CN114855846A - Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof - Google Patents

Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof Download PDF

Info

Publication number
CN114855846A
CN114855846A CN202210640540.0A CN202210640540A CN114855846A CN 114855846 A CN114855846 A CN 114855846A CN 202210640540 A CN202210640540 A CN 202210640540A CN 114855846 A CN114855846 A CN 114855846A
Authority
CN
China
Prior art keywords
seepage
water
layer
geotextile
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210640540.0A
Other languages
Chinese (zh)
Inventor
吴友邡
杨胜舜
陈鹏
易忠贵
卢刚
范勇
代安辉
李红云
喻安涛
张传华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Construction Engineering Xingyin Construction Engineering Co ltd
Original Assignee
Guizhou Construction Engineering Xingyin Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Construction Engineering Xingyin Construction Engineering Co ltd filed Critical Guizhou Construction Engineering Xingyin Construction Engineering Co ltd
Priority to CN202210640540.0A priority Critical patent/CN114855846A/en
Publication of CN114855846A publication Critical patent/CN114855846A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Environmental & Geological Engineering (AREA)
  • Public Health (AREA)
  • Health & Medical Sciences (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention is suitable for the technical field of seepage-proofing and pressure-reducing construction, and discloses an underground seepage-proofing and pressure-reducing anti-floating blind pipe structure and a construction method, wherein the blind pipe structure comprises a base surface (1), a foundation pit (2) is arranged inside the base surface (1), waterproof geotextile (3) covers the inside of the foundation pit (2), a liquid seepage drainage pipe (4) is arranged at the bottom end of the foundation pit (2), liquid seepage holes (5) are uniformly distributed around the liquid seepage drainage pipe (4), and water seepage geotextile (6) wraps the outside of the liquid seepage drainage pipe (4); gravel (9) is backfilled in the foundation pit (2), and water seepage geotextile (6) covers the gravel (9). The seepage drainage pipe is buried in the construction foundation pit, the measures are safe, reliable and strong in controllability, the static water pressure is utilized for drainage, and the seepage drainage pipe has the characteristics of economy, energy conservation and environmental protection and is an indispensable part in green buildings.

Description

Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
Technical Field
The invention belongs to the technical field of seepage-proofing and pressure-reducing of building construction, and particularly relates to an underground seepage-proofing and pressure-reducing anti-floating blind pipe structure and a construction method thereof.
Background
At present, along with the annual improvement of the urbanization level of China, underground structure buildings are more and more, so that the burial depth of the foundation of a high-rise building and a multi-rise building is increased, just because the burial depth of the foundation is correspondingly increased, multi-rise underground water-bearing layers always appear in the deep foundation, because the water-bearing layers in a soil structure are easy to cut off, the actual construction difficulty caused by the water seepage of a foundation pit is caused, and the underground structure is corroded by underground water for a long time, the leakage is easy to generate, the service life is shortened, so the long-term effect of the anti-seepage decompression on the basement is paid high attention; the basement structure is of a floating-free design, the floor area of the basement is larger than that of an upper building tower, so that the upper part of a part of the basement does not have enough building quality to be pressed and floated, and in order to solve the problems, an underground seepage-proofing pressure-reducing floating-resistant blind pipe structure and a construction method thereof are provided.
Disclosure of Invention
The invention provides an underground seepage-proofing pressure-reducing anti-floating blind pipe structure and a construction method thereof, which solve the problems in the background art.
In order to achieve the purpose, the invention adopts the following technical scheme:
a subsurface seepage-proofing, pressure-reducing and anti-floating blind pipe structure comprises a base surface, wherein a foundation pit is arranged inside the base surface, waterproof geotextile covers the inside of the foundation pit, a seepage drainage pipe is arranged at the bottom end of the foundation pit, seepage holes are uniformly distributed around the seepage drainage pipe, and seepage geotextile covers the outside of the seepage drainage pipe; and gravel is backfilled in the foundation pit, and water seepage geotextile covers the gravel.
Further, the aperture of the liquid seepage hole is 20 mm.
Furthermore, the waterproof geotextile is provided with flanges at two sides of the foundation pit, and the length of the flanges is not less than 100 mm.
Further, the lap joint length of the water seepage geotextile on the liquid seepage calandria is not less than 200 mm.
Furthermore, the lapping length of the water-permeable geotextile on the macadam and the waterproof geotextile at the edge of the foundation pit is not less than 100 mm; and backfilling the upper surface of the water-permeable geotextile with clay.
Further, waterproof geotechnical cloth and infiltration geotechnical cloth are green polypropylene fibre geotechnical cloth, and are 3mm thick.
Furthermore, the weeping calandria is made of PE pipes with three specifications, and the pipe diameters are DN200, DN315 and DN400 respectively.
The construction method of the underground seepage-proofing pressure-reducing anti-floating blind pipe structure is characterized by comprising the following steps of: the method comprises the following steps: firstly, preparing a water permeable PE pipe wrapped by water permeable geotextile → secondly positioning and lofting → thirdly digging and digging a groove → thirdly cleaning the bottom of the groove → thirdly laying waterproof geotextile → sixthly backfilling a gravel cushion layer → seventhly placing a hose → eighthly backfilling a filter material → niner sealing the water permeable geotextile →
Figure 100002_DEST_PATH_IMAGE002
Backfilling and tamping clay;
specifically, 1, burying a blind pipe:
1) the embedding depth is calculated according to the slope breaking direction of a plane arrangement diagram, brick built hidden falling wells are arranged at the positions of local beam bottom penetrating positions and high and low steps, brick built hidden wells are arranged at the corners and the intersections of pipelines, the embedding depth of a drainage blind pipe at the back of an outer wall of the basement is not less than 0.6m lower than the bottom plate of the basement, the lines are laid on the basement according to the position and the size of the blind pipe, then trench earthwork is dug, and the bottom of the trench is backfilled with lime soil and a slope is found;
2) trimming the trench wall according to the width of the blind pipe for molding, laying waterproof geotextile along the trench bottom, and enabling the lengths of the flanges at two sides to be not less than 100 mm;
3) the PE pipes are connected in a hot melting mode, the positions, corresponding to the holes, of the PE pipes are connected, after the connection is completed, the permeable PE pipes processed by the holes are wrapped by water permeable geotextile, and the lap joint length is not less than 200 mm;
4) the groove is backfilled by graded broken stones, after the groove is backfilled, the top of the groove is covered with a layer of water-permeable geotextile, the lap joint length of the water-permeable geotextile and the waterproof geotextile is not less than 100mm, and then the upper clay is backfilled;
2. and (3) water seepage and drainage layer:
1) for the structure with the reinforced concrete bottom plate, firstly, a bottom water seepage layer is made, and then a main body structure and a vertical wall water seepage and drainage layer are constructed; if no bottom plate is provided, after the main structure is constructed, a bottom and vertical wall seepage and drainage layer is constructed;
2) paving and filling the seepage and drainage layers in layers, wherein the thickness of each layer is not more than 300mm, and carefully tamping by using a flat vibrator;
3) when the water collecting pipe is paved and filled with stones slightly larger than the water seepage holes, when a concrete pipe or a clay pipe with the length of 500-700 mm and without holes is paved, a gap of 10-15 mm is reserved between the end parts of the pipes so as to facilitate water seepage into the pipes; the water collecting pipe and the drainage ditch have the gradient not less than 1%;
4) when backfilling, carefully tamping the soil layer by using a tamping machine; adopting a brick wall as a waterproof layer for protecting the outer part of the shear wall, and backfilling clay once when the shear wall is built to be lm high;
5) when in construction, the water level is reduced to be below the water filtering layer, the water filtering layer cannot be made in muddy water, and the constructed seepage and drainage system is kept smooth.
Further, there are two methods for draining water: one is that the water seepage layer is made into 1% gradient, set up concrete cushion and infiltration wall and escape canal between water seepage layer and soil body, the inside does not have water-collecting pipes, the water flows to the sump pit through the blind pipe of drainage, reuse the water pump to pump away; one is that there is no concrete cushion layer between the water seepage layer and the soil body, there is a water collecting well inside, the underground water flows into the nearby deep sewer well or the water pump pit inside the structure depending on the self gradient of the water seepage layer and the water collecting blind pipe, and then is pumped away.
Compared with the prior art, the invention has the beneficial effects that:
1. the seepage drainage pipe is buried in the construction foundation pit, the measures are safe, reliable and strong in controllability, the static water pressure is utilized for drainage, and the seepage drainage pipe has the characteristics of economy, energy conservation and environmental protection and is an indispensable part in green buildings.
2. The invention reduces the underground water level for a long time through the liquid-seepage calandria, ensures the construction soil to be dry, prevents the underground water from generating buoyancy on the basement bottom plate and prevents a large amount of drainage contained in the soil layer from being discharged, and the liquid-seepage calandria can meet the requirements of construction and play a role of precipitation in the service life of buildings, thereby really realizing the permanent combination.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a weep drain of the present invention;
FIG. 3 is a sectional view A-A of FIG. 2;
FIG. 4 is a schematic diagram of an anti-migration block according to the present invention;
FIG. 5 is a process flow diagram of the present invention.
In the figure: 1. a base surface; 2. a foundation pit; 3. waterproof geotextile; 4. liquid seepage calandria; 5. a weep hole; 6. water seepage geotextile; 7. an anti-offset block; 8. stabilizing the nail head; 9. and (4) crushing the stones.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it should be noted that unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly, e.g., as meaning fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed; the types of the electrical appliances provided in the present invention are only references, and different types of electrical appliances with the same function can be replaced according to actual use conditions, and for those skilled in the art, the specific meaning of the above terms in the present invention can be understood in specific situations.
Example 1: referring to fig. 1-3, an underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure comprises a base surface 1, wherein a foundation pit 2 is formed inside the base surface 1, waterproof geotextile 3 covers the inside of the foundation pit 2, a liquid seepage drainage pipe 4 is arranged at the bottom end of the foundation pit 2, seepage holes 5 are uniformly distributed around the liquid seepage drainage pipe 4, and water seepage geotextile 6 wraps the outside of the liquid seepage drainage pipe 4; broken stones 9 are filled in the foundation pit 2, and water-permeable geotextile 6 covers the broken stones 9;
the aperture of the liquid seepage hole 5 is 20 mm;
the waterproof geotextile 3 is provided with flanges at two sides of the foundation pit 2, and the length of the flanges is not less than 100 mm;
the lapping length of the water seepage geotextile 6 on the liquid seepage calandria 4 is not less than 200 mm;
the lapping length of the water-permeable geotextile 6 on the broken stone 9 and the waterproof geotextile 3 at the edge of the foundation pit 2 is not less than 100 mm; and the upper surface of the water-permeable geotextile 6 is backfilled with clay;
the waterproof geotextile 3 and the water-permeable geotextile 6 are green polypropylene geotextiles and have the thickness of 3 mm;
the weeping calandria 4 is made of PE pipes with three specifications and models, and the pipe diameters are DN200, DN315 and DN400 respectively.
Example 2: referring to fig. 1-4, the structure is the same as that of embodiment 1, further, a group of anti-deviation blocks 7 are respectively disposed on two sides of the weeping drain pipe 4 at the bottom end of the foundation pit 2, and the bottom ends of the anti-deviation blocks 7 are uniformly distributed and fixed with stable nail heads 8; the top of the anti-deviation block 7 is in a circular arc shape.
When in use: when the seepage calandria 4 is installed, the seepage calandria 4 reduces the underground water level and the horizontal thrust of water pressure to underground buildings, firstly the anti-deviation block 7 is placed at the position where the seepage calandria 4 needs to be installed, the stable nail head 8 at the bottom end of the anti-deviation block 7 is inserted into the bottom of the foundation pit 2 to form a stable placing effect, the seepage calandria 4 is placed at the top of the two anti-deviation blocks 7, thereby facilitating the rapid limit installation of the seepage calandria 4, in the water seepage process, water enters the seepage holes 5 through the seepage geotextile 6 and then enters the seepage calandria 4 to form underground water for recycling, the construction water cost of the project is reduced, and meanwhile, the buoyancy effect of the underground water contained in the soil layer on the bottom plate is reduced, the drainage device works in a stratum with abundant underground water, guides the underground water, ensures that soil is relatively dry, is beneficial to construction operation, and is convenient for carrying out efficient drainage effect on underground seepage water.
Referring to fig. 5, the construction method of the underground impermeable decompression anti-floating blind pipe structure comprises the following steps: firstly, preparing a water permeable PE pipe wrapped by water permeable geotextile → secondly positioning and lofting → thirdly digging and digging a groove → thirdly cleaning the bottom of the groove → thirdly laying waterproof geotextile → sixthly backfilling a gravel cushion layer → seventhly placing a hose → eighthly backfilling a filter material → niner sealing the water permeable geotextile →
Figure 540096DEST_PATH_IMAGE002
Backfilling and tamping clay;
specifically, 1, burying a blind pipe:
1) the embedding depth is calculated according to the slope breaking direction of a plane arrangement diagram, brick built hidden falling wells are arranged at the positions of local beam bottom penetrating positions and high and low steps, brick built hidden wells are arranged at the corners and the intersections of pipelines, the embedding depth of a drainage blind pipe at the back of an outer wall of the basement is not less than 0.6m lower than the bottom plate of the basement, the lines are laid on the basement according to the position and the size of the blind pipe, then trench earthwork is dug, and the bottom of the trench is backfilled with lime soil and a slope is found;
2) trimming the trench wall according to the width of the blind pipe for molding, laying waterproof geotextile along the trench bottom, and enabling the lengths of the flanges at two sides to be not less than 100 mm;
3) the PE pipes are connected in a hot melting mode, the positions, corresponding to the holes, of the PE pipes are connected, after the connection is completed, the permeable PE pipes processed by the holes are wrapped by water permeable geotextile, and the lap joint length is not less than 200 mm;
4) the groove is backfilled by graded broken stones, after the groove is backfilled, the top of the groove is covered with a layer of water-permeable geotextile, the lap joint length of the water-permeable geotextile and the waterproof geotextile is not less than 100mm, and then the upper clay is backfilled;
2. and (3) water seepage and drainage layer:
1) for the structure with the reinforced concrete bottom plate, firstly, a bottom water seepage layer is made, and then a main body structure and a vertical wall water seepage and drainage layer are constructed; if no bottom plate is provided, after the main structure is constructed, a bottom and vertical wall seepage and drainage layer is constructed;
2) paving and filling the seepage and drainage layers in layers, wherein the thickness of each layer is not more than 300mm, and carefully tamping by using a flat vibrator;
3) when the water collecting pipe is paved and filled with stones slightly larger than the water seepage holes, when a concrete pipe or a clay pipe with the length of 500-700 mm and without holes is paved, a gap of 10-15 mm is reserved between the end parts of the pipes so as to facilitate water seepage into the pipes; the water collecting pipe and the drainage ditch have the gradient not less than 1%;
4) when backfilling, carefully tamping in layers by using a tamping machine; adopting a brick wall as a waterproof layer for protecting the outer part of the shear wall, and backfilling clay once when the shear wall is built to be lm high;
5) when in construction, the water level is reduced to be below the water filtering layer, the water filtering layer cannot be made in muddy water, and the constructed seepage and drainage system is kept smooth.
Further, there are two methods for draining water: one is that the water seepage layer is made into 1% gradient, set up the concrete cushion and infiltration wall and escape canal between water seepage layer and soil body, the inside does not have water-collecting pipes, the water flows to the sump pit through the blind pipe of drainage, reuse the water pump to take away; one method is that no concrete cushion layer is arranged between the water seepage layer and the soil body, a water collecting well is arranged in the water seepage layer, underground water flows into a nearby deeper underground water well or a water pump pit in a structure by depending on the gradient of the water seepage layer and a water collecting blind pipe and is pumped away, and the filtered underground water is recycled by the two methods, so that the construction water cost of the project is reduced.
Application example:
the invention is applied to the construction project (first stage) of the modern cold chain logistics center in the west of copper kernel, and thoroughly solves the problem of water consumption in field construction by using the anti-seepage pressure-reducing blind pipe backflow technology and matching with a bright point water-saving measure of a box culvert water-collecting well, thereby greatly saving the water consumption for construction and saving a large amount of construction cost, according to the measurement and calculation of the construction water consumption of the project, the water consumption for field construction is at least about 50 tons every day, the water consumption can be saved by about 1.8 ten thousand tons in the whole construction period, and the saving cost is about 12.6 ten thousand yuan. The method has the advantages of obtaining good evaluation and quality assurance through detection of relevant departments and personnel, being convenient to construct and operate, having simple structure, realizing green construction and environmental protection, effectively improving the dirty, messy, poor and messy social image of building construction, establishing good social image, being beneficial to obtaining social support, ensuring the smooth proceeding of various works of engineering construction, even obtaining market favor, being easy to popularize and use and obtaining good social benefit and economic benefit.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (9)

1. The utility model provides an anti blind pipe structure that floats of underground prevention of seepage decompression, includes base plane (1), its characterized in that: a foundation pit (2) is formed in the base surface (1), waterproof geotextile (3) covers the foundation pit (2), a liquid seepage drainage pipe (4) is placed at the bottom end of the foundation pit (2), liquid seepage holes (5) are uniformly distributed around the liquid seepage drainage pipe (4), and water seepage geotextile (6) wraps the outside of the liquid seepage drainage pipe (4); gravel (9) is backfilled in the foundation pit (2), and water seepage geotextile (6) covers the gravel (9).
2. The underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to claim 1, characterized in that: the aperture of the liquid seepage hole (5) is 20 mm.
3. The underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to claim 1, characterized in that: the waterproof geotextile (3) is provided with flanges at two sides of the foundation pit (2), and the length of the flanges is not less than 100 mm.
4. The underground impermeable decompression anti-floating blind pipe structure according to claim 1, characterized in that: the lapping length of the water seepage geotextile (6) on the seepage drainage pipe (4) is not less than 200 mm.
5. The underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to claim 1, characterized in that: the lapping length of the water-permeable geotextile (6) on the broken stone (9) and the waterproof geotextile (3) at the edge of the foundation pit (2) is not less than 100 mm; and the upper surface of the water permeable geotextile (6) is backfilled with clay.
6. The underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to claim 1, characterized in that: waterproof geotechnique cloth (3) and infiltration geotechnique cloth (6) are green polypropylene fibre geotechnique's cloth, and are thick 3 mm.
7. The underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to claim 1, characterized in that: the liquid seepage calandria (4) is made of PE pipes with three specifications, and the pipe diameters are DN200, DN315 and DN400 respectively.
8. The construction method of the underground seepage-proofing, pressure-reducing and anti-floating blind pipe structure according to one of claims 1 to 7, characterized by comprising the following steps: the method comprises the following steps: firstly, preparing a permeable PE pipe wrapped by permeable geotextile → secondly, positioning and lofting → thirdly, digging a groove → fourthly, cleaningDitch arranging bottom → laying waterproof geotextile → backfilling gravel cushion layer → placing hose → backfilling filter material → sealing drainage geotextile → water filtering
Figure DEST_PATH_IMAGE002
Backfilling and tamping clay;
specifically, 1, burying a blind pipe:
1) the embedding depth is calculated according to the slope breaking direction of a plane arrangement diagram, brick built hidden falling wells are arranged at the positions of local beam bottom penetrating positions and high and low steps, brick built hidden wells are arranged at the corners and the intersections of pipelines, the embedding depth of a drainage blind pipe at the back of an outer wall of the basement is not less than 0.6m lower than the bottom plate of the basement, the lines are laid on the basement according to the position and the size of the blind pipe, then trench earthwork is dug, and the bottom of the trench is backfilled with lime soil and a slope is found;
2) trimming the trench wall according to the width of the blind pipe for molding, laying waterproof geotextile along the trench bottom, and enabling the lengths of the flanges at two sides to be not less than 100 mm;
3) the PE pipes are connected in a hot melting mode, the positions, corresponding to the holes, of the PE pipes are connected, after the connection is completed, the permeable PE pipes processed by the holes are wrapped by water permeable geotextile, and the lap joint length is not less than 200 mm;
4) the groove is backfilled by graded broken stones, after the groove is backfilled, the top of the groove is covered with a layer of water-permeable geotextile, the lap joint length of the water-permeable geotextile and the waterproof geotextile is not less than 100mm, and then the upper clay is backfilled;
2. and (3) water seepage and drainage layer:
1) for the structure with the reinforced concrete bottom plate, firstly, a bottom water seepage layer is made, and then a main body structure and a vertical wall water seepage and drainage layer are constructed; if no bottom plate is provided, after the main structure is constructed, a bottom and vertical wall seepage and drainage layer is constructed;
2) spreading and filling the water seepage and drainage layers layer by layer, wherein the thickness of each layer is not more than 300mm, and carefully tamping by using a flat vibrator;
3) when the water collecting pipe is paved and filled with stones slightly larger than the water seepage holes, when a concrete pipe or a clay pipe with the length of 500-700 mm and without holes is paved, a gap of 10-15 mm is reserved between the end parts of the pipes so as to facilitate water seepage into the pipes; the water collecting pipe and the drainage ditch have the gradient not less than 1%;
4) when backfilling, carefully tamping the soil layer by using a tamping machine; adopting a brick wall as a waterproof layer for protecting the outer part of the shear wall, and backfilling clay once when the shear wall is built to be lm high;
5) when in construction, the water level is reduced to be below the water filtering layer, the water filtering layer cannot be made in muddy water, and the constructed seepage and drainage system is kept smooth.
9. The construction method of the underground impermeable decompression anti-floating blind pipe structure according to claim 8, characterized in that: the water seepage and drainage have two methods: one is that the water seepage layer is made into 1% gradient, set up the concrete cushion and infiltration wall and escape canal between water seepage layer and soil body, the inside does not have water-collecting pipes, the water flows to the sump pit through the blind pipe of drainage, reuse the water pump to take away; one is that there is no concrete cushion layer between the water seepage layer and the soil body, there is a water collecting well inside, the underground water flows into the nearby deeper sewer well or the water pump pit inside the structure depending on the self gradient of the water seepage layer and the water collecting blind pipe, and then is pumped away.
CN202210640540.0A 2022-06-08 2022-06-08 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof Pending CN114855846A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210640540.0A CN114855846A (en) 2022-06-08 2022-06-08 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210640540.0A CN114855846A (en) 2022-06-08 2022-06-08 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN114855846A true CN114855846A (en) 2022-08-05

Family

ID=82624898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210640540.0A Pending CN114855846A (en) 2022-06-08 2022-06-08 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN114855846A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115559404A (en) * 2022-12-06 2023-01-03 福建省地质工程勘察院 Construction process and equipment for flexible drainage system of high-fill slope engineering berm
CN117418895A (en) * 2023-11-23 2024-01-19 中山大学 Semi-assembled open cut tunnel water-proof and drainage system and construction method thereof

Citations (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08199660A (en) * 1995-01-25 1996-08-06 Fujita Corp Unit osmos tube
KR20020000318A (en) * 2000-06-23 2002-01-05 오시덕 Method of horizontal drainage for pore water pumping of soft ground improvement
CN102051885A (en) * 2009-10-27 2011-05-11 江苏建业建设集团有限公司 Process for absorbing and discharging water under deep foundation concrete
RU2424401C1 (en) * 2010-06-17 2011-07-20 Федеральное государственное образовательное учреждение высшего профессионального образования "Орловский государственный аграрный университет" (ФГОУ ВПО Орел ГАУ) Drain of closed type
CN202157440U (en) * 2011-08-05 2012-03-07 深圳市居众装饰设计工程有限公司 Structure of sedimentation pond for preventing sedimentation and preventing water from leaking out of crack
CN103147453A (en) * 2013-03-22 2013-06-12 中交第一公路勘察设计研究院有限公司 Cutoff and drainage system for permafrost tunnel edge and heading slope and cutting slope and construction method thereof
CN203488208U (en) * 2013-09-28 2014-03-19 中铁二十局集团第二工程有限公司 Drainage system in tunnel hole
KR20150065475A (en) * 2013-12-05 2015-06-15 한국도로공사 Side gutter for mountain ridge and construction method
CN104712000A (en) * 2015-03-24 2015-06-17 中船第九设计研究院工程有限公司 Pressure reduction and water drainage system under ultra-deep underground space structure bottom plate
CN105201002A (en) * 2015-10-23 2015-12-30 金磐集团有限公司 Underground structure seepage drainage system and construction method thereof
CN205152970U (en) * 2015-10-23 2016-04-13 金磐集团有限公司 Underground structure oozes drainage system
CN206530363U (en) * 2016-08-30 2017-09-29 中铁二院工程集团有限责任公司 One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN206538789U (en) * 2017-03-02 2017-10-03 同济大学建筑设计研究院(集团)有限公司 A kind of pipe gallery
CN107445422A (en) * 2017-08-03 2017-12-08 山东建筑大学 A kind of pollution of river bed mud ecological restoring method
CN207362970U (en) * 2017-08-28 2018-05-15 中国建筑第二工程局有限公司 A kind of concave herbaceous field structure
CN108625403A (en) * 2018-02-12 2018-10-09 中铁十八局集团有限公司 A kind of basement bottom board uses the pre- anti-seep water construction method of blind pipe guide
CN109099213A (en) * 2018-09-27 2018-12-28 江苏清源管道技术有限公司 A kind of vacuum pipe anti-corrosive apparatus and construction technology
CN110439082A (en) * 2019-07-10 2019-11-12 江苏大学 A kind of backfill structure and construction method suitable for underground piping vibration isolation
CN210886972U (en) * 2019-07-22 2020-06-30 中冶天工集团有限公司 Blind drain infiltration pipe
CN211172034U (en) * 2019-10-29 2020-08-04 中铁二局第一工程有限公司 Water-rich basement falls drainage structures
CN111535369A (en) * 2020-05-28 2020-08-14 中冶天工集团有限公司 Anti-floating fixer for blind pipe and anti-floating construction process using same
CN211257027U (en) * 2019-07-30 2020-08-14 瑞洲建设集团有限公司 Drainage blind ditch at bottom of foundation pit
CN112523270A (en) * 2020-12-09 2021-03-19 深圳市天健(集团)股份有限公司 Anti-floating blind ditch for deep foundation pit in water-rich area and construction process thereof
CN112523272A (en) * 2020-12-09 2021-03-19 深圳市天健(集团)股份有限公司 Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN112709250A (en) * 2020-12-24 2021-04-27 西京学院 Be favorable to reducing seabed vacuum pipeline pile foundation cushion cap structure of buoyancy
CN213086883U (en) * 2020-08-18 2021-04-30 浙江绿城建筑设计有限公司 Buoyancy control structure of underground building
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN214090013U (en) * 2020-12-09 2021-08-31 深圳市天健(集团)股份有限公司 Anti blind ditch that floats to deep basal pit in rich water area
CN113718808A (en) * 2021-07-23 2021-11-30 新城控股集团实业发展有限公司 Precipitation structure for preventing underground structure from floating and construction method thereof
CN218175929U (en) * 2022-06-08 2022-12-30 贵州建工兴印建筑工程有限公司 Underground anti-seepage pressure-reducing anti-floating blind pipe structure

Patent Citations (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08199660A (en) * 1995-01-25 1996-08-06 Fujita Corp Unit osmos tube
KR20020000318A (en) * 2000-06-23 2002-01-05 오시덕 Method of horizontal drainage for pore water pumping of soft ground improvement
CN102051885A (en) * 2009-10-27 2011-05-11 江苏建业建设集团有限公司 Process for absorbing and discharging water under deep foundation concrete
RU2424401C1 (en) * 2010-06-17 2011-07-20 Федеральное государственное образовательное учреждение высшего профессионального образования "Орловский государственный аграрный университет" (ФГОУ ВПО Орел ГАУ) Drain of closed type
CN202157440U (en) * 2011-08-05 2012-03-07 深圳市居众装饰设计工程有限公司 Structure of sedimentation pond for preventing sedimentation and preventing water from leaking out of crack
CN103147453A (en) * 2013-03-22 2013-06-12 中交第一公路勘察设计研究院有限公司 Cutoff and drainage system for permafrost tunnel edge and heading slope and cutting slope and construction method thereof
CN203488208U (en) * 2013-09-28 2014-03-19 中铁二十局集团第二工程有限公司 Drainage system in tunnel hole
KR20150065475A (en) * 2013-12-05 2015-06-15 한국도로공사 Side gutter for mountain ridge and construction method
CN104712000A (en) * 2015-03-24 2015-06-17 中船第九设计研究院工程有限公司 Pressure reduction and water drainage system under ultra-deep underground space structure bottom plate
CN105201002A (en) * 2015-10-23 2015-12-30 金磐集团有限公司 Underground structure seepage drainage system and construction method thereof
CN205152970U (en) * 2015-10-23 2016-04-13 金磐集团有限公司 Underground structure oozes drainage system
CN206530363U (en) * 2016-08-30 2017-09-29 中铁二院工程集团有限责任公司 One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN206538789U (en) * 2017-03-02 2017-10-03 同济大学建筑设计研究院(集团)有限公司 A kind of pipe gallery
CN107445422A (en) * 2017-08-03 2017-12-08 山东建筑大学 A kind of pollution of river bed mud ecological restoring method
CN207362970U (en) * 2017-08-28 2018-05-15 中国建筑第二工程局有限公司 A kind of concave herbaceous field structure
CN108625403A (en) * 2018-02-12 2018-10-09 中铁十八局集团有限公司 A kind of basement bottom board uses the pre- anti-seep water construction method of blind pipe guide
CN109099213A (en) * 2018-09-27 2018-12-28 江苏清源管道技术有限公司 A kind of vacuum pipe anti-corrosive apparatus and construction technology
CN110439082A (en) * 2019-07-10 2019-11-12 江苏大学 A kind of backfill structure and construction method suitable for underground piping vibration isolation
CN210886972U (en) * 2019-07-22 2020-06-30 中冶天工集团有限公司 Blind drain infiltration pipe
CN211257027U (en) * 2019-07-30 2020-08-14 瑞洲建设集团有限公司 Drainage blind ditch at bottom of foundation pit
CN211172034U (en) * 2019-10-29 2020-08-04 中铁二局第一工程有限公司 Water-rich basement falls drainage structures
CN111535369A (en) * 2020-05-28 2020-08-14 中冶天工集团有限公司 Anti-floating fixer for blind pipe and anti-floating construction process using same
CN213086883U (en) * 2020-08-18 2021-04-30 浙江绿城建筑设计有限公司 Buoyancy control structure of underground building
CN112523270A (en) * 2020-12-09 2021-03-19 深圳市天健(集团)股份有限公司 Anti-floating blind ditch for deep foundation pit in water-rich area and construction process thereof
CN112523272A (en) * 2020-12-09 2021-03-19 深圳市天健(集团)股份有限公司 Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN214090013U (en) * 2020-12-09 2021-08-31 深圳市天健(集团)股份有限公司 Anti blind ditch that floats to deep basal pit in rich water area
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN112709250A (en) * 2020-12-24 2021-04-27 西京学院 Be favorable to reducing seabed vacuum pipeline pile foundation cushion cap structure of buoyancy
CN113718808A (en) * 2021-07-23 2021-11-30 新城控股集团实业发展有限公司 Precipitation structure for preventing underground structure from floating and construction method thereof
CN218175929U (en) * 2022-06-08 2022-12-30 贵州建工兴印建筑工程有限公司 Underground anti-seepage pressure-reducing anti-floating blind pipe structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
勇纯利: "市政工程监理细节100", vol. 978, 中国建材工业出版社, pages: 237 - 238 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115559404A (en) * 2022-12-06 2023-01-03 福建省地质工程勘察院 Construction process and equipment for flexible drainage system of high-fill slope engineering berm
CN117418895A (en) * 2023-11-23 2024-01-19 中山大学 Semi-assembled open cut tunnel water-proof and drainage system and construction method thereof

Similar Documents

Publication Publication Date Title
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN102535488B (en) Waterproof construction method for bottom plate of high-water-level basement
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN110219313B (en) Drainage system and construction method for underground construction blind well
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN114439027A (en) Construction method of concrete building foundation on deep and strong permeable foundation of hydroelectric engineering
CN218175929U (en) Underground anti-seepage pressure-reducing anti-floating blind pipe structure
CN210140850U (en) Leachate collection and drainage guide structure
CN218622343U (en) Pre-buried decompression sluicing mechanism
CN208455573U (en) A kind of full library basin Anti-seeping technology structure of karst area
CN107724405B (en) Dewatering of foundation construction method in a kind of underground pipe construction
CN107687155B (en) Anti-seepage and anti-lifting structure of basin and arrangement method
JP2006274655A (en) Drain structure of banking levee body and its construction method
CN110206062A (en) The dark construction method of underground river shallow embedding is worn under a kind of Urban Underground pipe gallery
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN108755724A (en) The external water drainage waterproof method of pipe gallery
CN110029689B (en) Percolate collecting and guiding and draining structure and construction method thereof
CN209891168U (en) Dredging engineering's floodgate case buried pipe formula outlet structure
CN210315653U (en) Cover plate ditch for laying underground buried pipe
CN208441115U (en) A kind of diaphram wall piping plugging structure
CN204435321U (en) A kind of steam power station water intaking open channel
CN208777319U (en) A kind of mound field structure kept suitable for soil quality
CN221001020U (en) Pit-in-pit waterproof structure
CN111794183A (en) Shallow-buried underground tunnel top riverbed bottom reinforcing structure and method
CN206477347U (en) The water storage structure of basement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220805