CN105587320B - Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method - Google Patents

Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method Download PDF

Info

Publication number
CN105587320B
CN105587320B CN201610062227.8A CN201610062227A CN105587320B CN 105587320 B CN105587320 B CN 105587320B CN 201610062227 A CN201610062227 A CN 201610062227A CN 105587320 B CN105587320 B CN 105587320B
Authority
CN
China
Prior art keywords
section
shaft structure
abnormal shape
shaft
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610062227.8A
Other languages
Chinese (zh)
Other versions
CN105587320A (en
Inventor
戴志仁
柳兴旺
王立新
王俊
康华
王天明
杨沛敏
杜宇
马晓波
李储军
曹伟
王博
杨小兵
毛念华
张海
罗世明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201610062227.8A priority Critical patent/CN105587320B/en
Publication of CN105587320A publication Critical patent/CN105587320A/en
Application granted granted Critical
Publication of CN105587320B publication Critical patent/CN105587320B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D8/00Shafts not provided for in groups E21D1/00 - E21D7/00
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/06Lining shafts; Linings therefor with iron or steel
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to rich water sand-pebble layer abnormal shape deep shaft structural system and its construction methods.It is influenced by built subway line and surrounding enviroment, conventional rectangle or Circular Shaft sectional form, may be limited by site condition and surrounding enviroment and not perform space.The present invention includes special-shaped deep shaft structure, includes from top to bottom triangular section shaft structure, digs section abnormal shape shaft structure and quadrangular section shaft structure;Triangular section shaft structure horizontal cross-section is triangular in shape, and horizontal cross-section is identical from top to bottom;Quadrangular section shaft structure horizontal cross-section is in quadrangle, and horizontal cross-section is identical from top to bottom;Triangular section shaft structure is extended to quadrangular section shaft structure by digging the transition of section abnormal shape shaft structure.The present invention has the characteristics that floor space is small, inner space is big, structural system transformation is flexible and adapts to all kinds of environmental requirements, meets up-small and down-big requirement, while adapting to surrounding enviroment.

Description

Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
Technical field
The invention belongs to Tunnel Engineering technical fields, and in particular to a kind of rich water sand-pebble layer abnormal shape deep shaft structure System and its construction method.
Background technology
For the railway traffic engineering of current cities in China, with the continuous encryption of subway gauze, follow-up subway line When road is built, influenced by built subway line and surrounding enviroment, in line alignment and paving mode, spatial relationship and structural type Formula and construction method and the requirement of engineering measure etc. are stringenter.Conventional rectangle or Circular Shaft sectional form can It can be limited by site condition and surrounding enviroment and not perform space.
Special-shaped deep shaft has flexible and changeable, adaptable, safe and reliable with the construction method that Tunneling by mining method is combined The features such as.Up-small and down-big cross-sectional configuration pattern is the essential characteristic of special-shaped deep shaft, and vertical shaft digs a section steel tube shed stratum pre-add Gu measure digs the structural stabilities measures such as section shaft wall slope requirement and grid steel frame solid matter, it is to ensure that special-shaped deep shaft The key of successful implementation.
Invention content
The object of the present invention is to provide a kind of rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method, A section steel tube shed stratum pre-reinforcement measure is digged by vertical shaft under complex environment, digs section requirement of shaft wall slope and a grid steel frame The structural stabilities measure such as solid matter, and interim type steel support inside vertical shaft is combined, the transformation for digging segment structure system is realized, it is real The special shaft structure pattern that existing top section is small, lower section is big.
The technical solution adopted in the present invention is:
Rich water sand-pebble layer abnormal shape deep shaft structural system, including special-shaped deep shaft structure, it is characterised in that:
Special-shaped deep shaft structure includes from top to bottom triangular section shaft structure, digs section abnormal shape shaft structure and four sides Shape section shaft structure;
Triangular section shaft structure horizontal cross-section is triangular in shape, and horizontal cross-section is identical from top to bottom;Quadrangular section is perpendicular Well construction horizontal cross-section is in quadrangle, and horizontal cross-section is identical from top to bottom;
Triangular section shaft structure is extended to quadrangular section vertical shaft knot by digging the transition of section abnormal shape shaft structure Structure.
It digs section abnormal shape shaft structure to dig from special-shaped deep shaft structure side, there is vertical shaft to dig inclined-plane, vertical shaft digs The slope on inclined-plane is no more than 1: 0.5.
It digs section abnormal shape shaft structure side and is provided with steel tube shed, oblique lower section is set, and setting is two rows of altogether up and down, is in plum blossom Type is arranged.
The interim type steel support of multiple tracks horizontal direction arrangement is provided in special-shaped deep shaft structure.
The construction method of rich water sand-pebble layer abnormal shape deep shaft structural system, it is characterised in that:
Include the following steps:
Step 1:Carry out dewatering construction, it is ensured that level of ground water 1m below excavation of foundation pit face, according to upside-down well wall approach principle The special-shaped deep shaft structure of construction, implements triangular section shaft structure at first, performs internal interim type steel support in time, special-shaped deep Shaft structure surrounding performs grid steel frame in time, welds guide pipe on last Pin grid steel frame before digging, guide pipe is adopted With 133 steel pipes of Φ, length 0.6m pushes up onto shaft structure face, circular arc is curved with the fixed steel bars of diameter 16mm, by guide pipe It is weldingly fixed on grid steel frame;
Step 2:Will be integrated poured comprising the grid steel frame progress including guide pipe, it performs into and is oriented to wall;
Step 3:Drilling machine job platform height is determined according to steel tube shed size and design hole position height, and brill is filled with the earthwork Machine operation platform carries out daguanpeng construction using down-the-hole drill, and steel tube shed angle with horizontal plane is 30 °, and oblique lower section is set, and is inserted Enter and is oriented to guide pipe pre-buried in wall;Pipe canopy often saves long 2m, is constructed using pipe-following drilling method, and pipe canopy overall length 12m is latent more than stratum In the plane of fracture, after the completion of steel tube shed performs, to pipe canopy internal pressure water filling cement mortar, component entirety bending stiffness is improved;
Step 4:Under the advance support effect of steel tube shed, proceeds by and dig the construction of section abnormal shape shaft structure, it is stringent to control System digs side slope and is no more than 1:0.5, while it is 0.5m that stringent control, which digs section vertical spacing of borehole wall grid steel frame, just starts to expand When digging, upper and lower three Pin grid steel frame solid matters processing;
Step 5:It digs after the completion of section abnormal shape shaft structure performs, carries out quadrangular section shaft structure construction;
Step 6:According to design requirement, special-shaped deep shaft is excavated to designated depth, vertical shaft back cover is completed and constructs, and Vertical shaft back cover quadrangle performs plain concrete.
The present invention has the following advantages:
The interim type steel support and vertical shaft that the present invention is arranged in the steel tube shed and vertical shaft that shaft wall digs section setting The grid steel frame etc. for the closure cyclization being arranged in the borehole wall, steel, cement mortar and the steel tube shed being related to set machinery used Equipment etc. is conventional material(Equipment), corresponding size is general type, manufacture easy to process;And steel tube shed length can basis Stratum source-sink activity is adjusted, and steel tube shed spacing can dig position, formation characteristics and load situation with quantity according to vertical shaft It is adjusted, steel tube shed rigidity can be determined according to the cement mortar grade of inside filling with steel pipe stiffness by itself information summary, be erected Well digs side slope and can be controlled 1 according to stratum stable case:0.3~1:0.5 hereinafter, grid steel frame and interim type steel support cloth Setting can be adjusted flexibly according to vertical shaft base pit stability result of calculation.Pass through the advanced stratum pre-reinforcement measure of steel tube shed, vertical shaft well Wall digs the setting of the control of slope over 10 and the encryption and internal interim type steel support of shaft wall grid steel frame, Ke Yishi The safety for now digging segment structure reduces potential insecurity, reaches that can to meet floor space small, and can meet internal sky Between big shaft structure requirement, the rigors and ground routine rectangle or circle of surrounding enviroment protection can be met Vertical shaft takes up a large area the adverse effect to surrounding enviroment.With higher economic benefit and social benefit, handed in city rail Have wide practical use in the engineerings such as logical, railway, highway.
Description of the drawings
Fig. 1 is special-shaped deep shaft structure section figure.
Fig. 2 is special-shaped deep shaft structural plan figure.
Fig. 3 is that special-shaped deep shaft digs a section pipe canopy detail structure figure(1).
Fig. 4 is that special-shaped deep shaft digs a section pipe canopy detail structure figure(2).
In figure, 1- abnormal shape deep shaft structures, 2- triangular section shaft structures, 3- digs section abnormal shape shaft structure, 4- tetra- Side shape section shaft structure, the interim type steel supports of 5-, 6- steel tube sheds, 7- are oriented to wall, 8- guide pipes, 9- grid steel frames, 10- vertical shafts Dig inclined-plane, 11- vertical shaft back covers, 12- element concretes, 13- fixed steel bars.
Specific implementation mode
The present invention will be described in detail With reference to embodiment.
The present invention provides a kind of novel deep shaft construction concepts, enrich existing Construction of Silo technique, have widened depth Vertical shaft mentality of designing.The design concept being combined with Tunneling by mining method using special-shaped deep shaft can meet specific construction condition To the rigors of engineering proposal, for ensure to realize engineering proposal rationally, engineering risk and the completion time of project is controllable, construction quality with Securely and reliably provide completely new thinking.
Rich water sand-pebble layer abnormal shape deep shaft structural system of the present invention, including special-shaped deep shaft structure 1, it is special-shaped Deep shaft structure 1 includes from top to bottom triangular section shaft structure 2, it is perpendicular to dig section abnormal shape shaft structure 3 and quadrangular section Well construction 4.2 horizontal cross-section of triangular section shaft structure is triangular in shape, and horizontal cross-section is identical from top to bottom;Quadrangular section is perpendicular 4 horizontal cross-section of well construction is in quadrangle, and horizontal cross-section is identical from top to bottom.Triangular section shaft structure 2 is by digging Duan Yi The transition of type shaft structure 3 is extended to quadrangular section shaft structure 4.Special-shaped deep shaft structure 1 is using conventional inverted side-wall Method is constructed, and the stability control that middle section digs section abnormal shape shaft structure 3 is the key point of entire engineering.
It digs section abnormal shape shaft structure 3 to dig from special-shaped 1 side of deep shaft structure, there is vertical shaft to dig inclined-plane 10, vertical shaft The slope for digging inclined-plane 10 is usually no more than 1: 0.5.It digs 3 side of section abnormal shape shaft structure and is provided with steel tube shed 6, obliquely Side is set, and setting is two rows of altogether up and down, is arranged in blossom type.Being horizontally disposed in work progress, in special-shaped deep shaft structure 1 has multiple tracks The interim type steel support of horizontal direction 5.
Before vertical shaft digs, by the stratum for digging 9 solid matter of grid steel frame and the double steel tube shed 6 of blossom type arrangement above section Pre-reinforcement measure, and its bending stiffness is improved in 6 internal pressure cementing mortar of steel tube shed, along with interim type steel support inside vertical shaft 5 common supporting effect, to ensure the monolithic stability of shaft structure.
Before steel tube shed 6 performs, direction and angle requirement is set to ensure that steel tube shed is set, need to implement leading for pipe canopy in advance To wall 7 and guide pipe 8, wherein steel tube shed 6 uses diameter 108mm, and wall thickness 6mm steel floral tubes, setting direction angle with horizontal plane is 30 °, oblique lower section is set, and pipe canopy often saves long 2m, is constructed using pipe-following drilling method, and pipe canopy is always about 12m, while in steel tube shed 6 The cement mortar of pressure injection must have good mobility and workability, it is ensured that filling is closely knit.The intensity and rigidity for being oriented to wall 7 need It disclosure satisfy that the requirement that steel tube shed 6 is set, the beam that sectional dimension is 0.8 × 2.0m can be generally made, using C35 coagulations Soil.Guide pipe 8 uses 133 steel pipes of Φ, length 0.6m to push up onto shaft structure face, circular arc is curved with the reinforcing bar of diameter 16mm, Guide pipe 8 is weldingly fixed on grid steel frame 9.
The length of steel tube shed 6 can be adjusted with angle is set according to stratum source-sink activity, but at least should be more than rupture Face 2m, the slope that vertical shaft digs inclined-plane 10 are no more than 1:0.5, it can be controlled in 1:0.3 or 1:It, specifically can be according to vertical shaft within 0.5 Internal space requirements are adjusted, the main shaft support measure such as grid steel frame 9 and interim type steel support 5, also can be according to stratum Situation and base pit stability result of calculation flexible arrangement.
