JPH09296415A - Balustrade for concrete wall and road side wall - Google Patents
Balustrade for concrete wall and road side wallInfo
- Publication number
- JPH09296415A JPH09296415A JP10989596A JP10989596A JPH09296415A JP H09296415 A JPH09296415 A JP H09296415A JP 10989596 A JP10989596 A JP 10989596A JP 10989596 A JP10989596 A JP 10989596A JP H09296415 A JPH09296415 A JP H09296415A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- insertion hole
- wall body
- road
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F15/00—Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
- E01F15/02—Continuous barriers extending along roads or between traffic lanes
- E01F15/04—Continuous barriers extending along roads or between traffic lanes essentially made of longitudinal beams or rigid strips supported above ground at spaced points
- E01F15/0476—Foundations
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、橋梁や道路に設け
られるコンクリート製壁高欄及び路側壁に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete wall balustrade and a road side wall provided on a bridge or a road.
【0002】[0002]
【発明が解決しようとする課題】ガードフェンスは、主
として走行車線を逸脱した車両が道路外あるいは対向車
線に逸脱することを防止するために設けられるものであ
り、十分な逸脱防止効果を備えていなければならない。
また、ブレーキトラブルなどの緊急事態においては、車
両をフェンスに擦りつけるようにして緊急停止するため
にも用いられ、十分な安定性と衝撃強度が要求される。
さらに、車両をスムーズに車線復帰させることも要求さ
れる。そして、従来の鋼製ガードフェンスに代わって強
度及び耐久性に優れたコンクリートガードフェンスが広
く用いられるようになっており、例えば、実開平2−1
1821号公報(実願昭63−88799号)では、防
護壁本体の両側下部に定着手段を設け、この定着手段を
介して路盤に固定する(同マイクロフィルム第7頁第3
〜4行)コンクリート防護壁が知られており、また、コ
ンクリートガードフェンスの強度を向上するものとし
て、実開平6−57918号公報(実願平5−1258
号)のコンクリートガードフェンスでは、ガードフェン
スの上部には塩ビ製のパイプが埋設され、このパイプに
横締用部材であるPC鋼材が挿通され(実願平5−12
58号のマイクロフィルムの第0011段)、そのPC
鋼材によりコンクリートガードフェンスに緊張力を付与
したコンクリートガードフェンスが知られており、この
コンクリートガードフェンスは、両側下部に設けた取付
用パイプに、アンカーボルトを挿通してコンクリート基
礎に固定(同第0013段)し、また、ガードフェンス
の幅方向両側をアンカーボルトにより基礎に固定してい
る。さらに、特公平6−29492号公報では、防護壁
ブロックの幅方向両側に側方に突出する脚部を形成し、
この脚部にアンカー受穴を設け、アンカーボルト受穴と
アンカーボルト固定ナットとの間に弾性体を挟み込んだ
ものが提案されている。The guard fence is provided mainly to prevent a vehicle deviating from the driving lane from departing from the road or into an oncoming lane, and must have a sufficient deviation preventing effect. I have to.
Further, in an emergency situation such as a brake trouble, it is also used for making an emergency stop by rubbing the vehicle against a fence, and sufficient stability and impact strength are required.
Further, it is required to smoothly return the vehicle to the lane. Further, concrete guard fences having excellent strength and durability have been widely used in place of the conventional steel guard fences.
In Japanese Patent No. 1821 (Jpn. Pat. Appln. No. 63-88799), fixing means are provided on the lower portions of both sides of the protective wall body, and the fixing means is fixed to the roadbed through the fixing means (the same microfilm, p.
(4 lines) A concrete protective wall is known, and as a means for improving the strength of a concrete guard fence, Japanese Utility Model Publication No. 6-57918 (Publication No. 5-1258).
No.) concrete guard fence, a pipe made of PVC is embedded in the upper part of the guard fence, and a PC steel material, which is a lateral fastening member, is inserted into the pipe (Practical application 5-12).
No. 58 microfilm stage 0011), its PC
A concrete guard fence in which tension is applied to the concrete guard fence with steel is known, and this concrete guard fence is fixed to a concrete foundation by inserting anchor bolts into mounting pipes provided on the lower parts of both sides (the same number 0013). Also, both sides in the width direction of the guard fence are fixed to the foundation with anchor bolts. Further, in Japanese Patent Publication No. 6-29492, leg portions protruding laterally are formed on both sides in the width direction of the protective wall block,
It is proposed that an anchor receiving hole is provided in this leg portion and an elastic body is sandwiched between the anchor bolt receiving hole and the anchor bolt fixing nut.
【0003】ところで、上記コンクリート防護壁では、
幅方向両側を定着手段により路盤に固定し、また、上記
コンクリートガードフェンス及び防護壁ブロックでは、
幅方向両側をアンカーボルトにより基礎に固定するもの
であるため、幅方向の一方を固定することができない場
所、例えば道路等の端部の路肩などの取付スペースに制
約のある場所や、橋梁等の端部の高欄等の代わりに使用
することができない。また、施工の手順において、路面
にアンカーボルトを固定した後、ガードフェンスを吊り
下ろして布設する場合、両側のアンカーボルトをアンカ
ー受穴等に合わせる作業が煩雑になることが予想され
る。By the way, in the above concrete protective wall,
Both sides in the width direction are fixed to the roadbed by fixing means, and in the concrete guard fence and the protection wall block,
Since both sides in the width direction are fixed to the foundation with anchor bolts, it is not possible to fix one side in the width direction, for example, where there is a restriction on the installation space such as the road shoulder at the end of the road, bridges, etc. It cannot be used in place of a balustrade on the edge. Further, in the construction procedure, when anchor bolts are fixed to the road surface and then the guard fence is hung and installed, it is expected that the work of aligning the anchor bolts on both sides with the anchor receiving holes will be complicated.
【0004】そこで、アンカーボルトを用いるものとは
異なるが、実開昭58−171914号公報(実願昭5
8−37009号)には、高速道路の欄干用ガードフェ
ンス(実願昭58−37009号のマイクロフィルムの
第12頁第9〜10行)が提案されており、同第4図に示さ
れているように、防護壁の幅方向中央に孔を穿設し、こ
の孔と舗装路面とに縦方向の棒状部材を挿通し、その棒
状部材の上,下端を防護壁内部と舗装路面下面とに固定
して、防護壁を舗装路面に固定するため、取付作業が煩
雑になると共に費用がかかるという問題があり、また、
前記棒状部材の下端を舗装路面下面で固定するため、普
通の道路や盛土の上部に形成した道路の端部では使用す
ることができない。しかも、それらのものはいずれもガ
ードフェンスを路盤に剛結するものであるから、例え
ば、図13に示すように、橋梁等の長さ方向の桁101 の
上にコンクリート床版102 を設け、このコンクリート床
版102 の上面により路面103 を構成し、この路面103 の
端部に欄干としてガードフェンス104 を設け、このガー
ドフェンス104 を縦方向の鋼材105 ,105 等により一体
に剛結してしまうと、そのガードフェンス104 への車両
の衝突によるモーメントが、桁102 上部の路面103 に集
中し、ここに亀裂Kが生じる等の虞があり、同時に衝突
車両の衝撃も大となる。Therefore, although different from the one using anchor bolts, Japanese Utility Model Publication No. 58-171914 (Japanese Utility Model Application No. 5).
No. 8-37009), a guard fence for parapets on expressways (Microfilm of Japanese Patent Application No. 58-37009, page 12, lines 9-10) is proposed and shown in FIG. As shown in the figure, a hole is made in the center of the protective wall in the width direction, and a vertical rod-shaped member is inserted into this hole and the paved road surface. The upper and lower ends of the rod-shaped member are placed inside the protective wall and on the lower surface of the paved road surface. Since it is fixed and the protective wall is fixed to the paved road surface, there is a problem that the installation work becomes complicated and costly.
Since the lower end of the rod-shaped member is fixed on the lower surface of the paved road surface, it cannot be used on an ordinary road or an end of a road formed on the top of the embankment. Moreover, since all of them are for rigidly connecting the guard fence to the roadbed, for example, as shown in FIG. 13, a concrete floor slab 102 is provided on a girder 101 in the length direction of a bridge or the like. If the road surface 103 is composed of the upper surface of the concrete floor slab 102, and a guard fence 104 is provided as a balustrade at the end of the road surface 103, and the guard fence 104 is rigidly connected integrally with the steel members 105, 105 in the vertical direction. The moment caused by the collision of the vehicle with the guard fence 104 may be concentrated on the road surface 103 above the girder 102, and a crack K may be generated there. At the same time, the impact of the collision vehicle becomes large.
【0005】そこで、本発明は、道路の端部等の使用に
適し、壁本体は健全で強固となり、衝突時の床版への影
響及び車両の衝撃を緩和することができるコンクリート
製壁高欄及び路側壁を提供することを目的とする。Therefore, the present invention is suitable for use at the end of a road, etc., the wall main body becomes sound and strong, and the impact on the floor slab and the impact of the vehicle at the time of collision can be mitigated. The purpose is to provide a roadside wall.
【0006】[0006]
【課題を解決するための手段】請求項1の発明は、基礎
に立設する固定部材と、壁本体の下面に形成され前記固
定部材の上部を挿入する縦方向の縦挿入孔と、前記壁本
体の側面に形成され前記縦挿入孔と交差する横方向の横
挿入孔と、この横挿入孔に挿入する連結部材と、前記固
定部材に穿設され前記連結部材を挿通する挿通孔とを備
えたものであり、縦挿入孔に固定部材の上部を挿入し、
壁本体の側面から横挿入孔に連結部材に挿入することに
より、道路の端部への据付が可能となり、また、壁本体
の道路側にアンカーを設ける必要がなく、しかも、下面
に形成した縦挿入孔に固定部材を挿入するものであるか
ら、吊り下ろしの際の位置合わせ作業が容易となる。According to a first aspect of the present invention, there is provided a fixing member which is erected on a foundation, a vertical insertion hole which is formed in a lower surface of a wall body and into which an upper portion of the fixing member is inserted, and the wall. A lateral insertion hole formed in a side surface of the main body and intersecting the vertical insertion hole; a connecting member inserted into the horizontal insertion hole; and an insertion hole formed in the fixing member and through which the connecting member is inserted. Insert the upper part of the fixing member into the vertical insertion hole,
By inserting the side wall of the wall body into the horizontal insertion hole into the connecting member, it is possible to install it on the end of the road, and it is not necessary to install an anchor on the road side of the wall body, and in addition, the vertical Since the fixing member is inserted into the insertion hole, the positioning work at the time of hanging can be facilitated.
【0007】請求項2の発明は、前記固定部材は、前記
基礎に固定する固定部と、前記縦挿入孔に挿入する挿入
部とを有し、前記固定部をアンカーボルトにより前記基
礎に固定すると共に、前記アンカーボルトの頭部と前記
基礎の上面との間に弾性部材を設けたものであり、新設
の基礎に予め固定されたアンカーボルトに固定部材を固
定し、あるいは既設の基礎にアンカーボルトにより固定
部材を固定する。そして、壁本体に車両が衝突しても、
アンカーボルトの頭部と前記基礎の上面との間に設けた
弾性部材が弾性変形することにより、道路側への衝撃と
衝突車両の衝撃が緩和される。According to a second aspect of the present invention, the fixing member has a fixing portion that is fixed to the foundation and an insertion portion that is inserted into the vertical insertion hole, and the fixing portion is fixed to the foundation by an anchor bolt. At the same time, an elastic member is provided between the head of the anchor bolt and the upper surface of the foundation, and the fixing member is fixed to the anchor bolt previously fixed to the new foundation, or the anchor bolt is attached to the existing foundation. To fix the fixing member. And even if the vehicle collides with the wall body,
The elastic member provided between the head of the anchor bolt and the upper surface of the foundation is elastically deformed, whereby the impact on the road side and the impact of the colliding vehicle are mitigated.
【0008】請求項3の発明は、長さ方向に隣合う前記
壁本体の間に目地部を設け、複数の前記壁本体を長さ方
向のPC鋼材により緊張一体化してなるものであり、目
地部を介して並ぶ壁本体を、PC鋼材により緊張一体化
したため、車両の衝突により壁本体が傾動して目地部間
が開く方向に力が加わると、これに対してPC鋼材によ
る緊張力が有効に作用して前記傾動を抑えることができ
る。According to a third aspect of the present invention, a joint portion is provided between the wall main bodies adjacent to each other in the lengthwise direction, and the plurality of wall main bodies are tension-integrated by the PC steel material in the lengthwise direction. Since the wall main bodies lined up via the joints are tension-integrated by the PC steel material, when the wall body tilts due to a vehicle collision and a force is applied in the direction in which the joints open, the tension force of the PC steel material is effective against this. It is possible to suppress the tilting by acting on.
【0009】[0009]
【発明の実施形態】以下、本発明の実施例を添付図面を
参照して説明する。図1乃至図11は本発明の第1実施
例を示し、コンクリート製壁高欄及び路側壁1は、図1
の断面図に示すように、下方に向かってテーパ状に僅か
に拡大する壁本体2を備え、この壁本体2は高強度コン
クリートのプレキャストコンクリート製である。前記壁
本体2の両側には、水平傾斜角である所定角度θが75
度以上90度未満程度をなす平坦傾斜面3,3が形成さ
れ、その壁本体2の内部には図示しない鉄筋が配筋さ
れ、この例では、壁本体2は高さが1m(メートル),
長さが3メートル程度に形成されている。また、図1に
示すように、図中右側の一方の傾斜面3は他方の傾斜面
3より所定角度θを小さく形成している。一方の前記平
坦傾斜面3の下部には、側方に突出する脚部4を設け、
この脚部4は、傾斜面4Aの下部に垂直面4Bを有す
る。また、他方の前記平坦傾斜面3の下部には垂直面5
を形成する。Embodiments of the present invention will be described below with reference to the accompanying drawings. 1 to 11 show a first embodiment of the present invention, in which a concrete wall balustrade and a road side wall 1 are shown in FIG.
As shown in the cross-sectional view of FIG. 1, a wall main body 2 that slightly expands downward is provided, and the wall main body 2 is made of high-strength concrete precast concrete. A predetermined angle θ, which is a horizontal inclination angle, is 75 on both sides of the wall body 2.
Flat inclined surfaces 3 and 3 that form an angle of not less than 90 degrees are formed, and a reinforcing bar (not shown) is arranged inside the wall body 2. In this example, the wall body 2 has a height of 1 m (meter),
The length is about 3 meters. Further, as shown in FIG. 1, one inclined surface 3 on the right side of the drawing is formed to have a smaller predetermined angle θ than the other inclined surface 3. On the lower part of the one flat inclined surface 3, a leg portion 4 protruding laterally is provided,
The leg portion 4 has a vertical surface 4B below the inclined surface 4A. Also, a vertical surface 5 is provided below the other flat inclined surface 3.
To form
【0010】前記壁本体2の下面2Aに、その幅方向略
中央に設ける溝状の縦挿入孔6と、下面溝7とを、該壁
本体2の長さ方向に複数形成し、連続する縦挿入孔6と
下面溝7は、図1に示すように、断面逆T型をなす。ま
た、前記脚部4の傾斜面4Aには、凹所8を形成し、こ
の凹所8に横方向の横挿入孔9を形成し、この横挿入孔
9は正面略角型をなし、前記縦挿入孔6の長さ方向中央
に交差する。さらに、前記壁本体2に、前記脚部4の傾
斜面4Aの上部と前記縦挿入孔6の上部を連通する孔を
穿設し、この孔に充填材注入孔たるホース10がその上端
を露出して挿入配置する。また、図10に示すように、
前記縦挿入孔6の長さ方向両縁には、下方に向かって拡
大するテーパー部6Aが形成されている。さらに、図1
1に示すように、前記脚部4の傾斜面4Aの上部と前記
縦挿入孔6の上部を連通する空気抜き孔10Aが形成され
ている。尚、この空気抜き孔10Aをホースにより構成し
てもよい。On the lower surface 2A of the wall main body 2, a plurality of groove-shaped vertical insertion holes 6 provided at approximately the center in the width direction and a plurality of lower surface grooves 7 are formed in the length direction of the wall main body 2 to form a continuous vertical direction. As shown in FIG. 1, the insertion hole 6 and the lower surface groove 7 have an inverted T-shaped cross section. Further, a concave portion 8 is formed on the inclined surface 4A of the leg portion 4, and a lateral lateral insertion hole 9 is formed in the concave portion 8. The lateral insertion hole 9 has a substantially square front shape. It intersects with the center of the vertical insertion hole 6 in the longitudinal direction. Further, the wall body 2 is provided with a hole for communicating the upper portion of the inclined surface 4A of the leg portion 4 with the upper portion of the vertical insertion hole 6, and the hose 10 serving as a filler injection hole exposes the upper end thereof. Then insert and place. Also, as shown in FIG.
Tapered portions 6A that expand downward are formed on both edges of the vertical insertion hole 6 in the longitudinal direction. Furthermore, FIG.
As shown in FIG. 1, an air vent hole 10A is formed to connect the upper portion of the inclined surface 4A of the leg portion 4 and the upper portion of the vertical insertion hole 6 to each other. The air vent hole 10A may be formed by a hose.
【0011】前記壁本体2は道路Rの端部に設けられ、
この例では、基礎を構成する橋梁等のコンクリート床版
11により道路Rを構成し、そのコンクリート床版11の上
面11Aの端部に欄干として前記壁本体2を設け、該コン
クリート床版11の端部には縦方向の端面11Bが形成され
ている。前記コンクリート床版11は、現場打ちコンクリ
ート製あるいはプレキャスト製であって、その上面11A
には、前記縦挿入孔6及び横挿入孔7に対応して、固定
部材12が立設される。この固定部材12は、前記縦挿入孔
6に遊挿する板状の挿入部13と、床版11に固定する板状
の固定部14とを一体に備えた金属製の逆T型金具であっ
て、前記挿入部13には、前記横挿入孔6に対応して角型
の挿通孔13Aを穿設し、前記固定部14の幅方向両側に
は、アンカーボルト15を挿入するアンカー孔14Aを複数
穿設している。また、前記アンカーボルト15はねじ棒15
Aを有し、このねじ棒15Aに頭部たる固定ナット17が螺
合される。さらに、この固定ナット17と固定部14との間
には、弾性部材が設けられ、図2に示すように、弾性部
材としてばね座金等の皿ばね16及び硬質ゴムシート18を
設け、前記固定部14と床版11の上面11Aとの間には、高
さ調整用を兼ねるスポンジなどの弾性シート部材19が設
けられている。尚、図2には、床版11に穿設した縦孔11
Tに、アンカーボルト15の一部を構成する筒体15Bを挿
入し、この筒体15Bに拡大先端部15Cを挿入し、前記ね
じ棒15Cを螺入することにより、前記拡大先端部15Cが
拡大するホールインアンカーを示したが、ケミカルアン
カーなどを用いることもでき、あるいは、床版11を貫通
するアンカーにより前記固定部材12を固定することもで
きる。また、前記横挿入孔9と挿通孔13Aには、金属角
棒からなる連結部材20が挿入され、この連結部材20より
前記横挿入孔9と挿通孔13Aの断面は大きく形成されて
いる。The wall body 2 is provided at the end of the road R,
In this example, concrete floor slabs such as bridges that form the foundation
A road R is constituted by 11, and the wall main body 2 is provided as a balustrade at an end portion of an upper surface 11A of the concrete floor slab 11, and an end surface 11B in a vertical direction is formed at an end portion of the concrete floor slab 11. The concrete floor slab 11 is made of cast-in-place concrete or precast, and has an upper surface 11A.
A fixing member 12 is provided upright in the vertical direction so as to correspond to the vertical insertion hole 6 and the horizontal insertion hole 7. The fixing member 12 is a metal inverted T-shaped metal fitting integrally provided with a plate-shaped insertion portion 13 loosely inserted in the vertical insertion hole 6 and a plate-shaped fixing portion 14 fixed to the floor slab 11. Then, the insertion portion 13 is provided with a rectangular insertion hole 13A corresponding to the lateral insertion hole 6, and anchor holes 14A into which the anchor bolts 15 are inserted are formed on both sides of the fixing portion 14 in the width direction. There are multiple holes. The anchor bolt 15 is a threaded rod 15
A fixed nut 17 having a head is screwed onto the screw rod 15A. Further, an elastic member is provided between the fixing nut 17 and the fixing portion 14, and a disc spring 16 such as a spring washer and a hard rubber sheet 18 are provided as the elastic member as shown in FIG. An elastic sheet member 19 such as a sponge that also serves to adjust the height is provided between 14 and the upper surface 11A of the floor slab 11. It should be noted that FIG. 2 shows a vertical hole 11 formed in the floor slab 11.
By inserting a tubular body 15B forming a part of the anchor bolt 15 into T, inserting an enlarged tip portion 15C into the tubular body 15B, and screwing the screw rod 15C, the enlarged tip portion 15C is enlarged. Although the hole-in-anchor is shown, a chemical anchor or the like can be used, or the fixing member 12 can be fixed by an anchor penetrating the floor slab 11. A connecting member 20 made of a metal square rod is inserted into the lateral insertion hole 9 and the insertion hole 13A, and the cross-sections of the lateral insertion hole 9 and the insertion hole 13A are larger than the connecting member 20.
【0012】前記壁本体2の長さ方向に横締用部材たる
PC鋼材21が配置され、このPC鋼材21は鋼製シース21
Aまたはダクト内に配置されたものであり、該PC鋼材
21は、PC鋼線の撚り線等からなり、該PC鋼材21の外
周にエポキシ樹脂及び防錆処理PC鋼材により防錆加工
を施している。また、前記PC鋼材21の両側に定着具22
が設けられ、この定着具22は内部にテーパー孔23Aを有
するスリーブ23と、前記テーパー孔23Aに前側が圧接す
る裁頭円錐形のクリップ24とからなり、このクリップ24
の中央に、円周方向に複数の突起を有する圧着孔25を設
けると共に、この圧着孔25に連通する4箇所の切り込み
25Aが形成され、孔を有する支圧板26を介して前記定着
具22が用いられ、前記突起を有する圧着孔25が前記PC
鋼材21の外周に圧着する。また、前記PC鋼材21は壁本
体2の上部の幅方向中央に挿通されているが、PC鋼材
21,21をたすき掛けする重複部27においては、図6に示
すように、前記シース21Aを幅方向両側に形成し、それ
らPC鋼材21,21の端部21T,21Tを、壁本体2,2の
上面に形成した定着用凹所2B,2Bに露出する。そし
て、これら定着用凹所2B,2Bは壁本体2の上面の長
さ方向両側にそれぞれ形成されており、それら定着用凹
所2B,2Bを有する壁本体2の間には、定着用凹所を
備えない壁本体2が複数配置され、これら壁本体2には
前記重複部27は形成されていない。さらに、前記壁本体
2の長さ方向端面には、相互に係合する突条28と凹条29
とが形成され、隣合う壁本体2,2の間には目地材33を
充填して目地部30が形成され、前記突条28と凹条29との
間には、前記シース21Aに対応して、スポンジパッキン
グ31が介在され、このパッキング31には前記PC鋼材21
を挿通する孔32が穿設されている。A PC steel material 21 as a lateral fastening member is arranged in the lengthwise direction of the wall body 2, and the PC steel material 21 is a steel sheath 21.
A or the one placed in the duct, the PC steel material
Reference numeral 21 is a stranded wire of PC steel wire or the like, and the outer periphery of the PC steel material 21 is rustproofed with epoxy resin and rustproof PC steel material. Further, the fixing tools 22 are provided on both sides of the PC steel material 21.
The fixing device 22 is provided with a sleeve 23 having a tapered hole 23A therein, and a truncated cone-shaped clip 24 whose front side is pressed against the tapered hole 23A.
A crimp hole 25 having a plurality of protrusions in the circumferential direction is provided at the center of the, and four notches communicating with the crimp hole 25 are provided.
25A is formed, the fixing tool 22 is used via a pressure plate 26 having a hole, and the pressure-bonding hole 25 having the protrusion is the PC.
It is crimped to the outer circumference of the steel material 21. Further, the PC steel material 21 is inserted through the widthwise center of the upper portion of the wall body 2,
As shown in FIG. 6, in the overlapping portion 27 where the 21 and 21 are struck, the sheath 21A is formed on both sides in the width direction, and the end portions 21T and 21T of the PC steel materials 21 and 21 are connected to the wall main bodies 2 and 2, respectively. It is exposed in the fixing recesses 2B, 2B formed on the upper surface of the. The fixing recesses 2B and 2B are formed on both sides of the upper surface of the wall main body 2 in the length direction, and the fixing recesses 2B and 2B are provided between the wall main bodies 2 having the fixing recesses 2B and 2B. A plurality of wall bodies 2 that do not have the above are arranged, and the overlapping portions 27 are not formed in these wall bodies 2. Further, on the end face in the length direction of the wall main body 2, a protrusion 28 and a recess 29 which engage with each other are provided.
And a joint portion 30 is formed by filling a joint material 33 between the adjacent wall bodies 2 and 2, and a space corresponding to the sheath 21A is formed between the protrusion 28 and the recess 29. The sponge packing 31 is interposed between the PC steel material 21 and the packing 31.
A hole 32 is formed to pass through.
【0013】さらに、前記壁本体2の下面2Aと前記コ
ンクリート床版11の上面11Aとの間には、壁本体2の幅
方向両側にゴムなどからなる弾性パッキン材34,34を配
置し、これら両側の弾性パッキン材33,33の間には、充
填材35を充填する下面空間36が形成される。Further, between the lower surface 2A of the wall body 2 and the upper surface 11A of the concrete floor slab 11, elastic packing members 34, 34 made of rubber or the like are arranged on both sides in the width direction of the wall body 2, A lower surface space 36 for filling the filling material 35 is formed between the elastic packing materials 33, 33 on both sides.
【0014】前記壁本体2の垂直面4B,5には、ぞれ
ぞれ埋込インサートにより横方向の雌ねじ部41を複数
形成し、この雌ねじ部41にボルト42を螺着して山形鋼か
らなる治具43を固定し、この治具43に固着したナット
に、縦方向の高さ調整ボルト44を螺合し、この高さ調整
ボルト44の下端と前記床版11の上面11Aとの間には、鋼
板等からなる支持プレート45が敷設される。On the vertical surfaces 4B and 5 of the wall body 2, a plurality of lateral female screw portions 41 are formed by means of embedded inserts, and bolts 42 are screwed into the female screw portions 41 so that the angle steel is formed. Is fixed to the jig 43, and a vertical height adjusting bolt 44 is screwed into a nut fixed to the jig 43. Between the lower end of the height adjusting bolt 44 and the upper surface 11A of the floor slab 11. A support plate 45 made of a steel plate or the like is laid on this.
【0015】次に前記コンクリート製壁高欄及び路側壁
1の施工について説明すると、本発明の壁高欄及び路側
壁1は道路Rの新設工事の際の施工、及び既設の道路R
への施工が可能であり、まず、床版11にドリルなどの穿
孔機(図示せず)により縦孔11Tを穿設し、アンカーボ
ルト15により固定部材12を固定する。そして、両側に弾
性パッキン材33,33を配置し、壁本体2を吊り上げ、縦
挿通孔6を固定部材12の挿入部13に合わせて、吊り下ろ
す。また、突条28と凹条29とは重なり合わないように
し、図6に示すように、突条28の先端と凹条29の両端面
29Aとを合わせている。Next, the construction of the concrete wall balustrade and the road side wall 1 will be described. The wall balustrade and the road side wall 1 of the present invention are constructed at the time of new construction of the road R and the existing road R.
First, a vertical hole 11T is formed in the floor slab 11 by a punching machine (not shown) such as a drill, and the fixing member 12 is fixed by an anchor bolt 15. Then, the elastic packing materials 33, 33 are arranged on both sides, the wall main body 2 is lifted, the vertical insertion hole 6 is aligned with the insertion portion 13 of the fixing member 12, and the wall is hung down. In addition, as shown in FIG. 6, the ridges 28 and the concave ridges 29 should not overlap with each other, and as shown in FIG.
Matched with 29A.
【0016】このようにして複数の壁本体2を床版11の
上に仮設した後、凹所8から横挿入孔9に連結部材20を
挿入すると共に、挿通孔13Aに挿通し、これにより床版
11に壁本体2が連結される。次に、治具43及び高さ調整
ボルト44を壁本体2にセットし、複数並んだ壁本体2,
2…の高さ、通り及び目地部30の間隔を調整した後、目
地部30に無収縮モルタルなどの目地材33を充填する。こ
の場合、連結部材20より前記横挿入孔9と挿通孔13Aの
断面が大きく形成されているため、連結部材20の挿入後
に、壁本体2の高さ及び通りの調整を行うことができ、
また、縦挿入孔6と挿入部13との間に隙間があるから、
幅方向及び長さ方向に位置調整ができる。尚、治具43及
び高さ調整ボルト44のセットは、工場で行ってもよく、
吊り下ろした後でもよい。前記目地材33の硬化後、図4
に示すように、隣合うPC鋼材21,21´の端部端部21
T,21T´を、たすき掛けのように交差したシース21
A,21Aにそれぞれ挿通し、端部21T,21T´が交差す
る重複部27を形成する。尚、端部21T´を備えたPC鋼
材21´は、前記端部21Tを備えたPC鋼材21と同一構成
である。そして定着用凹所2B内の端部21Tを、支圧板
26に挿通すると共に、スリーブ23を組み合わせたクリッ
プ24に挿通し、挿出した端部21Tをジャッキ(図示せ
ず)などにより所定の緊張力で斜め上方に引っ張ること
により、複数の壁本体2の長さ方向に緊張力を付与す
る。この場合、クリップ24がスリーブ23のテーパー孔23
Aに楔作用により食い込むと共に、切り込み25Aを設け
た圧着孔25が端部21Tに圧着して端部21Tが固定され
る。そして、定着後、定着用凹所2Bは無収縮モルタル
などの充填材35を充填して、壁本体2の上面と面一に仕
上げる。After the plurality of wall bodies 2 are temporarily installed on the floor slab 11 in this way, the connecting member 20 is inserted from the recess 8 into the lateral insertion hole 9 and is inserted into the insertion hole 13A, whereby the floor is formed. Edition
The wall body 2 is connected to 11. Next, the jig 43 and the height adjusting bolt 44 are set on the wall main body 2, and a plurality of wall main bodies 2 arranged side by side are set.
After adjusting the height of 2 and the distance between the joint and the joint portion 30, the joint portion 30 is filled with a joint material 33 such as non-shrink mortar. In this case, since the cross-sections of the lateral insertion hole 9 and the insertion hole 13A are formed to be larger than that of the connecting member 20, the height and passage of the wall body 2 can be adjusted after the connecting member 20 is inserted.
Moreover, since there is a gap between the vertical insertion hole 6 and the insertion portion 13,
The position can be adjusted in the width direction and the length direction. The jig 43 and the height adjusting bolt 44 may be set in the factory,
It may be after hanging. After hardening of the joint material 33, FIG.
As shown in, the end 21 of the adjacent PC steel material 21, 21 '
Sheath 21 that intersects T and 21T 'like a cross
Inserted through A and 21A, respectively, an overlapping portion 27 where end portions 21T and 21T 'intersect is formed. The PC steel material 21 'having the end portion 21T' has the same structure as the PC steel material 21 having the end portion 21T. Then, fix the end 21T in the fixing recess 2B to the pressure plate.
26 and a clip 24 in which the sleeve 23 is combined, and the inserted end 21T is pulled obliquely upward with a predetermined tension force by a jack (not shown) or the like, so that the plurality of wall bodies 2 Apply tension in the length direction. In this case, the clip 24 is attached to the taper hole 23 of the sleeve 23.
While being cut into A by a wedge action, the crimp hole 25 provided with the notch 25A is crimped to the end 21T to fix the end 21T. Then, after fixing, the fixing recess 2B is filled with a filler 35 such as non-shrink mortar to finish flush with the upper surface of the wall body 2.
【0017】このようにしてPC鋼材21により複数の壁
本体2を緊張一体化した後、ホース10から無収縮モルタ
ルなどの充填材35を充填すると、この充填材35が縦挿入
孔6及び横挿入孔9に充填され、さらに下面空間36に充
填され、その充填材35は挿通孔13Aと連結部材20との隙
間にも充填され、充填材35が硬化することにより、床版
11に壁本体2が固定される。この場合、壁本体2には空
気抜き孔10Aが形成されているから、充填材35の充填が
スムーズに行われる。尚、この下面空間36への充填作業
後、ホース10の傾斜面4Aから突出する部分は、図1に
示すように、切断等して取り除き、また、下面空間36内
の充填材35の硬化後、ボルト42を取り外し、雌ねじ部41
に充填材36を充填して仕上げる。また、凹所8に充填材
35を充填して傾斜面4Aを面一に仕上げる。尚、図中、
46は舗装層である。After the plurality of wall bodies 2 are tension-integrated with the PC steel material 21 in this way, and then the filling material 35 such as non-shrink mortar is filled from the hose 10, the filling material 35 is inserted vertically and horizontally. The holes 9 are filled, and further the lower space 36 is filled. The filling material 35 is also filled in the gap between the insertion hole 13A and the connecting member 20, and the filling material 35 is cured, so that the floor slab is cured.
The wall body 2 is fixed to 11. In this case, since the air vent hole 10A is formed in the wall body 2, the filling material 35 is smoothly filled. After the filling work into the lower space 36, the portion of the hose 10 protruding from the inclined surface 4A is removed by cutting or the like as shown in FIG. 1, and after the filling material 35 in the lower space 36 is cured. , Remove the bolt 42, female thread 41
Fill with a filler 36 to finish. Also, the filling material in the recess 8
Fill 35 to finish the inclined surface 4A flush. In the figure,
46 is a pavement layer.
【0018】このようにして壁本体2の中央を固定部材
12及び連結部材20により固定することにより、道路Rの
端部に壁高欄及び路側壁1を施工することができると共
に、壁本体2の道路R側には、固定部材等がまったく露
出しない。そして、道路Rを走行する車両が衝突して壁
本体2に衝撃力Fが加わり、壁本体2を倒す力が働いて
も、弾性部材が弾性変形することにより、道路Rを構成
する床版11に加わるモーメントなどを緩和することがで
きると共に、弾性部材である皿ばね16及び硬質ゴムシー
ト18がクッションとなって、衝突車両への衝撃も緩和す
ることができ、衝突に対して壁本体2が強固なものとな
り、健全性もある。また、車両が衝突した壁本体2が傾
動すると、目地部30が広がるが、壁本体2の上部に挿通
したPC鋼材21の緊張力によりその目地部30の広がりを
抑えることができ、この際、PC鋼材21が収縮方向のば
ね作用をなす。In this way, the center of the wall body 2 is fixed to the fixing member.
By fixing with 12 and the connecting member 20, the wall balustrade and the road side wall 1 can be constructed at the end of the road R, and the fixing member and the like are not exposed at all on the road R side of the wall body 2. Then, even if a vehicle traveling on the road R collides and an impact force F is applied to the wall main body 2 and a force for tilting the wall main body 2 is exerted, the elastic member is elastically deformed, so that the floor slab 11 constituting the road R is formed. It is possible to alleviate the moment applied to the vehicle and the cushion spring 16 and the hard rubber sheet 18, which are elastic members, to cushion the impact on the collision vehicle. It will be strong and sound. Further, when the wall body 2 that the vehicle collides with is tilted, the joint portion 30 expands, but the tension of the PC steel material 21 inserted in the upper portion of the wall body 2 can suppress the expansion of the joint portion 30. The PC steel material 21 acts as a spring in the contracting direction.
【0019】このように本実施例では、請求項1に対応
して、基礎たるコンクリート床版11に立設する固定部材
12と、壁本体2の下面2Aに形成され固定部材12の上部
たる挿入部13を挿入する縦方向の縦挿入孔6と、壁本体
2の側面に形成され縦挿入孔6と交差する横方向の横挿
入孔9と、この横挿入孔9に挿入する連結部材20と、固
定部材12に穿設され連結部材20を挿通する挿通孔13Aと
を備えたものであるから、縦挿入孔6に固定部材12の上
部を挿入し、壁本体2の側面から横挿入孔9に連結部材
20に挿入することにより、道路Rの端部への据付が可能
となり、また、壁本体2の道路R側にアンカーを設ける
必要がなく、しかも、下面2Aに形成した縦挿入孔6に
固定部材12を挿入するものであるから、従来のように、
幅方向両側をアンカーボルトにより固定するものとは異
なり、壁本体2の幅内において幅方向中央にて固定する
ものであるから、吊り下ろしの際の位置合わせ作業が容
易となる。As described above, in this embodiment, according to claim 1, a fixing member which is erected on the concrete floor slab 11 as a foundation.
12 and a vertical insertion hole 6 formed in the lower surface 2A of the wall body 2 for inserting the insertion portion 13 which is an upper portion of the fixing member 12, and a horizontal direction formed in the side surface of the wall body 2 and intersecting the vertical insertion hole 6. Since the horizontal insertion hole 9, the connecting member 20 to be inserted into the horizontal insertion hole 9, and the insertion hole 13A which is formed in the fixing member 12 and allows the connecting member 20 to pass therethrough, are provided in the vertical insertion hole 6. Insert the upper part of the fixing member 12 into the lateral insertion hole 9 from the side surface of the wall body 2
By inserting it into the road 20, it becomes possible to install it on the end of the road R, and it is not necessary to provide an anchor on the road R side of the wall body 2, and moreover, a fixing member to the vertical insertion hole 6 formed in the lower surface 2A. Since 12 is to be inserted, as in the past,
Unlike the method of fixing both sides in the width direction with anchor bolts, the method of fixing at the widthwise center within the width of the wall body 2 facilitates the positioning work at the time of hanging.
【0020】また、このように本実施例では、請求項2
に対応して、固定部材12は、基礎たる床版11に固定する
固定部14と、縦挿入孔6に挿入する挿入部13とを有し、
固定部14をアンカーボルト15により床版11に固定すると
共に、アンカーボルト15の頭部たる固定ナット17と床版
11の上面11Aとの間に弾性部材である皿ばね16及び硬質
ゴムシート18を設けたものであるから、新設の基礎に予
め固定されたアンカーボルト15に固定部材12を固定し、
あるいは既設の基礎にアンカーボルト15により固定部材
12を固定でき、この固定部材12により基礎に固定された
壁本体2に車両が衝突しても、固定ナット17と床版11の
上面11Aとの間に設けた弾性部材が弾性変形することに
より、壁本体2が傾動し、道路R側への衝撃と衝突車両
の衝撃を緩和することができる。As described above, according to this embodiment, the second aspect
Corresponding to, the fixing member 12 has a fixing portion 14 that is fixed to the floor slab 11 that is the foundation, and an insertion portion 13 that is inserted into the vertical insertion hole 6,
The fixing portion 14 is fixed to the floor slab 11 by the anchor bolt 15, and the fixing nut 17 that is the head of the anchor bolt 15 and the floor slab are used.
Since the disc spring 16 and the hard rubber sheet 18 which are elastic members are provided between the upper surface 11A and the upper surface 11A, the fixing member 12 is fixed to the anchor bolt 15 which is previously fixed to the new foundation,
Alternatively, it is fixed to the existing foundation with anchor bolts 15.
Even if the vehicle collides with the wall body 2 that can fix 12 and is fixed to the foundation by the fixing member 12, the elastic member provided between the fixing nut 17 and the upper surface 11A of the floor slab 11 is elastically deformed. The wall body 2 tilts, and the impact on the road R side and the impact of the colliding vehicle can be mitigated.
【0021】さらに、このように本実施例では、請求項
3に対応して、長さ方向に隣合う壁本体2の間に目地部
30を設け、複数の壁本体2,2…を長さ方向のPC鋼材
21により緊張一体化してなるものであるから、長さ方向
に隣合う壁本体2,2の間に目地部30を設けた複数の壁
本体2,2…を長さ方向のPC鋼材21により緊張一体化
してなるものであり、目地部30を介して並ぶ壁本体2,
2…を、PC鋼材21により緊張一体化したため、車両の
衝突により壁本体2が傾動して目地部30が開く方向に力
が加わると、これに対してPC鋼材21による緊張力が有
効に作用して傾動を抑えることができる。Further, in this embodiment, as described above, the joint portion is provided between the wall main bodies 2 adjacent to each other in the lengthwise direction according to claim 3.
30 is provided, and a plurality of wall bodies 2, 2 ...
Since the tension is integrated by the 21, a plurality of wall bodies 2, 2 ... Having joints 30 between the wall bodies 2, 2 adjacent in the length direction are tensioned by the PC steel material 21 in the length direction. The wall bodies 2, which are integrated and are arranged side by side through the joint portion 30,
Since the PC steel materials 21 are integrally tensioned with each other, when the wall main body 2 tilts due to the collision of the vehicle and a force is applied in the direction in which the joint portion 30 opens, the tension force of the PC steel materials 21 effectively acts on this. And tilt can be suppressed.
【0022】また、実施例上の効果として、壁本体2の
下面2Aと基礎たる床版11の上面11Aとの間には、壁本
体2の幅方向両側にパッキン材34,34を配置すると共
に、これら両側のパッキン材34,34間に下面空間36を形
成し、縦挿入孔6と壁本体2の側面とを連通する充填材
注入孔たるホース10を該壁本体2に形成したものである
から、ホース10から充填した充填材35により、固定部材
12及び連結部材20を介して、床版11に壁本体2を強固に
固定することができ、また、ホース10が斜めに設けられ
ると共に、該ホース10が縦挿入孔6の上部に連結されて
いるから、充填材35の充填を良好に行うことができる。Further, as an effect of the embodiment, packing materials 34, 34 are arranged on both sides in the width direction of the wall body 2 between the lower surface 2A of the wall body 2 and the upper surface 11A of the floor slab 11 as a base. The lower space 36 is formed between the packing materials 34 on both sides, and the wall body 2 is formed with a hose 10 serving as a filler injection hole for communicating the vertical insertion hole 6 with the side surface of the wall body 2. From the hose 10 by the filling material 35 filled with the fixing member
The wall body 2 can be firmly fixed to the floor slab 11 via 12 and the connecting member 20, and the hose 10 is obliquely provided, and the hose 10 is connected to the upper portion of the vertical insertion hole 6. Therefore, the filling material 35 can be satisfactorily filled.
【0023】また、実施例上の効果として、縦挿入孔6
の長さ方向両縁には、下方に向かって拡大するテーパー
部6A,6Aが形成されているから、縦挿入孔6への挿
入部13の挿入配置を容易にできる。さらに、連結部材20
より前記横挿入孔9と挿通孔13Aの断面を大きく形成し
たから、連結部材20の挿入作業を容易に行うことができ
ると共に、連結部材20の挿入後に、壁本体2の高さ及び
通りの調整を行うことができ、また、縦挿入孔6と挿入
部13との間に隙間があるから、壁本体2の幅方向及び長
さ方向の位置調整を簡便に行うことができる。さらにま
た、PC鋼材の境目において、1つの壁本体2にPC鋼
材21,21´の端部21A,21A´が十空くする重複部27を
形成したから、隣合う壁本体2の間で緊張力がとぎれる
ことなく、その全長に渡って緊張力を付与することがで
きる。また、壁本体2に、予め埋込インサートにより雌
ねじ部41を形成したから、高さ調整ボルト44の使用が容
易となる。さらに、壁本体2を高強度コンクリートによ
り成型したことにより、耐衝撃性が向上する。また、道
路R側にホース10の先端を設けたから、充填材35の充填
作業を道路R側から容易に行うことができる。また、壁
本体2の下面2Aに下面溝7を形成したから、固定部材
12の固定部14及びアンカーボルト15の上部を収納するこ
とができ、また、床版11の上面11Aに溝などを施工する
必要もないため、既設の道路における復旧用などに適し
たものとなる。As an effect of the embodiment, the vertical insertion hole 6
Since the taper portions 6A, 6A that expand downward are formed on both edges in the length direction of, the insertion arrangement of the insertion portion 13 into the vertical insertion hole 6 can be facilitated. Further, the connecting member 20
Since the cross-sections of the lateral insertion hole 9 and the insertion hole 13A are formed larger, the work of inserting the connecting member 20 can be easily performed, and the height and the passage of the wall body 2 can be adjusted after the connecting member 20 is inserted. Moreover, since there is a gap between the vertical insertion hole 6 and the insertion portion 13, the position adjustment of the wall body 2 in the width direction and the length direction can be easily performed. Furthermore, at the boundary between the PC steel materials, since the overlapping portion 27 is formed in one wall body 2 so that the end portions 21A and 21A 'of the PC steel materials 21 and 21' are sufficient, the tension force between the adjacent wall bodies 2 is increased. It is possible to apply tension over its entire length without interruption. Further, since the female screw portion 41 is formed in the wall body 2 in advance by the embedded insert, the height adjusting bolt 44 can be easily used. Furthermore, since the wall body 2 is molded from high-strength concrete, impact resistance is improved. Further, since the tip of the hose 10 is provided on the road R side, the filling work of the filling material 35 can be easily performed from the road R side. Further, since the lower surface groove 7 is formed on the lower surface 2A of the wall body 2, the fixing member
It is possible to store the fixed portions 14 of 12 and the upper portions of the anchor bolts 15, and since it is not necessary to construct a groove or the like on the upper surface 11A of the floor slab 11, it is suitable for restoration on an existing road. .
【0024】図12は本発明の第2実施例を示し、上記
第1実施例と同一部分に同一符号を付し、その詳細な説
明を省略して詳述すると、図11に示すように、弾性部
材たるばね座金等の皿ばね16のみを用いており、この例
においても、壁本体2に車両が衝突しても、アンカーボ
ルト15の頭部たる固定ナット17と床版11の上面11Aとの
間に設けた弾性部材たる皿ばね16が弾性変形することに
より、壁本体2が傾動し、道路Rを構成するコンクリー
ト床版11への衝撃と衝突車両が受ける衝撃とを緩和する
ことができる。FIG. 12 shows a second embodiment of the present invention, in which the same parts as those in the first embodiment are designated by the same reference numerals, and detailed description thereof will be omitted. As shown in FIG. Only the disc spring 16 such as a spring washer that is an elastic member is used. Also in this example, even if the vehicle collides with the wall body 2, the fixing nut 17 that is the head of the anchor bolt 15 and the upper surface 11A of the floor slab 11 are used. By elastically deforming the disc spring 16 as an elastic member provided between the walls, the wall body 2 tilts, and the impact on the concrete floor slab 11 forming the road R and the impact received by the colliding vehicle can be mitigated. .
【0025】尚、本発明は上記各実施例に限定されるも
のではなく、本発明の要旨の範囲内において、種々の変
形実施が可能である。例えば、壁本体の形状,寸法,大
きさ等は適宜選定可能である。また、弾性部材及び弾性
シート材は、弾性を有し収縮性を有するものであれば、
各種のものを用いることができる。さらに、充填材は無
収縮モルタルに限らず硬化性の各種の充填材を用いるこ
とができる。また、壁本体は床版に限らず各種道路に設
けることができる。さらに、硬質ゴムシート18をリング
状に形成してアンカーボルト15に挿入してもよい。The present invention is not limited to the above embodiments, and various modifications can be made within the scope of the gist of the present invention. For example, the shape, size, size, etc. of the wall body can be appropriately selected. In addition, the elastic member and the elastic sheet material, as long as they have elasticity and contractility,
Various types can be used. Further, the filler is not limited to non-shrink mortar, and various curable fillers can be used. The wall body can be provided not only on the floor slab but also on various roads. Further, the hard rubber sheet 18 may be formed in a ring shape and inserted into the anchor bolt 15.
【0026】[0026]
【発明の効果】請求項1の発明は、基礎に立設する固定
部材と、壁本体の下面に形成され前記固定部材の上部を
挿入する縦方向の縦挿入孔と、前記壁本体の側面に形成
され前記縦挿入孔と交差する横方向の横挿入孔と、この
横挿入孔に挿入する連結部材と、前記固定部材に穿設さ
れ前記連結部材を挿通する挿通孔とを備えたものであ
り、道路の端部等の使用に適し、衝突時の路面への影響
及び車両の衝撃を緩和することができるコンクリート製
壁高欄及び路側壁を提供することができる。According to the first aspect of the present invention, there are provided a fixing member which is erected on the foundation, a vertical insertion hole which is formed in the lower surface of the wall body and into which the upper portion of the fixing member is inserted, and a side surface of the wall body. A horizontal insertion hole formed in the lateral direction that intersects the vertical insertion hole; a connecting member to be inserted into the horizontal insertion hole; and an insertion hole that is formed in the fixing member and that inserts the connecting member. It is possible to provide a concrete rail balustrade and a road side wall that are suitable for use at the end of a road and can reduce the impact on the road surface and the impact of the vehicle at the time of collision.
【0027】請求項2の発明は、前記固定部材は、前記
基礎に固定する固定部と、前記縦挿入孔に挿入する挿入
部とを有し、前記固定部をアンカーボルトにより前記基
礎に固定すると共に、前記アンカーボルトの頭部と前記
基礎の上面との間に弾性部材を設けたものであり、道路
の端部等の使用に適し、衝突時の路面への影響及び車両
の衝撃を緩和することができるコンクリート製壁高欄及
び路側壁を提供することができる。According to a second aspect of the present invention, the fixing member has a fixing portion that is fixed to the foundation and an insertion portion that is inserted into the vertical insertion hole, and the fixing portion is fixed to the foundation by an anchor bolt. At the same time, an elastic member is provided between the head of the anchor bolt and the upper surface of the foundation, which is suitable for use at the end of the road, etc., and reduces the influence on the road surface at the time of collision and the impact of the vehicle. It is possible to provide a concrete wall balustrade and a road side wall that can be used.
【0028】請求項3の発明は、長さ方向に隣合う前記
壁本体の間に目地部を設け、複数の前記壁本体を長さ方
向のPC鋼材により緊張一体化してなるものであり、道
路の端部等の使用に適し、衝突時の路面への影響及び車
両の衝撃を緩和することができるコンクリート製壁高欄
及び路側壁を提供することができる。According to a third aspect of the present invention, a joint portion is provided between the wall main bodies adjacent to each other in the lengthwise direction, and the plurality of wall main bodies are tension-integrated by the PC steel material in the lengthwise direction. It is possible to provide a concrete rail balustrade and a road side wall that are suitable for use at the end portion of the road and can reduce the influence on the road surface at the time of collision and the impact of the vehicle.
【図1】本発明の第1実施例を示す幅方向の縦断面図で
ある。FIG. 1 is a longitudinal sectional view in a width direction showing a first embodiment of the present invention.
【図2】本発明の第1実施例を示す幅方向の要部の縦断
面図である。FIG. 2 is a vertical cross-sectional view of the essential parts in the width direction showing the first embodiment of the present invention.
【図3】本発明の第1実施例を示す長さ方向の縦断面図
である。FIG. 3 is a longitudinal cross-sectional view showing the first embodiment of the present invention.
【図4】本発明の第1実施例を示す壁高欄及び路側壁の
正面図である。FIG. 4 is a front view of a wall balustrade and a road side wall showing a first embodiment of the present invention.
【図5】本発明の第1実施例を示す重複部の一部切欠き
平面図である。FIG. 5 is a partially cutaway plan view of an overlapping portion according to the first embodiment of the present invention.
【図6】本発明の第1実施例を示す図5のY−Y線断面
図である。FIG. 6 is a sectional view taken along line YY of FIG. 5 showing the first embodiment of the present invention.
【図7】本発明の第1実施例を示す定着用凹所の縦断面
図である。FIG. 7 is a vertical cross-sectional view of a fixing recess according to the first embodiment of the present invention.
【図8】本発明の第1実施例を示す目地部の平面図であ
る。FIG. 8 is a plan view of a joint portion showing the first embodiment of the present invention.
【図9】本発明の第1実施例を示す目地部の縦断面図で
ある。FIG. 9 is a vertical cross-sectional view of a joint portion according to the first embodiment of the present invention.
【図10】本発明の第1実施例を示す高さ調整ボルトの
使用状態における幅方向の縦断面図である。FIG. 10 is a vertical cross-sectional view in the width direction in the use state of the height adjusting bolt according to the first embodiment of the present invention.
【図11】本発明の第1実施例を示す高さ調整ボルトの
使用状態における正面図である。FIG. 11 is a front view of the height adjusting bolt according to the first embodiment of the present invention in use.
【図12】本発明の第2実施例を示す幅方向の要部の縦
断面図である。FIG. 12 is a vertical cross-sectional view of a main part in the width direction showing a second embodiment of the present invention.
【図13】従来例を示す縦断面図である。FIG. 13 is a longitudinal sectional view showing a conventional example.
2 壁本体 2A 下面 6 縦挿入孔 9 横挿入孔 10 ホース(充填材注入孔) 11 コンクリート床版(基礎) 12 固定部材 13 挿入部 13A 挿通孔 14 固定部 15 アンカーボルト 16 皿ばね(弾性部材) 17 固定ナット(頭部) 18 硬質ゴムシート(弾性部材) 20 連結部材 21 PC鋼材 30 目地部 2 Wall body 2A Lower surface 6 Vertical insertion hole 9 Horizontal insertion hole 10 Hose (filler injection hole) 11 Concrete slab (foundation) 12 Fixing member 13 Insertion portion 13A Insertion hole 14 Fixing portion 15 Anchor bolt 16 Disc spring (elastic member) 17 Fixing nut (head) 18 Hard rubber sheet (elastic member) 20 Connecting member 21 PC steel 30 Joint
───────────────────────────────────────────────────── フロントページの続き (72)発明者 赤間 淳一 東京都千代田区麹町4−2 興和コンクリ ート株式会社内 (72)発明者 柳澤 正 東京都港区新橋5−33−11 日本ヒューム 管株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Junichi Akama 4-2 Kojimachi, Chiyoda-ku, Tokyo Within Kowa Concrete Co., Ltd. (72) Inventor Tadashi Yanagisawa 5-33-11, Shinbashi, Minato-ku, Tokyo Nippon Hume Co., Ltd. In the company
Claims (3)
面に形成され前記固定部材の上部を挿入する縦方向の縦
挿入孔と、前記壁本体の側面に形成され前記縦挿入孔と
交差する横方向の横挿入孔と、この横挿入孔に挿入する
連結部材と、前記固定部材に穿設され前記連結部材を挿
通する挿通孔とを備えたことを特徴とするコンクリート
製壁高欄及び路側壁。1. A fixing member which is erected on a foundation, a vertical insertion hole which is formed on a lower surface of a wall body and which inserts an upper portion of the fixing member, and a vertical insertion hole which is formed on a side surface of the wall body. A concrete wall balustrade characterized in that it has a transverse horizontal insertion hole that intersects, a connecting member that is inserted into the horizontal insertion hole, and an insertion hole that is formed in the fixing member and that inserts the connecting member. Roadside wall.
定部と、前記縦挿入孔に挿入する挿入部とを有し、前記
固定部をアンカーボルトにより前記基礎に固定すると共
に、前記アンカーボルトの頭部と前記基礎の上面との間
に弾性部材を設けたことを特徴とする請求項1記載のコ
ンクリート製壁高欄及び路側壁。2. The fixing member includes a fixing portion that is fixed to the foundation and an insertion portion that is inserted into the vertical insertion hole. The fixing portion is fixed to the foundation by an anchor bolt, and the anchor bolt is used. The concrete rail balustrade and road side wall according to claim 1, wherein an elastic member is provided between the head of the base and the upper surface of the foundation.
部を設け、複数の前記壁本体を長さ方向のPC鋼材によ
り緊張一体化してなることを特徴とする請求項1又は2
記載のコンクリート製壁高欄及び路側壁。3. A joint portion is provided between the wall main bodies adjacent to each other in the lengthwise direction, and a plurality of the wall main bodies are tension-integrated by a PC steel material in the lengthwise direction.
Concrete concrete balustrades and roadside walls.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10989596A JP3370847B2 (en) | 1996-04-30 | 1996-04-30 | Concrete road side wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10989596A JP3370847B2 (en) | 1996-04-30 | 1996-04-30 | Concrete road side wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09296415A true JPH09296415A (en) | 1997-11-18 |
JP3370847B2 JP3370847B2 (en) | 2003-01-27 |
Family
ID=14521890
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10989596A Expired - Lifetime JP3370847B2 (en) | 1996-04-30 | 1996-04-30 | Concrete road side wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3370847B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002146721A (en) * | 2000-11-14 | 2002-05-22 | Chiyoda Engineering Consultants Co Ltd | Precast wall balustrade installation method |
KR100442641B1 (en) * | 2001-12-22 | 2004-08-02 | 주식회사 포스코 | Post fixing structure of steel barrier for steel deck bridge using plate of stress distribution |
JP2013249617A (en) * | 2012-05-31 | 2013-12-12 | Ihi Corp | Bridge |
CN114737475A (en) * | 2022-04-28 | 2022-07-12 | 西安理工大学 | Assembled energy-dissipation anti-collision wall and assembling method thereof |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102119595B1 (en) * | 2018-05-31 | 2020-06-08 | 충남대학교산학협력단 | Safety barrier |
-
1996
- 1996-04-30 JP JP10989596A patent/JP3370847B2/en not_active Expired - Lifetime
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002146721A (en) * | 2000-11-14 | 2002-05-22 | Chiyoda Engineering Consultants Co Ltd | Precast wall balustrade installation method |
KR100442641B1 (en) * | 2001-12-22 | 2004-08-02 | 주식회사 포스코 | Post fixing structure of steel barrier for steel deck bridge using plate of stress distribution |
JP2013249617A (en) * | 2012-05-31 | 2013-12-12 | Ihi Corp | Bridge |
CN114737475A (en) * | 2022-04-28 | 2022-07-12 | 西安理工大学 | Assembled energy-dissipation anti-collision wall and assembling method thereof |
CN114737475B (en) * | 2022-04-28 | 2023-08-11 | 中国水利水电第十四工程局有限公司 | Assembled energy-dissipation anti-collision wall and assembling method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP3370847B2 (en) | 2003-01-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5285964A (en) | Method for constructing a railroad in concrete having vertical and lateral adjustment steps prior to concrete pouring | |
US5145278A (en) | Modular steel bridge and traffic barrier and methods of fabrication and application therefor | |
RU2413814C2 (en) | Road guide structure | |
KR101633431B1 (en) | Expandable bridge sidewalk and it's construction method | |
JP2008121374A (en) | Structure for embedding expansion joint in highway bridge | |
JP4823937B2 (en) | Fall bridge prevention structure | |
CA2219383C (en) | Interface strip for road/rail crossing | |
KR101604640B1 (en) | Footbridges footbridges installed by the installation method and installation method | |
JP3370847B2 (en) | Concrete road side wall | |
JP3370846B2 (en) | Concrete road side wall | |
JP2010001730A (en) | Replacing guard fence column for bridge in existing ground-covering concrete | |
CN109537393B (en) | Municipal works road laying structure | |
JP6360769B2 (en) | Widening method of existing road bridge | |
US6439470B1 (en) | Prefabricated embedded railway track system with removable inserts | |
JPH0738330Y2 (en) | Height adjustment structure for bridge slab | |
KR102291171B1 (en) | Across river | |
JPH09291516A (en) | Concrete guard fence | |
JP2007231631A (en) | Load bearing expansion joint of elevated road | |
KR100508773B1 (en) | A Floor of Temporary Bridge for using Seet Pile and It's Constructing Method | |
JPH082164Y2 (en) | Bridge slab repair structure | |
KR100659732B1 (en) | Slant type anchor and Set up method of expansion joint using the anchor | |
KR102501119B1 (en) | expandable footbridge with level adjustable | |
KR970043630A (en) | Prefabricated retaining wall device and its installation method | |
KR102291172B1 (en) | Across river | |
JP3661999B2 (en) | Construction method of guardrail foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071115 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081115 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091115 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101115 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101115 Year of fee payment: 8 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101115 Year of fee payment: 8 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101115 Year of fee payment: 8 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111115 Year of fee payment: 9 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121115 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121115 Year of fee payment: 10 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121115 Year of fee payment: 10 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131115 Year of fee payment: 11 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |