JPH082164Y2 - Bridge slab repair structure - Google Patents
Bridge slab repair structureInfo
- Publication number
- JPH082164Y2 JPH082164Y2 JP1991107566U JP10756691U JPH082164Y2 JP H082164 Y2 JPH082164 Y2 JP H082164Y2 JP 1991107566 U JP1991107566 U JP 1991107566U JP 10756691 U JP10756691 U JP 10756691U JP H082164 Y2 JPH082164 Y2 JP H082164Y2
- Authority
- JP
- Japan
- Prior art keywords
- slab
- concrete
- floor slab
- concrete floor
- new
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】[0001]
【産業上の利用分野】本考案は既設の橋梁床版に用いる
床版の補修構造に係わり、特にコンクリート床版を用い
た橋梁床版の補修構造に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slab repair structure used for an existing bridge slab, and more particularly to a bridge slab repair structure using a concrete slab.
【0002】[0002]
【従来の技術】近年、短い交通規制期間内での施工を必
要とする橋梁などの床版の補修において、工期の短縮が
可能なプレキャストコンクリート床版を用いることによ
って、交通量の少ない夜間に全面通行止め或いは片側通
行止めを実施して補修作業を行うとともに、交通量の多
い昼間に路面を全面解放して、通行上の支障を来さない
ようにする方法が一般化している。この方法は、先ず補
修すべき既設のコンクリート床版を取り壊してこれを主
桁などより撤去し、その後、この撤去部分に高さ調整用
のボルトを介して新設のコンクリート床版を主桁上に載
置して、一旦路面の通行を仮解放する。次に、補修部の
路面を再び通行止めにした後、前記新設のコンクリート
床版に対して仮緊張を行うとともに、各コンクリート床
版間の目地に、無収縮モルタルなどの硬化性の充填部材
を打設し、この無収縮モルタルが硬化した後に本緊張を
行うことによって、路面の通行を再度解放するようにし
ている。In recent years, in the repair of slabs, such as bridges that require construction in the short traffic regulation period, by using a precast concrete slab shortening that is possible construction period, at night less traffic performs repair work to implement a full way and stopper or side road closures, road and entirely released, how to prevent hexa the passage on the trouble has been generalized to daytime heavily traveled. In this method, the existing concrete floor slab to be repaired is first demolished and removed from the main girder, etc., and then the newly installed concrete floor slab is placed on the main girder at this removed part through the bolts for height adjustment. Place and temporarily release road traffic. Next, after the road surface of the repair section was closed again, temporary tension was applied to the new concrete floor slab, and at the joints between the concrete floor slabs, a curable filling member such as non-shrink mortar was struck. After the non-shrink mortar is hardened, the main tension is applied to reopen the road surface.
【0003】上記従来技術においては、仮交通規制解除
時には、新設のコンクリート床版が何等固定されずにそ
のまま載置されており、新設のコンクリート床版上の路
面は不安定な状態となって、その通行に極めて危険を伴
うといった問題点を有していた。In the above prior art, when the temporary traffic regulation is released, the new concrete floor slab is placed as it is without being fixed, and the road surface on the new concrete floor slab becomes unstable. There was a problem that the passage was extremely dangerous.
【0004】そこで、特開平3−103510号公報で
は、新床版と旧床版との間に一時的に櫛歯状軸力伝達具
を挿入配置し、該伝達具と旧床版との間に超速硬コンク
リートを充填する合成桁床版の打換え施工方法であっ
て、前記伝達具は、新床版の側面より一定間隔毎に突設
した、それぞれ配力筋を避ける凹部を間けつ的に形成し
たものが提案されている。 Therefore, in Japanese Patent Laid-Open No. 3-103510,
Is a comb-shaped axial force transmitting device between the new floor slab and the old floor slab.
Insert and place the ultra-fast hard concrete between the transmission tool and the old floor slab.
It is a replacement construction method for synthetic girder floor slabs filled with REIT.
The transmission tool is projected from the side of the new floor slab at regular intervals.
Recesses are formed in intervals to avoid force distribution muscles.
Have been proposed.
【0005】[0005]
【考案が解決しようとする課題】上記合成桁床版の打換
え施工方法では、前記旧床版と櫛歯状伝達具とは超速硬
コンクリートにより連結されるものの、前記新床版の側
面に伝達具の端面を突き当てているだけであるため、旧
床版に新床版が連結されておらず、また、新床版の前記
配力筋に合わせて伝達具に凹部を形成するため、伝達具
の製作が煩雑になると共に、型代などにより伝達具の製
作費が大となることが予想され、さらに、伝達具を新旧
の床版の間に挿入配置した後、旧床版と伝達具との隙間
に超速硬コンクリートを充填するため、そのコンクリー
トの硬化時間が必要となり、現場での施工性に劣るとい
う問題がある。 [Problems to be solved by the invention] Replacement of the above synthetic girder slab
In the construction method, the old floor slab and the comb-shaped transmitter are ultra-fast
Although connected by concrete, the side of the new slab
Since the end face of the transmission tool is only abutted against the surface,
The new floor slab is not connected to the floor slab, and
Since the recess is formed in the transmitter according to the distribution muscle,
Manufacturing becomes complicated, and the transmission tool is
Expected to cost a lot of money
After placing it between the floor slabs, the gap between the old floor slab and the transmission tool
The concrete is filled with ultra-quick concrete.
It takes time to harden and the workability at the site is inferior.
I have a problem.
【0006】そこで本考案は上記問題点を解決して、既
設のコンクリート床版への新設のプレキャストコンクリ
ート床版の連結作業を短時間で簡便に行うことができ、
仮交通規制解除時において、新設のコンクリート床版上
の路面に対して、その通行の安全を確保できる橋梁床版
の補修構造を提供することを目的とする。[0006] Accordingly, the present invention is to solve the above problems, already
New precast concrete to concrete floor slab
The connection work of the floor slab can be done easily in a short time,
It is an object of the present invention to provide a bridge slab repair structure that can ensure the safety of traffic on a new concrete slab when temporary traffic restrictions are lifted.
【0007】[0007]
【課題を解決するための手段】本考案は、路面をなす既
設のコンクリート床版の一部を撤去し、この撤去部分に
新設のプレキャストコンクリート床版を載置した橋梁床
版の補修構造において、前記既設のコンクリート床版と
新設のコンクリート床版にそれぞれアングルの 一側を上
方に突設すると共に、これらアングルの一側間を両端に
ナットを螺合する丸鋼により連結したものである。[Means for Solving the Problems] The present invention is a bridge slab repair structure in which a part of an existing concrete floor slab forming a road surface is removed, and a new precast concrete slab is placed on the removed portion. Place one side of the angle on each of the existing concrete slab and the new concrete slab.
It is projected to one side and one side of these angles is at both ends.
The nuts are connected with each other by threaded round steel .
【0008】[0008]
【作用】上記構成によって、既設のコンクリート床版と
新設のプレキャストコンクリート床版は、アングルを介
して両端にナットを螺合する丸鋼によって一体的に連結
され、これによって新しいコンクリート床版の仮固定が
図られる。また、床版の上に突出したアングルの一側
を、両端にナットを螺合した丸鋼により連結するため、
その連結作業を短時間で簡便に行うことができる。 [Operation] With the above structure, the existing concrete floor slab and the new precast concrete floor slab are inserted through the angle.
And both ends nuts are coupled to the thus integrally screwed round steel and thereby the temporary fixing of a new concrete slab can be achieved. Also, one side of the angle protruding above the floor slab
Are connected by round steel with nuts screwed on both ends,
The connecting work can be performed easily in a short time.
【0009】[0009]
【実施例】以下、本考案の一実施例を添付図面を参照し
て説明する。図1及び図2において、1は橋梁などに並
設されるH型の主桁であり、この主桁1の上下方向に形
成されたフランジ部2の上面には既設のコンクリート床
版3が架設され、両面通行の可能な平面状の路面4が形
成されている。5は、補修すべきの路面4の片側に形成
された切断面であり、この切断面5によって既設のコン
クリート床版3の一部が撤去される。そして、この撤去
された部分には、新しいプレキャストコンクリート床版
6が路面4に対して複数直角方向に載置されている。コ
ンクリート床版6は、予め路面4と平行な貫通孔7が穿
設されるとともに、内方側面にアングル8が固着され
る。また、各コンクリート床版6間に形成される目地9
の適所には、弾性部材たるゴムパッキン10が介在され
る。そして、コンクリート床版6の載置時においては、
路面4の中央寄りに位置する主桁1のフランジ部2と、
前記アングル8との間に高さ調整ボルト11を螺入し、こ
の高さ調整ボルト11を介して、各コンクリート床版6に
対するレベル調整を順次行う。なお、12はコンクリート
床版6に埋設された棒状の異径鉄筋である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the accompanying drawings. In FIGS. 1 and 2, reference numeral 1 denotes an H-shaped main girder installed in parallel on a bridge or the like, and an existing concrete floor slab 3 is installed on the upper surface of a flange portion 2 formed in the vertical direction of the main girder 1. Thus, a flat road surface 4 capable of passing on both sides is formed. Reference numeral 5 is a cut surface formed on one side of the road surface 4 to be repaired, and the cut surface 5 removes a part of the existing concrete floor slab 3. Then, a plurality of new precast concrete floor slabs 6 are placed at right angles to the road surface 4 in the removed portion. In the concrete floor slab 6, a through hole 7 parallel to the road surface 4 is previously drilled, and an angle 8 is fixed to the inner side surface. In addition, joints 9 formed between each concrete floor slab 6
A rubber packing 10, which is an elastic member, is interposed at a proper position. When the concrete floor slab 6 is placed,
The flange portion 2 of the main girder 1 located near the center of the road surface 4,
A height adjusting bolt 11 is screwed into the angle 8 and the level of each concrete floor slab 6 is sequentially adjusted through the height adjusting bolt 11. In addition, 12 is a rod-shaped rebar of different diameter embedded in the concrete floor slab 6.
【0010】13は、新設のコンクリート床版6の外方両
端上下方向、及び内方側面に配設された一対の仮緊張具
である。この仮緊張具13はその略中央に抜孔14が穿設さ
れており、この抜孔14に鋼製のねじ棒たるゲビンデスタ
ーブ15が路面4と平行に挿通される。また、16は既設の
各コンクリート床版3と新設の各コンクリート床版6と
の間に連結される継手部材であり、この継手部材16は、
コンクリート床版6に埋設されるインサート17とボルト
18とによりアングル19を固設するとともに、コンクリー
ト床版3のはつり部分にホールインアンカー20を打ち込
んで別のアングル21を固設し、ナット22により前記アン
グル19,21間に丸鋼23を固着することによって構成され
るものである。Numeral 13 is a pair of temporary tensioning tools which are arranged on both outer and upper and lower sides of the new concrete floor slab 6 and on the inner side surfaces. The provisional tensioning tool 13 has a hole 14 formed substantially in the center thereof, and a steel threaded rod, a Gevin disturb 15, is inserted into the hole 14 in parallel with the road surface 4. 16 is a joint member connected between each existing concrete slab 3 and each new concrete slab 6, and the joint member 16 is
Insert 17 and bolt embedded in concrete floor slab 6
The angle 19 is fixed by 18 and the hole-in anchor 20 is driven into the edge of the concrete slab 3 to fix another angle 21, and the nut 22 fixes the round steel 23 between the angles 19 and 21. It is configured by
【0011】図4は、新設のコンクリート床版6を載置
した後における、コンクリート床版6の仮緊張状態を示
すものである。仮緊張具13は予めボルト25によってコン
クリート床版6に固着されており、この仮緊張具13の一
方に位置するゲビンデスターブ15の一端には、仮緊張具
13の立設面26に当接するナット27が螺入されるととも
に、新設のコンクリート床版6の側面には伸縮可能なジ
ャッキ28が横設され、このジャッキ28の移動部29にゲビ
ンデスターブ15の他端が固着される。そして、ジャッキ
28の移動部29を外方に移動させることにより、各ゲビン
デスターブ15に対して引張力を与え、これによって、目
地9にゴムパッキン10を介在させた状態で各コンクリー
ト床版6の仮緊張が行われる。FIG. 4 shows a temporary tension state of the concrete floor slab 6 after placing the new concrete floor slab 6. The temporary tensioning tool 13 is fixed to the concrete floor slab 6 in advance by bolts 25, and one end of the Gebin Desturb 15 located at one side of the temporary tensioning tool 13 has a temporary tensioning tool.
A nut 27 that comes into contact with the standing surface 26 of 13 is screwed in, and an expandable and contractible jack 28 is laterally provided on the side surface of the new concrete floor slab 6, and the moving portion 29 of this jack 28 has the Gevin Desturb 15 The other end is fixed. And jack
By moving the moving part 29 of 28 to the outside, a tensile force is applied to each of the Gevin disturbs 15, so that the temporary tension of each concrete floor slab 6 with the rubber packing 10 interposed in the joint 9 is applied. Done.
【0012】コンクリート床版6の仮緊張後には、一
旦、交通規制の仮解除が行われる。すなわち、図5に示
すように、コンクリート床版6の外方に位置する仮緊張
具13及びケビンデスターブ15上にH型の鋼材31が配設さ
れるとともに、継手部材16上を覆うようにして単管バリ
ケード32が設けられ、さらに、路面4上の凹所に必要に
応じて覆工板を配設することで、路面4上の通行を可能
とする。After the temporary tension of the concrete floor slab 6, the traffic restrictions are temporarily released. That is, as shown in FIG. 5 , the H-shaped steel material 31 is arranged on the temporary tensioning tool 13 and the Kevin disturb 15 located outside the concrete floor slab 6 and covers the joint member 16. A single pipe barricade 32 is provided, and a lining plate is provided in a recessed portion on the road surface 4 as necessary, so that the road surface 4 can be passed.
【0013】次いで、再度通行規制を行う際、図6に示
すように、仮緊張状態のまま前記目地9に硬化性を有す
る充填部材たる無収縮モルタル34を打設する。ここで、
再び交通規制を解除し、無収縮モルタル34が硬化した後
に、通行規制を行う。そして、新設のコンクリート床版
6を仮緊張した状態で、このコンクリート床版6の反対
側に位置する路面4も、上記と同様に、新しいコンクリ
ート床版6を載置し、その後、継手部材16によってコン
クリート床版6どうしを固定し、仮緊張を行う。こうし
て、路面4の全面にわたって無収縮モルタル34が硬化し
た後、鋼材31及び単管バリケード32等を撤去して、新設
のコンクリート床版6に対して仮緊張を解く。Next, when the passage is restricted again, as shown in FIG. 6 , a non-shrink mortar 34, which is a filling member having a hardening property, is placed on the joint 9 in the temporary tension state. here,
The traffic restrictions are released again, and after the non-shrink mortar 34 is hardened, traffic restrictions are applied. Then, with the newly installed concrete slab 6 temporarily tensioned, a new concrete slab 6 is placed on the road surface 4 located on the opposite side of the concrete slab 6 in the same manner as above, and then the joint member 16 By fixing the concrete slabs 6 to each other, temporary tension is applied. In this way, after the non-shrink mortar 34 has hardened over the entire road surface 4, the steel material 31, the single pipe barricade 32 and the like are removed, and the temporary tension is released to the new concrete floor slab 6.
【0014】図3は、コンクリート床版6の本緊張状態
を示すものである。コンクリート床版6の貫通孔7には
鋼製の緊張材35が挿通され、定着具36により緊張材35を
引張ることにより、コンクリート床版6の本緊張を行
う。緊張材35は、シースにより巻装されている。そし
て、図7に示すように、双方の異径鉄筋12を溶接等によ
り固着し、コンクリート床版6,6間に超早硬コンクリ
ート37を打設するとともに、路面4上の他の凹所に対し
て同様に超早硬コンクリート37を打設して新たな路面4
を形成し、さらに、フランジ部2の上面とアングル8及
びコンクリート床版6の底面との間に無収縮モルタル30
を打設して、補修を完了する。FIG. 3 shows the concrete floor slab 6 in the fully tensioned state. The through-hole 7 of the concrete slab 6 is inserted tendons 35 made of steel, by pulling <br/> tendons 35 by a fixing device 36, performs the tension of the concrete slab 6. The tension member 35 is wound by a sheath. Then, as shown in FIG. 7, the different-diameter rebars 12 are fixed by welding or the like, and the super quick-hardening concrete 37 is placed between the concrete floor slabs 6 and at the other recesses on the road surface 4. On the other hand, a new road surface 4 was created by placing super-hardened concrete 37 in the same way.
And a non-shrink mortar 30 between the upper surface of the flange portion 2 and the bottom surface of the angle 8 and the concrete floor slab 6.
To complete the repair.
【0015】このように、上記実施例においては、既設
のコンクリート床版3と新設のコンクリート床版6に突
出したアングル21,19の一側を、両端にナット22,22を
螺合する丸鋼23により連結することによって既設のコン
クリート床版3と新設のコンクリート床版6とを連結す
ることが可能であり、路面4の仮交通規制解除時におい
て、既設のコンクリート床版3と新設のコンクリート床
版6との固定及び一体化を図って、新設のコンクリート
床版6上の通行の安全を確保することができる。また、
既設のコンクリート床版3と新設のコンクリート床版6
との連結は、コンクリート床版3,6の上に突出したア
ングル21,19の一側を、両端にナット22,22を螺合する
丸鋼23により連結するため、その連結作業を短時間で簡
便に行うことができる。 As described above, in the above embodiment, the existing
On concrete floor slab 3 and new concrete floor slab 6
Put the nuts 22 and 22 on both sides of the angle 21 and 19
It is possible to connect the existing concrete floor slab 3 and the new concrete floor slab 6 by connecting with the round steel 23 that is screwed , and when the temporary traffic regulation of the road surface 4 is released, the existing concrete floor slab 3 It is possible to secure and integrate the new concrete floor slab 6 and the new concrete floor slab 6 to ensure the safety of traffic on the new concrete floor slab 6. Also,
Existing concrete slab 3 and new concrete slab 6
The connection with the
The nuts 22 and 22 are screwed to both ends of one side of the dongles 21 and 19
Since it is connected with round steel 23, the connection work can be simplified in a short time.
Can be done by stool.
【0016】また、この新設のコンクリート床版6間に
ゴムパッキン10を介在させながら仮緊張を行うと、新設
のコンクリート床版6どうしも安定した状態で固定され
るため、継手部材16によって既設のコンクリート床版3
と新設のコンクリート床版6間はより強固に、かつ一体
的に固定され、その安全性をさらに向上させることがで
きる。Further, in this new the between the concrete slab 6 performs temporary tension while interposing a rubber packing 10, since they are fixed in a state of stable servants do concrete slab 6 of new, existing by coupling member 16 Concrete floor slab 3
And the new concrete floor slab 6 are more firmly and integrally fixed, and the safety thereof can be further improved.
【0017】なお、本考案は上記実施例に限定されるも
のではなく、本考案の要旨の範囲内において種々の変形
実施が可能である。例えば、継手部材の大きさ、寸法形
状等は、載置するコンクリート床版に応じて適宜選定可
能である。 The present invention is not limited to the above embodiment, and various modifications can be made within the scope of the present invention. For example, the size of the joint hand member, dimensions, etc., Ru suitably configurable der according to the concrete slab to be placed.
【0018】[0018]
【考案の効果】本考案は路面をなす既設のコンクリート
床版の一部を撤去し、この撤去部分に新設のプレキャス
トコンクリート床版を載置した橋梁床版の補修構造にお
いて、前記既設のコンクリート床版と新設のコンクリー
ト床版にそれぞれアングルの一側を上方に突設すると共
に、これらアングルの一側間を両端にナットを螺合する
丸鋼により連結したものであり、既設のコンクリート床
版への新設のプレキャストコンクリート床版の連結作業
を短時間で簡便に行うことができ、仮交通規制解除時に
おいて、新設のコンクリート床版上の路面に対して、そ
の通行の安全を確保できる橋梁床版の補修構造を提供す
ることができる。[Effect of the Invention] The present invention removes a part of the existing concrete floor slab that forms the road surface, and a new precasing is installed in this removed part.
In the repair structure of the bridge slab on which the concrete slab is placed , it is common that one side of the angle is projected upward to the existing concrete slab and the new concrete slab.
Then, screw nuts on both ends between one side of these angles.
An existing concrete floor that is connected by round steel
Connecting the new precast concrete floor slab to the slab
Therefore, it is possible to provide a bridge slab repair structure capable of ensuring the safety of traffic on a road surface on a new concrete slab when the temporary traffic regulation is lifted.
【図1】本考案の一実施例を示す仮緊張時の斜視図であ
る。FIG. 1 is a perspective view showing an embodiment of the present invention during temporary tension.
【図2】同上コンクリート床版載置状態の要部の正面図
である。FIG. 2 is a front view of the main part of the concrete floor slab mounted on the same.
【図3】同上本緊張後の断面図である。3 is a cross-sectional view after ibid present tense.
【図4】同上仮緊張時における一部拡大側面図である。4 is a partially enlarged side view when ibid temporary tension.
【図5】同上仮緊張時における要部の正面図である。FIG. 5 is a front view of the main part when the above temporary tension is applied.
【図6】同上無収縮モルタル打設時における要部の拡大
断面図である。FIG. 6 is an enlarged cross-sectional view of a main part when the non-shrink mortar is placed .
【図7】同上本緊張後における要部の正面図である。FIG. 7 is a front view of the main part of the same after the main tension.
4 路面 3 コンクリート床版 6 プレキャストコンクリート床版 16 継手部材19,21 アングル 22 ナット 23 丸鋼 4 Road surface 3 Concrete slab 6 Precast concrete slab 16 Joint member 19, 21 Angle 22 Nut 23 Round steel
Claims (1)
部を撤去し、この撤去部分に新設のプレキャストコンク
リート床版を載置した橋梁床版の補修構造において、前
記既設のコンクリート床版と新設のコンクリート床版に
それぞれアングルの一側を上方に突設すると共に、これ
らアングルの一側間を両端にナットを螺合する丸鋼によ
り連結したことを特徴とする橋梁床版の補修構造。[Claim 1] to remove a portion of the existing concrete slab forming the road surface, in the repair structure of a bridge deck mounting the precast Conc <br/> Ried slab of newly established this removal portion, said existing to the concrete floor slab of concrete slab with the newly established
Each one side of the angle is projected upward, and this
A repair structure for a bridge slab, characterized in that one side of the angle is connected by round steel with nuts screwed on both ends .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1991107566U JPH082164Y2 (en) | 1991-12-26 | 1991-12-26 | Bridge slab repair structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1991107566U JPH082164Y2 (en) | 1991-12-26 | 1991-12-26 | Bridge slab repair structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0554610U JPH0554610U (en) | 1993-07-23 |
JPH082164Y2 true JPH082164Y2 (en) | 1996-01-24 |
Family
ID=14462421
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1991107566U Expired - Lifetime JPH082164Y2 (en) | 1991-12-26 | 1991-12-26 | Bridge slab repair structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH082164Y2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6778159B2 (en) * | 2017-07-31 | 2020-10-28 | 鹿島建設株式会社 | Reinforcing structure and floor slab replacement method when replacing the floor slab |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03103510A (en) * | 1989-09-14 | 1991-04-30 | Nippon Steel Corp | Reconstruction method for synthetic girder floor system |
-
1991
- 1991-12-26 JP JP1991107566U patent/JPH082164Y2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03103510A (en) * | 1989-09-14 | 1991-04-30 | Nippon Steel Corp | Reconstruction method for synthetic girder floor system |
Also Published As
Publication number | Publication date |
---|---|
JPH0554610U (en) | 1993-07-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4823937B2 (en) | Fall bridge prevention structure | |
JP2023085814A (en) | Installation structure of floor slab and installation method of floor slab | |
JP5065341B2 (en) | Precast pillar and foundation connection method and temporary cradle. | |
JP2599885B2 (en) | Precast railing and method of joining precast railing and floor slab | |
JP4934779B2 (en) | Boarding / exit structure and boarding / exiting method | |
CN108547209B (en) | Single-hole prefabricated hollow slab bridge without expansion joint and construction method thereof | |
JP2717126B2 (en) | Repair method of median strip and protective wall block used for it | |
JPH082164Y2 (en) | Bridge slab repair structure | |
JPH0782709A (en) | Reinforcing method for concrete structure, employing hollow pc steel bar | |
JPH0738330Y2 (en) | Height adjustment structure for bridge slab | |
WO1996033311A1 (en) | Hinged section construction for a gerber bridge | |
JP2002356814A (en) | Construction method of bridge pc floor slab | |
KR0140845Y1 (en) | Expansion joint for road and bridge | |
JP3450054B2 (en) | Installation method of floor slab on bridge girder and slab cradle | |
KR101986794B1 (en) | Integrated precast slab track system | |
JPH086289B2 (en) | Temporary tensioning method for bridge slab repair work | |
JPH09296415A (en) | Balustrade for concrete wall and road side wall | |
KR100611722B1 (en) | Installation structure of railing support | |
JP3160839B2 (en) | Tie bar with socket for concrete pavement | |
JPH09296414A (en) | Balustrade for concrete wall and road side wall | |
JP7034229B2 (en) | How to build a connected structure of precast structural member and cast-in-place cured material of repaired part of cross-section repair | |
JP7250967B1 (en) | Precast concrete slab and its construction method | |
KR102527063B1 (en) | Expansion Joint Device Capable Of Prestressing Sound Absorbing Material | |
KR102086932B1 (en) | Precasted Inverted T Concerete Girder and Method for making thereof | |
JP4093427B2 (en) | High-strength reinforced concrete precast plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |