JPS5568921A - Construction method of underground continuous wall - Google Patents

Construction method of underground continuous wall

Info

Publication number
JPS5568921A
JPS5568921A JP14373278A JP14373278A JPS5568921A JP S5568921 A JPS5568921 A JP S5568921A JP 14373278 A JP14373278 A JP 14373278A JP 14373278 A JP14373278 A JP 14373278A JP S5568921 A JPS5568921 A JP S5568921A
Authority
JP
Japan
Prior art keywords
steel
guide
water
underground continuous
easy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14373278A
Other languages
Japanese (ja)
Inventor
Toyohiko Nagai
Hitoshi Takeuchi
Yukinori Miyoshi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP14373278A priority Critical patent/JPS5568921A/en
Publication of JPS5568921A publication Critical patent/JPS5568921A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE: To obtain the subject method wherein guide steel frames act simultaneously as interclocking pipe, cut-off wall and joint, easy and simple in construction, avoid of deviation in excavating alignment, owing to the action of the guides, easy in mutual engagement and fixing works among guide steel frames and most suited for construction work at deep level.
CONSTITUTION: In the preparation of underground continuous walls by utilizing muddy water, the guiding steel frame 1 having the partition steel plate 3 with many projecting steel reinforcing rod for jointing 6 on its surface between two water- stopping steel plates equipped with the engagement 5 on one end and the guide 4 on the other is used as the inter-locking material. This guiding steel frame 1 is connected continuously in digging of unit grooves and the concreate 7 is filled in between the water-stopping steel plates 2.
COPYRIGHT: (C)1980,JPO&Japio
JP14373278A 1978-11-21 1978-11-21 Construction method of underground continuous wall Pending JPS5568921A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14373278A JPS5568921A (en) 1978-11-21 1978-11-21 Construction method of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14373278A JPS5568921A (en) 1978-11-21 1978-11-21 Construction method of underground continuous wall

Publications (1)

Publication Number Publication Date
JPS5568921A true JPS5568921A (en) 1980-05-24

Family

ID=15345714

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14373278A Pending JPS5568921A (en) 1978-11-21 1978-11-21 Construction method of underground continuous wall

Country Status (1)

Country Link
JP (1) JPS5568921A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403338A (en) * 2018-10-12 2019-03-01 江苏省送变电有限公司 A kind of assembly lattice configuration steel TRD engineering method diaphram wall and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403338A (en) * 2018-10-12 2019-03-01 江苏省送变电有限公司 A kind of assembly lattice configuration steel TRD engineering method diaphram wall and its construction method

Similar Documents

Publication Publication Date Title
JPS5568921A (en) Construction method of underground continuous wall
JPS5568919A (en) Construction of underground continuous wall
JPS57180714A (en) Method of executing water stop work for sheet pile wall
JPS5552424A (en) Method of installing underground continuous wall constructing standard pile
JPS57151725A (en) Underground wall construction work and covering element therefor
JPS5530042A (en) Process for making continuous underground wall
JPS56159419A (en) Continuous underground wall and construction thereof
ES478369A1 (en) Method of constructing vertical wall structure in ground from underground conduit
JPS5664028A (en) Sheathing construction work by antecedent support framework
JPS5634818A (en) H-section steel sheet pile
JPS5748018A (en) Constructing method for pile foundation with underground wall
JPS55116921A (en) Reference pile for continuous underground wall construction
JPS5670322A (en) Construction of underground wall by column strip
JPS57155423A (en) Method of construction of solidification of muddy water
JPS55116922A (en) Jointing method of continuous underground wall
JPS55161117A (en) Constructing method for underground continuous wall by precast concrete member
JPS5771938A (en) Outer water-proofing work
FR2425508A1 (en) Joint between normal precast concrete wall panels - uses forked end of one panel to house reinforcing bars and define channel for concrete
JPS5768419A (en) Executing method for underground continuous wall
JPS54128486A (en) Excavation method using stabilizing fluid in engineering fundamental work
GB1252321A (en)
JPS6417994A (en) Method of executing underground structure
FR2450911A1 (en) Construction technique for reinforcing narrow excavations - uses side grout type material instead of trench timbers
JPS5516172A (en) Excavation work method and apparatus for preventing landslide at ditch scooping
JPS5641924A (en) Construction engineering for continuous underground wall