JPH11209027A - Installation method for elevator - Google Patents

Installation method for elevator

Info

Publication number
JPH11209027A
JPH11209027A JP756498A JP756498A JPH11209027A JP H11209027 A JPH11209027 A JP H11209027A JP 756498 A JP756498 A JP 756498A JP 756498 A JP756498 A JP 756498A JP H11209027 A JPH11209027 A JP H11209027A
Authority
JP
Japan
Prior art keywords
tower
car frame
guide rail
hoistway
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP756498A
Other languages
Japanese (ja)
Inventor
Atsushi Nagase
厚史 長瀬
Toshiyuki Tadokoro
俊之 田所
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP756498A priority Critical patent/JPH11209027A/en
Publication of JPH11209027A publication Critical patent/JPH11209027A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/002Mining-hoist operation installing or exchanging guide rails

Abstract

PROBLEM TO BE SOLVED: To improve working efficiency at the time of installing an elevator, and install the elevator in a variety of buildings different in building conditions. SOLUTION: A first stage part 3a of a steel tower 3 and a first stage part 6a of a guide rail 6 are constructed, a second stage part 3b of the steel tower 3 is constructed on the upper part of the first stage part 3a of the steel tower 3 for attaching a second stage part 6b of the guide rail 6 to the second stage part 3b. After a car frame 5 is assembled to attach a car ceiling 12 to the upper part of the car frame 5, a third stage part 3c of the steel tower 3 is connected to an upper part of the second stage part 3b of the steel tower 3 to connect a third stage part 6c of the guide rail 6 to the second stage part 6b of the guide rail 6. After an operator gets on the temporary working floor 13 which is installed on the third stage part 6c to carry out the installation work, the temporary working floor 13 is removed for a time to lift up the car frame 5 by driving of a hoister 8. And then each assembly operation of a fourth stage part 3d of the steel tower 3, a fourth stage part 6d of the guide rail 6 and the like, and the lifting-operation of the car frame 5 are repeated to the top of a hoist way 1 in a similar manner for installing in-hoist way equipment.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、エレベータの据付
方法に係り、特に、昇降路内機器が取付けられる強度部
材を形成する鉄塔を備えた小型エレベータの据付作業を
行なうのに好適なエレベータの据付方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator installation method, and more particularly to an elevator installation suitable for performing an installation operation of a small elevator having a steel tower forming a strength member to which equipment in a hoistway is attached. About the method.

【0002】[0002]

【従来の技術】一般に小型エレベータは、建物自体の強
度がエレベータ全体の荷重を支える程度の強度を期待で
きない小規模住居建物が対象となっている。また、建物
の高さ制限の条件により、巻上機などを設置する機械室
を昇降路上部に設けることができないことが多い。
2. Description of the Related Art Generally, small elevators are intended for small residential buildings in which the strength of the building itself cannot be expected to be strong enough to support the load of the entire elevator. In addition, a machine room for installing a hoist or the like cannot be provided in an upper portion of a hoistway in many cases due to a condition of height restriction of a building.

【0003】そこで従来、例えば特開平8−32491
6号公報に記載されているように、エレベータのかご自
重等の垂直荷重を受ける強度部材を形成する鉄塔を有す
るとともに、昇降路内に巻上機などを設置した構造の小
型エレベータが提案されている。
[0003] Conventionally, for example, Japanese Patent Laid-Open No. 8-32491
As described in Japanese Patent Publication No. 6 (1994), a small elevator having a structure having a steel tower forming a strength member that receives a vertical load such as an elevator car's own weight and having a hoist installed in a hoistway has been proposed. I have.

【0004】このような小型エレベータを据付ける際に
は、最上階の乗場から昇降路内にいわゆる跳ね出し足場
等を組立て、この足場を利用して揚重機を建屋に取付け
て、鉄塔および昇降路機器をそれぞれ揚重して取付けて
いた。
When such a small elevator is installed, a so-called jumping scaffold or the like is assembled from the landing on the top floor into a hoistway, and a hoist is mounted on a building using this scaffold, and a steel tower and a hoistway are installed. Each device was lifted and installed.

【0005】[0005]

【発明が解決しようとする課題】ところで、上述した従
来のエレベータの据付方法では、最上階の乗場から昇降
路内に跳ね出し足場等を組立てるため、仮設材である跳
ね出し足場を運搬して設置する手間がかかるので作業効
率が劣るという問題があった。また、揚重機を建屋に取
付けるため、この建屋側に揚重機を設置可能な程度の強
度を有する必要があり、建屋条件により据付方法を変更
するなど適用範囲が限定されるという問題もあった。
According to the above-described conventional elevator installation method, a bouncing scaffold as a temporary material is transported and installed in order to assemble a bouncing scaffold or the like from the landing on the top floor into the hoistway. The work efficiency is inferior because of troublesome work. Further, in order to mount the lifting machine to the building, it is necessary to have strength enough to install the lifting machine on the building side, and there is also a problem that the application range is limited, such as changing the installation method depending on the building conditions.

【0006】本発明はこのような従来技術における実情
に鑑みてなされたもので、その目的は、エレベータ据付
時の作業効率を向上できるとともに、建屋条件の異なる
種々の建屋にエレベータを据付けることのできるエレベ
ータの据付方法を提供することにある。
SUMMARY OF THE INVENTION The present invention has been made in view of such circumstances in the prior art, and has as its object to improve the work efficiency at the time of elevator installation and to install elevators in various buildings having different building conditions. It is an object of the present invention to provide an elevator installation method which can be performed.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するた
め、本発明の請求項1に係る発明は、昇降路に立設さ
れ、昇降路内機器が取付けられる強度部材を形成する鉄
塔を有し、この鉄塔に、この鉄塔内で昇降するかご枠を
案内するガイドレールが設けられたエレベータの据付方
法において、前記鉄塔の下部を前記昇降路の下部で組立
てて固定し、前記ガイドレールの下部を立設して前記鉄
塔の下部に固定した後、前記ガイドレールの下部にかご
床を係合させた状態で前記かご枠を組立てて、次いで、
このかご枠を足場として、前記鉄塔下部の上方に前記鉄
塔の上部を連結するとともに、前記ガイドレール下部の
上方に前記ガイドレールの上部を連結して前記鉄塔の上
部に固定し、前記かご枠の上方に仮設作業床を設置した
後、この仮設作業床を足場として前記鉄塔上部に揚重機
を設けて、この揚重機の駆動により前記かご枠を上昇さ
せながら前記昇降路内機器を取付け、次いで、前記鉄塔
上部およびガイドレール上部のそれぞれの組立てと前記
かご枠の上昇とを前記昇降路の頂部に至るまで繰り返し
て行なう構成にしてある。
In order to achieve the above object, the invention according to claim 1 of the present invention comprises a steel tower which is erected on a hoistway and forms a strength member to which equipment in the hoistway is attached. The method for installing an elevator provided with a guide rail that guides a car frame that moves up and down in the pylon in the pylon, assembles and fixes a lower part of the pylon at a lower part of the hoistway, and fixes a lower part of the guide rail. After being erected and fixed to the lower part of the tower, the car frame is assembled in a state where the car floor is engaged with the lower part of the guide rail,
Using this car frame as a scaffold, the upper part of the tower is connected above the lower part of the tower, and the upper part of the guide rail is connected above the lower part of the guide rail and fixed to the upper part of the tower. After installing the temporary work floor above, a lifting machine is provided above the steel tower using the temporary work floor as a scaffold, and the equipment in the hoistway is mounted while the car frame is raised by driving the lift machine, The assembling of the upper part of the tower and the upper part of the guide rail and the raising of the car frame are repeated until reaching the top of the hoistway.

【0008】また、上記目的を達成するため、本発明の
請求項2に係る発明は、昇降路に立設され、昇降路内機
器が取付けられる強度部材を形成する鉄塔を有し、この
鉄塔の一部がかご枠を案内するガイドレール部を兼ねる
ようにしたエレベータの据付方法において、前記鉄塔の
下部を前記昇降路の下部で組立てて固定し、前記鉄塔の
下部に含まれるガイドレール部に係合させた状態で前記
かご枠を組立てて、次いで、このかご枠を足場として前
記鉄塔下部の上方に前記鉄塔の上部を連結するととも
に、前記かご枠の上方に仮設作業床を設置した後、この
仮設作業床を足場として前記鉄塔の上部に揚重機を設け
て、この揚重機の駆動により前記かご枠を上昇させなが
ら前記昇降路内機器を取付け、次いで、前記鉄塔上部の
組立てと前記かご枠の上昇とを前記昇降路の頂部に至る
まで繰り返して行なう構成にしてある。
In order to achieve the above object, the invention according to claim 2 of the present invention comprises a steel tower which is erected on a hoistway and forms a strength member to which equipment in the hoistway is attached. In an elevator installation method in which a part also serves as a guide rail for guiding a car frame, a lower part of the tower is assembled and fixed at a lower part of the hoistway, and is engaged with a guide rail part included in a lower part of the tower. Assembling the car frame in the combined state, and then connecting the upper part of the tower above the lower part of the tower using the car frame as a scaffold, and installing a temporary work floor above the car frame, Using a temporary work floor as a scaffold, a hoist is provided at the top of the tower, and the hoist is driven to mount the equipment in the hoistway while raising the car frame. Then, assembling the upper part of the tower and the car frame The rise are the repeatedly performed configuration up to the top of the hoistway.

【0009】上記のように構成した本発明の請求項1,
2に係る発明では、昇降路内機器が取付けられる強度部
材を形成する鉄塔の各部分を昇降路の下方から上方へ積
み重ねながら、前記の鉄塔の各部分に揚重機を設けるよ
うになっているため、この揚重機を建屋に取付ける必要
がなく、建屋条件の異なる種々の建屋にエレベータを据
付けることができる。また、前記の揚重機の駆動により
かご枠を昇降させるとともに、このかご枠の上方に仮設
作業床を設置して、これらのかご枠および仮設作業床の
両方を足場として昇降路の下方から順に作業位置を確保
するので、従来のように昇降路内の上部に跳ね出し足場
を組立てる必要がなくて済み、すなわち、エレベータ据
付時の作業効率を向上できる。
According to the first aspect of the present invention having the above structure,
In the invention according to the second aspect, a hoist is provided at each part of the steel tower while each part of the steel tower forming the strength member to which the equipment in the hoistway is attached is stacked from below to above the hoistway. Therefore, it is not necessary to attach the hoist to the building, and the elevator can be installed in various buildings having different building conditions. In addition, the car frame is moved up and down by driving the above-mentioned lifting machine, and a temporary work floor is installed above the car frame, and work is sequentially performed from below the hoistway using both the car frame and the temporary work floor as scaffolds. Since the position is ensured, it is not necessary to assemble the projecting scaffold at the upper part in the hoistway as in the prior art, that is, the work efficiency at the time of installing the elevator can be improved.

【0010】[0010]

【発明の実施の形態】以下、本発明のエレベータの据付
方法の実施の形態を図に基づいて説明する。図1は本発
明の一実施形態に係るエレベータの据付方法により鉄塔
の2段目を組立てる工程を示す図、図2は本実施形態の
据付方法により鉄塔の3段目を組立てる工程を示す図、
図3は本実施形態の据付方法により鉄塔の4段目を組立
てる工程を示す図、図4は本実施形態の据付方法に用い
られる仮設作業床をガイドレールの3段目まで上昇させ
た状態を示す図、図5は本実施形態の据付方法の作業手
順を示すフローチャートである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of an elevator installation method according to the present invention will be described with reference to the drawings. FIG. 1 is a diagram showing a process of assembling a second stage of a tower by an elevator installation method according to an embodiment of the present invention. FIG. 2 is a diagram showing a process of assembling a third stage of a tower by an installation method of the present embodiment.
FIG. 3 is a view showing a process of assembling the fourth stage of the tower by the installation method of the present embodiment, and FIG. 4 shows a state where the temporary work floor used in the installation method of the present embodiment is raised to the third stage of the guide rail. FIG. 5 and FIG. 5 are flowcharts showing work procedures of the installation method of the present embodiment.

【0011】図1〜図4に示すエレベータでは、昇降路
1の底部に設置したピットベース2上に、エレベータの
垂直荷重を支持する強度部材を形成する鉄塔3が立設さ
れ、この鉄塔3は、昇降路1壁に図示しないブラケット
を介して固定されており、例えば地震時の横方向の荷重
を支持する構造となっている。この鉄塔3を大きく分け
ると、昇降路1の下部に位置する下部と、この鉄塔3の
下部の上方に位置する上部とからなっている。さらに、
上述した鉄塔3の下部は、1段目3aおよび2段目3b
と、この1段目3aおよび2段目3bをそれぞれ連結す
る梁4a、4bとから構成され、上述した鉄塔3の上部
は、3段目3c、4段目3dおよび図示しない上段鉄塔
と、3段目3c、4段目3dおよび図示しない上段鉄塔
をそれぞれ連結する梁4cなどとから構成されている。
In the elevator shown in FIGS. 1 to 4, a steel tower 3 forming a strength member for supporting a vertical load of the elevator is erected on a pit base 2 installed at the bottom of the hoistway 1. Is fixed to the wall of the hoistway 1 via a bracket (not shown), and has a structure for supporting a lateral load during an earthquake, for example. The tower 3 is roughly divided into a lower part located below the hoistway 1 and an upper part located above the lower part of the tower 3. further,
The lower part of the above-mentioned steel tower 3 has a first stage 3a and a second stage 3b.
And beams 4a and 4b connecting the first stage 3a and the second stage 3b, respectively. The upper part of the above-mentioned steel tower 3 is provided with a third stage 3c, a fourth stage 3d and an upper steel tower (not shown). It is composed of a stage 3c, a stage 3d, and a beam 4c for connecting the upper tower (not shown).

【0012】また、上記の示すエレベータは、鉄塔3内
を昇降するかご枠5を有し、このかご枠5を案内するガ
イドレール6が鉄塔3に取付けられている。このガイド
レール6を大きく分けると、昇降路1の下部に位置する
下部と、このガイドレール6の下部の上方に位置する上
部とからなっている。さらに、上述したガイドレール6
の下部は、梁4aを介して鉄塔3の1段目3aに固定さ
れる1段目6aと、梁4bを介して鉄塔3の2段目3b
に固定される2段目6bとから構成され、上述したガイ
ドレール6の上部は、梁4cを介して鉄塔3の3段目3
cに固定される3段目6cと、前記の梁4cを介して鉄
塔3の4段目3dに固定される4段目6dと、図示しな
い梁を介してそれぞれ鉄塔3の上段に固定される上段レ
ールとから構成されている。
Further, the elevator shown above has a car frame 5 which moves up and down inside the steel tower 3, and a guide rail 6 for guiding the car frame 5 is attached to the steel tower 3. The guide rail 6 is roughly divided into a lower part located at the lower part of the hoistway 1 and an upper part located above the lower part of the guide rail 6. Further, the above-described guide rail 6
The lower part of the first stage 6a is fixed to the first stage 3a of the tower 3 via the beam 4a, and the second stage 3b of the tower 3 is
The upper part of the above-mentioned guide rail 6 is connected to the third stage 3 of the steel tower 3 via the beam 4c.
c, the fourth stage 6d fixed to the fourth stage 3d of the steel tower 3 via the beam 4c, and the upper stage of the steel tower 3 via the beam (not shown). It consists of an upper rail.

【0013】そして、本実施形態の据付方法によりエレ
ベータ据付を行なう際には、かご枠5のかご床5aの下
部にプーリ7が設けられ、かご床5aより上方の位置、
例えば梁4b、4cなどに、ワイヤロープ9を介してか
ご枠5を吊上げる揚重機8と、ワイヤロープ9の先端1
0とがそれぞれ設けられている。ワイヤロープ9の中間
部は、前記のプーリ7に巻掛けられるとともに、かご枠
5は、ガイドレール6に係合するストッパ11により支
持可能である。さらに、かご枠5の上部に本設のかご天
井12が設けられるとともに、このかご天井12の上方
に仮設作業床13が設けられている。
When the elevator is installed by the installation method of the present embodiment, a pulley 7 is provided below the car floor 5a of the car frame 5, and a position above the car floor 5a,
For example, a hoist 8 that lifts the car frame 5 on the beams 4b and 4c via the wire rope 9, and a tip 1 of the wire rope 9
0 is provided respectively. An intermediate portion of the wire rope 9 is wound around the pulley 7, and the car frame 5 can be supported by a stopper 11 that engages with the guide rail 6. Further, a permanent car ceiling 12 is provided above the car frame 5, and a temporary work floor 13 is provided above the car ceiling 12.

【0014】この実施形態の据付方法にあっては、図5
に示す作業手順にしたがってエレベータ据付を行なうよ
うになっている。すなわち、まず手順S1として、図1
に示すように昇降路1の底部にピットベース2を設置
し、このピットベース2上に鉄塔3の1段目3aを組立
てて梁4aにより固定した後、ガイドレール6の1段目
6aを立設して前記の梁4aに固定し、手順S2とし
て、鉄塔3の1段目3aの上方に2段目3bを連結する
とともに、ガイドレール6の1段目6a上に2段目6b
を連結する。次いで、手順S3として、ガイドレール6
の1段目6aにストッパ11を係合させて、このストッ
パ11上で、ガイドレール6に係合させた状態でかご枠
5を組立て、手順S4として、かご枠5のかご床5aに
作業者が乗り込んでかご枠5の上部にかご天井12を取
付ける。
In the installation method of this embodiment, FIG.
The elevator installation is performed according to the operation procedure shown in FIG. That is, first, as a procedure S1, FIG.
The pit base 2 is installed at the bottom of the hoistway 1 as shown in FIG. 1 and the first step 3a of the steel tower 3 is assembled on the pit base 2 and fixed by the beam 4a, and then the first step 6a of the guide rail 6 is set up. In step S2, a second stage 3b is connected above the first stage 3a of the steel tower 3 and a second stage 6b is mounted on the first stage 6a of the guide rail 6.
Concatenate. Next, in step S3, guide rail 6
The stopper 11 is engaged with the first stage 6a, and the car frame 5 is assembled on the stopper 11 while being engaged with the guide rail 6, and as a step S4, the worker is mounted on the car floor 5a of the car frame 5. Gets on the car ceiling 12 above the car frame 5.

【0015】次いで手順S5として、前記のかご天井1
2上に作業者が乗込んで、図2に示すように鉄塔3の2
段目3bの上端を梁4bにより固定し、この梁4bにガ
イドレール6の2段目6bの上端を固定するとともに、
鉄塔3の2段目3bの上方に3段目3cを連結してガイ
ドレール6の2段目6b上に3段目6cを連結した後、
手順S6として、図示しないレールクリップまたはボル
トを介してガイドレール6の3段目6cに仮設作業床1
3を取付ける。
Next, in step S5, the car ceiling 1
An operator gets on board 2 and, as shown in FIG.
The upper end of the step 3b is fixed by the beam 4b, and the upper end of the second step 6b of the guide rail 6 is fixed to the beam 4b.
After connecting the third step 3c above the second step 3b of the steel tower 3 and connecting the third step 6c on the second step 6b of the guide rail 6,
In step S6, the temporary work floor 1 is attached to the third step 6c of the guide rail 6 via a rail clip or bolt (not shown).
3 Install.

【0016】次いで手順S7として、仮設作業床13上
に作業者が乗り込んで、図3に示すように鉄塔3の3段
目3cの上端を梁4cにより連結するとともに、この梁
4cにガイドレール6の3段目6cの上端を固定した
後、仮設作業床13を一旦、取外す。手順S8として、
梁4cより揚重機8を吊下げて、ワイヤロープ9の中間
部をかご床5a下のプーリ7に巻掛けてワイヤロープ9
の先端10を梁4cに支持し、この状態で揚重機8の駆
動によりかご枠5を図4に示す高さ位置まで上昇させた
後、ガイドレール6に係合するストッパ11によりかご
枠5を支持する。
Next, in step S7, an operator gets on the temporary work floor 13, connects the upper end of the third stage 3c of the steel tower 3 with the beam 4c as shown in FIG. After fixing the upper end of the third stage 6c, the temporary work floor 13 is once removed. As step S8,
The lifting machine 8 is hung from the beam 4c, and the intermediate part of the wire rope 9 is wound around the pulley 7 under the car floor 5a, and the wire rope 9
Of the car frame 5 is supported by the beam 4c. In this state, the car frame 5 is raised to the height position shown in FIG. To support.

【0017】次いで手順S9として、同様の手順で鉄塔
3の4段目3dおよびガイドレール6の4段目6dなど
のそれぞれの組立てとかご枠5の上昇とを昇降路1の頂
部に至るまで繰り返して昇降路内機器を据付けることに
よりエレベータ据付作業が完了する。
Next, in step S9, the assembling of the fourth stage 3d of the tower 3 and the fourth stage 6d of the guide rail 6 and the raising of the car frame 5 are repeated in the same manner until the top of the hoistway 1 is reached. The elevator installation work is completed by installing the equipment in the hoistway.

【0018】このように構成した実施形態では、昇降路
内機器が取付けられる強度部材を形成する鉄塔3の1段
目3a、2段目3b、3段目3c、4段目3dなど各部
分を昇降路1の下方から上方へ順次積み重ねるととも
に、この鉄塔3の各部分に揚重機8を設けるようになっ
ているため、この揚重機8を建屋に取付ける必要がなく
て済み、建屋条件の異なる種々の建屋にエレベータを据
付けることができる。
In the embodiment constructed as described above, each part such as the first stage 3a, the second stage 3b, the third stage 3c, the fourth stage 3d of the steel tower 3 forming the strength member to which the equipment in the hoistway is attached is formed. Since the hoistway 1 is sequentially stacked from the lower side to the upper side, and the hoisting machine 8 is provided at each part of the steel tower 3, it is not necessary to attach the hoisting machine 8 to a building. The elevator can be installed in the building.

【0019】また、本実施形態では、前記の揚重機8の
駆動によりかご枠5を昇降させて、このかご枠5を足場
として昇降路1の下方から順に作業位置を確保するの
で、従来のように昇降路1内の上部に跳ね出し足場を組
立てる必要がなくて済み、エレベータ据付時の作業効率
を向上できる。
In the present embodiment, the car frame 5 is moved up and down by driving the above-mentioned lifting machine 8, and the car frame 5 is used as a foothold to secure the working position in order from below the hoistway 1. Therefore, it is not necessary to assemble a scaffold that projects from the upper part in the hoistway 1, thereby improving the work efficiency when installing the elevator.

【0020】また、本実施形態では、ガイドレール6の
各部分に簡易的に取付け可能な仮設作業床13で作業位
置を確保することにより鉄塔3およびガイドレール6を
複数本連結でき、これにより、揚重機13によるかご枠
5の昇降行程を延長できるので、揚重機13の設置位置
の取替え回数を少なくすることができる。
Further, in this embodiment, a plurality of steel towers 3 and guide rails 6 can be connected by securing a work position on a temporary work floor 13 which can be easily attached to each part of the guide rails 6. Since the lifting process of the car frame 5 by the hoist 13 can be extended, the number of times of changing the installation position of the hoist 13 can be reduced.

【0021】なお、本実施形態にあっては、昇降路1に
立設した鉄塔3にガイドレール6を取付ける構成のエレ
ベータに関して説明したが、鉄塔の一部がかご枠を案内
するガイドレール部を兼ねるようにしたエレベータにお
いても、昇降路内に鉄塔の各部分を下方から上方へ順次
積み重ねるとともに、この鉄塔の各部分に揚重機を設け
てかご枠を上昇させながら、このかご枠を足場として昇
降路内機器を下方から上方へ順次据付けることにより同
様の効果が得られる。
In this embodiment, the description has been given of the elevator in which the guide rail 6 is mounted on the tower 3 erected in the hoistway 1. However, a part of the tower forms a guide rail portion for guiding the car frame. In an elevator that is also used as an elevator, each part of the tower is sequentially stacked from the bottom up in the hoistway, and a hoist is installed at each part of this tower, and the car frame is raised while the car frame is used as a foothold. A similar effect can be obtained by sequentially installing the devices in the road from below to above.

【0022】さらに、本実施形態にあっては、かご床5
a下のプーリ7に揚重機8のワイヤロープ9を巻掛けて
かご枠5を昇降させるようにしたが、かご床5aの上部
にプーリを取付けて、このプーリに揚重機8のワイヤロ
ープ9を巻掛けてかご枠5を昇降させることもできる。
Further, in the present embodiment, the car floor 5
The wire rope 9 of the hoist 8 is wound around the lower pulley 7 to raise and lower the car frame 5, but a pulley is mounted on the upper part of the car floor 5a, and the wire rope 9 of the hoist 8 is attached to this pulley. The car frame 5 can be raised and lowered by winding.

【0023】さらに、本実施形態では、かご枠5の上方
に1つの仮設作業床13を取付けるようにしたが、昇降
路1の行程に応じて複数個の仮設作業床を設けることも
できる。
Further, in this embodiment, one temporary work floor 13 is mounted above the car frame 5, but a plurality of temporary work floors can be provided according to the stroke of the hoistway 1.

【0024】[0024]

【発明の効果】以上説明したように、本発明の請求項
1,2に係る発明によれば、従来のように揚重機を建屋
に取付けることや、いわゆる跳ね出し足場を昇降路上部
に仮設することを要せずに、エレベータ据付作業を行な
える。したがって、エレベータ据付時の作業効率を向上
できるため、作業コストを抑制できるとともに、建屋条
件の異なる種々の建屋にエレベータを据付けできるた
め、汎用性に富むエレベータの据付方法が得られるとい
う効果がある。
As described above, according to the first and second aspects of the present invention, a lifting machine is attached to a building as in the prior art, and a so-called jumping scaffold is temporarily installed at the upper part of a hoistway. Elevator installation work can be performed without the need. Therefore, since the working efficiency at the time of installing the elevator can be improved, the working cost can be suppressed, and the elevator can be installed in various buildings having different building conditions, so that there is an effect that a method for installing the elevator with high versatility can be obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態に係るエレベータの据付方
法により鉄塔の2段目を組立てる工程を示す図である。
FIG. 1 is a view showing a process of assembling a second stage of a steel tower by an elevator installation method according to an embodiment of the present invention.

【図2】本実施形態の据付方法により鉄塔の3段目を組
立てる工程を示す図である。
FIG. 2 is a diagram showing a process of assembling a third stage of a steel tower by the installation method of the present embodiment.

【図3】本実施形態の据付方法により鉄塔の4段目を組
立てる工程を示す図である。
FIG. 3 is a diagram showing a process of assembling a fourth stage of a steel tower by the installation method of the present embodiment.

【図4】本実施形態の据付方法に用いられる仮設作業床
をガイドレールの3段目まで上昇させた状態を示す図で
ある。
FIG. 4 is a diagram showing a state in which a temporary work floor used in the installation method of the present embodiment has been raised to the third stage of the guide rail.

【図5】本実施形態の据付方法の作業手順を示すフロー
チャートである。
FIG. 5 is a flowchart showing a work procedure of the installation method of the embodiment.

【符号の説明】[Explanation of symbols]

1 昇降路 3 鉄塔 3a 1段目 3b 2段目 3c 3段目 3d 4段目 5 かご枠 5a かご床 6 ガイドレール 6a 1段目 6b 2段目 6c 3段目 6d 4段目 7 プーリ 8 揚重機 9 ワイヤロープ 11 ストッパ 12 かご天井 13 仮設作業床 DESCRIPTION OF SYMBOLS 1 Hoistway 3 Steel tower 3a 1st stage 3b 2nd stage 3c 3rd stage 3d 4th stage 5 Car frame 5a Car floor 6 Guide rail 6a 1st stage 6b 2nd stage 6c 3rd stage 6d 4th stage 7 Pulley 8 Lifting Heavy equipment 9 Wire rope 11 Stopper 12 Car ceiling 13 Temporary work floor

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 昇降路に立設され、昇降路内機器が取付
けられる強度部材を形成する鉄塔を有し、この鉄塔に、
この鉄塔内で昇降するかご枠を案内するガイドレールが
設けられたエレベータの据付方法において、 前記鉄塔の下部を前記昇降路の下部で組立てて固定し、
前記ガイドレールの下部を立設して前記鉄塔の下部に固
定した後、前記ガイドレールの下部にかご床を係合させ
た状態で前記かご枠を組立てて、次いで、このかご枠を
足場として、前記鉄塔下部の上方に前記鉄塔の上部を連
結するとともに、前記ガイドレール下部の上方に前記ガ
イドレールの上部を連結して前記鉄塔の上部に固定し、
前記かご枠の上方に仮設作業床を設置した後、この仮設
作業床を足場として前記鉄塔上部に揚重機を設けて、こ
の揚重機の駆動により前記かご枠を上昇させながら前記
昇降路内機器を取付け、次いで、前記鉄塔上部およびガ
イドレール上部のそれぞれの組立てと前記かご枠の上昇
とを前記昇降路の頂部に至るまで繰り返して行なうこと
を特徴とするエレベータの据付方法。
Claims: 1. A steel tower, which is erected on a hoistway and forms a strength member to which equipment in the hoistway is attached,
In an elevator installation method provided with a guide rail that guides a car frame that moves up and down in a tower, the lower part of the tower is assembled and fixed at the lower part of the hoistway,
After the lower part of the guide rail is erected and fixed to the lower part of the tower, the car frame is assembled in a state where the car floor is engaged with the lower part of the guide rail, and then the car frame is used as a scaffold, Connecting the upper part of the tower above the lower part of the tower, connecting the upper part of the guide rail above the lower part of the guide rail, and fixing the upper part of the tower,
After installing the temporary work floor above the car frame, a lifting machine is provided above the steel tower using the temporary work floor as a scaffold, and the equipment in the hoistway is raised while driving the car frame by driving the lift machine. A method of installing an elevator, comprising: repeatedly mounting and then assembling the upper part of the tower and the upper part of the guide rail and raising the car frame up to the top of the hoistway.
【請求項2】 昇降路に立設され、昇降路内機器が取付
けられる強度部材を形成する鉄塔を有し、この鉄塔の一
部がかご枠を案内するガイドレール部を兼ねるようにし
たエレベータの据付方法において、 前記鉄塔の下部を前記昇降路の下部で組立てて固定し、
前記鉄塔の下部に含まれるガイドレール部に係合させた
状態で前記かご枠を組立てて、次いで、このかご枠を足
場として前記鉄塔下部の上方に前記鉄塔の上部を連結す
るとともに、前記かご枠の上方に仮設作業床を設置した
後、この仮設作業床を足場として前記鉄塔の上部に揚重
機を設けて、この揚重機の駆動により前記かご枠を上昇
させながら前記昇降路内機器を取付け、次いで、前記鉄
塔上部の組立てと前記かご枠の上昇とを前記昇降路の頂
部に至るまで繰り返して行なうことを特徴とするエレベ
ータの据付方法。
2. An elevator according to claim 1, further comprising a steel tower which is erected on the hoistway and forms a strength member to which equipment in the hoistway is attached, and a part of the steel tower also serves as a guide rail for guiding the car frame. In the installation method, the lower part of the tower is assembled and fixed at the lower part of the hoistway,
Assembling the car frame in a state where the car frame is engaged with the guide rail portion included in the lower part of the tower, and then connecting the upper part of the tower above the lower part of the tower using the car frame as a scaffold, After installing the temporary work floor above, a lifting machine is provided at the top of the steel tower using the temporary work floor as a scaffold, and the hoistway equipment is mounted while the car frame is raised by driving the lift machine, Next, the assembling method of the elevator, wherein the assembling of the upper part of the tower and the raising of the car frame are repeatedly performed until reaching the top of the hoistway.
【請求項3】 前記かご枠の上部にかご天井を組立てた
後、このかご天井を足場としてかご天井の上方に前記仮
設作業床を設置するようにしたことを特徴とする請求項
1または2記載のエレベータの据付方法。
3. The temporary work floor is installed above the car ceiling using the car ceiling as a foothold after assembling the car ceiling on the upper part of the car frame. Elevator installation method.
JP756498A 1998-01-19 1998-01-19 Installation method for elevator Pending JPH11209027A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP756498A JPH11209027A (en) 1998-01-19 1998-01-19 Installation method for elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP756498A JPH11209027A (en) 1998-01-19 1998-01-19 Installation method for elevator

Publications (1)

Publication Number Publication Date
JPH11209027A true JPH11209027A (en) 1999-08-03

Family

ID=11669306

Family Applications (1)

Application Number Title Priority Date Filing Date
JP756498A Pending JPH11209027A (en) 1998-01-19 1998-01-19 Installation method for elevator

Country Status (1)

Country Link
JP (1) JPH11209027A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001044096A1 (en) * 1999-12-06 2001-06-21 Otis S.P.A. Method for installing elevators
KR20020078342A (en) * 2001-04-09 2002-10-18 주식회사 새한산업 Car for elevator rail equipment
NL2007277C2 (en) * 2011-08-18 2013-02-19 Reco Special Products B V A method for assembling a modular lift apparatus, a method for de-assembling a modular lift apparatus, and a modular lift apparatus.

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001044096A1 (en) * 1999-12-06 2001-06-21 Otis S.P.A. Method for installing elevators
KR20020078342A (en) * 2001-04-09 2002-10-18 주식회사 새한산업 Car for elevator rail equipment
NL2007277C2 (en) * 2011-08-18 2013-02-19 Reco Special Products B V A method for assembling a modular lift apparatus, a method for de-assembling a modular lift apparatus, and a modular lift apparatus.
EP2559647A1 (en) 2011-08-18 2013-02-20 Reco Special Products B.V. A method for assembling a modular lift apparatus, a method for de-assembling a modular lift apparatus, and a modular lift apparatus

Similar Documents

Publication Publication Date Title
JPH07100582B2 (en) Elevator work platform and elevator installation method
JP6813123B2 (en) How to apply elevator lift extension technology
JP2018070362A (en) Elevator installation method
JPH11209027A (en) Installation method for elevator
JP3348018B2 (en) Elevator installation method
JPH11209026A (en) Installation method for elevator
JP2000226169A (en) Elevator erection method
JP3193609B2 (en) Elevator installation method
JP3301923B2 (en) Elevator work scaffolding equipment
JP2001335255A (en) Elevator installation construction method, and elevator installation unit
JP3519009B2 (en) Elevator installation method
JP2000335847A (en) Elevator installation device
JP4125027B2 (en) Load receiving bracket
JP3630596B2 (en) How to hang an elevator rope
JP3920527B2 (en) Elevator for construction
JP2001072354A5 (en)
CN113753716B (en) Method for installing guide rail of elevator arraying crane with machine room
JP2877593B2 (en) Elevator installation method
JP2002060158A (en) Installation method for elevator
JP2004189367A (en) Installation method of elevator
JP2005231780A (en) Elevator device, and installation method therefor
JP2939064B2 (en) Elevator installation template
JP3347968B2 (en) Hydraulic elevator installation method
JPH05201648A (en) Installation of elevator
JP2000063055A (en) Elevator installation construction