section 10 . It should be noted that, in the examples shown in FIGS. 2 to 4 , the number of pulp bags 1001 is one, and in some other embodiments, the number of pulp bags 1001 may also be two or more. It can be evenly arranged along the circumference of the CFST pile section 10, and the two adjacent slurry bags 1001 can also be connected to each other. Those skilled in the art can configure the number and arrangement of the slurry bags 1001 according to the actual situation. , the present invention is not limited to this.

更进一步的,所述注浆挤扩装置100还包括注浆管1002,所述注浆管1002附设于所述钢管混凝土桩段10的外周壁之外并与所述束浆袋1001连接,用于向所述束浆袋1001注浆以形成水泥浆挤扩段1003。如此配置,通过注浆管1002向束浆袋1001注浆,束浆袋1001向周围膨胀,一方面挤压桩侧区4的水泥浆,另一方面挤压钢管混凝土桩段10的桩侧土体,并最终向外挤扩形成水泥浆挤扩段1003,有效提高了钢管混凝土桩段10的承载效率,同时也有效缩短了桩长和缩小了桩径。Further, the grouting extrusion and expansion device 100 further includes a grouting pipe 1002, which is attached to the outside of the outer peripheral wall of the concrete-filled steel pipe pile section 10 and is connected with the grouting bag 1001. Then, the slurry bag 1001 is grouted to form the cement slurry extrusion and expansion section 1003 . In this configuration, grouting is carried out through the grouting pipe 1002 to the grouting bag 1001, and the grouting bag 1001 expands to the surroundings, squeezes the cement slurry in the pile side area 4 on the one hand, and squeezes the pile side soil of the CFST pile section 10 on the other hand. The body is extruded and expanded outward to form the cement slurry extruded and expanded section 1003, which effectively improves the bearing efficiency of the CFST pile section 10, and also effectively shortens the length and diameter of the pile.

请参考图4,所述立柱桩本体1还包括钢管混凝土立柱段20,所述钢管混凝土立柱段20用于与基坑的多个支撑装置5连接。如此配置,立柱桩本体1包括钢管混凝土桩段10以及钢管混凝土立柱段20,钢管混凝土桩段10植入基坑底以下部分的钻孔3中,钢管混凝土立柱段20位于基坑底以上部分并与多个支撑装置5连接,避免了现有技术中,需要将格构柱或钢管立柱6植入钻孔灌注桩7中的工序,优化了施工工序,提高了施工效率。Please refer to FIG. 4 , the column pile body 1 further includes a CFST column section 20 , and the CFST column section 20 is used for connecting with a plurality of supporting devices 5 of the foundation pit. In this configuration, the column pile body 1 includes a CFST pile section 10 and a CFST column section 20. The CFST pile section 10 is implanted in the borehole 3 below the bottom of the foundation pit, and the CFST column section 20 is located above the foundation pit bottom. Being connected with a plurality of supporting devices 5 avoids the need to insert lattice columns or steel pipe columns 6 into bored piles 7 in the prior art, optimizes construction procedures and improves construction efficiency.

请继续参考图4,所述钢管混凝土立柱段20与所述钢管混凝土桩段10一体设置。如此配置,钢管混凝土桩段10与钢管混凝土立柱段20一体设置,取消了现有技术中格构柱或钢管立柱6与钻孔灌注桩7的搭接工艺,节省材料的同时,也降低了工程造价。Please continue to refer to FIG. 4 , the CFST column section 20 is integrally arranged with the CFST pile section 10 . In this configuration, the CFST pile section 10 and the CFST column section 20 are integrally arranged, eliminating the lap joint process of the lattice column or the steel pipe column 6 and the bored pile 7 in the prior art, saving materials and reducing engineering costs. cost.

请参考图1以及图5至图10,本实施例还提供了一种注浆挤扩钢管混凝土立柱桩施工方法,应用于如上所述的注浆挤扩钢管混凝土立柱桩;所述注浆挤扩钢管混凝土立柱桩施工方法包括:Please refer to FIG. 1 and FIG. 5 to FIG. 10 , this embodiment also provides a construction method for grouting and expanding concrete-filled steel tubular column piles, which is applied to the above-mentioned grouting and expanding concrete-filled steel tubular column piles; The construction method of expanded steel tube concrete column pile includes:

步骤S1:在地面钻进以形成钻孔3,对所述钻孔3进行清孔;Step S1: drilling on the ground to form a borehole 3, and clearing the borehole 3;

步骤S2:将注浆挤扩装置100安装在所述钢管混凝土桩段10的钢管的底部;Step S2: installing the grouting extrusion and expansion device 100 on the bottom of the steel pipe of the CFST pile section 10;

步骤S3:将所述钢管混凝土桩段10的钢管、所述注浆挤扩装置100以及泥浆置换管2植入所述钻孔3中;Step S3: implanting the steel pipe of the CFST pile section 10, the grouting extrusion device 100 and the mud replacement pipe 2 into the borehole 3;

步骤S4:在所述钢管混凝土桩段10的钢管的内部安装混凝土灌注导管,并进行二次清孔;Step S4: installing a concrete pouring conduit inside the steel pipe of the CFST pile section 10, and performing secondary hole cleaning;

步骤S5:通过所述混凝土灌注导管向所述钢管混凝土桩段10的钢管的内部灌注混凝土,同时,通过所述泥浆置换注浆管2向桩侧区4注浆;Step S5: pouring concrete into the inside of the steel pipe of the CFST pile section 10 through the concrete pouring conduit, and at the same time pouring grout into the pile side area 4 through the mud replacement grouting pipe 2;

步骤S6:待所述桩侧区4的水泥浆养护完成后,通过注浆管1002向束浆袋1001注浆以在所述钢管混凝土桩段10的底部形成水泥浆挤扩段1003。Step S6 : After the cement slurry maintenance of the pile side area 4 is completed, grouting is performed into the grouting bag 1001 through the grouting pipe 1002 to form the cement slurry extrusion and expansion section 1003 at the bottom of the CFST pile section 10 .

需要说明的,步骤S1、步骤S2并非限制各步骤之间的执行顺序,即不限于按顺序执行,也可以不按顺序执行。在图1至图10示出的示范例中,混凝土灌注导管均未示出,本领域技术人员可以理解的,混凝土灌注导管为一具有一定内径的圆管,其用于将混凝土注入钢管混凝土桩段10的内部,而在一些其他的实施例中,混凝土灌注导管也可以为其他具有相同作用的构件,本发明对此不限。It should be noted that, step S1 and step S2 do not limit the execution order between the steps, that is, they are not limited to be executed in sequence, and may also be executed out of sequence. In the examples shown in FIGS. 1 to 10 , the concrete pouring conduit is not shown. Those skilled in the art can understand that the concrete pouring conduit is a circular tube with a certain inner diameter, which is used for pouring concrete into the concrete-filled steel pipe pile. The interior of the segment 10, and in some other embodiments, the concrete pouring conduit can also be other components with the same function, which is not limited in the present invention.

在一个可替代的示范例中,利用钻机在地面钻进以形成钻孔3;利用起重机将钢管混凝土桩端10的钢管、注浆挤扩装置100以及泥浆置换注浆管2植入钻孔3中;利用注浆泵通过泥浆置换注浆管2向桩侧区4注浆;两次清孔均可采用正循环清孔或反循环清孔的方式进行,本领域技术人员可以理解的,二次清孔的目的是为了使桩底沉渣的厚度满足规范要求。当然在一些其他的实施例中,完成上述步骤的构件均可以是其他行之有效的构件,本发明对此不限。In an alternative example, a drilling rig is used to drill on the ground to form a borehole 3; a crane is used to implant the steel pipe of the concrete-filled steel tube pile end 10, the grouting and expansion device 100, and the mud replacement grouting pipe 2 into the borehole 3 use the grouting pump to replace the grouting pipe 2 with the mud to grouting the pile side area 4; the two times of hole cleaning can be carried out in the way of positive circulation hole cleaning or reverse circulation hole cleaning. Those skilled in the art can understand that two The purpose of the secondary hole cleaning is to make the thickness of the pile bottom sediment meet the specification requirements. Of course, in some other embodiments, the components for completing the above steps may be other effective components, which is not limited in the present invention.

进一步的,所述注浆挤扩钢管混凝土立柱桩施工方法还包括:Further, the construction method of the concrete-filled steel tubular column pile by grouting extrusion and expansion also includes:

步骤S7:将所述基坑的多个支撑装置5架设于钢管混凝土立柱段20。Step S7 : erecting the plurality of supporting devices 5 of the foundation pit on the CFST column section 20 .

需要说明的,请参考图4,当钢管混凝土桩段10的底部形成水泥浆挤扩段1003后,与其一体设置的钢管混凝土立柱段20已立设于基坑底部以上部分,此时,将多个支撑装置5架设于钢管混凝土立柱段20上,钢管混凝土立柱段20可直接将支撑装置5撑起以完成对基坑围护的支撑作用。It should be noted that, referring to FIG. 4 , after the cement slurry extrusion and expansion section 1003 is formed at the bottom of the CFST pile section 10, the CFST column section 20 integrated with it has been erected above the bottom of the foundation pit. Each supporting device 5 is erected on the CFST column section 20, and the CFST column section 20 can directly support the supporting device 5 to complete the supporting effect on the enclosure of the foundation pit.

作为一种优选的实施方式,所述桩侧区4的水泥浆的养护时间为不小于48h。需要说明的,当桩侧区4的水泥浆经过不小于48h的养护时间后,其强度得到一定的提升,此时,通过注浆管1002向束浆袋1001注浆以形成水泥浆挤扩段1003,进一步提升了钢管混凝土桩段10的承载性能。As a preferred embodiment, the curing time of the cement slurry in the pile side area 4 is not less than 48 hours. It should be noted that the strength of the cement slurry in the pile side area 4 will be improved to a certain extent after the curing time of not less than 48h. 1003, the bearing performance of the CFST pile section 10 is further improved.

作为一种优选的实施方式,利用注浆泵通过所述注浆管1002向所述束浆袋1001注浆。需要说明的,这里的注浆泵需要提供高压将水泥浆通过注浆管1002注入束浆袋1001中,以挤扩桩侧区4的水泥浆层和土体,并形成水泥浆挤扩段1003。As a preferred embodiment, the slurry bag 1001 is grouted through the grouting pipe 1002 using a grouting pump. It should be noted that the grouting pump here needs to provide high pressure to inject the cement slurry into the grouting bag 1001 through the grouting pipe 1002, so as to squeeze and expand the cement slurry layer and soil body in the pile side area 4, and form the cement slurry extrusion and expansion section 1003 .

综上,在本发明实施例提供的一种注浆挤扩钢管混凝土立柱桩及其施工方法中,所述注浆挤扩钢管混凝土立柱桩包括立柱桩本体和泥浆置换注浆管;所述立柱桩本体包括钢管混凝土桩段,所述钢管混凝土桩段用于容置于钻孔中,所述钢管混凝土桩段的外周壁之外形成桩侧区;所述泥浆置换注浆管附设于所述钢管混凝土桩段的外周壁之外,并用于向所述桩侧区注浆。所述钢管混凝土桩段包括注浆挤扩装置,所述注浆挤扩装置位于所述钢管混凝土桩段的底部。To sum up, in the grouting extrusion-expanded concrete-filled steel tubular column pile and the construction method thereof provided by the embodiments of the present invention, the grouting extrusion-expanded concrete-filled steel tubular column pile includes a column pile body and a mud replacement grouting pipe; the column The pile body includes a concrete-filled steel tube pile section, the concrete-filled steel tube pile section is used to be accommodated in a bore hole, and a pile side area is formed outside the outer peripheral wall of the concrete-filled steel tube pile section; the mud replacement grouting pipe is attached to the outside the outer peripheral wall of the concrete-filled steel tubular pile section, and for grouting the side area of the pile. The CFST pile section includes a grouting and expansion device, and the grouting and expansion device is located at the bottom of the CFST pile section.

如此配置,通过泥浆置换注浆管向桩侧区注浆,增加了钢管混凝土桩段的侧阻力;同时,通过注浆挤扩装置进行注浆挤扩,使得钢管混凝土桩段的侧阻力进一步提高;另一方面,利用钢管代替了钢筋笼,减少了制作钢筋笼这一工序,节省了材料,降低了工程造价;此外,混凝土灌注与桩侧注浆能够同时进行,提高了施工效率。With this configuration, the grouting pipe is used to replace the grouting pipe to the side area of the pile, which increases the lateral resistance of the CFST pile section. On the other hand, the use of steel pipes instead of steel cages reduces the process of making steel cages, saves materials, and reduces engineering costs; in addition, concrete pouring and pile side grouting can be carried out at the same time, which improves construction efficiency.

上述描述仅是对本发明较佳实施例的描述,并非对本发明范围的任何限定,本发明领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求书的保护范围。The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes and modifications made by those of ordinary skill in the field of the present invention according to the above disclosure all belong to the protection scope of the claims.

Claims (10)

1.一种注浆挤扩钢管混凝土立柱桩,其特征在于,包括:立柱桩本体和泥浆置换注浆管;1. A grouting extruding and expanding concrete-filled steel tubular column pile is characterized in that, comprising: a column pile body and a mud replacement grouting pipe; 所述立柱桩本体包括钢管混凝土桩段,所述钢管混凝土桩段用于容置于钻孔中,所述钢管混凝土桩段的外周壁之外形成桩侧区;The column pile body comprises a concrete-filled steel tubular pile section, the concrete-filled steel tubular pile section is used for being accommodated in a borehole, and a pile side area is formed outside the outer peripheral wall of the concrete-filled steel tubular pile section; 所述泥浆置换注浆管附设于所述钢管混凝土桩段的外周壁之外,并用于向所述桩侧区注浆。The mud replacement grouting pipe is attached outside the outer peripheral wall of the concrete-filled steel pipe pile section, and is used for grouting to the pile side area. 2.如权利要求1所述的注浆挤扩钢管混凝土立柱桩,其特征在于,所述钢管混凝土桩段包括注浆挤扩装置,所述注浆挤扩装置位于所述钢管混凝土桩段的底部。2 . The grouting and expansion concrete-filled steel tubular column pile according to claim 1 , wherein the concrete-filled steel tubular pile section comprises a grouting and expansion device, and the grouting and expansion device is located at the end of the concrete-filled steel tubular pile section. 3 . bottom. 3.如权利要求2所述的注浆挤扩钢管混凝土立柱桩,其特征在于,所述注浆挤扩装置包括束浆袋,所述束浆袋贴附于所述钢管混凝土桩段的外周壁的外侧。3 . The grouting and expanding concrete-filled steel tubular column pile according to claim 2 , wherein the grouting and expanding device comprises a grouting bag, and the grouting bag is attached to the outer periphery of the CFST pile section. 4 . outside of the wall. 4.如权利要求3所述的注浆挤扩钢管混凝土立柱桩,其特征在于,所述注浆挤扩装置还包括注浆管,所述注浆管附设于所述钢管混凝土桩段的外周壁之外并与所述束浆袋连接,用于向所述束浆袋注浆以形成水泥浆挤扩段。4 . The grouting and expanding concrete-filled steel tubular column pile according to claim 3 , wherein the grouting and expanding device further comprises a grouting pipe, and the grouting pipe is attached to the outer periphery of the CFST pile section. 5 . outside the wall and connected to the slurry bag for grouting the slurry bag to form a grout expansion section. 5.如权利要求1所述的注浆挤扩钢管混凝土立柱桩,其特征在于,所述立柱桩本体还包括钢管混凝土立柱段,所述钢管混凝土立柱段用于与基坑的多个支撑装置连接。5. The grouting-expanded concrete-filled steel tubular column pile according to claim 1, wherein the column pile body further comprises a concrete-filled steel tubular column segment, and the concrete-filled steel tubular column segment is used for a plurality of supporting devices of the foundation pit. connect. 6.如权利要求5所述的注浆挤扩钢管混凝土立柱桩,其特征在于,所述钢管混凝土立柱段与所述钢管混凝土桩段一体设置。6 . The grouting extrusion-expanded concrete-filled steel tubular column pile according to claim 5 , wherein the concrete-filled steel tubular column section and the concrete-filled steel tubular pile section are integrally arranged. 7 . 7.一种注浆挤扩钢管混凝土立柱桩施工方法,其特征在于,应用于根据权利要求1~6中任一项所述的注浆挤扩钢管混凝土立柱桩;所述注浆挤扩钢管混凝土立柱桩施工方法包括:7. A construction method for grouting and expanding concrete-filled steel tubular column piles, characterized in that it is applied to the grouting and expanding concrete-filled steel tubular column piles according to any one of claims 1 to 6; Concrete column pile construction methods include: 在地面钻进以形成钻孔,对所述钻孔进行清孔;Drilling in the ground to form a borehole, clearing the borehole; 将注浆挤扩装置安装在所述钢管混凝土桩段的钢管的底部;installing the grouting extrusion and expansion device on the bottom of the steel pipe of the concrete-filled steel pipe pile section; 将所述钢管混凝土桩段的钢管、所述注浆挤扩装置以及泥浆置换注浆管植入所述钻孔中;implanting the steel pipe of the CFST pile section, the grouting extrusion device and the mud replacement grouting pipe into the borehole; 在所述钢管混凝土桩段的钢管的内部安装混凝土灌注导管,并进行二次清孔;Install a concrete pouring conduit inside the steel pipe of the concrete-filled steel pipe pile section, and carry out secondary hole cleaning; 通过所述混凝土灌注导管向所述钢管混凝土桩段的钢管的内部灌注混凝土,同时,通过所述泥浆置换注浆管向桩侧区注浆;Concrete is poured into the inside of the steel pipe of the concrete-filled steel tube pile section through the concrete pouring conduit, and at the same time, the pile side area is poured through the mud replacement pouring tube; 待所述桩侧区的水泥浆养护完成后,通过注浆管向束浆袋注浆以在所述钢管混凝土桩段的底部形成水泥浆挤扩段。After the curing of the cement slurry in the pile side area is completed, grouting is carried out into the bundled slurry bag through a grouting pipe to form a squeezed and expanded section of the cement slurry at the bottom of the CFST pile section. 8.如权利要求7所述的注浆挤扩钢管混凝土立柱桩施工方法,其特征在于,所述注浆挤扩钢管混凝土立柱桩施工方法还包括:8. The construction method for grouting and expanding concrete-filled steel tubular column piles according to claim 7, characterized in that, the construction method for grouting and expanding concrete-filled steel tubular column piles further comprises: 将所述基坑的多个支撑装置架设于钢管混凝土立柱段。A plurality of supporting devices of the foundation pit are erected on the concrete-filled steel tubular column section. 9.如权利要求7所述的注浆挤扩钢管混凝土立柱桩施工方法,其特征在于,所述桩侧区的水泥浆的养护时间为不小于48h。9 . The method for grouting and expanding concrete-filled steel tubular column piles according to claim 7 , wherein the curing time of the cement slurry in the pile side area is not less than 48h. 10 . 10.如权利要求7所述的注浆挤扩钢管混凝土立柱桩施工方法,其特征在于,利用注浆泵通过所述注浆管向所述束浆袋注浆。10 . The construction method of grouting extrusion-expanded concrete-filled steel tubular column pile according to claim 7 , wherein the grouting bag is grouted through the grouting pipe by using a grouting pump. 11 .
CN202210432181.XA 2022-04-22 2022-04-22 Grouting and expanding concrete-filled steel tubular column pile and its construction method Pending CN114808944A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210432181.XA CN114808944A (en) 2022-04-22 2022-04-22 Grouting and expanding concrete-filled steel tubular column pile and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210432181.XA CN114808944A (en) 2022-04-22 2022-04-22 Grouting and expanding concrete-filled steel tubular column pile and its construction method

Publications (1)

Publication Number Publication Date
CN114808944A true CN114808944A (en) 2022-07-29

Family

ID=82507219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210432181.XA Pending CN114808944A (en) 2022-04-22 2022-04-22 Grouting and expanding concrete-filled steel tubular column pile and its construction method

Country Status (1)

Country Link
CN (1) CN114808944A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115874618A (en) * 2023-01-03 2023-03-31 上海同人里岩土工程技术有限公司 Grouting squeezing-expanding steel pipe anchor rod structure and construction method thereof
CN115897553A (en) * 2022-11-14 2023-04-04 沙焕焕 Reverse construction integrated pile support system and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605773A (en) * 2012-04-16 2012-07-25 上海市建工设计研究院有限公司 Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof
CN205369231U (en) * 2016-01-29 2016-07-06 中国科学院武汉岩土力学研究所 Steel -pipe pile is filled in drilling
CN216108676U (en) * 2021-06-30 2022-03-22 中国十九冶集团有限公司 Steel pipe of reinforced concrete upright pile structure
CN217298896U (en) * 2022-04-22 2022-08-26 上海同人里岩土工程技术有限公司 Grouting squeezing expansion steel pipe concrete upright pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605773A (en) * 2012-04-16 2012-07-25 上海市建工设计研究院有限公司 Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof
CN205369231U (en) * 2016-01-29 2016-07-06 中国科学院武汉岩土力学研究所 Steel -pipe pile is filled in drilling
CN216108676U (en) * 2021-06-30 2022-03-22 中国十九冶集团有限公司 Steel pipe of reinforced concrete upright pile structure
CN217298896U (en) * 2022-04-22 2022-08-26 上海同人里岩土工程技术有限公司 Grouting squeezing expansion steel pipe concrete upright pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115897553A (en) * 2022-11-14 2023-04-04 沙焕焕 Reverse construction integrated pile support system and construction method
CN115874618A (en) * 2023-01-03 2023-03-31 上海同人里岩土工程技术有限公司 Grouting squeezing-expanding steel pipe anchor rod structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN103510510B (en) A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN114808944A (en) Grouting and expanding concrete-filled steel tubular column pile and its construction method
CN110130427A (en) Reinforcing Method of Prefabricated Hollow Pipe Pile and Composite Pile Foundation
CN212175815U (en) Deep foundation pit supporting structure
CN115726347A (en) Pipe pile extension, bottom expanding and diameter expanding integrated device and construction method
CN217298896U (en) Grouting squeezing expansion steel pipe concrete upright pile
CN206706803U (en) Large diameter concrete filled steel pipe pile
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
CN109137924B (en) Structure for reducing pile length of deep soft soil layer by forming composite foundation and construction method
CN219157668U (en) Grouting extrusion expansion steel pipe anchor rod structure
CN212335996U (en) Resistance to compression resistance to plucking variable diameter steel reinforcement cage club-footed pile
CN205999941U (en) A kind of underground continuous wall section attachment means
CN114411717B (en) A prefabricated concrete pipe pile that can be lengthened and combined after grouting
CN101691753B (en) Pile mould for PCC pile and construction method for overlong PCC pile
CN206233232U (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN107059908A (en) Large diameter steel pipe concrete-pile
CN103911988A (en) A New Wall-protecting Pile for Foundation Pit Support
CN204199279U (en) Prefabricated reinforced concrete anchor pole
CN111441368B (en) A deep foundation pit support structure and construction method
CN210766749U (en) A special-shaped cast-in-place pile
CN207244614U (en) A kind of constructing device for superpressure retaining wall cast-in-situ bored pile
JP4724879B2 (en) Foundation pile structure
CN212835402U (en) Expansion high-pressure grouting pipe
CN206495202U (en) A kind of top expansion type cement-soil composite pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220729