CN208473930U - A kind of jacking construction active well - Google Patents

A kind of jacking construction active well Download PDF

Info

Publication number
CN208473930U
CN208473930U CN201820926819.4U CN201820926819U CN208473930U CN 208473930 U CN208473930 U CN 208473930U CN 201820926819 U CN201820926819 U CN 201820926819U CN 208473930 U CN208473930 U CN 208473930U
Authority
CN
China
Prior art keywords
bottom plate
active well
well
jacking
ontology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820926819.4U
Other languages
Chinese (zh)
Inventor
葛成
陈煜�
李鸿鹏
金炜
葛斐
蒯圣宇
谢涛
盛金马
常江
王力
罗正帮
刘西民
梁东跃
吴义阳
肖俊俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Anhui Electric Power Co Ltd
Anhui Huadian Engineering Consulting and Design Co Ltd
Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Anhui Electric Power Co Ltd
Anhui Huadian Engineering Consulting and Design Co Ltd
Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Anhui Electric Power Co Ltd, Anhui Huadian Engineering Consulting and Design Co Ltd, Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Anhui Electric Power Co Ltd
Priority to CN201820926819.4U priority Critical patent/CN208473930U/en
Application granted granted Critical
Publication of CN208473930U publication Critical patent/CN208473930U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

A kind of jacking construction active well.It includes ontology, in the surrounding of ontology, gutter is set, reserved opening and jacking hole is arranged in side wall, and haunch is set in inside right angle, borehole wall lower end is arranged to the blade foot with tyre tread, and body bottom portion is provided with bottom plate, and bottom plate is placed in the groove of its neighbouring borehole wall, and sump is set on well inner bottom plating, and bottom plate is equipped with certain slope towards sump direction, and back cover and the bottom of a pan are successively set under bottom plate.The feature that the utility model overcomes existing cast in situs active well long in time limit, the upper pipe working well that a kind of design is reasonable, globality is strong, stability is good, structure is simple, improves construction efficiency is provided, and influence when reducing construction to close to buildings, it is practical, it is easy to promote the use of under the conditions of identical geology.

Description

A kind of jacking construction active well
[technical field]
The utility model relates to a kind of caisson structures, in particular to a kind of work well construction of jacking construction.
[background technique]
Pipe-jacking project is a kind of construction method of the embedded underground utilities of modernization, using the municipal buried pipe of jacking construction Net engineering is located at mostly on the main line road of cities and towns, is compared with corresponding cutting sunken tube method with shield construction, push pipe Construction has apparent superiority, and this method does not need to excavate ground notch, but must open at the both ends of laid underground piping Several active wells are dug, active well is divided into jacking active well and received well again, and wherein reinforced concrete rectangular active well is more normal See, current active well generally uses excavation pit, live assembling reinforcement, formwork supporting plate casting concrete, the construction then backfilled Method, the active well site operation duration is longer, necessarily current to construction section traffic to cause large effect, and pollutes week The environment on side has seriously affected the normal life of neighbouring resident.
[utility model content]
The main purpose of the utility model is to provide a kind of jacking construction active wells, overcome existing cast in situs active well Feature long in time limit provides the push pipe work that a kind of design is reasonable, globality is strong, stability is good, structure is simple, improves construction efficiency Influence when making well, and reducing construction to close to buildings, it is practical, it is easy to promote the use of under the conditions of identical geology.
To achieve the above object, the technical solution that the utility model is taken are as follows:
A kind of jacking construction active well, it includes ontology, gutter is arranged in the surrounding of ontology, reserved opening is arranged in side wall With jacking hole, and haunch is set in inside right angle, borehole wall lower end is arranged to the blade foot with tyre tread, and body bottom portion is provided with bottom Plate, and bottom plate is placed in the groove of its neighbouring borehole wall, and sump is arranged on well inner bottom plating, and bottom plate is set towards sump direction There is certain slope, and back cover and the bottom of a pan are successively set under bottom plate.
Further, the sump length and width, deep size are respectively 2.0m, 0.8m, 0.6m.
Further, the reserved opening and jacking dimension of opening are 1200mm*1200mm.
Further, the active well is to pour the reinforced concrete structure for building up an entirety.
Further, the blade foot carries out feather plucking processing.
Compared with prior art, the utility model has the beneficial effects that active well ontology described in (1) is using upper and lower uniform thickness Stalk type, the structure of the type can preferably constrain the borehole wall, and easily controllable vertical subsidence is smaller to range of disturbance around, and mould Plate can repeatedly use.
(2) the active well body plane shape described in is rectangle, effectively increases the utilization rate in open caisson space and convenient for pre- The setting of box out mouth and jacking hole, while four corners of inner wall are equipped with haunch, improve the integrally-built intensity of open caisson.
(3) setting of reserved opening facilitates and underground gallery, trench, pipeline, water inlet window in the beneficial effect (2) described in Equal holes are attached.
(4) the active well body bottom portion described in is equipped with bottom plate and is placed in groove, connect back cover bottom plate more preferably with the borehole wall, And play the role of effective waterproof while enhancing structure globality.
(5) back cover and the bottom of a pan are set gradually below beneficial effect (4) insole board described in, compared with not back cover open caisson, The load that this kind of structure foundation unit area is born is smaller, so that it is relatively fewer to stop the heavy rear settling amount of punching;And the bottom of a pan is set It sets and then enhances the overall stability of retaining wall compared with flat-bottom structure.
(6) active well described in is equipped with gutter and sump, facilitates water flooding within the scope of open caisson in the construction process Drainage has been effectively ensured the stabilization of the construction period soil body and the safety of construction, has saved working hour and manpower, it will be apparent that improved work Make efficiency, and the pollution for reducing site environment and the influence caused by traffic, living environment.
(7) active well ontology described in is that cast in situs is compared with assembled, this kind of construction method as a whole, Have the advantages that the big good rigidity of intensity, and excavated volume is small in the work progress of open caisson, contacts closely, guarantee with surrounding soil The quality of active well.
[Detailed description of the invention]
Fig. 1 is the floor map of utility model;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is the B-B sectional view of Fig. 1.
[specific embodiment]
To be easy to understand the technical means, creative features, achievement of purpose, and effectiveness of the utility model, below In conjunction with specific embodiment, the utility model is further described.
As shown in Figure 1-3, a kind of jacking construction active well, it includes ontology 1, and the surrounding of ontology 1 is provided with gutter 2, and a concrete road surface 12 is set around gutter 2, and has a slope 13 between the road surface and ground, 1 side wall of main body Reserved opening 5 and jacking hole 6 are set, and haunch 8 is set in inside right angle, borehole wall lower end is arranged to the blade foot 7 with tyre tread, 1 bottom of ontology is provided with bottom plate 9, and bottom plate 9 is placed in the groove 4 of its neighbouring borehole wall, and sump is arranged on well inner bottom plating 9 3, and bottom plate 9 is equipped with certain slope, specially 0.5% gradient towards sump direction, and back cover 10 is successively arranged under bottom plate With the bottom of a pan 11.
The sump locally digs deep ensure that within the scope of sump having a size of 2.0mx0.8mx0.6m (long x wide x deep) Back cover thickness and back cover is laid with c25 concrete, with a thickness of 0.7m, the lower part the bottom of a pan is filled with block stone, and bosom reaches 0.5m.
The reserved opening and jacking dimension of opening is all 1200mmx1200mm, and the setting of reserved opening is convenient for and ground Lower gallery, trench, pipeline, the water inlet connection such as window, and the setting at jacking hole is then convenient for tool pipe or development machine from active well Interior shift onto received well always across soil layer is sling.
Active well ontology is reinforced concrete structure, enters well and the reserved opening of well should be blocked up temporarily before sinking out Plug, and be 8mm with diameter, spacing is that the reinforcing bar of 200mm is reinforced, and blade foot should also carry out feather plucking processing, and open caisson is being constructed Well-points dewatering is used in the process and is enclosed in well does water-level observation.
The active well of the utility model, which pours, builds up an entirety, and intensity is big compared with fabricated active well, good rigidity, with The cast-in-place active well of excavation pit is small compared to excavated volume, and the close stabilization for guaranteeing the construction period soil body is contacted with surrounding soil, is applied Work safety, it is high-efficient, reduce the pollution site environment and the influence caused by traffic, living environment.
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, for this For the technical staff in field, various modifications and changes may be made to the present invention.It is all in the spirit and principles of the utility model Within, any modification, equivalent replacement, improvement and so on should be included in the protection scope of the utility model.

Claims (5)

1. a kind of jacking construction active well, it is characterised in that: it includes ontology, gutter is arranged in the surrounding of ontology, side wall is set Reserved opening and jacking hole are set, and haunch is set in inside right angle, borehole wall lower end is arranged to the blade foot with tyre tread, ontology bottom Portion is provided with bottom plate, and bottom plate is placed in the groove of its neighbouring borehole wall, and sump is arranged on well inner bottom plating, and bottom plate is towards collection Well direction is equipped with certain slope, and back cover and the bottom of a pan are successively arranged under bottom plate.
2. active well according to claim 1, it is characterised in that: the sump length and width, deep size are respectively 2.0m、0.8m、0.6m。
3. active well according to claim 1, it is characterised in that: the reserved opening and jacking dimension of opening are 1200mm*1200mm。
4. active well according to claim 1, it is characterised in that: the active well be pour build up an entirety reinforcing bar it is mixed Xtah Crude Clay structure.
5. active well according to claim 1, it is characterised in that: the blade foot carries out feather plucking processing.
CN201820926819.4U 2018-06-14 2018-06-14 A kind of jacking construction active well Active CN208473930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820926819.4U CN208473930U (en) 2018-06-14 2018-06-14 A kind of jacking construction active well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820926819.4U CN208473930U (en) 2018-06-14 2018-06-14 A kind of jacking construction active well

Publications (1)

Publication Number Publication Date
CN208473930U true CN208473930U (en) 2019-02-05

Family

ID=65213743

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820926819.4U Active CN208473930U (en) 2018-06-14 2018-06-14 A kind of jacking construction active well

Country Status (1)

Country Link
CN (1) CN208473930U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108798775A (en) * 2018-06-14 2018-11-13 国网安徽省电力有限公司经济技术研究院 A kind of jacking construction active well

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108798775A (en) * 2018-06-14 2018-11-13 国网安徽省电力有限公司经济技术研究院 A kind of jacking construction active well

Similar Documents

Publication Publication Date Title
CN102162253B (en) Precipitation construction method employing pipe embedded in deep foundation pits
CN210395607U (en) Side slope buried drainage structure
CN104846836B (en) Water feeding and draining device and construction method based on this water feeding and draining device for deep basal pit
CN108798775A (en) A kind of jacking construction active well
CN102888847B (en) Construction method free from lowering water level for local deep foundation pit of elevator shaft
CN215329049U (en) Track structure with drainage pump station in integral ballast bed
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
KR100665984B1 (en) The construction method of basement self drainage
CN110952574A (en) Method for treating landslide deformation body
CN208473930U (en) A kind of jacking construction active well
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN111424685A (en) Deep water falling hole processing structure and method for backfilling foundation in large karst depression
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN213477808U (en) Structure is found fast to steel construction underground garage
CN211735421U (en) Force transmission structure for sensitive deep foundation pit
CN212405178U (en) Deep water falling hole processing structure of backfill foundation in large karst depression
CN204435321U (en) A kind of steam power station water intaking open channel
CN110397049B (en) Buttress type retaining wall with drainage function and construction method thereof
CN210369276U (en) Combined water pump house of underground tunnel
CN206090593U (en) Concrete cofferdam and steel sheet piling cofferdam combination formula cofferdam structure
CN221001020U (en) Pit-in-pit waterproof structure
CN213014584U (en) Inspection shaft is reformed transform to pipe jacking construction well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant