CN109403338A - Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof - Google Patents

Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof Download PDF

Info

Publication number
CN109403338A
CN109403338A CN201811190402.7A CN201811190402A CN109403338A CN 109403338 A CN109403338 A CN 109403338A CN 201811190402 A CN201811190402 A CN 201811190402A CN 109403338 A CN109403338 A CN 109403338A
Authority
CN
China
Prior art keywords
steel
lattice
wall
trd
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811190402.7A
Other languages
Chinese (zh)
Inventor
顾海荣
吉宏
张鹏
刘泽鹏
曹永春
陈荣刚
王磊
董志高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Power Transmission And Distribution Co ltd
Nanjing Tech University
Original Assignee
Jiangsu Power Transmission And Distribution Co ltd
Nanjing Tech University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Power Transmission And Distribution Co ltd, Nanjing Tech University filed Critical Jiangsu Power Transmission And Distribution Co ltd
Priority to CN201811190402.7A priority Critical patent/CN109403338A/en
Publication of CN109403338A publication Critical patent/CN109403338A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses an underground continuous wall of an assembled lattice section steel TRD construction method and a construction method thereof.A lattice assembly is arranged in the wall of the TRD construction method to form the underground continuous wall of the assembled lattice section steel TRD construction method, and cement soil in the underground continuous wall is changed into a three-dimensional compression state from a one-way stretch bending stress state which is arranged on the outer side of section steel in the traditional construction method, so that the characteristic that the compression strength of the cement soil is far greater than the tensile strength and the shearing strength is fully exerted, and the horizontal support rigidity of the wall of the TRD construction method can be greatly improved; the technical problem that the lattice steel is difficult to integrally insert into the cement soil is solved by a successive insertion assembly mode, and the horizontal support rigidity of the wall in the TRD construction method can be effectively regulated and controlled by arranging the lattice area change and the combination of the lattice area change and the independent steel reinforcement body on the wall in the square lattice and the TRD construction method.

Description

A kind of assembly lattice configuration steel TRD engineering method diaphram wall and its construction method
Technical field
The invention belongs to geotechnical engineering pattern foundation pit supporting structure fields, and in particular to a kind of assembly lattice configuration steel TRD engineering method underground connects Continuous wall and its construction method.
Background technique
Traditional diaphram wall is constructed using framing, is the weak link of sealing at Construction Joint, working procedure mostly with week Phase is long, if cannot be combined into one with underground structure side wall, cost is excessively high, this also constrains what it was applied in general base pit engineering Restriction condition.
TRD engineering method changes conventional soil cement stirring wall as equal thickness cement mixing wall Choice of Construction Technique of Water Stop Curtain Single solum horizontal stirring mode, but the vertical stirring mode of different soil is realized by cutting box, have construction depth is big (can Up to 60m), adapt to stratum is wide, mixing effect is good, seamless connection high at wall precision, suitable for height-limited operating environment.
The lateral rigidity of traditional SMW engineering method stake is mainly undertaken by the fashioned iron being inserted into, and cement mixing method is as flexible pile Or Half rigid pile almost illegal its lateral rigidity of consideration contribution, the horizontal distortion of traditional SMW engineering method stake is larger, this is also to restrict The bottleneck that this engineering method is applied in deep big foundation pit engineering.For SMW engineering method stake, if the rigidity for only relying on raising profile is come The lateral rigidity for improving entire compound pile body, then will be sharply increased, pile body section also will be enlarged by, this certainly will make its warp with steel cost Ji property is reduced to be increased with difficulty of construction.It mainly should be from taking effective way so to improve the working performance core of diaphram wall Improve or play the lateral rigidity of Soil-cement Wall.
Cup type steel drum Rigid cable is by being enclosed in cup type steel drum for the stake core cement-soil of cement mixing method Inside given full play to cement so that the soil cement inside steel drum becomes three dimension stress state from unidirectional stretch bending stress Native compression strength is much larger than tension, the characteristic of shearing strength, to greatly improve the horizontal support rigidity of cement mixing wall.But Cup type steel drum, since soil encircles effect of contraction as insertion depth is deepened, is inserted into extremely difficult when being inserted into cement mixing method;And And due to the pile diameter domination of cement mixing method, so that steel drum diameter can not flexibly change, thus the support rigidity of such pile-type It can not accomplish flexible modulation.
Summary of the invention
The present invention provides a kind of assembly lattice configuration steel TRD engineering method diaphram wall and its construction methods, solve tradition Unidirectional stretch bending stress, Compressive Strength of Soil-cement Mixture are less than tension and shearing strength, TRD on the outside of soil cement in diaphram wall The weak problem of the horizontal support rigidity of engineering method wall.
In order to solve the above-mentioned technical problem, the technical scheme adopted by the invention is that: a kind of assembly lattice configuration steel TRD engineering method Diaphram wall, including TRD engineering method wall, the TRD engineering method are equipped with lattice component within the walls, and the lattice component includes narrow wing I-shaped Steel and the straight line shaped steel plate pile on the outside of two edges of a wing of narrow wing I-steel.
Further, straight line shaped steel plate pile both ends are equipped with fore shaft.
Further, it is connected between the straight line steel sheet pile on the outside of the adjacent same side wing edge of the narrow wing I-steel.
Further, pass through straight line steel sheet pile between the straight line steel sheet pile on the outside of the adjacent same side wing edge of the narrow wing I-steel Fore shaft connection.
A kind of construction method for assembling lattice configuration steel TRD engineering method diaphram wall, which comprises the following steps:
S1, surveying setting-out;
After S2, cell wall reinforce center line setting-out, Reinforcement Measures are carried out to construction site, it is ensured that construction site meets machinery and sets The standby requirement to foundation bearing capacity, it is ensured that the stability of stake machine;
S3, provided box is hung;
S4, stake machine are in place;
S5, cutting box is hung paragraph by paragraph into pre-buried cave with crane, is fixed using supporting table;It sets at TRD host mobility to pre-buried acupuncture point Cutting box is connected, host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth;
S6, it excavates in advance: being injected by mudjack and excavate liquid, cutting box is pushed ahead, and native soil layer, cutting one section of row of grooving are excavated Journey;Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box is withdrawn again to cutting starting point;It is stirred at wall Mix: cutting box withdraw to cutting starting point after exchanges slurries, by mudjack inject solidify liquid, cutting box push ahead and with digging It digs liquid mixing mud to be mixed, forms uniform thickness Soil-cement Wall;
On the outside of S7, narrow two edge of a wing of wing I-steel and straight line shaped steel plate pile smears interleaving agent;
The guide frame and hanging beam that S8, setting lattice configuration steel are inserted into;
Before S9, soil cement are unhardened, by the inclinometer being mounted on inside cutting box, the vertical precision management of wall is carried out, to TRD Soil-cement is vertically vertically inserted into narrow wing I-steel within the walls, is then inserted into straight line on the outside of two edges of a wing of narrow wing I-steel Shape steel plate completes the half side of a rectangular lattice;
Another adjacent rectangular lattice of S10, completion is half side, and the fore shaft of adjacent linear type steel sheet pile is connected together with fore shaft, Form the rectangular lattice unit of assembly;
S11, after stirring at wall, region injection is pulled out with proportion solidify liquid drafting cutting box and rising, side rises and draws out slip casting, to cutting It cuts case to occupy cavity progress dense packing effect and effectively reinforce, terminates straightway wall construction;
Soil excavation in S12, foundation pit completes building underground structure main body construction;
S13, the inside and outside smearing interleaving agent of combination lattice is heated and softened, the guide frame and hanging beam that setting lattice is extracted are extracted The combination lattice of TRD engineering method within the walls, Foundation Pit Construction finish.
Further, in the step S11, solidify liquid proportion is identical as solidify liquid proportion in step S6.
Further, in the step S2, Reinforcement Measures include being laid with steel plate to construction site.
Advantageous effects of the invention: the present invention is equipped with lattice component by TRD engineering method within the walls, assembly lattice are constituted Configuration steel TRD engineering method diaphram wall, soil cement in diaphram wall is by the unidirectional drawing that is placed on the outside of fashioned iron in traditional engineering method Curved stress becomes three dimension stress state, has given full play to Compressive Strength of Soil-cement Mixture and has been much larger than tension, the characteristic of shearing strength, The horizontal support rigidity of TRD engineering method wall can be greatly improved;Gradually plugging in fitting assembly model solves lattice configuration steel globality Be inserted into the technical problem of soil cement difficulty, rectangular lattice and TRD engineering method wall can by be arranged lattice area change and its with independence The horizontal support rigidity of Effective Regulation TRD engineering method wall is capable of in the combination of fashioned iron reinforcing body.
Detailed description of the invention
Fig. 1 is lattice component diagram of the present invention;
Fig. 2 is the wall schematic cross-sectional view of present invention assembly lattice configuration steel TRD engineering method diaphram wall.
In figure: 1- TRD engineering method wall;The narrow wing I-steel of 2-;3- straight line shaped steel plate pile;4- fore shaft.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following embodiment is only used for clearly illustrating the present invention Technical solution, and not intended to limit the protection scope of the present invention.
1, a kind of construction method for assembling lattice configuration steel TRD engineering method diaphram wall, comprising the following steps:
Step 1: accurately calculating cell wall according to the coordinate basis of design drawing point and reinforcing center line angular coordinate, utilize whole station Instrument carries out setting-out, and carries out coordinate data review, while carrying out fender pile.
Step 2: carrying out being laid with the Reinforcement Measures such as steel plate to construction site after cell wall reinforces center line setting-out, it is ensured that Construction site meets requirement of the mechanical equipment to foundation bearing capacity, it is ensured that the stability of stake machine.Preceding excavator construct along cell wall It reinforces centerline parallel direction and excavates working channel to undisturbed soil depth, to detect shallow-layer (within 3m) with the presence or absence of underground obstacle Object does not find the section of barrier in time with the plain earthen backfill excavated;Groove width about 1.4m, trench depth about 1.2m.
Step 3: using excavator along water-stop curtain center line excavate deep about 5m, be about 2m, width about 1m pre-buried cave it Afterwards, provided box is hung in pre-buried cave with crane.
Step 4: stake machine is in place;
Step 5: being hung cutting box into pre-buried cave paragraph by paragraph with crane, fixed using supporting table;TRD host mobility is to pre-buried cave Position connects cutting box, and host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth.
Step 6: excavating in advance: being injected by mudjack and excavate liquid, cutting box is pushed ahead, and is excavated and is loosened native soil layer, cuts It is cut into slot a trip.Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box is withdrawn again to cutting Starting point.Stir at wall: cutting box exchanges slurries after withdrawing to cutting starting point, injects solidify liquid, cutting box by mudjack It pushes ahead and is mixed with liquid mixing mud is excavated, form uniform thickness Soil-cement Wall;
Step 7: narrow wing I-steel outside and straight line shaped steel plate pile smear interleaving agent;Narrow wing I-steel is the narrow wing of 600*150mm I-steel;
Step 8: guide frame and hanging beam that setting combined steel plate pile is inserted into;
Step 9:, by the inclinometer being mounted on inside cutting box, carrying out the vertical precision pipe of wall before soil cement is unhardened Reason.It is vertically vertically inserted into narrow wing I-steel within the walls to TRD engineering method, straight line shaped steel plate pile is then inserted on the outside of upper lower flange, it is complete At half side structure of a lattice cell cube;Straight line shaped steel plate pile is the straight line shaped steel plate pile of YSP-FL;
Step 10: continue to complete half side structure of another adjacent lattice cell cube, the fore shaft of adjacent linear type steel sheet pile with Fore shaft is connected together, to form a rectangular lattice unit;
Step 11: acting the solidify liquid pulled out region and inject same proportion drafting cutting box, side rises and draws out note after stirring at wall Slurry, it is ensured that cavity is occupied to cutting box and carries out dense packing effect and effectively reinforces, terminates straightway wall construction.
Step 12: heating and softening, combination lattice is inside and outside to smear interleaving agent, the guide frame and suspension that setting lattice is extracted Beam extracts the combination lattice in TRD engineering method wall;
Step 13: Foundation Pit Construction finishes.
A kind of assembly lattice configuration steel TRD engineering method diaphram wall (such as Fig. 2), the diaphram wall include lattice component (such as Fig. 1), TRD engineering method wall 1, wall top crown beam;Lattice component includes straight line shaped steel plate pile 3, narrow wing I-steel 2;Wherein, straight line fashioned iron Sheet pile 3 is located on the outside of two edges of a wing of narrow wing I-steel 2, and the two is respectively positioned in TRD engineering method wall 1;Lattice configuration steel is inserted into TRD work The arrangement mode of method wall 1 are as follows: first according to the horizontal rigidity demand of fashioned iron TRD engineering method wall 1, determine the area of rectangular lattice with it is narrow 2 spacing of wing I-steel is inserted into narrow wing I-steel 2 according to pitch requirements, is inserted into straight line on the outside of the upper lower flange of narrow wing I-steel 2 Shape steel plate 3, and the fore shaft of straight line shape steel plate 34 and fore shaft 4 are connected with each other, it combines to form square grid with narrow wing I-steel 2 Structure, to constitute assembly lattice configuration steel TRD engineering method diaphram wall.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvement and deformations can also be made, these improvement and deformations Also it should be regarded as protection scope of the present invention.

Claims (7)

1. a kind of assembly lattice configuration steel TRD engineering method diaphram wall, including TRD engineering method wall, which is characterized in that the TRD engineering method It is equipped with lattice component within the walls, the lattice component includes narrow wing I-steel and the straight line on the outside of two edges of a wing of narrow wing I-steel Shaped steel plate pile.
2. a kind of assembly lattice configuration steel TRD engineering method diaphram wall according to claim 1, which is characterized in that described straight Line style steel sheet pile both ends are equipped with fore shaft.
3. a kind of assembly lattice configuration steel TRD engineering method diaphram wall according to claim 1, which is characterized in that described narrow It is connected between straight line steel sheet pile on the outside of the adjacent same side wing edge of wing I-steel.
4. a kind of assembly lattice configuration steel TRD engineering method diaphram wall according to claim 2, which is characterized in that described narrow It is connected between straight line steel sheet pile on the outside of the adjacent same side wing edge of wing I-steel by the fore shaft of straight line steel sheet pile.
5. a kind of construction method for assembling lattice configuration steel TRD engineering method diaphram wall according to any one of claims 1 to 4, Characterized by comprising the following steps:
S1, surveying setting-out;
After S2, cell wall reinforce center line setting-out, Reinforcement Measures are carried out to construction site, it is ensured that construction site meets machinery and sets The standby requirement to foundation bearing capacity, it is ensured that the stability of stake machine;
S3, provided box is hung;
S4, stake machine are in place;
S5, cutting box is hung paragraph by paragraph into pre-buried cave with crane, is fixed using supporting table;It sets at TRD host mobility to pre-buried acupuncture point Cutting box is connected, host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth;
S6, it excavates in advance: being injected by mudjack and excavate liquid, cutting box is pushed ahead, and native soil layer, cutting one section of row of grooving are excavated Journey;Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box is withdrawn again to cutting starting point;It is stirred at wall Mix: cutting box withdraw to cutting starting point after exchanges slurries, by mudjack inject solidify liquid, cutting box push ahead and with digging It digs liquid mixing mud to be mixed, forms uniform thickness Soil-cement Wall;
On the outside of S7, narrow two edge of a wing of wing I-steel and straight line shaped steel plate pile smears interleaving agent;
The guide frame and hanging beam that S8, setting lattice configuration steel are inserted into;
Before S9, soil cement are unhardened, by the inclinometer being mounted on inside cutting box, the vertical precision management of wall is carried out, to TRD Soil-cement is vertically vertically inserted into narrow wing I-steel within the walls, is then inserted into straight line on the outside of two edges of a wing of narrow wing I-steel Shape steel plate completes the half side of a rectangular lattice;
Another adjacent rectangular lattice of S10, completion is half side, and the fore shaft of adjacent linear type steel sheet pile is connected together with fore shaft, Form the rectangular lattice unit of assembly;
S11, after stirring at wall, region injection is pulled out with proportion solidify liquid drafting cutting box and rising, side rises and draws out slip casting, to cutting It cuts case to occupy cavity progress dense packing effect and effectively reinforce, terminates straightway wall construction;
Soil excavation in S12, foundation pit completes building underground structure main body construction;
S13, the inside and outside smearing interleaving agent of combination lattice is heated and softened, the guide frame and hanging beam that setting lattice is extracted are extracted The combination lattice of TRD engineering method within the walls, Foundation Pit Construction finish.
6. a kind of construction method for assembling lattice configuration steel TRD engineering method diaphram wall according to claim 4, feature exist In in the step S11, solidify liquid proportion is identical as solidify liquid proportion in step S6.
7. a kind of construction method for assembling lattice configuration steel TRD engineering method diaphram wall according to claim 4, feature exist In in the step S2, Reinforcement Measures include being laid with steel plate to construction site.
CN201811190402.7A 2018-10-12 2018-10-12 Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof Pending CN109403338A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811190402.7A CN109403338A (en) 2018-10-12 2018-10-12 Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811190402.7A CN109403338A (en) 2018-10-12 2018-10-12 Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof

Publications (1)

Publication Number Publication Date
CN109403338A true CN109403338A (en) 2019-03-01

Family

ID=65467798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811190402.7A Pending CN109403338A (en) 2018-10-12 2018-10-12 Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof

Country Status (1)

Country Link
CN (1) CN109403338A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080249A (en) * 2019-06-14 2019-08-02 上海智平基础工程有限公司 A kind of pressure filling formula Diaphragm Wall Support Structure and its construction method
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN111636455A (en) * 2020-05-27 2020-09-08 上海宝冶集团有限公司 Comprehensive construction method of TRD (Top gas recovery device) and rotary drilling lead hole depth waterproof curtain
CN114215070A (en) * 2021-12-23 2022-03-22 浙江省建筑设计研究院 Super-deep TRD (blast furnace direct reduction) wall forming construction method for gravel water-rich stratum based on assembled L-shaped guide wall
CN114837168A (en) * 2022-04-20 2022-08-02 浙江交工集团股份有限公司 Comprehensive pipe gallery enclosure wall and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5568921A (en) * 1978-11-21 1980-05-24 Kajima Corp Construction method of underground continuous wall
CN106049458A (en) * 2016-05-31 2016-10-26 余巍 Underground diaphragm wall structure and construction method thereof
CN106088102A (en) * 2016-06-22 2016-11-09 南京工业大学 Lattice type combined steel sheet pile cement soil composite pile and construction method thereof
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5568921A (en) * 1978-11-21 1980-05-24 Kajima Corp Construction method of underground continuous wall
CN106049458A (en) * 2016-05-31 2016-10-26 余巍 Underground diaphragm wall structure and construction method thereof
CN106088102A (en) * 2016-06-22 2016-11-09 南京工业大学 Lattice type combined steel sheet pile cement soil composite pile and construction method thereof
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
樊洪波: "论述TRD等厚度水泥土搅拌墙工艺技术", 《建筑装饰》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080249A (en) * 2019-06-14 2019-08-02 上海智平基础工程有限公司 A kind of pressure filling formula Diaphragm Wall Support Structure and its construction method
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN111636455A (en) * 2020-05-27 2020-09-08 上海宝冶集团有限公司 Comprehensive construction method of TRD (Top gas recovery device) and rotary drilling lead hole depth waterproof curtain
CN114215070A (en) * 2021-12-23 2022-03-22 浙江省建筑设计研究院 Super-deep TRD (blast furnace direct reduction) wall forming construction method for gravel water-rich stratum based on assembled L-shaped guide wall
CN114837168A (en) * 2022-04-20 2022-08-02 浙江交工集团股份有限公司 Comprehensive pipe gallery enclosure wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN109403338A (en) Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN108589699A (en) A kind of interpolation H profile steel TRD walls and its construction method
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN107905814B (en) Large span loess tunnel top bar CD construction method
CN106522989A (en) Air shaft structure and shield excavation parallel construction method
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN108560536A (en) The continuous piling wall construction method of Soil-cement
CN102953737A (en) Construction method for inverted arch of VI-level water-enriched surrounding rock tunnel
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN110306531A (en) High water level erratic boulder stratum construction of diaphragm wall technique
CN109882185A (en) The construction method in the soft or hard uneven tunnel of rock matter under a kind of large ground pressure
CN109723089A (en) Protect structure and method in a kind of high-tension electricity pipe culvert original place
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN108643167A (en) The slotting shape steel rolled stock type TRD engineering methods wall and its construction method of one type anchor pole
CN108612083A (en) One kind can sealing interpolation S shaped steel TRD walls and its construction method
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN108729919B (en) One kind is rockfilled stratum arc variable cross-section Tunnels in Shallow Buried excavating construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301

RJ01 Rejection of invention patent application after publication