The construction method of above-mentioned rich water sand-pebble layer abnormal shape deep shaft structural system, includes the following steps:
Step 1:Carry out dewatering construction, it is ensured that level of ground water 1m below excavation of foundation pit face, according to upside-down well wall approach principle The special-shaped deep shaft structure 1 of construction, implements triangular section shaft structure 2, performs inner horizontal in time to interim shaped steel branch at first Support 5, special-shaped 1 surrounding of deep shaft structure performs grid steel frame 9, and guide pipe is welded on last Pin grid steel frame 9 before digging 8, guide pipe 8 uses 133 steel pipes of Φ, length 0.6m to push up onto shaft structure face, curved with the fixed steel bars 13 of diameter 16mm Guide pipe 8 is weldingly fixed on grid steel frame 9 by circular arc;
Step 2:To be carried out comprising the grid steel frame 9 including guide pipe 8 it is integrated poured, perform into be oriented to wall 7;
Step 3:Drilling machine job platform height is determined according to 6 size of steel tube shed and design hole position height, and brill is filled with the earthwork Machine operation platform carries out steel tube shed 6 using down-the-hole drill and constructs, and steel tube shed angle with horizontal plane is 30 °, and oblique lower section is set, It is inserted into the guide pipe 8 being oriented in wall 7;Pipe canopy often saves long 2m, is constructed using pipe-following drilling method, and pipe canopy overall length 12m is latent more than stratum In the plane of fracture, after the completion of steel tube shed 6 performs, to pipe canopy internal pressure water filling cement mortar;
Step 4:Under the advance support effect of steel tube shed 6, proceeds by and dig the construction of section abnormal shape shaft structure 3, strictly Control digs side slope 10 and is no more than 1:0.5, while it is 0.5m that stringent control, which digs 9 vertical spacing of section borehole wall grid steel frame, just When starting to dig, upper and lower three Pin grid steel frames, 9 solid matter processing;
Step 5:It digs after the completion of section abnormal shape shaft structure 3 performs, carries out quadrangular section shaft structure 4 and construct;
Step 6:According to design requirement, special-shaped deep shaft 1 is excavated to designated depth, vertical shaft back cover 11 is completed and constructs, and Plain concrete 12 is performed in vertical shaft back cover for 11 4 jiaos.
The arbitrary cross-section shaft structure and its construction method of various requirement can be adapted to completely by theoretically finding out, existing Theoretical level and construction technology under the conditions of, still have sizable difficulty, because shaft excavation is to surrounding formations in Practical Project Disturbance be inevitable to a certain extent, and foundation pit protection require other than oneself factor, it is also necessary in view of week The different of surrounding environment require, especially close on existing subway station and tunnel, underground commerce synthesis and hospital, school with In the case that object is laid special stress on protecting in laboratory etc., current special-shaped deep shaft structure design and construction, still need to according to " strong supporting, Short drilling depth, few disturbance, with digging with support, first support and dig afterwards " basic principle progress.
Top section that " the special-shaped deep shaft structure " of the present invention refers mainly to dig the formation of section abnormal shape shaft structure 3 is small, under The big special shaft structure pattern in portion section, disclosure satisfy that floor space is small, surrounding enviroment are influenced with controllable basic demand, keeps away Exempt from conventional circular or rectangular section vertical shaft take up a large area, the deficiency of bad adaptability.Wherein, top half triangular-section vertical shaft 2 can determine according to ground surface environment, and lower half portion quadrangular section vertical shaft 4 can be adjusted according to internal space requirements, because greatly Pipe canopy length can according to stratum source-sink activity range respective change, steel tube shed spacing and quantity can be digged according to vertical shaft position, Formation characteristics is adjusted with load situation, and steel tube shed rigidity can be according to the cement mortar grade and steel pipe stiffness by itself feelings of inside filling Condition synthesis determines that vertical shaft digs side slope can be according to stratum stable case 1:0.3~1:0.5 or less range adjusts, grid steel Frame can be adjusted flexibly with interim type steel support arrangement according to vertical shaft base pit stability result of calculation.Pass through the advanced stratum of steel tube shed Pre-reinforcement measure, shaft wall dig the control of slope over 10 and the encryption of shaft wall grid steel frame and internal interim shaped steel The safety for digging segment structure may be implemented in the setting of support, reduces potential insecurity, and floor space can be met by reaching It is small, and the big shaft structure requirement in inner space can be met, the rigors and ground of surrounding enviroment protection can be met Face conventional rectangular or Circular Shaft take up a large area the adverse effect to surrounding enviroment, may be implemented when city underground gauze is first Tool scale, urban rail corridor have already taken up below major urban arterial highway in the case of main space, and newly-built underground engineering remains to adopt With the purpose of vertical shaft+Tunneling by mining method this conventional means implementation.With higher economic benefit and social benefit, in city rail Have wide practical use in the engineerings such as road traffic, railway, highway.
Present disclosure is not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, it is that claim of the invention is covered.

Claims (1)

1. the construction method of rich water sand-pebble layer abnormal shape deep shaft structural system, it is characterised in that:
The rich water sand-pebble layer abnormal shape deep shaft structural system includes special-shaped deep shaft structure(1), special-shaped deep shaft structure (1)Include triangular section shaft structure from top to bottom(2), dig section abnormal shape shaft structure(3)With quadrangular section vertical shaft knot Structure(4);
Triangular section shaft structure(2)Horizontal cross-section is triangular in shape, and horizontal cross-section is identical from top to bottom;Quadrangular section vertical shaft Structure(4)Horizontal cross-section is in quadrangle, and horizontal cross-section is identical from top to bottom;
Triangular section shaft structure(2)By digging section abnormal shape shaft structure(3)Transition, be extended to quadrangular section vertical shaft Structure(4);
Dig section abnormal shape shaft structure(3)From special-shaped deep shaft structure(1)Side digs, and there is vertical shaft to dig inclined-plane(10), erect Well digs inclined-plane(10)Slope be no more than 1: 0.5;
Dig section abnormal shape shaft structure(3)Side is provided with steel tube shed(6), oblique lower section sets, two rows is arranged altogether up and down, are in plum Flower pattern is arranged;
The construction method includes the following steps:
Step 1:Carry out dewatering construction, it is ensured that level of ground water 1m below excavation of foundation pit face constructs according to upside-down well wall approach principle Special-shaped deep shaft structure(1), implement triangular section shaft structure at first(2), internal interim type steel support is performed in time(5), Special-shaped deep shaft structure(1)Surrounding performs grid steel frame in time(9), last Pin grid steel frame before digging(9)Upper welding Guide pipe(8), guide pipe(8)Using 133 steel pipes of Φ, length 0.6m is pushed up onto shaft structure face, with the fixation of diameter 16mm Reinforcing bar(13)Circular arc is curved, by guide pipe(8)It is weldingly fixed on grid steel frame(9)On;
Step 2:It will include guide pipe(8)Grid steel frame inside(9)Carry out it is integrated poured, perform into be oriented to wall(7);
Step 3:According to steel tube shed(6)Size and design hole position height determine drilling machine job platform height, and drilling machine is filled with the earthwork Job platform carries out steel tube shed using down-the-hole drill(6)Construction, steel tube shed angle with horizontal plane are 30 °, and oblique lower section is set, It is inserted into and is oriented to wall(7)In pre-buried guide pipe(8);Pipe canopy often saves long 2m, is constructed using pipe-following drilling method, and pipe canopy overall length 12m surpasses Cross stratum source-sink activity, steel tube shed(6)After the completion of performing, to pipe canopy internal pressure water filling cement mortar, it is rigid to improve component entirety bending resistance Degree;
Step 4:In steel tube shed(6)Advance support effect under, proceed by and dig section abnormal shape shaft structure(3)Construction, will expand It digs side to extend to depth direction and horizontal direction, a line is extended to two sides, stringent control digs side slope(10)Do not surpass Cross 1:0.5, while stringent control digs a section borehole wall grid steel frame(9)Vertical spacing is 0.5m, when just starting to dig, upper and lower three Pin Grid steel frame(9)Solid matter processing;
Step 5:Dig section abnormal shape shaft structure(3)After the completion of performing, quadrangular section shaft structure is carried out(4)Construction;
Step 6:According to design requirement, by special-shaped deep shaft(1)It is excavated to designated depth, completes vertical shaft back cover(11)Construction, and In vertical shaft back cover(11)Quadrangle performs plain concrete(12).
CN201610062227.8A 2016-01-29 2016-01-29 Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method Active CN105587320B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610062227.8A CN105587320B (en) 2016-01-29 2016-01-29 Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610062227.8A CN105587320B (en) 2016-01-29 2016-01-29 Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method

Publications (2)

Publication Number Publication Date
CN105587320A CN105587320A (en) 2016-05-18
CN105587320B true CN105587320B (en) 2018-07-17

Family

ID=55927198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610062227.8A Active CN105587320B (en) 2016-01-29 2016-01-29 Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method

