JPH09235726A - Construction method of underground continuous wall - Google Patents

Construction method of underground continuous wall

Info

Publication number
JPH09235726A
JPH09235726A JP4639596A JP4639596A JPH09235726A JP H09235726 A JPH09235726 A JP H09235726A JP 4639596 A JP4639596 A JP 4639596A JP 4639596 A JP4639596 A JP 4639596A JP H09235726 A JPH09235726 A JP H09235726A
Authority
JP
Japan
Prior art keywords
concrete
wall
underground
constructing
partition plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4639596A
Other languages
Japanese (ja)
Other versions
JP3536270B2 (en
Inventor
Katsuhiko Kimura
克彦 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP04639596A priority Critical patent/JP3536270B2/en
Publication of JPH09235726A publication Critical patent/JPH09235726A/en
Application granted granted Critical
Publication of JP3536270B2 publication Critical patent/JP3536270B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To increase the placement speed of concrete when constructing an underground continuous wall. SOLUTION: A method, which constructs an underground wall A as an element, is designed to secure a connection space 7 with an adjacent wall outside a partition plate 6 by excavating a groove 2 for an underground wall underground, positioning a cage 4 into the groove 4, placing concrete 10 into an inside space segmented with the partition plate 6 mounted on the cage 4 by way of a tremie pipe. Prior to concrete placement, a porous pipe 20 is inserted into the cage 4 so as to suck up the moisture contained in the concrete. While the concrete 10 is being placed, the moisture contained in the concrete 10 is sucked up with the porous pipe 20 and drained, thereby lowering the fluidity of the placed concrete 10 and reducing a lateral pressure acting on the partition plate 6.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、現場でコンクリー
トを打設して地下壁を構築する地下連続壁の施工方法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing an underground continuous wall by placing concrete on site to construct an underground wall.

【0002】[0002]

【従来の技術】図5、図6、図7を用いて従来の地下連
続壁の施工方法の一例を説明する。この施工方法では、
図7に示すように、まず、構築しようとする地下連続壁
Hを、先行エレメントAと後行エレメントBとに分け
る。そして、図7(a)に示すように、先行エレメント
Aを間隔をおいて先行して施工し、次いで、図7(b)
に示すように、両側を先行エレメントA、Aで挟まれた
部分に後行エレメントBを施工し、それにより連続した
地下壁(地下連続壁)Hを完成する。
2. Description of the Related Art An example of a conventional underground continuous wall construction method will be described with reference to FIGS. 5, 6, and 7. In this construction method,
As shown in FIG. 7, first, the underground continuous wall H to be constructed is divided into a leading element A and a trailing element B. Then, as shown in FIG. 7 (a), the preceding element A is installed in advance at an interval, and then, as shown in FIG. 7 (b).
As shown in FIG. 5, the trailing element B is applied to the portion sandwiched by the leading elements A and A on both sides, thereby completing the continuous underground wall (underground continuous wall) H.

【0003】先行エレメントAの施工では、まず、図5
(a)に示すように、地盤1中(土中)に、地下壁を作
るための所定深さおよび所定長さの溝2を掘削し、スラ
イム3を除去する。次に、図5(b)に示すように、溝
2の内部に鉄筋かご4をクレーンで吊り下ろして建て込
む。その際、鉄筋かご4の鉄筋5には、仕切板6とベラ
シート8を取り付けておく。ベラシート8は、溝2の幅
方向(地下連続壁の厚さ方向)の土壁に面する部分に設
ける。この部分は、所要のコンクリート圧力に耐える強
度を持っている。また、仕切板6は、溝2の長さ方向両
端部に位置する部分の鉄筋5に連結部材(図示略)を用
いて取り付ける。この場合、仕切板6の外側(溝2の長
さ方向両端部)に、後行エレメントとの連結用空間7を
確保するよう設ける。
In constructing the preceding element A, first, referring to FIG.
As shown in (a), a groove 2 having a predetermined depth and a predetermined length for making an underground wall is excavated in the ground 1 (in the soil), and the slime 3 is removed. Next, as shown in FIG. 5 (b), the reinforcing bar cage 4 is hung inside the groove 2 by a crane to be built. At that time, the partition plate 6 and the vera sheet 8 are attached to the reinforcing bar 5 of the reinforcing bar car 4. The vera sheet 8 is provided in a portion facing the soil wall in the width direction of the groove 2 (thickness direction of the underground continuous wall). This part is strong enough to withstand the required concrete pressure. Further, the partition plate 6 is attached to the reinforcing bars 5 located at both ends in the length direction of the groove 2 by using a connecting member (not shown). In this case, it is provided outside the partition plate 6 (both ends in the length direction of the groove 2) so as to secure a space 7 for connection with the succeeding element.

【0004】鉄筋かご4を建て込んだら、図5(c)に
示すように、両方の仕切板6、6とベラシート8、8と
で囲まれた内側の空間内に、トレミー管9を介してコン
クリート10を打設する。そして、先行エレメントAと
しての地下壁を完成する。
After the reinforcing bar cage 4 is built in, as shown in FIG. 5 (c), the tremie pipe 9 is inserted into the inner space surrounded by the partition plates 6 and 6 and the vera sheets 8 and 8. Concrete 10 is poured. Then, the underground wall as the preceding element A is completed.

【0005】図7(a)に示すように先行エレメントA
を完成したら、次に、図6(d)に示すように、先行エ
レメントA、A間の土砂11を除去し、先行エレメント
A、A間の残りの部分の溝12を掘削する。この溝12
は、先行エレメントAを施工する際に残した両側の連結
用空間7、7とつながる。次いで、図6(e)に示すよ
うに、この溝12に鉄筋かご14を建て込み、鉄筋かご
14を建て込んだら、図6(f)に示すように、トレミ
ー管9を介してコンクリート10を打設し、先行エレメ
ントAの鉄筋5と連結した後行エレメントBを構築し
て、これにより地下連続壁Hを完成する。
As shown in FIG. 7A, the preceding element A
When the above is completed, next, as shown in FIG. 6D, the earth and sand 11 between the preceding elements A and A is removed, and the groove 12 of the remaining portion between the preceding elements A and A is excavated. This groove 12
Is connected to the connecting spaces 7, 7 on both sides left when the preceding element A is constructed. Next, as shown in FIG. 6 (e), a reinforcing bar cage 14 is built in this groove 12, and after the reinforcing bar cage 14 is built in, concrete 10 is put through the tremie pipe 9 as shown in FIG. 6 (f). A trailing element B, which is cast and connected to the reinforcing bars 5 of the preceding element A, is constructed, thereby completing the underground continuous wall H.

【0006】[0006]

【発明が解決しようとする課題】上記の施工方法では、
先行エレメントAを施工する際に、鉄筋かご4に取り付
けた仕切板6によって、次に施工する後行エレメントB
との連結用空間7を確保している。したがって、コンク
リート10を打設した際には、コンクリート10の側圧
を、全面的にこの仕切板6およびベラシート8で受けな
ければならない。この場合、コンクリート10は、所要
の施工性を得るに必要な水分を含み、高い流動性を持っ
た状態で打設されるので、打設高さが増すにつれて、流
動体による大きな側圧が仕切板6の下部にかかることに
なる。このため、側圧が過大にならないように、ある程
度の凝結の進行を待ちながら、ゆっくりとコンクリート
10を打設している。
[Problems to be Solved by the Invention] In the above construction method,
When constructing the preceding element A, the trailing element B to be constructed next by the partition plate 6 attached to the rebar cage 4
A space 7 for connection with is secured. Therefore, when the concrete 10 is cast, the lateral pressure of the concrete 10 must be entirely received by the partition plate 6 and the vera sheet 8. In this case, since the concrete 10 contains water necessary for obtaining the required workability and is placed in a state of high fluidity, as the placement height increases, a large lateral pressure due to the fluid is applied to the partition plate. It will be at the bottom of 6. For this reason, concrete 10 is slowly poured while waiting for the progress of setting to some extent so that the lateral pressure does not become excessive.

【0007】しかし、例えば100m以上の深さの地下
連続壁を施工する場合に、5m/hの速度でコンクリー
トを打設すると、20時間以上の施工時間がかかること
になる。従って、施工時間の関係で、コストの高騰や、
住宅地の場合は夜間の騒音問題が持ち上がってくる。
However, for example, when constructing an underground continuous wall having a depth of 100 m or more, if concrete is poured at a speed of 5 m / h, it takes 20 hours or more for construction. Therefore, due to the construction time, soaring costs,
In the case of residential areas, nighttime noise problems will arise.

【0008】本発明は、上記事情を考慮し、簡単な手段
を講じることで、コンクリートの打設速度を上げて、施
工時間の短縮を図ることのできる地下連続壁の施工方法
を提供することを目的とする。
In view of the above circumstances, the present invention provides a method for constructing an underground continuous wall, which is capable of increasing the concrete pouring speed and shortening the construction time by taking simple measures. To aim.

【0009】[0009]

【課題を解決するための手段】請求項1の発明は、土中
に地下壁構築用の溝を掘削し、溝内に鉄筋かごを建て込
み、鉄筋かごに取り付けた仕切板で画成された内側の空
間にトレミー管を介してコンクリートを打設し、仕切板
の外側に隣接壁との連結用空間を確保した状態で地下壁
を構築する地下連続壁の施工方法において、コンクリー
ト打設前に、鉄筋かごの中にコンクリート中の水分を吸
い上げるための吸い上げ部材を挿入し、コンクリートを
打設しながら、吸い上げ部材によってコンクリート中の
水分を吸い上げて排水することにより、打設済みコンク
リートの流動性を低下させて、仕切板に作用する側圧を
低減することを特徴とする。
According to a first aspect of the present invention, a groove for constructing an underground wall is excavated in the soil, a rebar cage is built in the groove, and a partition plate attached to the rebar cage is defined. In the method of constructing an underground continuous wall where concrete is placed in the inner space via a tremie pipe and the space for connecting with the adjacent wall is secured outside the partition plate, before the concrete is placed in the construction method of the underground continuous wall. By inserting a wicking member to wick moisture in the concrete into the reinforced basket and pouring the concrete, the wicking member wicks the moisture in the concrete and drains it to improve the fluidity of the placed concrete. It is characterized by lowering the lateral pressure acting on the partition plate.

【0010】この場合、吸い上げ部材としては、請求項
2の発明のように管壁に多数の孔を有した有孔管を用い
たり、請求項4の発明のように長尺の不織布を用いたり
することができる。また、有孔管を用いる場合は、請求
項3の発明のように、有孔管の外周に、コンクリートの
管内への流入を防ぐフィルタ材を設けるのがよい。
In this case, as the suction member, a perforated pipe having a large number of holes in the pipe wall as in the invention of claim 2 or a long non-woven fabric as in the invention of claim 4 is used. can do. When a perforated pipe is used, it is preferable that a filter material for preventing concrete from flowing into the pipe is provided on the outer periphery of the perforated pipe as in the invention of claim 3.

【0011】[0011]

【発明の実施の形態】以下、本発明の実施形態を図面に
基づいて説明する。この実施形態の施工方法は、前述の
図5〜図7の地下連続壁の施工方法において、先行エレ
メントAを施工するに当たって、一部改良を加えたもの
である。即ち、コンクリート10の打設前に、図1及び
図2に示すように、鉄筋かご4の中に、コンクリート1
0中の水分を吸い上げるための有孔管20(吸い上げ部
材)を挿入し、コンクリート10を打設しながら、有孔
管20によってコンクリート10中の水分22を吸い上
げて排水するものである。その他の構成は前述の従来例
と同じである。
Embodiments of the present invention will be described below with reference to the drawings. The construction method of this embodiment is the construction method of the continuous underground wall shown in FIG. 5 to FIG. 7, with some improvements made in constructing the preceding element A. That is, before placing the concrete 10, as shown in FIGS. 1 and 2, the concrete 1
A perforated pipe 20 (sucking member) for sucking up the water in 0 is inserted, and while pouring the concrete 10, the water 22 in the concrete 10 is sucked up by the perforated pipe 20 and drained. Other configurations are the same as those of the above-mentioned conventional example.

【0012】有孔管20は、図3に示すように、管壁に
多数の孔20aを有したもので、コンクリート10の内
部に適当間隔で位置するように配置してあり、その外周
がフィルタ材としての不織布21により覆われ、管内に
コンクリート10が流入しないようになっている。
As shown in FIG. 3, the perforated pipe 20 has a large number of holes 20a in the pipe wall and is arranged so as to be positioned inside the concrete 10 at appropriate intervals, and its outer periphery is a filter. It is covered with a non-woven fabric 21 as a material so that the concrete 10 does not flow into the pipe.

【0013】このような有孔管20を鉄筋かご4内に挿
入した上で、コンクリート10を打設することにより、
コンクリート10中の水分22を積極的に取り除いて、
打設済みコンクリート10の流動性を低下させることが
できる。つまり、打設されたコンクリート10の自重に
よりコンクリート10の加圧脱水を行い、積極的にコン
クリート10の流動性を失わせて、見掛け上の凝結を進
め、それにより、仕切板6に対する側圧の低減を図るこ
とができる。従って、側圧の低減効果により、コンクリ
ート10の打設速度をアップさせることができ、例えば
打設速度を5m/hから7m/hにすることにより、1
00mの地下連続壁を施工するに当たり、施工時間を2
0時間から15時間程度に短縮することができる。その
結果、深夜にかからずに作業を終了することができて、
施工の合理化とコストの低減が図れる。
By inserting such a perforated pipe 20 into the rebar cage 4 and then placing concrete 10,
By actively removing the water 22 in the concrete 10,
The fluidity of the cast concrete 10 can be reduced. That is, the weight of the cast concrete 10 is dewatered under pressure to positively lose the fluidity of the concrete 10 and promote apparent coagulation, thereby reducing the lateral pressure on the partition plate 6. Can be achieved. Therefore, due to the effect of reducing the lateral pressure, the pouring speed of the concrete 10 can be increased. For example, by changing the pouring speed from 5 m / h to 7 m / h, 1
It takes 2 hours to construct a continuous underground wall of 00m.
It can be shortened from 0 hours to about 15 hours. As a result, I was able to finish the work in the middle of the night,
Rationalization of construction and cost reduction can be achieved.

【0014】なお、有孔管20以外に、図4に示すよう
に、長尺の不織布30を吸い上げ部材として、何本かベ
ラシート8に沿って配設してもよいし、ベラシート8自
体に排水機能を持たせてもよい。
In addition to the perforated pipe 20, as shown in FIG. 4, a long non-woven fabric 30 may be arranged along the vera sheet 8 as a suction member, or the vera sheet 8 itself may be drained. It may have a function.

【0015】[0015]

【発明の効果】以上説明したように、請求項1の発明に
よれば、吸い上げ部材によって打設済みのコンクリート
の水分を排除し、コンクリート自重により加圧脱水を進
めながら、コンクリートを打設するので、コンクリート
の流動性を低下させることができて、仕切板に作用する
側圧を低減することができる。従って、側圧の低減効果
により、コンクリートの打設速度を上げることができ、
施工の合理化及びコストの低減を図ることができる。な
お、吸い上げ部材としては、請求項2の発明のように有
孔管を用いたり、請求項4の発明のように長尺の不織布
を用いたりすることができ、いすれの場合も、簡単な部
材を新たに追加するだけで、技術的に実現が容易であ
る。また、有孔管を用いる場合は、請求項3の発明のよ
うにフィルタ材で外周を覆うことで、コンクリートの管
内への流入を防止することができ、水分のみの除去が可
能になる。
As described above, according to the first aspect of the present invention, the moisture is removed from the concrete that has been cast by the suction member, and the concrete is cast while the pressure dehydration is promoted by the weight of the concrete. The fluidity of concrete can be reduced, and the lateral pressure acting on the partition plate can be reduced. Therefore, due to the side pressure reduction effect, the concrete pouring speed can be increased,
It is possible to rationalize construction and reduce costs. As the suction member, a perforated pipe as in the invention of claim 2 or a long non-woven fabric as in the invention of claim 4 can be used. It is technically easy to realize by simply adding a new member. When a perforated pipe is used, by covering the outer periphery with a filter material as in the third aspect of the invention, it is possible to prevent the concrete from flowing into the pipe, and it is possible to remove only water.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施形態の施工方法により、先行エレ
メントとしての地下壁のコンクリートを打設した状態を
示す平面図である。
FIG. 1 is a plan view showing a state in which concrete for a subterranean wall as a preceding element is placed by a construction method according to an embodiment of the present invention.

【図2】図1のII−II矢視断面図である。FIG. 2 is a sectional view taken along the line II-II of FIG.

【図3】図2のIII−III矢視断面図である。FIG. 3 is a sectional view taken along the line III-III in FIG.

【図4】本発明の別の実施形態の施工方法により、先行
エレメントとしての地下壁のコンクリートを打設した状
態を示す平面図である。
FIG. 4 is a plan view showing a state in which concrete of a subterranean wall as a preceding element is placed by a construction method according to another embodiment of the present invention.

【図5】従来の地下連続壁の施工方法の説明図であり、
図(a)、(b)、(c)は先行エレメントを施工する
場合の工程を順に示す図で、各(a)、(b)、(c)
の上の図は地下壁の壁面に沿った鉛直断面図、下の図は
地下壁の水平断面図である。
FIG. 5 is an explanatory diagram of a conventional underground continuous wall construction method,
(A), (b), (c) is a figure which shows the process at the time of constructing a preceding element in order, (a), (b), (c)
The upper figure is a vertical sectional view along the wall surface of the underground wall, and the lower figure is a horizontal sectional view of the underground wall.

【図6】従来の地下連続壁の施工方法の説明図であり、
図(d)、(e)、(f)は後行エレメントを施工する
場合の工程を順に示す図で、各(d)、(e)、(f)
の上の図は地下壁の壁面に沿った鉛直断面図、下の図は
地下壁の水平断面図である。
FIG. 6 is an explanatory view of a conventional underground continuous wall construction method,
Drawings (d), (e), and (f) are views showing the steps in the case of constructing the trailing element in order, and (d), (e), and (f)
The upper figure is a vertical sectional view along the wall surface of the underground wall, and the lower figure is a horizontal sectional view of the underground wall.

【図7】従来の地下連続壁の施工順序の説明に用いる模
式図であり、(a)は先行エレメントを施工した状態を
示し、(b)は次いで後行エレメントを施工した状態を
示す図である。
[Fig. 7] Fig. 7 is a schematic diagram used for explaining the order of construction of a conventional underground continuous wall, in which (a) shows a state in which a preceding element is constructed and (b) shows a state in which a trailing element is constructed next. is there.

【符号の説明】[Explanation of symbols]

2 溝 4 鉄筋かご 6 仕切板 7 連結用空間 9 トレミー管 10 コンクリート 20 有孔管(吸い上げ部材) 20a 孔 21 不織布(フィルタ材) 30 不織布(吸い上げ部材) 2 groove 4 rebar cage 6 partition plate 7 connecting space 9 tremie pipe 10 concrete 20 perforated pipe (sucking member) 20a hole 21 non-woven fabric (filter material) 30 non-woven fabric (sucking member)

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 土中に地下壁構築用の溝を掘削し、溝内
に鉄筋かごを建て込み、鉄筋かごに取り付けた仕切板で
画成された内側の空間にトレミー管を介してコンクリー
トを打設し、仕切板の外側に隣接壁との連結用空間を確
保した状態で地下壁を構築する地下連続壁の施工方法に
おいて、 前記コンクリート打設前に、鉄筋かごの中にコンクリー
ト中の水分を吸い上げるための吸い上げ部材を挿入し、
コンクリートを打設しながら、吸い上げ部材によってコ
ンクリート中の水分を吸い上げて排水することにより、
打設済みコンクリートの流動性を低下させることを特徴
とする地下連続壁の施工方法。
1. A trench for constructing an underground wall is excavated in the soil, a rebar cage is built in the trench, and concrete is inserted through a tremie pipe into an inner space defined by a partition plate attached to the rebar cage. In the method of constructing an underground continuous wall that is placed and constructs an underground wall in a state where a space for connection with an adjacent wall is secured on the outside of the partition plate, before the concrete placing, the water content in the concrete in the rebar cage Insert a suction member to suck up
While pouring concrete, the suction member absorbs the water in the concrete and drains it.
A method for constructing an underground continuous wall characterized by reducing the fluidity of cast concrete.
【請求項2】 前記吸い上げ部材として、管壁に多数の
孔を有した有孔管を用いることを特徴とする請求項1記
載の地下連続壁の施工方法。
2. The method for constructing an underground continuous wall according to claim 1, wherein a perforated pipe having a large number of holes in the pipe wall is used as the suction member.
【請求項3】 前記有孔管の外周を、コンクリートの管
内への流入を防ぐフィルタ材で覆ったことを特徴とする
請求項2記載の地下連続壁の施工方法。
3. The method for constructing a continuous underground wall according to claim 2, wherein the perimeter of the perforated pipe is covered with a filter material for preventing concrete from flowing into the pipe.
【請求項4】 前記吸い上げ部材として、長尺の不織布
を用いることを特徴とする請求項1記載の地下連続壁の
施工方法。
4. The method for constructing an underground continuous wall according to claim 1, wherein a long non-woven fabric is used as the suction member.
JP04639596A 1996-03-04 1996-03-04 Construction method of underground continuous wall Expired - Fee Related JP3536270B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04639596A JP3536270B2 (en) 1996-03-04 1996-03-04 Construction method of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04639596A JP3536270B2 (en) 1996-03-04 1996-03-04 Construction method of underground continuous wall

Publications (2)

Publication Number Publication Date
JPH09235726A true JPH09235726A (en) 1997-09-09
JP3536270B2 JP3536270B2 (en) 2004-06-07

Family

ID=12745967

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04639596A Expired - Fee Related JP3536270B2 (en) 1996-03-04 1996-03-04 Construction method of underground continuous wall

Country Status (1)

Country Link
JP (1) JP3536270B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808414A (en) * 2012-08-24 2012-12-05 天津市建筑科学研究院有限公司 Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN105133574A (en) * 2015-07-23 2015-12-09 青岛静力工程股份有限公司 End point closing wall forming device of extrusion type underground diaphragm wall and application method
CN105178314A (en) * 2015-07-23 2015-12-23 青岛静力工程股份有限公司 Squeezing type underground continuous wall gapless steering device
CN111778962A (en) * 2020-07-29 2020-10-16 中国建筑第八工程局有限公司 Construction method of partially-empty underground continuous wall
CN114182721A (en) * 2021-12-22 2022-03-15 新疆路桥建设集团有限公司 Construction method for bearing casing bored pile and pouring pile of raft at collapsible loess section

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605790B (en) * 2012-03-14 2014-06-18 中冶交通工程技术有限公司 Post grouting device for squeezed branch pile and post grouting construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808414A (en) * 2012-08-24 2012-12-05 天津市建筑科学研究院有限公司 Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN105133574A (en) * 2015-07-23 2015-12-09 青岛静力工程股份有限公司 End point closing wall forming device of extrusion type underground diaphragm wall and application method
CN105178314A (en) * 2015-07-23 2015-12-23 青岛静力工程股份有限公司 Squeezing type underground continuous wall gapless steering device
CN111778962A (en) * 2020-07-29 2020-10-16 中国建筑第八工程局有限公司 Construction method of partially-empty underground continuous wall
CN114182721A (en) * 2021-12-22 2022-03-15 新疆路桥建设集团有限公司 Construction method for bearing casing bored pile and pouring pile of raft at collapsible loess section

Also Published As

Publication number Publication date
JP3536270B2 (en) 2004-06-07

Similar Documents

Publication Publication Date Title
KR20030026055A (en) a under drainage method for building using perforated drain pipes
KR100616123B1 (en) Device for drain underground water and method for construction the same
CN110409420B (en) Underground continuous wall with pit facing surface and precipitation function
JP3536270B2 (en) Construction method of underground continuous wall
CN111456056A (en) Construction method of dewatering well in deep foundation pit
CN108798775A (en) A kind of jacking construction active well
CN210288405U (en) Local deep pit water conservancy diversion escape canal system
KR100926694B1 (en) Groundwater collection and drainage system of the substructure under the underground structure
JP3648299B2 (en) Consolidation promotion method for soft ground
JP2001164564A (en) Installation method of drain structure for impervious wall and wall joint section
CN208473930U (en) A kind of jacking construction active well
KR20120139874A (en) Drainage system for soft ground using open channel and water-permeable drainage member
KR100655383B1 (en) Method of drain construction for basement
KR100821742B1 (en) Vertical reinforcement sump system
KR20020013168A (en) A drainage construction method of ground floor
KR200314875Y1 (en) Connector for apparatus draining
KR20050102160A (en) Surface treatment for soil improvement of solf reclaimed land
JPH09228362A (en) Continuous wall by continuously driven hollow pile having pumping and draining device installed thereto
CN111676992B (en) Core tube spring leakage blocking method used under complex geological conditions
JP2001020291A (en) Groundwater draining method
CN208830283U (en) A kind of nursery stock weeper drain
JP2662363B2 (en) Oil-water separation tank manufacturing method
JP2634442B2 (en) Underground wall
WO2008066247A1 (en) Drainage system using water drainable and permeable member for soil improvement of soft ground and soil improvement method for soft ground using the same
JP2003138611A (en) Method for constructing water collecting well

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20031224

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040224

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040305

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees