JPS57155423A - Method of construction of solidification of muddy water - Google Patents
Method of construction of solidification of muddy waterInfo
- Publication number
- JPS57155423A JPS57155423A JP4079581A JP4079581A JPS57155423A JP S57155423 A JPS57155423 A JP S57155423A JP 4079581 A JP4079581 A JP 4079581A JP 4079581 A JP4079581 A JP 4079581A JP S57155423 A JPS57155423 A JP S57155423A
- Authority
- JP
- Japan
- Prior art keywords
- muddy water
- hole
- section
- tremie pipe
- hole bottom
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
Abstract
PURPOSE:To conduct economical execution while forming stratiform cured bodies, strength thereof becomes larger successively toward a hole bottom, by compounding a stabilizing liquid so that low strength is obtained in an upper section and high strength toward a lower section when solidifying the stabilizing liquid in a ditch hole. CONSTITUTION:A tremie pipe 2 is inserted up to the bottom of the ditch hole 1 excavated by using non-curing muddy water 3, selft-curing muddy water 4 for low strength is inserted first through the tremie pipe 2, and the muddy water 3 is moved upward and replaced with the muddy water 4. Self-curing muddy water 5 for high strength is inserted to the hole bottom section through the tremie pipe 2, the muddy water 4, 3 are shifted upward under conditions that they are left as they are, and the hole bottom section is replaced with the muddy water 5. Lastly, mortar or concrete 6 is inserted to the hole bottom section through the tremie pipe 2, the hole bottom section is replaced, and the ditch hole section is foot-protected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4079581A JPS57155423A (en) | 1981-03-20 | 1981-03-20 | Method of construction of solidification of muddy water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4079581A JPS57155423A (en) | 1981-03-20 | 1981-03-20 | Method of construction of solidification of muddy water |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS57155423A true JPS57155423A (en) | 1982-09-25 |
JPS6238486B2 JPS6238486B2 (en) | 1987-08-18 |
Family
ID=12590546
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4079581A Granted JPS57155423A (en) | 1981-03-20 | 1981-03-20 | Method of construction of solidification of muddy water |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS57155423A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60105707A (en) * | 1983-11-14 | 1985-06-11 | Taisei Corp | Construction method for cut-off wall |
JPS61290120A (en) * | 1985-06-17 | 1986-12-20 | Ohbayashigumi Ltd | Construction work of underground continuous wall or in-situ pile |
JP2003041576A (en) * | 2001-07-31 | 2003-02-13 | Ohbayashi Corp | Composite underground continuous wall and construction method of the wall |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5149507A (en) * | 1974-10-28 | 1976-04-28 | Kumagai Gumi Co Ltd | |
JPS5161119A (en) * | 1974-10-26 | 1976-05-27 | Kumagai Gumi Co Ltd | |
JPS543322A (en) * | 1977-06-09 | 1979-01-11 | Mitsui Constr | Method of constructing underground structure |
-
1981
- 1981-03-20 JP JP4079581A patent/JPS57155423A/en active Granted
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5161119A (en) * | 1974-10-26 | 1976-05-27 | Kumagai Gumi Co Ltd | |
JPS5149507A (en) * | 1974-10-28 | 1976-04-28 | Kumagai Gumi Co Ltd | |
JPS543322A (en) * | 1977-06-09 | 1979-01-11 | Mitsui Constr | Method of constructing underground structure |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60105707A (en) * | 1983-11-14 | 1985-06-11 | Taisei Corp | Construction method for cut-off wall |
JPH0258405B2 (en) * | 1983-11-14 | 1990-12-07 | Taisei Corp | |
JPS61290120A (en) * | 1985-06-17 | 1986-12-20 | Ohbayashigumi Ltd | Construction work of underground continuous wall or in-situ pile |
JP2003041576A (en) * | 2001-07-31 | 2003-02-13 | Ohbayashi Corp | Composite underground continuous wall and construction method of the wall |
JP4576768B2 (en) * | 2001-07-31 | 2010-11-10 | 株式会社大林組 | Composite type underground continuous wall and construction method of the same wall |
Also Published As
Publication number | Publication date |
---|---|
JPS6238486B2 (en) | 1987-08-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS57155423A (en) | Method of construction of solidification of muddy water | |
JPS5781530A (en) | Placement work of underwater concrete and form therefor | |
JPS5598520A (en) | Composite grouting method | |
JPS5771923A (en) | Construction work of continuous underground wall | |
JPS53140798A (en) | Precast concrete block and method of building structure thereby | |
JPS5536548A (en) | Construction method for prefabricated concrete retaining-wall and stay rod member | |
JPS5295577A (en) | Solidifying treatment of al elecrolysis waste material | |
JPS56135625A (en) | Construction of underwater structure | |
JPS5552424A (en) | Method of installing underground continuous wall constructing standard pile | |
CN205475280U (en) | Interim dock entrance cofferdam structure convenient to resume | |
JPS5729725A (en) | Pouring method for ground and device thereof | |
JPS56159419A (en) | Continuous underground wall and construction thereof | |
JPS5774427A (en) | Construction method for underground continuous wall | |
JPS56119013A (en) | Hollow fill-type dam | |
JPS55161117A (en) | Constructing method for underground continuous wall by precast concrete member | |
JPS54128486A (en) | Excavation method using stabilizing fluid in engineering fundamental work | |
JPS5761111A (en) | Reduction of extra-banking concrete for head of pile driven in situ | |
JPS5592426A (en) | Construction method employing free slope frame | |
JPS5585717A (en) | Forming method for cut-off membrane to side of cavity of excavated reservoir | |
JPS5634818A (en) | H-section steel sheet pile | |
JPS5568931A (en) | Construction of block piled retaining wall and block | |
JPS57108321A (en) | Construction of foundation for building and structure | |
JPS5327994A (en) | Method of constructing large floating vessel assembly in use of prestressed concrete blocks | |
JPS5592421A (en) | Multi-pouring pipe device and ground pouring method adopting the said device | |
JPS57155424A (en) | Executing method for underground outer wall |