Country Status (1)

Country Link
CN (1) CN105587320B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593450B (en) * 2017-01-13 2018-09-28 沈阳建筑大学 Deep layer tunnel rainwater becomes a mandarin silo system
CN107905817B (en) * 2017-12-01 2023-06-23 中铁第一勘察设计院集团有限公司 Pre-reinforcing system for ground working well advance pipe shed penetrating existing objects in shield region
CN108397197A (en) * 2018-03-05 2018-08-14 中国水利水电第五工程局有限公司 A kind of suppleing level super thick soil property country rock shaft excavation method
CN108643625B (en) * 2018-05-28 2020-02-28 山东科技大学 Urban vertical circulation type underground parking garage building structure and construction method thereof
CN110987335B (en) * 2019-12-20 2021-10-15 防灾科技学院 Method and device for determining position of potential fracture surface of two-stage reinforced soil structure
CN111456737B (en) * 2020-04-13 2021-06-25 中国水利水电建设工程咨询渤海有限公司 Shaft construction method for preventing collapse in construction period under unfavorable geological conditions
CN114183144B (en) * 2021-11-04 2023-06-09 中铁隧道勘测设计院有限公司 Construction method for special-shaped inverted well wall simultaneously built by vertical shaft and thrown-out air well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203499692U (en) * 2013-11-25 2014-03-26 中铁十八局集团有限公司 Special-shaped shaft adopted for subway construction under pipeline conditions
CN203559904U (en) * 2013-07-09 2014-04-23 北京城建设计发展集团股份有限公司 Reinforced supporting structure for creating horsehead on reversal borehole wall shaft well side wall
CN204851266U (en) * 2015-07-28 2015-12-09 中铁十八局集团有限公司 Secretly dig shaft structure directly over station
CN205503131U (en) * 2016-01-29 2016-08-24 中铁第一勘察设计院集团有限公司 Dark shaft structure system of rich water sand cobble stratum abnormal shape

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000104482A (en) * 1998-09-28 2000-04-11 Anezaki Kensetsu:Kk Shaft construction method and earth retaining plate
JP2000230388A (en) * 1999-02-12 2000-08-22 Taisei Corp Construction method of ultra-deep large bore shaft

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203559904U (en) * 2013-07-09 2014-04-23 北京城建设计发展集团股份有限公司 Reinforced supporting structure for creating horsehead on reversal borehole wall shaft well side wall
CN203499692U (en) * 2013-11-25 2014-03-26 中铁十八局集团有限公司 Special-shaped shaft adopted for subway construction under pipeline conditions
CN204851266U (en) * 2015-07-28 2015-12-09 中铁十八局集团有限公司 Secretly dig shaft structure directly over station
CN205503131U (en) * 2016-01-29 2016-08-24 中铁第一勘察设计院集团有限公司 Dark shaft structure system of rich water sand cobble stratum abnormal shape

Also Published As

Publication number Publication date
CN105587320A (en) 2016-05-18

Similar Documents

Publication Publication Date Title
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN106567718B (en) A kind of construction method of compound stratum list arch super-span subway station kerve support replacement
CN205742213U (en) Foundation pit supporting construction
CN108005664A (en) A kind of hole pile construction method of platform structure
CN106703814A (en) Mined metro station hole pile construction method
CN104929648A (en) Method for constructing branch guide pits of tunnels
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN108643231A (en) A kind of inner city subway station half range structure roof cover and cut construction method
CN108412502B (en) A kind of deep tunnel passes through upper-soft lower-hard ground construction method
CN104676110A (en) On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit
CN114016513B (en) Time-sequence-sharing excavation method of complex foundation pit group supporting system
CN110700841B (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN110566223B (en) Deep-buried PBA subway station section design method
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN109403338A (en) Underground continuous wall adopting assembled lattice section steel TRD construction method and construction method thereof
CN111810200B (en) Shield tunnel expanding and excavating system and method based on middle upright post and inverted arch
CN109899087A (en) A kind of hole column tunneling is inverse to build underground structure and construction method
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN114197477B (en) Construction method for zero-distance crossing of high-speed rail viaduct under construction deep foundation pit
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN107489106A (en) A kind of rocky bed subaqueous bearing platform construction method
CN204851266U (en) Secretly dig shaft structure directly over station
CN106013173A (en) Subway station construction body envelop enclosing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant