JPS55155825A - Burying method for pile with extension shoe - Google Patents

Burying method for pile with extension shoe

Info

Publication number
JPS55155825A
JPS55155825A JP6451379A JP6451379A JPS55155825A JP S55155825 A JPS55155825 A JP S55155825A JP 6451379 A JP6451379 A JP 6451379A JP 6451379 A JP6451379 A JP 6451379A JP S55155825 A JPS55155825 A JP S55155825A
Authority
JP
Japan
Prior art keywords
pile
rod
hole
extension shoe
driving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6451379A
Other languages
Japanese (ja)
Inventor
Masao Miyake
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MARUGO KISO KOGYO KK
Original Assignee
MARUGO KISO KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MARUGO KISO KOGYO KK filed Critical MARUGO KISO KOGYO KK
Priority to JP6451379A priority Critical patent/JPS55155825A/en
Publication of JPS55155825A publication Critical patent/JPS55155825A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE: To enlarge the pressurized area of the lower part of the pile and to increase the yield strength of the ground by setting the prepared pile on the extension shoe after boring is done and performing the foot protection by using the cement milk of high density.
CONSTITUTION: The extension shoe 2 is engaged rotatably with the lower end of a prepared pile 1 by an engaging means 3, while a rod 4 for driving is inserted and a stirring device 6 for earth and sand at the tip thereof is allowed to pierc and protrude through an inner pipe 24. The cement milk or the like is sent, under pressure, in the water-injecting hole of the rod 4 for driving and gushed out from the tip and the boring is performed by rotating the rod 4. The own weight of the prepared pile 1 is applied to the extension shoe 2 and, through the intermediary thereof, to the stirring device 6, thereby the digging being promoted. After the hole reaches a support layer C, the foot protection is conducted by injecting the cement milk B of high density in the bottom part of a bored hole A. After that, the rod 4 for driving is pulled up together with the stirring device 6 for earth and sand and the aperture between the outer periphery of the pile and the hole is filled up.
COPYRIGHT: (C)1980,JPO&Japio
JP6451379A 1979-05-23 1979-05-23 Burying method for pile with extension shoe Pending JPS55155825A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6451379A JPS55155825A (en) 1979-05-23 1979-05-23 Burying method for pile with extension shoe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6451379A JPS55155825A (en) 1979-05-23 1979-05-23 Burying method for pile with extension shoe

Publications (1)

Publication Number Publication Date
JPS55155825A true JPS55155825A (en) 1980-12-04

Family

ID=13260355

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6451379A Pending JPS55155825A (en) 1979-05-23 1979-05-23 Burying method for pile with extension shoe

Country Status (1)

Country Link
JP (1) JPS55155825A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02243820A (en) * 1988-11-22 1990-09-27 Chunshen Tsuan Reinforcing concrete load bearing pipe having plurality of branches and spread post root part and means for forming pile
CN102226344A (en) * 2011-04-02 2011-10-26 中国石油大学(北京) Pile shoe structure for retractable drilling platforms
CN106149713A (en) * 2016-07-05 2016-11-23 武汉船用机械有限责任公司 A kind of shoe
CN107119679A (en) * 2017-05-23 2017-09-01 中国石油天然气股份有限公司 The jack-up unit shoe of the easy pile pulling of high-bearing capacity and drilling platforms
CN107245993A (en) * 2017-05-23 2017-10-13 中国石油天然气股份有限公司 Platform pile shoe and drilling platforms

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02243820A (en) * 1988-11-22 1990-09-27 Chunshen Tsuan Reinforcing concrete load bearing pipe having plurality of branches and spread post root part and means for forming pile
CN102226344A (en) * 2011-04-02 2011-10-26 中国石油大学(北京) Pile shoe structure for retractable drilling platforms
CN106149713A (en) * 2016-07-05 2016-11-23 武汉船用机械有限责任公司 A kind of shoe
CN106149713B (en) * 2016-07-05 2018-04-27 武汉船用机械有限责任公司 A kind of shoe
CN107119679A (en) * 2017-05-23 2017-09-01 中国石油天然气股份有限公司 The jack-up unit shoe of the easy pile pulling of high-bearing capacity and drilling platforms
CN107245993A (en) * 2017-05-23 2017-10-13 中国石油天然气股份有限公司 Platform pile shoe and drilling platforms
CN107245993B (en) * 2017-05-23 2020-01-07 中国石油天然气股份有限公司 Platform pile shoe and drilling platform

Similar Documents

Publication Publication Date Title
JPS55155825A (en) Burying method for pile with extension shoe
JPS6475715A (en) Soil cement composite pile
JPS5536592A (en) Construction method for cast-in-place differential- diameter pile
JPS56146516A (en) Foundation work and foundation pile
JPS55116923A (en) Method for construction of pile foundation
JPS5673722A (en) Withdrawing work for existing hollow pile
JPS573915A (en) Method and apparatus for construction of reaction resistor body underground
JPS5532848A (en) Grouting method
JPH0372764B2 (en)
JPS6471917A (en) Soil cement composite pile and its construction
JPS5664018A (en) Concrete pile
JPS5829378B2 (en) Anchor construction method
JP2512157B2 (en) Reinforcement method for soft ground
JPS5542990A (en) Burying process for preformed pile
JPS5545910A (en) Pile pulling method
JPS5937400B2 (en) Lock bolt construction method
JPH07216883A (en) Pipe rod process
JPS57174529A (en) Structure of cylinder for underground pile
JPS6448925A (en) Construction of pile
JPH0626036A (en) Concrete pile installation method by inner excavation
JPS5552428A (en) Method of constructing pile foundation
JPS5670325A (en) Burying of prefabricated pile
JPS57216A (en) Internal excavation and foot protection work for pile
JPS56159422A (en) Bury and fixing of concrete pile
JPS6147931B2 (en)