CN111535369A - Anti-floating fixer for blind pipe and anti-floating construction process using same - Google Patents

Anti-floating fixer for blind pipe and anti-floating construction process using same Download PDF

Info

Publication number
CN111535369A
CN111535369A CN202010465757.3A CN202010465757A CN111535369A CN 111535369 A CN111535369 A CN 111535369A CN 202010465757 A CN202010465757 A CN 202010465757A CN 111535369 A CN111535369 A CN 111535369A
Authority
CN
China
Prior art keywords
blind
floating
layer
construction process
blind pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010465757.3A
Other languages
Chinese (zh)
Inventor
李建刚
徐万升
程建民
吴国堂
杜书先
杨雪峰
黄满红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202010465757.3A priority Critical patent/CN111535369A/en
Publication of CN111535369A publication Critical patent/CN111535369A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses an anti-floating fixer for a blind pipe and an anti-floating construction process using the same. The invention can effectively fix the blind pipe, avoid the dislocation of the joint and the displacement of the blind pipe and realize the purpose of firmly fixing the whole blind pipe drainage ring network. The blind pipe is prevented from shifting and the joint is prevented from being misplaced when the pebbles are backfilled, the construction process is simplified, the survival at one time is ensured, the reworking is avoided, the construction cost is effectively reduced, and the construction time is greatly saved.

Description

Anti-floating fixer for blind pipe and anti-floating construction process using same
Technical Field
The invention relates to the technical field of building construction industry, in particular to an anti-floating fixer for a blind pipe and an anti-floating construction process using the same.
Background
Technical scheme of prior art
Adopt the blind pipe to dredge secret confined water, form from drainage system and reduce groundwater to the whole buoyancy of underground structure, guarantee that the structure fracture that produces because of buoyancy is too big, uplift phenomenon can not appear after the underground structure construction is accomplished, guarantee security, the durability of underground structure in the later stage use. By utilizing the characteristics of high porosity and good durability of the blind pipes, a unique and communicated underground downstream self-drainage precipitation ring network is formed around the underground garage, so that the water pressure of underground water is utilized to actively reduce the anti-floating water level of the underground structure, the buoyancy of underground water is released, and the influence of the buoyancy of underground water on the garage structure is reduced.
The anti-floating blind pipe adopts plastic tubing (thermoplasticity synthetic resin) to bury underground forever, form and fall drainage system, reduce groundwater to the buoyancy of underground structure, prevent that ground water level from to the buoyancy of underground structure and causing the destruction of structure, the anti-floating blind pipe in underground wraps up whole pipe parcel with geotechnological cloth, lay with the assigned position, with taking off the nail between blind pipe and the blind pipe firmly, backfill closely knit with the cobble on every side, wrap up geotechnological cloth outside the plastic tubing and prevent clay and sand jam plastic tubing, influence later stage dewatering effect.
According to the traditional method for fixing and butting the blind pipes, the blind pipes are firmly nailed by the cramps, the blind pipes are prone to deviation when pebbles are backfilled, the joints are staggered, the pebbles are not prone to being dug out after the blind pipes are staggered, the cramps are prone to damaging the blind pipes when the blind pipes are displaced, and a self-drainage ring net cannot be formed after the joints are staggered, so that the drainage effect is affected.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the anti-floating fixer for the blind pipe and the anti-floating construction process using the same solve the problems that the blind pipe is easy to deviate in the traditional blind pipe construction process, and the blind pipe is not firmly fixed and is easy to damage.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows:
an anti-floating fixer for a blind pipe comprises an arc-shaped metal sheet and two metal connecting pieces, wherein the two metal connecting pieces are respectively fixed at two ends of the arc-shaped metal sheet.
The arc-shaped metal sheet is made of galvanized flat steel, and the metal connecting piece is made of galvanized flat steel
Figure BDA0002512608170000021
Round steel, a metal connecting piece is welded on the arc-shaped metal sheet,
the anti-floating construction process utilizing the anti-floating fixer for the blind pipe comprises the following steps:
step 1, paving a backfill soil layer;
step 2, paving a granular layer of 0.5mm-2mm on the backfill soil layer in the step 1;
3, paving a layer of 60-200mm particles above the 0.5-2 mm particle layer in the step 2, paving blind pipes on the 60-200mm particles according to a construction process, sleeving a plurality of arc-shaped metal sheets which are distributed at intervals along the length direction of the blind pipes on the outer wall of the topmost blind pipe, fixing metal connecting pieces at two ends of each arc-shaped metal sheet, vertically inserting the metal connecting pieces into the 60-200mm particles below the blind pipes along the tangential direction of the blind pipes at the bottom layer to fix the blind pipes, continuously paving the 60-200mm particles after the blind pipes are fixed and accepted, till a 60-200mm particle layer is formed, and clamping the blind pipes in the 60-200mm layer;
step 4, paving a 0.5mm-2mm particle layer on the 60-200mm particle layer in the step 3 again;
and 5, paving a backfill soil layer on the 0.5-2 mm particle layer in the step 4 until the highest construction position is reached.
Geotextiles are laid between the particle layer of 60-200mm and the particle layer of 0.5-2 mm, two adjacent geotextiles are in lap joint and are matched, the lap joint length of the geotextile is 250-350mm so as to ensure the filtering effect, the edges of the geotextiles are fixed by coal gangue bricks through blank pressing, and the distance between two adjacent coal gangue bricks is 950-1050 mm so as to avoid the movement of the geotextile caused in the construction process.
The 0.5mm-2mm particle layers are paved in a coarse sand layered backfilling compaction mode, and the thickness of each 0.5mm-2mm particle layer is 960-1100 mm.
The granular layer of 60-200mm is formed by paving pebbles, firstly, pebble layers with the thickness not less than 300mm are paved on the geotextile by utilizing the pebbles, the blind pipes are paved and fixed on the pebble layers according to the blind pipe construction process, and the pebbles are backfilled on the two sides of the blind pipes after the blind pipes are qualified by inspection until the thickness of the pebble layers reaches 1200-1400 mm.
The backfill soil layer is formed by the following steps of: 9, backfilling and tamping the lime soil layer by layer.
The interval between two adjacent arc-shaped metal sheets is not more than 1500mm, and the arc-shaped metal sheets are arranged at the positions which are 160mm away from the blind pipe interface 120 so as to achieve the effect of integrally fixing the blind pipe and prevent the situations of displacement and joint dislocation in the blind pipe construction process.
The depth of the metal connecting piece inserted into the particle layer of 60-200mm is not less than 200 mm.
And 3, wrapping geotextile on the outer wall of the blind pipe after the butt joint of the blind pipe is finished, and firmly binding the geotextile on the two sides of the blind pipe joint through binding wires so as to avoid the geotextile scattering influence on the filtering effect in the process of backfilling pebbles.
The invention has the beneficial effects that: the invention can effectively fix the blind pipe, avoid the dislocation of the joint and the displacement of the blind pipe and realize the purpose of firmly fixing the whole blind pipe drainage ring network. The blind pipe is prevented from shifting and the joint is prevented from being misplaced when the pebbles are backfilled, the construction process is simplified, the survival at one time is ensured, the reworking is avoided, the construction cost is effectively reduced, and the construction time is greatly saved.
The invention has the beneficial effects that: the invention can effectively fix the blind pipe, avoid the dislocation of the joint and the displacement of the blind pipe and realize the purpose of firmly fixing the whole blind pipe drainage ring network. The blind pipe is prevented from shifting and the joint is prevented from being misplaced when the pebbles are backfilled, the construction process is simplified, the survival at one time is ensured, the reworking is avoided, the construction cost is effectively reduced, and the construction time is greatly saved.
Drawings
FIG. 1 is a cross-sectional view of a blind drain system according to the present invention.
Fig. 2 shows the fixing mode of the fixator in the two blind pipe states in the invention.
Fig. 3 shows the fixing mode of the fixator in the three blind pipe states in the invention.
Fig. 4 is a schematic structural view of the anchor of the present invention.
Fig. 5 is a schematic view of the fastener installation at the joint.
Fig. 6 is a schematic view of the installation of the whole fixer on the blind pipe.
Graphic notation: 1. backfilling the soil layer; 2. a coarse sand layer; 3. a pebble layer; 4. a blind pipe; 5. a geotextile layer; 6. an arc-shaped metal sheet; 7. and (3) a metal connecting piece.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
An anti-floating fixer for blind pipe is composed of 40-4 galvanized flat steel and two segments
Figure BDA0002512608170000031
Of round steel, two sections
Figure BDA0002512608170000032
The round steel is respectively welded at two ends of the 40-4 galvanized flat steel.
The anti-floating construction process utilizing the anti-floating fixer for the blind pipe comprises the following steps:
step 1, laying a backfill soil layer 1, popping up a marking line on the side wall of the underground structure, and backfilling earthwork by adopting a design requirement 1: 9, backfilling and tamping the lime soil layer by layer to the bottom elevation position of the coarse sand layer;
step 2, backfilling coarse sand with the thickness of 1000mm on the backfill soil layer in the step 1, and backfilling and compacting in layers to form a coarse sand layer 2;
and 3, paving geotextile above the coarse sand layer 2 in the step 2 to form a geotextile layer 5, wherein two adjacent geotextiles are in lap joint fit, the lap joint length of the geotextile is 300mm, the longer the lap joint is, the better the effect is, but the higher the cost is, the edge of the geotextile is fixed by pressing edges of gangue bricks, the distance between the two adjacent gangue bricks is 1000mm, the smaller the distance is, the better the effect is, but the relative cost is higher, then paving 350 mm-thick pebbles on the geotextile, popping up a blind pipe elevation control line on the upper part of the outer wall of the garage, strictly controlling the elevation according to the control line, reserving the drainage gradient of the blind pipe 4, then paving blind pipes on 60-200mm particles according to a construction process, strictly adopting the blind pipes made of thermoplastic synthetic resin according to the design requirements, wherein the outer diameter of the blind pipes is 300mm, and the wall. After butt-jointing the blind pipes, sheathing geotextile, wrapping the geotextile with 300mm wide geotextile at the joint, firmly binding the geotextile at two sides by binding wires so as to prevent the geotextile at the joint from scattering when backfilling pebbles and influence the filtering effect, sheathing the outer wall of the topmost blind pipe 4 by a plurality of arc-shaped metal sheets 6 which are distributed at intervals along the length direction of the blind pipe, fixing metal connecting pieces 7 at two ends of the arc-shaped metal sheets, vertically inserting the metal connecting pieces 7 into a pebble layer 3 below the blind pipe along the tangential direction of the blind pipe at the bottom layer to fix the blind pipe 4, laying the blind pipe 4 in a single-layer tiled mode in the graph 2, sheathing the arc-shaped metal sheets on the two blind pipes 4, leading out the metal connecting pieces 7 from two sides of the two blind pipes 4 to be inserted into the pebble layer, or adopting multi-layer stacking as shown in the graph 3, increasing the number of the blind pipes from top to bottom layer by layer, sheathing the arc-shaped metal sheets on the, then inserting a metal connecting piece into the pebble bed 3 from two sides of a lower-layer blind pipe, wherein the distance between two arc-shaped metal sheets 6 is not more than 1500mm, arc-shaped metal sheets are arranged at positions 150mm away from a connector of a blind pipe 4, specifically, as shown in fig. 6, the arc-shaped metal sheets 6 are arranged at positions 150mm away from the connector of the blind pipe, then adding the two arc-shaped metal sheets 6 at intervals along the length direction of the blind pipe, the distances between the four arc-shaped metal sheets 6 are 1200mm, 1300mm and 1200mm respectively, the smaller the distance is, the better the fixing effect is, but the higher the cost is, meanwhile, the metal connecting piece 7 is inserted into the pebbles to the depth of 300mm, the deeper the inserting is, the better the fixing effect is, but the higher the cost is, after the blind pipe 4 is fixed and accepted, sand eggs should be simultaneously backfilled at two sides of the blind pipe, the situation that the installed blind pipe is laterally, The small excavator is matched with artificial backfilling to ensure the quality of the blind pipes and backfilled pebbles, the pebble layer with the thickness of 1300 is continuously paved with pebble particles until the blind pipes are clamped in the pebble layer, and geotextile is paved on the upper part of the pebble layer to form a geotextile layer 5;
step 4, paving a coarse sand layer 2 with the thickness of 1000mm on the pebble layer in the step 3 again in a layered backfilling and compacting mode;
and 5, backfilling soil on the coarse sand layer 2 according to the level of the site field in the step 4, wherein the specific construction process for forming the backfilled soil layer 1 is the same as that in the step 1. And the finished product is protected, so that the water path is ensured to be smooth.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides an anti fixer that floats that blind pipe was used which characterized in that: the metal connecting piece is composed of a section of arc-shaped metal sheet and two sections of metal connecting pieces, wherein the two sections of metal connecting pieces are respectively fixed at two ends of the arc-shaped metal sheet.
2. An anti-floating anchor for blind canals according to claim 1, wherein: the arc-shaped metal sheet is made of galvanized flat steel, and the metal connecting piece is made of galvanized flat steel
Figure FDA0002512608160000011
Round steel, and the metal connecting piece is welded on the arc-shaped metal sheet.
3. The anti-floating construction process of the anti-floating fixer for the blind pipe, which is used by the method of claim 1, is characterized in that: the method comprises the following steps:
step 1, paving a backfill soil layer;
step 2, paving a granular layer of 0.5mm-2mm on the backfill soil layer in the step 1;
3, paving a layer of 60-200mm particles above the 0.5-2 mm particle layer in the step 2, paving blind pipes on the 60-200mm particles according to a construction process, sleeving a plurality of arc-shaped metal sheets which are distributed at intervals along the length direction of the blind pipes on the outer wall of the topmost blind pipe, fixing metal connecting pieces at two ends of each arc-shaped metal sheet, vertically inserting the metal connecting pieces into the 60-200mm particles below the blind pipes along the tangential direction of the blind pipes at the bottom layer to fix the blind pipes, continuously paving the 60-200mm particles after the blind pipes are fixed and accepted, till a 60-200mm particle layer is formed, and clamping the blind pipes in the 60-200mm layer;
step 4, paving a 0.5mm-2mm particle layer on the 60-200mm particle layer in the step 3 again;
and 5, paving a backfill soil layer on the 0.5-2 mm particle layer in the step 4 until the highest construction position is reached.
4. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: geotextiles are laid between the particle layer of 60-200mm and the particle layer of 0.5-2 mm, two adjacent geotextiles are in lap joint and match, the lap joint length of the geotextiles is 250-350mm, the edges of the geotextiles are fixed by coal gangue bricks through blank pressing, and the distance between two adjacent coal gangue bricks is 950-1050 mm.
5. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: the 0.5mm-2mm particle layers are paved in a coarse sand layered backfilling compaction mode, and the thickness of each 0.5mm-2mm particle layer is 960-1100 mm.
6. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: the granular layer of 60-200mm is formed by paving pebbles, firstly, pebble layers with the thickness not less than 300mm are paved on the geotextile by utilizing the pebbles, the blind pipes are paved and fixed on the pebble layers according to the blind pipe construction process, and the pebbles are backfilled on the two sides of the blind pipes after the blind pipes are qualified by inspection until the thickness of the pebble layers reaches 1200-1400 mm.
7. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: the backfill soil layer is formed by the following steps of: 9, backfilling and tamping the lime soil layer by layer.
8. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: the distance between two adjacent arc-shaped metal sheets is not more than 1500mm, and the arc-shaped metal sheets are arranged at positions 120 mm away from the blind pipe interface and 160mm away from the blind pipe interface.
9. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: the depth of the metal connecting piece inserted into the particle layer of 60-200mm is not less than 200 mm.
10. The anti-floating construction process using the anti-floating fixture for blind pipes according to claim 3, wherein: and 3, after the butt joint of the blind pipes is finished, the outer walls of the blind pipes are wrapped with geotextile, and the geotextile on two sides of the blind pipe joints are firmly tied through binding wires.
CN202010465757.3A 2020-05-28 2020-05-28 Anti-floating fixer for blind pipe and anti-floating construction process using same Pending CN111535369A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010465757.3A CN111535369A (en) 2020-05-28 2020-05-28 Anti-floating fixer for blind pipe and anti-floating construction process using same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010465757.3A CN111535369A (en) 2020-05-28 2020-05-28 Anti-floating fixer for blind pipe and anti-floating construction process using same

Publications (1)

Publication Number Publication Date
CN111535369A true CN111535369A (en) 2020-08-14

Family

ID=71974056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010465757.3A Pending CN111535369A (en) 2020-05-28 2020-05-28 Anti-floating fixer for blind pipe and anti-floating construction process using same

Country Status (1)

Country Link
CN (1) CN111535369A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114855846A (en) * 2022-06-08 2022-08-05 贵州建工兴印建筑工程有限公司 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071808A (en) * 2011-01-13 2011-05-25 中建四局第三建筑工程有限公司 Anti-floating positioning method and structure for core mould pipe
CN203361180U (en) * 2013-06-24 2013-12-25 浙江省天正设计工程有限公司 Elasticity adjusting anti-floating fixing structure for buried horizontal tank
CN203412159U (en) * 2013-08-15 2014-01-29 上海建工七建集团有限公司 Limiting device with built-in high-strength composite thin wall pipe
CN108411893A (en) * 2018-05-14 2018-08-17 兰州理工大学 A kind of frost damage prevention water seepage mechanism and its construction method
CN110439082A (en) * 2019-07-10 2019-11-12 江苏大学 A kind of backfill structure and construction method suitable for underground piping vibration isolation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071808A (en) * 2011-01-13 2011-05-25 中建四局第三建筑工程有限公司 Anti-floating positioning method and structure for core mould pipe
CN203361180U (en) * 2013-06-24 2013-12-25 浙江省天正设计工程有限公司 Elasticity adjusting anti-floating fixing structure for buried horizontal tank
CN203412159U (en) * 2013-08-15 2014-01-29 上海建工七建集团有限公司 Limiting device with built-in high-strength composite thin wall pipe
CN108411893A (en) * 2018-05-14 2018-08-17 兰州理工大学 A kind of frost damage prevention water seepage mechanism and its construction method
CN110439082A (en) * 2019-07-10 2019-11-12 江苏大学 A kind of backfill structure and construction method suitable for underground piping vibration isolation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张彬: "《防水工长》", 28 February 2014 *
本书委员会编: "《管道工程安装便携手册》", 31 January 2007 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114855846A (en) * 2022-06-08 2022-08-05 贵州建工兴印建筑工程有限公司 Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN102966072B (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN109944314B (en) Rapid construction method for rainfall-free large-diameter wound pipe composite joint
CN109024701B (en) Phosphogypsum reservoir slope seepage prevention method
CN107780425A (en) A kind of large-scale yard drain french drain method to set up of banketing in Gullied Rolling Loess Region
CN110847327A (en) Waterproof and drainage construction method for large-area basement roof
CN104988927A (en) Reinforced backfill earthwork ramp and construction method thereof
CN111535369A (en) Anti-floating fixer for blind pipe and anti-floating construction process using same
WO2022100168A1 (en) Drainage chute and drainage culvert combined plugging and dredging method for tailings pond
CN109083100B (en) River channel excavation construction process after mud blowing and landing
CN203716064U (en) Roadbed sewer convenient for dredging
US10113285B2 (en) Revetment system
CN204898465U (en) Ecological drainage facility of permafrost region dish
CN215857878U (en) Drainage structures is prevented in basement bottom plate post-cast strip
CN210288013U (en) Interim drainage facility of central authorities' median convenient to construction
CN113882491A (en) Method for reducing infiltration line of tailing pond or phosphogypsum pond
CN110387908B (en) Multi-layer restraining anti-leakage post-pouring belt construction method
CN210621363U (en) Be applied to embankment structure that permeates water of gully district
CN109779682B (en) Water-rich section highway tunnel escape canal structure system
CN207988083U (en) The orthogonal anti-structure of drainning off floodwaters of Gobi Region solar energy optical-thermal place
CN111851399A (en) Sand river bed water and soil loss prevention and control and water quality purification system
CN111676890A (en) Ecological reconstruction construction method for river bottom of black and odorous water body river
CN213508323U (en) Wet tailing storehouse emergency flood control structure of arranging
CN105178133A (en) Disc-shaped ecological water drainage facility in permafrost region and construction method for disc-shaped ecological water drainage facility
CN104631425A (en) Method for accelerating seepage eliminating and solidification of coal ash

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200814