JPS6294688A - Method of constructing large-depth shaft - Google Patents

Method of constructing large-depth shaft

Info

Publication number
JPS6294688A
JPS6294688A JP23098085A JP23098085A JPS6294688A JP S6294688 A JPS6294688 A JP S6294688A JP 23098085 A JP23098085 A JP 23098085A JP 23098085 A JP23098085 A JP 23098085A JP S6294688 A JPS6294688 A JP S6294688A
Authority
JP
Japan
Prior art keywords
shaft
diameter
steel pipe
pipe
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP23098085A
Other languages
Japanese (ja)
Inventor
昌彦 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP23098085A priority Critical patent/JPS6294688A/en
Publication of JPS6294688A publication Critical patent/JPS6294688A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は上水道、下水道、トンネル等の工事において構
築される大深度竪状の構築法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing deep vertical structures for construction of waterworks, sewers, tunnels, etc.

(従来の技術) 従来、この種の整梳の構築に際しては、山留支保工、ケ
ーソンエ等が使用され、地下水位が高い場合には補助工
法として薬液注入工法、ディープウェル工法が併用され
た。
(Conventional technology) Conventionally, when constructing this type of combing, mountain retaining shoring, caisson etc. were used, and when the groundwater level was high, chemical injection method and deep well method were used as auxiliary methods.

(発明が解決しようとする問題点) 前記従来の方法は、地盤の良否にも影響されるが、大規
模な工事となり、工費が嵩み、工期が延引するという問
題点があった。
(Problems to be Solved by the Invention) The conventional method has problems in that, although it is affected by the quality of the ground, it requires large-scale construction, increases construction costs, and prolongs the construction period.

(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案された
もので、竪坑構築予定地点に大口径掘削機をセットし、
同掘削機によって所定の深度まで竪孔を掘削し1次いで
同竪孔径より多少小径の大口径鋼管を竪孔内に上下方向
に継接しながら建込んだのち底部コンクリートを打設し
、次いで前記大口径鋼管と竪孔内壁面との間にグラウト
を注入するとともに、銅管内の水を排除することを特徴
とする大深度竪坑構築法に係るものである。
(Means for Solving the Problems) The present invention was proposed to solve these problems, and involves setting a large-diameter excavator at the site where the shaft is planned to be constructed,
A shaft is excavated to a predetermined depth using the same excavator, and then a large-diameter steel pipe with a diameter slightly smaller than the diameter of the shaft is built into the shaft while being connected vertically, and the bottom concrete is poured. This method relates to a method for constructing a deep shaft, which is characterized by injecting grout between the diameter steel pipe and the inner wall surface of the shaft and removing water within the copper pipe.

(作用) 本発明においては前記したように1整梳構築予定地点に
セットした大口径掘削機によって所定の深度まで大口径
の竪孔を掘削し、同大口径の竪孔内に穿孔径より多少小
径の大口径鋼管を竪孔掘削方向に継接しながら建込むこ
とによって、大口径鋼管を所定深度まで容易に挿入する
ことができる。
(Function) In the present invention, as described above, a large-diameter excavator is set at the planned construction site to excavate a large-diameter pit to a predetermined depth, and a hole slightly larger than the drilling diameter is placed inside the large-diameter pit. By erecting small-diameter large-diameter steel pipes while joining them in the shaft excavation direction, the large-diameter steel pipes can be easily inserted to a predetermined depth.

かくして大口径鋼管を所定深度まで挿入したのち、底部
コンクリートを打設して鋼管底部を竪孔内底部に固定し
、同盟孔内壁面と前記大口径鋼管との間にグラウトを注
入して同鋼管を前記竪孔内壁面に固定するとともに鋼管
内の水を排除し、内壁面を大口径鋼管で保護された竪坑
を構築するものである。
After inserting the large-diameter steel pipe to a predetermined depth, concrete is placed at the bottom to fix the bottom of the steel pipe to the inner bottom of the shaft, and grout is injected between the inner wall of the hole and the large-diameter steel pipe. is fixed to the inner wall surface of the shaft, water in the steel pipe is removed, and a shaft is constructed in which the inner wall surface is protected by a large-diameter steel pipe.

(発明の効果) 本発明においてはこのように大口径掘削機を利用して所
定の地盤内に竪孔を掘削し、同盟孔の壁面防護工として
大口径鋼管を建込み、底部コンクリートを施工したのち
同鋼管と前記竪孔内壁面との間にグラウトを注入すると
ともに前記鋼管内を排水して、竪孔内に大口径鋼管が一
体化された竪坑を構成するものであり、本発明によれば
大口径掘削機を利用して大深度の竪坑を容易に構築しう
るものであって、工期を縮減し、工費を節減しうるもの
である。
(Effects of the Invention) In the present invention, as described above, a large-diameter excavator is used to excavate a pit in a predetermined ground, a large-diameter steel pipe is installed as a wall protection work for the adjacent hole, and the bottom is concreted. Thereafter, grout is injected between the steel pipe and the inner wall surface of the shaft, and the inside of the steel pipe is drained to form a shaft in which a large-diameter steel pipe is integrated within the shaft. For example, a large-diameter excavator can be used to easily construct a deep shaft, which can shorten the construction period and reduce construction costs.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

先ず所定の地盤にスタンドパイプ(1)を圧入し、同パ
イプ(1)内にクレン(2)を介して大口径掘削機(3
)を吊込み、同掘削機(3)によって竪孔(A)を掘削
するとともに、同盟孔(勾に静水(4)または泥水を注
入して竪孔囚の内壁面の崩壊を防止する。
First, a stand pipe (1) is press-fitted into the specified ground, and a large-diameter excavator (3) is inserted into the pipe (1) via a crane (2).
) is suspended and the shaft (A) is excavated by the same excavator (3), and still water (4) or muddy water is injected into the associated hole (diagonal) to prevent the inner wall of the shaft from collapsing.

図中(5)はサクションポンプ、(6)は沈澱槽、(7
)は竪孔(A)に対する給水用水槽、(8)はリターン
パイプである。(第1図参照) かくして前記掘削機(3)によって所定深度まで竪孔(
A)を掘削したのち、クレーン(2)を介して同盟孔(
Al内に竪孔(Alより多少小径の第1の鋼管(Bl)
を建込み1次いで第2の鋼管(B2)を建込み、両鋼管
(Bl)(B2)を現場で溶接する。なお鋼管内周面に
円環状の挫屈防止材(9)は工場で溶接して現場に搬入
する。(第2図参照)以下同様にして鋼管(B1) (
B2) (B3 ) −(Bn)を継接して前記竪孔(
Al内に大口径の鋼管(B)を建込み、底版コンクリー
ト補強材(lotを吊込み、トレミー管αυをセットす
る。
In the figure, (5) is a suction pump, (6) is a sedimentation tank, and (7
) is a water tank for supplying water to the pit (A), and (8) is a return pipe. (See Figure 1) In this way, the excavator (3) excavates the shaft (
After drilling hole A), use crane (2) to excavate the alliance hole (
A vertical hole (a first steel pipe (Bl) with a diameter slightly smaller than that of the Al) is formed in the Al.
The first steel pipe (B2) is then erected, and both steel pipes (Bl) (B2) are welded on site. The annular buckling prevention material (9) on the inner peripheral surface of the steel pipe is welded at the factory and delivered to the site. (See Figure 2) Similarly, the steel pipe (B1) (
B2) (B3) - (Bn) are joined to form the vertical hole (
A large-diameter steel pipe (B) is erected in the aluminum, the bottom concrete reinforcement material (lot) is suspended, and a tremie pipe αυ is set.

(第3図) 次いで前記トレミー管(11)より底部コンクリートα
のを打設して、鋼管(B)の底部を竪孔(Nの底部に固
定する。(第4図参照) 次いで前記鋼管CB)と竪孔(A)内局面との間にグラ
ウト注入管(13を介してグラウトα荀を充填するとと
もに、鋼管(B3内の水を排除して、竪孔(A)の内壁
面が鋼管(Blで保護された竪坑を構築する。(第5図
参照) 前記実施例によれば、大口径掘削機(3)を利用して所
定の地盤内に所定深度の竪孔(Alを掘削するとともに
、同盟孔fAlに大口径鋼管(B)を一体化させること
によって、大深度、大口径の竪坑を容易に構築しうるも
のであって、工期を短縮し、工費を節減しうるものであ
る。
(Fig. 3) Next, the bottom concrete α is poured from the tremie pipe (11).
The bottom of the steel pipe (B) is fixed to the bottom of the shaft (N) (see Figure 4). Next, a grout injection pipe is installed between the steel pipe CB) and the inner surface of the shaft (A). (13), and remove the water in the steel pipe (B3) to construct a shaft in which the inner wall surface of the shaft (A) is protected by the steel pipe (Bl). (See Figure 5) ) According to the embodiment, a large-diameter excavator (3) is used to excavate a vertical hole (Al) at a predetermined depth in a predetermined ground, and a large-diameter steel pipe (B) is integrated into the associated hole fAl. By doing so, it is possible to easily construct a shaft of great depth and large diameter, and the construction period can be shortened and construction costs can be reduced.

第8図乃至第11図は本発明の他の実施例を示し、前記
の方法によって竪坑を構築したのち、同整梳の本杭に対
する結合部外周地盤に薬液注入による改良地盤aつを造
成して止水を行ない、本杭(C)を整梳部分まで掘進す
る。(第8図参照) 次いで竪坑における本杭結合部の鋼管(Blの管壁を切
断し、本杭(C)内の配管tteを竪抗内に延長し、(
第9図参照)本杭(C)内の配管α印に接続された整梳
内の立上り配管(Iηの補強筋賭を同竪坑内に配筋して
コンクリート員を打設し、(第10図参照)以下前記配
管αηの溶接による継接とコンクIJ−) (Liの打
設とを反覆し、整梳頂部にマンホール(21%を施工し
て水道配管を内蔵した竪坑の構築を完了するものである
Figures 8 to 11 show another embodiment of the present invention, in which, after constructing a shaft by the method described above, an improved ground is created by injecting a chemical into the ground around the outer circumference of the joint of the same leveled comb to the main pile. After that, the main pile (C) is dug to the leveled area. (See Figure 8) Next, cut the pipe wall of the steel pipe (Bl) of the main pile connection part in the shaft, extend the pipe tte in the main pile (C) into the shaft,
(Refer to Figure 9) Reinforcement bars of the upright pipe (Iη) in the leveling shaft connected to the pipe α in the main pile (C) are placed in the same shaft and concrete members are placed. (Refer to the figure) Below, repeat the welding of the pipe αη and the concrete IJ-) (Repeat the Li pouring, and construct a manhole (21%) at the top of the comb to complete the construction of the shaft containing the water pipe. It is something.

以上本発明を実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく1本発
明の精神を逸脱しない範囲内で種々の設計の改変を施し
うるものである。
Although the present invention has been described above with reference to embodiments, the present invention is of course not limited to these embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第5図は本発明に係る大深度竪坑構築法の一
実施例の工程を示す縦断面図、第6図は底部コンクリー
トの補強材の平面図、第7図は第5図の横断平面図、第
8図乃至第11図は本発明の他の実施例の工程を示す縦
断面図である。 (A)・・・型孔       (B)・・・鋼管(3
)・・・大口径掘削機   αか・・底部コンクリート
側・・・グラウト 代理人 弁理士  岡 本 重 文 外2名 第7図 第11図
1 to 5 are longitudinal cross-sectional views showing the steps of an embodiment of the deep shaft construction method according to the present invention, FIG. 6 is a plan view of the bottom concrete reinforcement, and FIG. 7 is the same as that of FIG. The cross-sectional plan view and FIGS. 8 to 11 are longitudinal cross-sectional views showing steps of other embodiments of the present invention. (A)...Mold hole (B)...Steel pipe (3
)...Large-diameter excavator α...Bottom concrete side...Grout agent Patent attorney Shige Okamoto 2 people Fig. 7 Fig. 11

Claims (1)

【特許請求の範囲】[Claims] 竪坑構築予定地点に大口径掘削機をセットし、同掘削機
によつて所定の深度まで竪孔を掘削し、次いで同竪孔径
より多少小径の大口径鋼管を竪孔内に上下方向に継接し
ながら建込んだのち底部コンクリートを打設し、次いで
前記大口径鋼管と竪孔内壁面との間にグラウトを注入す
るとともに、鋼管内の水を排除することを特徴とする大
深度竪坑構築法。
A large-diameter excavator is set at the location where the shaft is planned to be constructed, and the excavator excavates the shaft to a predetermined depth. Next, a large-diameter steel pipe with a diameter slightly smaller than the diameter of the shaft is vertically connected inside the shaft. A method for constructing a deep shaft, which is characterized in that after the shaft is erected, concrete is poured at the bottom, and then grout is injected between the large-diameter steel pipe and the inner wall surface of the shaft, and water in the steel pipe is removed.
JP23098085A 1985-10-18 1985-10-18 Method of constructing large-depth shaft Pending JPS6294688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23098085A JPS6294688A (en) 1985-10-18 1985-10-18 Method of constructing large-depth shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23098085A JPS6294688A (en) 1985-10-18 1985-10-18 Method of constructing large-depth shaft

Publications (1)

Publication Number Publication Date
JPS6294688A true JPS6294688A (en) 1987-05-01

Family

ID=16916336

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23098085A Pending JPS6294688A (en) 1985-10-18 1985-10-18 Method of constructing large-depth shaft

Country Status (1)

Country Link
JP (1) JPS6294688A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0622964U (en) * 1992-04-08 1994-03-25 オルガン針株式会社 Contact probe

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58181998A (en) * 1982-04-17 1983-10-24 株式会社 白石 Method of excavation construction of pit and excavator

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58181998A (en) * 1982-04-17 1983-10-24 株式会社 白石 Method of excavation construction of pit and excavator

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0622964U (en) * 1992-04-08 1994-03-25 オルガン針株式会社 Contact probe

Similar Documents

Publication Publication Date Title
JP2002146811A (en) Construction method for underwater structure foundation
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
JP2006194031A (en) Pillar construction method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JP2784317B2 (en) Open caisson structure
JP3930954B2 (en) Construction method of structure
JPS6294688A (en) Method of constructing large-depth shaft
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP3091859B2 (en) Piling method for shafts with openings at the top
JPS63280153A (en) Underground inverted lining method
JP3794097B2 (en) Construction method for underground structures
CN212427155U (en) Tongue-and-groove type prefabricated underground continuous wall structure
CN115324087B (en) Deep water rock-socketed combined light cofferdam
JPH059945A (en) Underground skeleton constructing method
JP6851180B2 (en) How to rebuild the building
JP2745083B2 (en) Tunnel construction method
JPS62117911A (en) Setting of pipe for well
JPS5850218A (en) Connecting structure system for head of cast-in-place concrete pile and footing
JPH02132226A (en) Method for constructing retaining wall
JPS6192235A (en) Fixing of embedded pipe
JP2022137952A (en) Construction method of eccentric substructural column
CN116290100A (en) Reverse construction method for constructing junction of underground garage in stages
JPH02232414A (en) Protecting method for underground utilities or the like
JPH02200920A (en) Modification of grade of slope face
CN113802600A (en) Construction method for excavating and installing pipeline in narrow space