CN211172034U CN201921826771.0U CN201921826771U CN211172034U CN 211172034 U CN211172034 U CN 211172034U CN 201921826771 U CN201921826771 U CN 201921826771U CN 211172034 U CN211172034 U CN 211172034U
Authority
CN
China
Prior art keywords
water
blind pipe
falls
drainage
escape canal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921826771.0U
Other languages
Chinese (zh)
Inventor
胡刚
王国炜
尹江
张志河
余飞
麻瑀
郭廷
郭铭跃
李兴海
焦鑫鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju 1st Engineering Co Ltd filed Critical China Railway Erju 1st Engineering Co Ltd
Priority to CN201921826771.0U priority Critical patent/CN211172034U/en
Application granted granted Critical
Publication of CN211172034U publication Critical patent/CN211172034U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model provides a drainage structures falls in rich water base, including the blind pipe that permeates water, the blind pipe that permeates water is that surface distribution sets up the semicircle pipe in the hole of permeating water, and the blind pipe overcoat that permeates water is equipped with the nylon wire, and the blind pipe that permeates water is detained along the length direction who falls the escape canal and is located the ditch end that falls the escape canal, and the one end that falls the escape canal extends to sump pit department, and the regional packing in the outside that falls the blind pipe that permeates water in the escape canal has the granule rubble. The problems that filter pipes of dewatering wells are damaged and blocked in a large amount in the existing excavation process, and when the foundation part is excavated, the foundation dewatering and drainage requirements cannot be met are solved. Belongs to the technical field of drainage construction of deep foundation pit bases.

Description

Water-rich basement falls drainage structures
Technical Field
The utility model relates to a drainage structures falls in rich water basement belongs to deep basal pit basement and falls drainage construction technical field.
Background
In the Zhujiang Delta area, because the groundwater content is abundant, before the excavation of a deep foundation pit, dewatering and drainage are required in advance, and because the geological conditions are complex, the upper geology is silt, silty sand bed and muddy sand bed. In the process of excavation of the foundation pit, due to the fact that the dewatering well and the earth excavation process of the foundation pit are careless, the dewatering well is prone to being damaged by filtering pipes and blocked, and cannot meet the drainage requirement when the foundation pit is excavated to the base, and drainage measures need to be additionally arranged. Taking the civil engineering of the general Buddha ring line GFHD-1 standard scientific central station of the triangle-shaped city as an example, the excavation depth of a foundation pit is 36.5m, and the underground water level is about 2.3 m. The surrounding environment of the foundation pit is complex, the distance of 100m to the side of the foundation pit is the Zhujiang, the underground water level is high, and the underground water is rich; the station geological conditions are as follows from top to bottom: miscellaneous fill, a seaside sediment sand layer, a seaside sediment facies soil layer and argillaceous sandstone; the basement part is mainly formed by strongly weathered argillaceous sandstone. Most of dewatering well filter pipes are damaged and blocked in the excavation process, when the foundation part is excavated, the foundation dewatering and drainage requirements cannot be met, the foundation water level is guaranteed to be below the excavation surface, meanwhile, the upper structure construction is met as a main control point, and the requirements cannot be met by the conventional construction method.
Disclosure of Invention
The utility model provides a drainage structures falls in rich water basement to solve present excavation in-process, precipitation well chimney filter can be destroyed in a large number and block up, when excavation to basement position, can't satisfy the problem of basement precipitation, drainage requirement already.
In order to realize the above purpose, the utility model discloses plan to adopt such drainage structures falls in rich water base, including the blind pipe that permeates water, the blind pipe that permeates water is that surface distribution sets up the semicircle pipe in the hole of permeating water, and the blind pipe overcoat that permeates water is equipped with the nylon wire, and the blind pipe that permeates water is detained along the length direction who falls the escape canal and is located the ditch end that falls the escape canal, and the one end that falls the escape canal extends to sump pit department, and the regional packing in the outside that falls the blind pipe that permeates water in the escape canal has the granule rubble.
In the water-rich substrate drainage structure, the granular broken stones are filled to be level to the surface of the foundation pit, waterproof linoleum is laid above the granular broken stones, and two sides of the waterproof linoleum are laid in a region of 20-30cm of the extension of two sides of the upper end of the drainage ditch;
in the water-rich substrate dewatering and drainage structure, the water-permeable blind pipes are formed by cutting the dewatering well filter pipes from the middle along the length direction, the water-permeable blind pipes are cut into two symmetrical semicircular structures, namely two water-permeable blind pipes, and if the water-permeable blind pipes are not long enough, two or more water-permeable blind pipes are butted to form the required water-permeable blind pipes.
Compared with the prior art, the water permeable blind pipe in the water-rich foundation dewatering and drainage structure can be processed by adopting the abandoned dewatering well filter pipe in the construction site, the processing and the manufacturing are simple, and the cost is saved; the semi-circular water-permeable blind pipe is processed and manufactured, so that water on the substrate can be gathered into the pipe, and the water-permeable effect is improved; plays an important role in the drainage process of the deep foundation pit substrate; the water-rich basement drainage structure is verified in actual use in civil engineering of the bead triangle inter-city Guangfu loop GFHD-1 standard scientific central station, and is safe in construction, reliable in quality, convenient and fast in construction, low in cost and good in benefit. Through the successful application of the engineering, the method has important guiding significance for the drainage construction of similar water-rich substrates.
Drawings
Fig. 1 is a cross-sectional view of the present invention;
fig. 2 is the utility model discloses well blind pipe that permeates water settles the schematic structure drawing in falling the escape canal.
Detailed Description
To further clarify the objects, technical solutions and advantages of the present invention, a more particular description of the invention will be rendered by reference to the appended drawings, which are illustrated in the appended drawings.
Examples
Referring to the attached drawings 1 and 2, the embodiment provides a water-rich basement drainage structure, which comprises a water-permeable blind pipe 1, wherein the surface of the water-permeable blind pipe 1 is provided with semi-circular pipes with water-permeable holes, the water-permeable blind pipe 1 is formed by cutting a dewatering well filter pipe from the middle along the length direction, the water-permeable blind pipe 1 is processed by utilizing the discarded dewatering well filter pipe at the construction site and is cut into two symmetrical semi-circular structures, if the length is not enough, two or more than two water-permeable blind pipes are butted to form the required water-permeable blind pipe 1, a nylon net 3 is sleeved outside the water-permeable blind pipe 1, the water-permeable blind pipe 1 is buckled at the bottom of the dewatering ditch 2 along the length direction of the dewatering ditch 2, one end of the dewatering ditch 2 extends to a water collection pit, the outer side area of the water-permeable blind pipe 1 in the dewatering ditch 2 is filled with crushed stone 4, the crushed stone 4 is filled to be level with the, and two sides of the waterproof asphalt felt 5 are paved to the areas of 25cm of the extension of the two sides of the upper end of the drainage ditch 2;
the construction process flow is as follows:
construction preparation (excavation of a foundation pit to a designed elevation, processing of a permeable blind pipe 1) → excavation of a descending drainage ditch 2 → paving of a nylon net 3, placing of the permeable blind pipe 1 and wrapping of the permeable blind pipe 1 → backfilling of granular broken stones 4 and covering of a layer of waterproof felt 5 → pouring of a concrete cushion.
The specific operating points are as follows:
1. preparation for construction
1.1 processing of Water permeable Blind pipes
The blind pipe 1 that permeates water is formed by the useless precipitation well filter tube processing of job site, and the blind pipe 1 that permeates water is 377mm for the external diameter, and the precipitation well filter tube that wall thickness t equals 4mm cuts into two semicircles.
1.2 Deviational drainage ditch excavation
After the foundation ditch excavation reached design elevation, hang large-scale excavator from the foundation ditch, change into small-size excavator and fall escape canal 2 excavation, fall escape canal 2 excavation depth H and become 30cm, excavation width B becomes 50 cm. After the trench is dug to the bottom of the trench, whether the trench bottom is flat or not is checked, and the slag soil and sundries at the bottom of the trench are cleaned.
1.3 laying nylon net, placing permeable blind pipe and wrapping permeable blind pipe
Nylon net 5 is laid at the bottom of the ditch, nylon net 5's width is 1m, mainly consider nylon net 5 will permeate water the width of blind pipe 1 parcel round, after laying nylon net 5, will process the blind pipe 1 back-off that permeates water that makes at the bottom of the ditch, then wrap up blind pipe 1 that will permeate water with nylon net 5, make 1 surface of blind pipe that permeates water cover at least one deck nylon net 5, tie up nylon net 5 and blind pipe 1 that permeates water through 12# lead wire again, carry out the inspection after the ligature is accomplished, ensure that the ligature is firm.
1.4 backfilling particle macadam and covering a layer of waterproof asphalt felt
After the permeable blind pipe 1 is installed, backfilling granular broken stones 4, wherein the broken stones are granular broken stones with the diameters of 3-5cm and irregular shapes, covering a layer of waterproof felt 5 on the top after the broken stones are backfilled, and mainly aiming at preventing cement paste from entering a drainage ditch 2 to cause blockage when cushion concrete pouring is carried out, wherein the width of the felt is 1m, the drainage is carried out, and the left side and the right side of the drainage ditch are overlapped by 25 cm.
1.5 cast concrete cushion
After the waterproof asphalt felt 5 is paved, whether the drainage ditch 2 can normally drain water is checked, after all the drainage ditches meet the requirements, the top concrete cushion is poured, and in the process of pouring the cushion, cement paste is prevented from falling into the drainage ditch as much as possible.
2 basic principle
The basic principle of the cement soil pouring device is as follows: the method comprises the following steps of excavating a drainage ditch 2, burying a permeable blind pipe 1 underground, collecting water at the bottom of a foundation pit to the bottom of the drainage ditch 2 through permeable broken stone particles and the permeable blind pipe 1, collecting the water into a water collection pit through the drainage ditch 2, and discharging the water in the foundation pit to the outside of the foundation pit through a water pump.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (3)

1. The utility model provides a water-rich basement falls drainage structures which characterized in that: including the blind pipe (1) that permeates water, the blind pipe (1) that permeates water is the semicircle pipe that surface distribution seted up the hole of permeating water, and the blind pipe (1) overcoat that permeates water is equipped with nylon wire (3), and the blind pipe (1) that permeates water is detained along the length direction who falls escape canal (2) and is located the ditch bottom of falling escape canal (2), and the one end that falls escape canal (2) extends to sump pit department, and the regional packing in the outside of the blind pipe (1) that permeates water in the escape canal (2) has granule rubble (4).
2. The water-rich substrate dewatering and drainage structure of claim 1, wherein: the particle gravel (4) is filled to be level with the foundation pit surface, a waterproof felt (5) is laid above the particle gravel (4), and the two sides of the waterproof felt (5) are laid to extend to the two sides of the upper end of the drainage ditch (2) for 20-30 cm.
3. The water-rich substrate dewatering and drainage structure of claim 1, wherein: the permeable blind pipe (1) is formed by cutting the middle of a dewatering well filter pipe along the length direction.
CN201921826771.0U 2019-10-29 2019-10-29 Water-rich basement falls drainage structures Active CN211172034U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921826771.0U CN211172034U (en) 2019-10-29 2019-10-29 Water-rich basement falls drainage structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921826771.0U CN211172034U (en) 2019-10-29 2019-10-29 Water-rich basement falls drainage structures

Publications (1)

Publication Number Publication Date
CN211172034U true CN211172034U (en) 2020-08-04

Family

ID=71822780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921826771.0U Active CN211172034U (en) 2019-10-29 2019-10-29 Water-rich basement falls drainage structures

Country Status (1)

Country Link
CN (1) CN211172034U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114855846A (en) * 2022-06-08 2022-08-05 贵州建工兴印建筑工程有限公司 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN115075276A (en) * 2022-07-01 2022-09-20 中交路桥建设有限公司 Foundation pit underground water collection structure and foundation pit bottom sealing construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114855846A (en) * 2022-06-08 2022-08-05 贵州建工兴印建筑工程有限公司 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN115075276A (en) * 2022-07-01 2022-09-20 中交路桥建设有限公司 Foundation pit underground water collection structure and foundation pit bottom sealing construction method

Similar Documents

Publication Publication Date Title
CN101560757B (en) Seepage-intercepting and pollutant-removing system of large channel non-water passing slope
CN102425421B (en) Novel water control method suitable for mine shafts
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN211172034U (en) Water-rich basement falls drainage structures
CN113250220A (en) Novel dewatering method for deep foundation pit close to existing building
CN110453699B (en) Drainage slide-resistant pile structure of 'rice' -shaped pile core and construction method thereof
CN214194602U (en) Precipitation structure suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN202627002U (en) Tailing dam for water-inrush section of river-cut tailing pond
CN110777821B (en) Method for treating water burst disaster of fissures of weathered rock slope
CN112343020A (en) Environmental risk prevention and control integrated system and method for historical legacy tailing pond
CN201778330U (en) Clay waterproof curtain wall
CN216275788U (en) Drainage device used after failure of water interception curtain of deep foundation pit
CN112523272B (en) Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN113279408A (en) Method for carrying out engineering pile construction at bottom of deep soft soil foundation pit
Alexandris et al. Remediation of the Pissouri landslide in Cyprus
TWI328061B (en) Three-dimensional drainage process and structure in the gravity field
CN219732221U (en) Transverse water interception blind ditch structure suitable for mountain region wind power plant road
CN214363565U (en) A drainage structures and pipeline network fall fast in foundation ditch bottom for suspension type curtain
RU2176700C1 (en) Method for protecting territory from flooding
CN212358351U (en) Foundation ditch is backfilled with falling drainage system
US20060171781A1 (en) Pipeline trench system and method of construction
CN219490576U (en) Drainage blind ditch structure
CN210658632U (en) Infiltration ditch structure
CN212560972U (en) Fill out and dig road side ditch of section to sloping foot district rainfall prevention of seepage structure